Greetings from Chiang Mai Hope all of you had a good weekend

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 12th February 2017

Karolina Szczypka will be on leave from 13/2 to 17/2 .. Happy holidays

Some Points Before Starting

Also note that Shridar will be on long leave from 17 Feb 2017 to 20th

March

Page 4: TW@ESI 12th February 2017

Projects and Deadlines

16_041_RSM_Security

We need to close off here – the sooner the better

SAI/CCI please give me a list of works which are pending by others and a date by when we will finish

16_025_DeLaRue_OFX

Training by overseas specialists was delivered and we now await client to install hardware in machines so as for us to commission

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017

Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs

16_007_LeMeridien

We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-

We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here

16_058_Methode

Another fast tack project Jace Based AHU control system here –Panel design is completed

Panel build is to be completed by 17/2. Installation to commence with cable pulling by Sub contractors – for this project , in my absence, I will need Dennis/Clifton and Claudio to take over and ensure we deliver on time

Page 5: TW@ESI 12th February 2017

Projects and Deadlines

16_023_GGY

We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017

15_023_FM panels

D20 ASRD being built by sub contractor and scheduled for 9th March 2017

D05 M 110 – scheduled for 1st May 2017

D20 ASRD 690 is presently in quotation stage

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others-

we also have to deliver the pool panel

15_038_new_HA_Ovt and 15_026_Apap

Residence

These two home automation projects are now urgent- we need to complete all installation

We also need to start working of the software development- they are urgent and we have to perform

Page 6: TW@ESI 12th February 2017

Projects and Deadlines

12_043_LSP

We have an important and urgent snag to be rectified ASAP – treating the rust on enclosures

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

14_08_Siggiewi School-

We have made a commitment to do training1. Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers

13_070- SCM Lagoona Plant room

We need to conclude all pending installation works – we will also try to finish the programming but commissioning will be on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 7: TW@ESI 12th February 2017

Projects and Deadlines

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

Page 8: TW@ESI 12th February 2017

01 02 03 04

DesignFor the Past week we have been working on the following

OVT – completed Intruder Panel Drawing

AAP – completed LTG-G Panel Drawing As built udpateAAP – started implementation of Additions (to be continued after CFH leave)

FM Env – D20-ASRD – completed Design, including numerous updates from clientFM Env – D5M-110 - completed Design, including numerous updates from client

Design

OTM – Q020 Netherlocks – Completed & submitted TF3_NVC_004OTM – Q020 Netherlocks – Started TF3_NVC_002

Page 9: TW@ESI 12th February 2017

01 02 03 04

DesignAnd next week… we will work on

OTM – Q020 Netherlocks – complete & submit TF3_NVC_002OTM – Q020 Netherlocks – switch to BH1_NVC_001

Preparation design works for new project

Design

Page 10: TW@ESI 12th February 2017

This is what the Installation team have been working on last week

Testing of IO.s on 5DP02 at OTM

Continued with works at OVT

Connected out goers on 5DP02 at OTM

Installation

Started Data terminations at OVT

Page 11: TW@ESI 12th February 2017

….. And this is what is planned for next week

commissioning at RSM

Continue with works at OVT penthouseComplete data at OVT

Installation

Additional DALI Sensors at RSM

Page 12: TW@ESI 12th February 2017

Next week we will • 16_058_Methode- We need to complete this by 17/2-

come what may• FM Env D20-ASRD – This will be built by a sub contractor as

soon as we get the parts

Panel Build

Panel Build

Page 13: TW@ESI 12th February 2017

Week 07PPMYearly Field devices checks, IR images & coordinated tests Feb-- D11-CC2, D12-CC1, F02-CC1, F05-CC1, F05-CC4, F05-CC5

Quarterly panel checks Feb -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D05-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2,D12-CC1

Weekly update of antivirus on all BMS stations

Mater Dei Maintenance

ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberWO- 116184572 (Q131)To supply and replace existing control gear for F2-CHW1-P2 with a new simocode and sirus soft starter

Mater Dei Maintenance

Page 14: TW@ESI 12th February 2017

Sterling Chemicals Line 2 PLC system – This is now a contract –

Well done to all!!

lighting control systems in Qatar

Quote for Fire alarm

Building automation in a private clinic

16_040_Playmobil_Factory_Ext_BMS- This is now finally a contract too!! Well

done to all !!These are the quotes the business development

team have been working on

Business Development

Page 15: TW@ESI 12th February 2017

\

HAPPY BIRTHDAYKAROLINA SZCZYPKA FEBRUARY 16

Page 16: TW@ESI 12th February 2017

Some Last Thoughts

As can be seen we have now won 2 major projects and we are also aiming to get new people on board.... I cannot stress more the importance of trying to work together and respect each other- It is the only we we can be successful!!!

Page 17: TW@ESI 12th February 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable

Some Last Thoughts

Page 18: TW@ESI 12th February 2017

I wish you all a good and productive

week