Hope all of you had a good weekend

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 22nd January 2017

We have new employees Steve Vassallo who is also on the linkedin group – welcome aboard!!!

Drinks after work!!! Next scheduled for 27/1/17- keep the afternoon free and may as many of you join this social event

Note that I will be on long leave from 13th Feb to 24th Feb (both days

included)

Some Points Before Starting

Also note that Shridar will be on long leave from 17 Feb 2017 for 5 weeks

Page 4: TW@ESI 22nd January 2017

Projects and Deadlines

16_051_Baxter_AHU

We have nearly put this project to sleep!

Some snags pending – the remote access of the system and installation and commissioning of the valve actuator- the remote access should have now been sorted and we need to demonstrate the power of this system to the client

16_041_RSM_Security

We have done some good progress here – well done to all pulling the ropes!!!

Next would be programming , Testing and commissioning

We really need to have these systems commissioned by end of January 2017

16_025_DeLaRue_OFX

Design will be ready this week , materials have been delivered and training by overseas specialists will be on 30/1 onwards

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017

Q021_TF4- Panel is on site and installed- we need to power up and start connecting and powering up MOVs

16_007_LeMeridien

We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-

This week we will be doing the next roof panel so as to have a smoother transition when Shridar is on leave

Page 5: TW@ESI 22nd January 2017

Projects and Deadlines

16_023_GGY

We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017

16_015_RSM_Lighting

This lighting control project is to be completed soon

The contractor has started installing and terminating devices- it is critical that we finish off this project and move on

15_023_FM panels

We have a new 2 panels for FM environmental (D5M-110) ... The delivery date is not know – design is completed

16_058_Methode

Another fast tack project Jace Based AHU control system here – we will kick it off in this week – Target is to finish it by end of February 2017- we have started ordering the long lead items here – the plan is to start Panel design ASAP and start panel build on 3 or 4th week of Jan 2017. We also need to start surveying installation works on site- We need to work hard to ensure the panel is completed before Shridar leaves for his long leave

Page 6: TW@ESI 22nd January 2017

Projects and Deadlines

12_043_LSP

We have an important and urgent snag to be rectified ASAP – treating the rust on enclosures

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

12_027- Parliament

We have finalised the documentation and eventually need to integrate ProWatch.

15_038_new_HA_Ovt and 15_026_Apap

Residence

are two home automation projects scheduled for Q1 2017 – we have built all panels for these projects and we are awaiting others to complete their installation

We also need to start working of the software development

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others- After 16/1

we also have to deliver the pool panel

Page 7: TW@ESI 22nd January 2017

Projects and Deadlines

14_081_Siggiewi School-

there are some snags pending here due to louvers- we also need to meet to schedule an amount of service on site.

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

13_070- SCM Lagoona Plant room

We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 8: TW@ESI 22nd January 2017

01 02 03 04

DesignFor the Past week we have been working on the following

completed CCI’s Westin Panel Drawings Feedback/

Started RSM Security Panel Drawings (80% complete)/ General – Update of Intruder Templates from Stefan – add Sounder as per sketch

Methode SMT – received all Panel Material’s quotes, and release to orderMethode SMT – completed Panel Design, now started Panel Draughting

Design

OTM – power Incomer issue

Page 9: TW@ESI 22nd January 2017

01 02 03 04

DesignAnd next week… we will work on

Complete RSM Security Panel DrawingsRSM Security DAC Drawings (get from SAi)

Methode SMT – put Field Devices Part Nos on P&IDs, update to next Revision, distribute to allMethode SMT – hopefully conclude Panel DraughtingMethode SMT – put part numbers on Materials list (70% complete)

Meridien – Site Visit with DSH re: Mech & Elec Additions Installations required

Design

Page 10: TW@ESI 22nd January 2017

This is what the Installation team have been working on last week

Started with Dali terminations at RSM

Finished with paint work on panels at Lifesciences- Prosit

Attempted to energize the new panel at OTM

Installation

Le Meridien. Started panel modifications

Page 11: TW@ESI 22nd January 2017

….. And this is what is planned for next week

Continue with works at Mosta workshop

RSM complete terminations for panels

OVT, put panels in place

Continue with panel modifications at Le Meridien

Installation

Page 12: TW@ESI 22nd January 2017

Next week we will • Continue with panel modifications at Le Meridien• RSM security panels (DAC/Intruder)Further on• 16_058_Methode- 3rd or 4th week of Jan 2017

Panel Build

Panel Build

Page 13: TW@ESI 22nd January 2017

Week 04

Yearly Field devices checks, IR images & coordinated tests Jan-- D10-CC1, D10-CC2, D10-CC3, D11-CC1, DP6-CC1

Quarterly panel checks A01-CC1, AP1-CC1, A02-CC1, A02-CC2, AP2-CC1, A03-CC1, A03-CC3, B01-CC1, BP1-CC1, B02-CC1, BP2-CC1, B03-CC1, C01-CC1, CP1-CC1. C01-CC2, C02-CC1, C03-CC1, C04-CC1, C05-CC1, C06-CC1, C07-CC1, C07-CC2, C08-CC1, CP2-CC1 CF1-CC1 Weekly update of antivirus on all BMS stations

Two yearly S7-300 CPU V2 Replacement Battery D08-CC1, D08-CC2, D09-CC2, D11-CC1, D11-CC2, D10-CC1, D10-CC2, P04-CC1, CF1-CC1

Mater Dei Maintenance

ReactiveHandling of reactive work orders

OthersParticipating in weekly fire drillsNew Angiography ProjectTraining of new team member

Mater Dei Maintenance

Page 14: TW@ESI 22nd January 2017

Sterling Chemicals Line 2 PLC system

S5 PLC upgrade for Kordin Grain terminals

lighting control systems in Qatar.

And…. We may still have a chance to win a VERY large

BMS job

We have won a new project – Home Automation 17_003_SCA_AGo_Res- I

will be kicking it off this weekThese are the quotes the business development

team have been working on

Business Development

Page 15: TW@ESI 22nd January 2017

\

BIRTHDAYS TO CELEBRATE

STEFAN AZZOPARDI 28TH JAN

Page 16: TW@ESI 22nd January 2017

Some Last Thoughts

One of the most de-motivating thing for me personally, is to see internal conflicts and arguments!! Especially when I know they will effect the way we perform as company- To me this is simply not acceptable! We should all be working on the same side to deliver projects and systems with the best margins for our owner- anyone not working towards this objective is simply not pulling in the same direction! Petty arguments and conflicts have to be resolved so that we all focus on what we need to be focussing

Page 17: TW@ESI 22nd January 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable