TW@ESI 1 st May 2016 Happy May Day to all The following is a record of what was done during the past week and a forecast of the next week.....

Upload: simon-abela

Post on 20-Feb-2017

97 views

Category:

Business


0 download

TRANSCRIPT

Page 1: TW@ESI 1st May 2016

TW@ESI1st May 2016Happy May Day to all

The following is a record of what was done during the past week and a forecast of the next week.....

Page 2: TW@ESI 1st May 2016

A General Note before we start- New premises

The new premises.... I have a commitment from Dennis, Rullu and Clinton to complete all works by 10th May 2016.... Preferably before!!! Lets make sure we finish and move everyone back into place. We need to ensure that we also complete by the datea) Intercom installation on new doorb) Connect and commission DALI (at least we can switch on /

off lightingc) Have permanent power and AC supplyd) All Data/Telephone outlets are completed and functional.e) Office DAC and intruder are re commissioned

Page 3: TW@ESI 1st May 2016

A General Note before we start- Internal Re organisationThe integrated security department will be taken over by Clifton, who will, as of, 10th May 2016 have a new technician ... Stefan Azzopardi

As of 12th may 2016, we will also have a new student part timer- Andrew Scicluna- working half day 0700-1100hrs on Thursdays and a full day 0700-1530 or more on Fridays with the Jace team- in summer he will be switched to full time.

Page 4: TW@ESI 1st May 2016

Projects and deadlines

• 15_044_Hilton_Restaurant_Kitchen_AHU and 15_034_Hilton_Calorifier_Monitoring. We have managed to commission basic closed loop controls ... Next would be the full commissioning of the project

• 15_033_Westin_7-AHU- Most of the T&C should by now be completed. Pending is documentation

• 15_008 - Aurobindo PH02 BMS- We have made progress on commissioning here- we will also soon need to come up with a plan and target date here.

Page 5: TW@ESI 1st May 2016

Projects and deadlines• 13_052 New offices- Now a target is – Complete all

installations and everyone to move back to their places – new target – Mid May 2016... Latest!!

• 14_089_MGA- installation of 2 x readers and 2 x REX – this is a very urgent project which Clifton and Dennis will be tackling- I would like to have your estimated date of completion here!!

• 12_027- Parliament installation of St James lift intercom and DAC system, this too , is a very urgent project which Clifton and Dennis will be tackling- I would like to have your estimated date of completion here!!

Page 6: TW@ESI 1st May 2016

Projects and deadlines• 14_001_Fadalah-There are some snags here which

are to be resolved (by others)• Projects 12_026 SCM Buildings 02, 03, R3 & R4 and

12_027 Security Systems Parliament- are still pending projects and we need to tackle these with our internal re organisation

• 13_070_SCM Lagoona_Pump room- We have pulled most cables .All terminations possible are to be completed ASAP

• 16_011_Intruder_UOM- This project will be started shortly

Page 7: TW@ESI 1st May 2016

DesignLast week• Concluded Siggiewi As Built with Clifton• Life Sciences - start gathering Panel Drawings

from Clifton, and implement accordingly.• Life Sciences - Print 1 set Panel Drawings for

MPa O&M• OVT –concluded Plan Drawings• AAP – Started design (P&IDs)

Page 8: TW@ESI 1st May 2016

DesignNext Week:• AAP Villa –design (P&IDs) and plans

Page 9: TW@ESI 1st May 2016

InstallationPast week:– Passed cables, tested and terminated at MGA for

DAC– Fitted 3x3 boxes in gypsum, installed REX switches

and card readers at MGA– Installed a canopy above MCC-1 at Westin– Assisted Claudio in configuring the AHU’s PID Loop

at Hilton– Completed design office and corridor At ESI– Met with Joe Grech re lift at City Gate (Parliament)

Page 10: TW@ESI 1st May 2016

InstallationNext week:– Move intruder panel (RIO) to new premises– 2nd, 3rd fix and painting of CVA office at ESI offices– Change old distribution board with the new one at

ESI– Start commissioning of additional card readers and

REX’s at MGA– Start works on parliament lift– Meet with DLI and discuss installation of OVT

Penthouse

Page 11: TW@ESI 1st May 2016

Panel BuildThere are no Panel Build activities at this point

Page 12: TW@ESI 1st May 2016

Mater DeiThe following are the tasks being worked on and planned for the next weeks• FIELD DEVICES CHECKS FROM SITE E01-CC1, E02-CC1, EP1-CC1• COORDINATED FRIDGE / FREEZER TEST BETWEEN ESI AND BIOMEDICAL - APRIL• QUARTERLY REVISED BMS DOCUMENTATION /QUARTERLY BACKUP /QUARTERLY BACKUP -

EACH CPU DATA• BMS Field Devices PPM -A01-CC1. AP1-CC1 / A03-CC1. A03-CC3 / A02-CC1. A02-CC2, AP2-

CC1• Coordinated Checks of Alarms from 3rd party devices A01-CC1, AP1-CC1, A02-CC1, A02-

CC2, AP2-CC1, A03-CC1, A03-CC3 and Various REF Equipment• PANEL THERMOGRAPHICAL IMAGES A01-CC1, AP1-CC1, A02-CC1, A02--CC2, AP2-CC1, A02-

CC1, A03-CC3• MCC PANEL CHECKS C01-CC1, CP1-CC1. C01-CC2, C02-CC1, C03-CC1, C04-CC1, D05-CC1,

C05-CC1, C07-CC1, C07-CC2, C08-CC1, CP2-CC1 CF1-CC1• MCC PANEL CHECKS A01-CC1, AP1-CC1. A02-CC1, A02-CC2, AP2-CC1, A03--CC1, B01-CC1,

BP1-CC1, B02-CC1, BP2-CC1, B03-CC11• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Quotation works new angiography project• WinCC upgrade HMI D06-CC2 / D07-CC2/ HMI D09-CC1- We have done quite some

progress here- well done!!

Page 13: TW@ESI 1st May 2016

Development and Commissioning• We have done large important steps on finishing off the

Parliament we need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION- we have an urgent quote to implement on Parliament St James lift (intercom and DAC readers)

• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• Life Sciences- We have also concluded with Training now... Documentation and some snags are pending

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we awaiting the client

Page 14: TW@ESI 1st May 2016

Development and Commissioning• OTM urgent jobs and snags – P12/ Tank Field 3 and quotinf for

the AS410 change over• Another project that needs attention is CCA Villa ... There are still

some snags to be addressed –intruder alarm integration and intruder snags

• The Siggiewi Primary school project – we need to close off with data collection , snags and documentation here

• Oncology 14_066- We have done most of the work here and are waiting from Panta on this

• Aurobindo we are proceeding with software development and we have done quite some progress – we are also now commissioning this project- we will need to come up with a plan here.

Page 15: TW@ESI 1st May 2016

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- We are

presently working on a task list and POW as well as setting up the test rigs

Page 16: TW@ESI 1st May 2016

Sales and Business Development• We have been working on a quote for Actavis and

soon we will be quoting OTM for the change over of their PLC/Operating system and re writing of their core software.

• We are also working to close off a large project at Meridien and a larger than life home automation system

• Next Thursday ESI will be Gold sponsors for a Chamber of Engineers conference – Intelligent Buildings... See http://www.coe.org.mt/component/content/article/43-conferences/269-chamber-of-engineers-annual-conference-2016

Page 17: TW@ESI 1st May 2016

ISO Audit• As you all are aware , next Tuesday and

Wednesday 3rd and 4th May we will be ISO audited by our external auditors AJA

• I was pleasantly surprised with the pro activeness and feedback of the internal ISO training last Friday

Page 18: TW@ESI 1st May 2016

• More lessons to follow shortly – very shortly

Page 19: TW@ESI 1st May 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 20: TW@ESI 1st May 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• Have a good week