TW@ESI24th April 2016Hope that you and all your families had a good weekend.

The following is a record of what was done during the past week and a forecast of the next week.....

Page 2: TW@ESI 24th April 2016

A General Note before we startWe now have all glass doors installed. The following are the next steps a) Intercom installation on new door – we have done

progress on commissioning this.b) Lighting, power, data installation in design and

commissioning offices- target for these to be completed and all of us to move back to our places – by End April 2016- we can achieve this – lets work together to do this

Page 3: TW@ESI 24th April 2016

Projects and deadlines

• 15_044_Hilton_Restaurant_Kitchen_AHU and 15_034_Hilton_Calorifier_Monitoring. We have managed to start up all equipment- We need a date from CVA/CCI on when we can have some basic closed loop controls installed and commissioned. Basic controls will now be installed early next week

• 15_033_Westin_7-AHU- Most of the T&C should by now be completed. Pending is documentation

Page 4: TW@ESI 24th April 2016

Projects and deadlines• 14_001_Fadalah-There are some snags here

which are to be resolved (by others)• Projects 12_026 SCM Buildings 02, 03, R3 & R4

and 12_027 Security Systems Parliament- are still pending projects and we need to tackle these with our internal re organisation

• 13_070_SCM Lagoona_Pump room- We have pulled most cables .All terminations possible are to be completed ASAP

Page 5: TW@ESI 24th April 2016

Projects and deadlines• 15_008 - Aurobindo PH02 BMS- We have made

progress on commissioning here- we will also soon need to come up with a plan and target date here.

• 13_052 New offices- Now a target is – Complete all installations and everyone to move back to their places by end of April 2016

• 14_089_MGA- installation of 2 x readers and 2 x REX – this is a very urgent project which Clifton and Dennis will be tackling

• 12_027- Parliament installation of St James lift intercom and DAC system, this too , is a very urgent project which Clifton and Dennis will be tackling

Page 6: TW@ESI 24th April 2016

DesignLast week• MDH MAU - 5x print-outs of ‘For Construction’ old

drawings, all on A4.• Life Sciences - implemented JGH hand-marks

accordingly. - Life Sciences - Prints for O&M all drawings except Panel Drawings

• Hilton – taken note of Terminating Matrix feedback• MDH MAU – Hand-over engraved labels to JGa @

MDH – concluded Rivets for above engraved labels• OVT – Concluded both set of P&IDs with TBr and

Started on Plan Drawings

Page 7: TW@ESI 24th April 2016

DesignNext Week:• Conclude Siggiewi As Built with Clifton• Life Sciences - start gathering Panel Drawings

from Clifton, and implement accordingly.• Life Sciences - Print 1 set Panel Drawings for

MPa O&M• OVT – continue & conclude Plan Drawings• AAP – Start design (P&IDs), get Points list from

TBR first

Page 8: TW@ESI 24th April 2016

InstallationPast week:– Repairs on PA-VA system at SCM– Re routed GO Telephones main cable to new server

room at ESI offices– Design office second and third fix ready and

energized– Design office and corridor painting 70% ready

Page 9: TW@ESI 24th April 2016

InstallationNext week:– Complete design office and corridor– Move intruder panel (RIO) to new premises– Painting at ESI offices– Install a canopy above MCC-1 at Westin– Pass cables and commission at SCM-MGA for DAC– Start commissioning at Hilton 15_044– Plan works on new lift at City Gate (Parliament)

Page 10: TW@ESI 24th April 2016

Panel BuildThere are no Panel Build activities at this point

Page 11: TW@ESI 24th April 2016

Mater DeiThe following are the tasks being worked on and planned for the next weeks• FIELD DEVICES CHECKS FROM SITE E01-CC1, E02-CC1, EP1-CC1• COORDINATED FRIDGE / FREEZER TEST BETWEEN ESI AND BIOMEDICAL - APRIL• QUARTERLY REVISED BMS DOCUMENTATION /QUARTERLY BACKUP /QUARTERLY BACKUP -

EACH CPU DATA• BMS Field Devices PPM -A01-CC1. AP1-CC1 / A03-CC1. A03-CC3 / A02-CC1. A02-CC2, AP2-

CC1• Coordinated Checks of Alarms from 3rd party devices A01-CC1, AP1-CC1, A02-CC1, A02-

CC2, AP2-CC1, A03-CC1, A03-CC3 and Various REF Equipment• PANEL THERMOGRAPHICAL IMAGES A01-CC1, AP1-CC1, A02-CC1, A02--CC2, AP2-CC1, A02-

CC1, A03-CC3• MCC PANEL CHECKS C01-CC1, CP1-CC1. C01-CC2, C02-CC1, C03-CC1, C04-CC1, D05-CC1,

C05-CC1, C07-CC1, C07-CC2, C08-CC1, CP2-CC1 CF1-CC1• MCC PANEL CHECKS A01-CC1, AP1-CC1. A02-CC1, A02-CC2, AP2-CC1, A03--CC1, B01-CC1,

BP1-CC1, B02-CC1, BP2-CC1, B03-CC11• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Quotation works new angiography project• WinCC upgrade HMI D06-CC2 / D07-CC2/ HMI D09-CC1- We have done quite some

progress here- well done!!

Page 12: TW@ESI 24th April 2016

Development and Commissioning• We have done large important steps on finishing off the

Parliament we need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION- we have an urgent quote to implement on Parliament St James lift (intercom and DAC readers)

• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• Life Sciences- We have also concluded with Training now... Documentation and some snags are pending

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we awaiting the client

Page 13: TW@ESI 24th April 2016

Development and Commissioning• OTM urgent jobs and snags were also done in the last weeks• Another project that needs attention is CCA Villa ... There are

still some snags to be addressed –intruder alarm integration• Oncology 14_066- We have done most of the work here and

are waiting from Panta on this• The Siggiewi Primary school project – we need to close off

with data collection , snags and documentation here• Aurobindo we are proceeding with software development

and we have done quite some progress – we are also now commissioning this project- we will need to come up with a plan here.

Page 14: TW@ESI 24th April 2016

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- We are

presently working on a task list and POW as well as setting up the test rigs

Page 15: TW@ESI 24th April 2016

Sales and Business Development

• We have been working on a quote for CCTV at Enemalta and quotes for variations for existing projects.

• We are also working to close off a large project at Meridien

• I also urge you to follow updates and new information on www.esimalta.com

Page 16: TW@ESI 24th April 2016

• More lessons to follow shortly – this next week

Page 17: TW@ESI 24th April 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 18: TW@ESI 24th April 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• Have a good week