TW@ESI 13 th March 2016 Hope that you and all your families had a good weekend. The following is a forecast of the next week.....

Upload: simon-abela

Post on 14-Apr-2017

232 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Tw@ESI 13th March 2016

TW@ESI13th March 2016Hope that you and all your families had a good weekend.

The following is a forecast of the next week.....

Page 2: Tw@ESI 13th March 2016

A General Note before we startI would like to thank all the team for the efforts to complete the offices upstairs. The plan next for this week is: a) Relocate Margaret with IT and Phone functionalb) Finish all paintwork upstairsc) Finish installations upstairsd) Fix roller shutter in show room e) Fix and change all Air conditioning units upstairs and

downstairsf) IBIS will start terminating and testing all IP/Telephone

points in showroom, tech room and upstairs

Page 3: Tw@ESI 13th March 2016

Projects and deadlines

• 15_033_Westin_7-AHU- by 26/2 ... Manually start up AHUs in Plant room MCC1 by 7/3 – this has been achieved well done !! by 16 and 17/3 Manual start up AHUS in Banquet and by 28/3 Complete all T&C works. It is important to also give the client the facility to switch on and off the units through the network (quick after the 17/3)

• 13_070_SCM Lagoona_Pump room- We have pulled most cables and need to now start terminations on site... This, too, is going to become a hot project- All terminations possible are to be completed by 28/3

Page 4: Tw@ESI 13th March 2016

Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and

15_034_Hilton_Calorifier_Monitoring- Panels to be completed within March – the earlier the better!!... All installation and manual start up by end first week of April 2016- Manual start-up, soon after. Full T&C by end of April 2015. We have given most of the installation works to Panta and we need to ensure that Panta’s work is to the required standard.

• Projects 12_026 SCM Buildings 02, 03, R3 & R4 and 12_027 Security Systems Parliament- LVA and JPO will put whatever efforts necessary to close off whatever can be closed off by 1st April 2016.

Page 5: Tw@ESI 13th March 2016

Projects and deadlines• 15_008 - Aurobindo PH02 BMS- We will re start

commissioning this week and we need to give priority to the commissioning of air systems- we will also soon need to come up with a plan and target date here.

• 13_052 New offices- Get the Automation in the new area offices ready by March 2016!! Make sure it is fully functional and de snagged- Installation upstairs to be ready by Mid March 2016.... Design and Technical offices will be moved soon after that!

Page 6: Tw@ESI 13th March 2016

DesignLast week• Intercontinental – Panel Drawing As Built update• Started organizing of ESI Acad blocks (P&IDs, Plans,

Schematics)• Hilton – Calorifiers, kitchen restaurant AHUs –

released Panel Build to Lino• Sliema Graham Apartments – Revised Schematic &

PIR Plan sketches (as per variation meeting, Kenneth feedback)

• Vibrant Helvar Lighting – Created Schematic and Plans.

Page 7: Tw@ESI 13th March 2016

DesignNext Week:• Vibrant Helvar Lighting – Panel Design of LCP• Sterling Chemicals – Silvio update SAS-000928 (complete by 18-

03-2016)• Siggiewi – Stickers for Switches, after receipt of info from Cci• OVt New Residence 15_038 – Conclude Enclosures’ sizing &

location in Storage Room - awaiting TBR• MDH MAU - research & request for quote of Engraved labels

for D00-CC1• OTM – evaluate S/steel punched-labels Prices, and send to SSA,

SAA.• SCM Lagoon – conclude Terminating details with SAA for

Grundfos Panel

Page 8: Tw@ESI 13th March 2016

InstallationPast week:– Completed cable pulling at Westin– Completed cable ladder at Westin– Installed and terminated field devices on roof and A/V

room at Westin– Completed ELV terminations on MCC 2 at Westin– Completed first and second fix at ESI offices level 1– Completed second fix at ESI offices level 1– Completed 75% of painting at ESI offices level 1– Terminations and commissioning of A/C’s at Fimbank– Started terminations on MVP at SCM Sea water pump

room

Page 9: Tw@ESI 13th March 2016

InstallationNext week:– Complete plastering and painting at ESI offices level

1– Commissioning at Life sciences– Change over remaining AHU’s to work manually on

MCC 2 at Westin– Modifications to supply utp extenders and switched

on MCC 2 and Existing panel at Westin– Commissioning of cctv and DAC at parliament

Page 10: Tw@ESI 13th March 2016

Panel Build• We have completed 2 of the 3 hilton panels and

the idea is to have these completed and tested by 22nd March and installed on site by 25th March 2016.

Page 11: Tw@ESI 13th March 2016

Mater Dei

• It would be good to start getting feedback of what was done during the week and what is planned for the next from MDH- I am expecting that every week, someone from MDH starts updating the works done and the plan for the next week.

Page 12: Tw@ESI 13th March 2016

Development and Commissioning• We have done large important steps on finishing off the

Parliament we need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION

• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• The plan for Life sciences is to complete all works by 18th March and training by 21st March 2016

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we awaiting the client

Page 13: Tw@ESI 13th March 2016

Development and Commissioning• OTM urgent jobs and snags were also done in the last weeks• Another project that needs attention is CCA Villa ... There are

still some snags to be addressed – Wall mounted controller on wall in Dining area and issues with AC integration and intruder alarm integration

• Oncology 14_066- We have done most of the work here and are waiting from Panta on this

• The Siggiewi Primary school project – we need to close off – the quicker the better!!

• Aurobindo we are proceeding with software development and we have done quite some progress – we now will be starting commissioning

Page 14: Tw@ESI 13th March 2016

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- We are

presently working on a task list and POW as well as setting up the test rigs

Page 15: Tw@ESI 13th March 2016

Sales and Business Development

• We have been working on Home automation offerings and quotes for OTM (some of which are quite large) , a quote for CCTV at Enemalta and quotes for variations for existing projects.

• We have also handed in a bid for Le Meridien Hotel- Upgrade of old Niagara R2 platform hardware and software

Page 16: Tw@ESI 13th March 2016

Birthday wishes go to

Clifton Camenzuli 16th March

Page 17: Tw@ESI 13th March 2016

• More lessons to follow shortly

Page 18: Tw@ESI 13th March 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 19: Tw@ESI 13th March 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• Have a good week