1 11-06-2007 GENERAL REVISION - ISSUED FOR IMPLEMENTATION DDC DRC HOD 0 26-06-2000 ISSUED FOR IMPLEMENTATION DDC DRC HOD Rev . No Date Purpose Prepared by Reviewed by Approved by Template No. 5-0000-0001-T1 Rev. 1 Copyrights EIL – All rights reserved Document No. 8-2744-1003 Rev. No. 1 Page 1 of 15 PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM FOR LSTK CONTRACT PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM FOR LSTK CONTRACT THIS SHALL FORM PART OF BID DOCUMENT

Upload: vuongxuyen

Post on 01-Feb-2018

255 views

Category:

Documents


12 download

TRANSCRIPT

Page 1: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

1 11 - 0 6 - 2 0 0 7 GENERAL REVISION - ISSUED FOR IMPLEMENTATION

DDC DRC HOD

0 26 - 0 6 - 2 0 0 0 ISSUED FOR IMPLEMENTATION DDC DRC HOD

Rev. No

Date Purpose Prepared by Reviewed by Approved by

Template No. 5-0000-0001-T1 Rev. 1 Copyrights EIL – All rights reserved

Document No. 8-2744-1003 Rev. No. 1

Page 1 of 15

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM FOR LSTK CONTRACT

THIS SHALL FORM PART OF BID DOCUMENT

Page 2: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 2 of 15

Abbreviations: LSTK - Lumpsum Turnkey PMC - Project Management Consultant MR - Material Requisition AFC - Approved for Construction WBS - Work Breakdown Structure UOM - Unit of measurement PR - Purchase Requisition PO - Purchase Order P&ID - Piping & Instrumentation Diagram

Document Drafting Committee Members: Mr. SP Sinachoudhury Mr. R Mohan Mr. MK Jain Mr. TK Nanda Mr. R Shailendra Mr. SS Madan Mr. KN Choudhary Mr. Sudershan Kumar Document Review Committee Members: Mr. AK Gautam Mr. VK Sawhney Mr. VL Rajani Mr. R Mohan

Page 3: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 3 of 15

CONTENTS Clause Title Page No. 1.0 INTRODUCTION 4 2.0 DEFINITIONS 4 3.0 ABBREVIATIONS 4 4.0 DOCUMENTS ALONG WITH BID 4 5.0 AFTER AWARD OF WORK 5 6.0 PROJECT SCHEDULES 6 7.0 UPDATION OF PROJECT SCHEDULES 10 8.0 REVIEW MEETINGS 11 9.0 PROGRESS REPORTING 12 10.0 BULK MATERIAL CONTROL 13 11.0 PLANNING PACKAGE 14 12.0 CONTROL ROOM DISPLAY 14 13.0 SOFTWARE PACKAGES 15 14.0 PROVISION OF COMPUTER FACILITIES 15

ATTACHMENT I PROJECT SCHEDULE HIERARCHY (1 Sheet) II WORK BREAK DOWN STRUCTURE (1 Sheet) III MONTHLY PROGRESS REPORT (37 Sheet) IV FLOW OF DOCUMENTS (3 Sheet)

V INDICATIVE PROGRESS MEASUREMENT WEIGHTAGE AT VARIOUS LEVELS (3 Sheet)

Page 4: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 4 of 15

1.0 INTRODUCTION

To ensure timely completion, the Lumpsum Turnkey (LSTK) Contractor shall establish and maintain an effective Planning, Scheduling, Monitoring and Control system, including mobilization of required number of professionally qualified and experienced Planning Engineers for design office and construction site. The system shall be capable of accurate and timely prediction of trend, evolution of adequate preventive actions for likely slippages, and formulation of suitable catch-up schedule for delays, if any, that have occurred.

Schedules, reports and documents to be prepared and submitted by the LSTK contractor for review of Client/ Project Management Consultant (PMC) at various stages and details of meetings to be held are described here.

2.0 DEFINITIONS

Work Breakdown Structure (WBS) Work Breakdown Structure is a diagram that depicts various units in a project and each unit is detailed with work items/equipments and major workloads. Design Office

Where Residual Basic Engineering, Detailed engineering, procurement activities for the contract are performed by LSTK contractor. Functions Function means basic components of the projects e.g. Residual Basic Engineering, Detailed engineering, ordering, manufacturing & delivery, construction and commissioning. Each function is divided into various disciplines. In case of engineering, various disciplines are architecture, civil, structure, piping etc.

3.0 ABBREVIATIONS LSTK - Lumpsum Turnkey PMC - Project Management Consultant MR - Material Requisition AFC - Approved for Construction WBS - Work Breakdown Structure UOM - Unit of measurement PR - Purchase Requisition PO - Purchase Order P&ID - Piping & Instrumentation Diagram

4.0 DOCUMENTS ALONG WITH BID

The LSTK bidder shall submit following documents along with the bid: a) Proposed Overall Project Schedule in network form showing all the details unit wise. b) Write up on Project Planning, Scheduling, Monitoring and Control system (proposed). c) Organizational set up for Planning, Scheduling, Monitoring & Control at LSTK

Contractor’s Design Office and Site Office. d) Progress Measurement Methodology with details such as weightages, milestones,

frequency etc. e) Project execution methodology.

Page 5: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 5 of 15

f) Function wise Resource Deployment Schedule (HO & Site manpower and construction equipment).

g) Softwares to be used for planning and material control. h) Statement confirming compliance to the “Planning, Scheduling, Monitoring and Control

System” requirements regarding contents of the documents to be submitted to Client/PMC.

5.0 AFTER AWARD OF WORK 5.1 90 DAYS FRONT END SCHEDULE

The LSTK Contractor shall prepare and submit a detailed 90 days front-end schedule within one week of award. Pending finalisation of Overall Schedule, this schedule shall be the basis of monitoring of front-end activities. The schedule shall cover all activities to be carried out during initial 90 days period of the contract. The schedule shall be reviewed in the kick-off meeting.

5.2 KICK OFF MEETING

A Kick Off Meeting shall be organised within two weeks of award of contract. The meeting shall be attended by Client’s and PMC’s representatives. During the meeting, the following with respect to Planning, Scheduling, Monitoring and Control system shall be discussed and finalized:

1. Planning deliverables required for Project Monitoring and Control. 2. Work Breakdown Structure for Project Schedules, organisation and level of detailing

for Overall Project Schedule and Functional Schedules. 3. Procedure for Project Planning, Scheduling, Monitoring & Control system including all

reporting formats. 4. Progress Measurement Methodology and Unit, Function, Discipline, and Deliverable

wise weightage breakdown (refer Attachment V for indicative weightage). 5. List of engineering deliverables with indicative schedule for submission. 6. List of unit wise milestones to be included in the network, in addition to milestones

specified in the Contract, if any (the number of milestones shall be at least 2 to 3 per unit per month).

7. List of critical equipment and materials for the fortnightly expediting report to be issued by the LSTK Contractor.

8. Procedure for Bulk material control. 9. Cut off dates, distribution list with number of copies and Project calendar indicating

submission of various planning documents and revisions. 10. Any other document as required.

5.3 PROGRESS MEASUREMENT METHODOLOGY

The LSTK Contractor shall submit during Kick Off Meeting, the detailed methodology of progress measurement of Residual Basic Engineering, Detailed Engineering, Ordering, Manufacturing & Delivery, Sub-contracting, Construction and Commissioning for review by Client/PMC. LSTK Contractor shall also furnish the methodology of progress measurement for sub-contracted packages such as DM plant, Cooling tower etc. and integration of the same with the overall progress.

Page 6: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 6 of 15

During the Kick Off meeting, Client/PMC shall finalise weighted values to be used for the following:- a) Unit wise within the package, if applicable. b) Function wise within each unit. c) Milestone weightage within each deliverable.

Effort based weighted values for the following, along with the basis of their derivation, shall be submitted by LSTK Contractor for review by Client/PMC, and the comments if any shall be incorporated by LSTK Contractor before submission of functional schedules that use these weighted values as the basis: a) Discipline wise within each function. b) Deliverable level weightage Percentage. Progress figures at Unit / Function / Discipline level shall be summarized from deliverable level and indicated in the functional schedules.

6.0 PROJECT SCHEDULES

Following schedules shall be prepared and submitted by LSTK contractor to Client/PMC for approval. A hierarchy of all schedules to be generated by LSTK Contractor is shown in Attachment – I.

6.1 OVERALL PROJECT SCHEDULE NETWORK (Summarised & Detailed)

The LSTK Contractor shall submit within four weeks of award a network based detailed overall project schedule (unit wise) on time scale, for all units in the package and all functions of the work along with a Work Breakdown Structure indicating unit wise workload (sample format as Attachment - II). The schedule shall highlight interface activities in the scope of Client/PMC and clearly reflect strategies and philosophy of execution. Major milestones for each unit shall be depicted at the beginning of the network. The project schedule shall be developed for contractual duration and or target duration decided with Client/PMC. Grace period, if any as per contract shall not be considered for schedule. The schedule shall be reviewed by Client/PMC and the comments if any shall be incorporated and the schedule shall be issued for implementation within one week from the receipt of comments. This schedule once approved by Client/PMC shall not be revised without the prior written permission of Client/PMC. Overall Project Schedule Network (Summarised) will be derived from Overall Project Schedule Network (Detailed) and will include all major / critical activities & summarised activities at macro-level. Overall Project Schedule Network (Detailed) shall be used for trend / detailed analysis whereas summarised Overall Schedule will be used to project status at a glance to higher management along with the Monthly Progress Report.

6.2 FUNCTIONAL SCHEDULES

The LSTK Contractor shall prepare resource based detailed Unit wise functional schedules for all functions in spreadsheet format in line with overall project schedule for monitoring and control. LSTK Contractor shall submit the same within six weeks of award for review except construction schedule, which shall be submitted within eight weeks of award. Unit wise “S” curves for schedule progress shall also be submitted along with the functional

Page 7: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 7 of 15

schedules. The schedule shall be reviewed by Client/PMC and comments, if any, shall be incorporated and issued for implementation within one week from receipt of comments. The Schedule “S” curves shall remain firm during the execution of the project. LSTK Contractor shall also ensure preparation, submission and updation of all functional schedules as described herein for all sub contracted packages like Heaters, DM Plant, WWTP, Cooling Tower, Nitrogen Plant etc.

6.2.1 Residual Basic Engineering Schedule

The LSTK Contractor shall submit a Unit wise schedule for all Residual Basic Engineering Activities like finalisation including updation (incorporating vendor data) of P&IDs for process units and utilities & offsites, release of line schedules, finalisation of process data sheets for equipment etc. as per page 14 of Attachment - III.

6.2.2 Detailed Engineering Schedule

The LSTK Contractor shall submit a Unit wise schedule of all engineering deliverable/documents such as AFC drawings, Isometrics, Specifications, Material Requisition, Purchase Requisition, Design calculations etc. as per page 14 of Attachment - III.

6.2.3 Ordering Schedule

The LSTK contractor shall submit a Unit wise schedule for all ordering activities as per pages 17 &18 of Attachment - III. This shall include all MRs listed in Engineering Schedule.

6.2.4 Manufacturing / Delivery Schedule

The LSTK contractor shall submit a Unit wise schedule for all Manufacturing & Delivery activities as per page 22 of Attachment - III. These shall include all orders listed in the Ordering Schedule. The progress at Function/Unit level shall be summarised considering weighted values of tagged items and bulk material to report overall Manufacturing and Delivery progress. LSTK Contractor shall also submit along with Weekly Progress Report, status of drawings and documents for all vendors on whom orders have been placed, as per page 16 of Attachment - III. In addition to the above, for critical items as mutually agreed between LSTK Contractor and Client/PMC, LSTK Contractor shall ensure that vendors prepares and updates logical networks for Manufacturing & Delivery and submit the same on weekly / monthly basis to Client/PMC if asked for.

6.2.5 Sub-contracting Schedule

The contractor shall submit a Unit wise schedule for all Sub-contracting activities as per page 23 of Attachment - III. This shall include all tenders envisaged for the Project.

6.2.6 CONSTRUCTION SCHEDULE

The LSTK Contractor shall prepare and submit a Detailed Construction Schedule unit wise for Client/PMC review. The LSTK Contractor shall describe resources (manpower and machinery) required to be mobilised. The schedule shall have interface with Engineering,

Page 8: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 8 of 15

Ordering and Manufacturing & Delivery activities and also interface required from Client/PMC. The LSTK Contractor shall also define construction quantity for each activity. LSTK Contractor shall finalise discipline wise Construction ”S” Curves and quantum schedule.

6.3 OVERALL ‘S’ CURVES

The LSTK Contractor shall prepare unit wise and Overall “S” curves showing cumulative schedule progress taking into consideration “S” curves for Residual Basic Engineering, Detailed Engineering, Ordering, Manufacturing & delivery, Sub-contracting and Construction “S” Curves. The overall “S” curves shall be updated immediately after finalisation of construction schedule. The overall “S” curves shall be submitted for Client/PMC review, with necessary back ups and shall form part of monthly progress report.

6.4 OTHER SCHEDULES

The control philosophy for construction activities involves monitoring at the unit/discipline/subcontract/area level from the initial stages of construction and supplementing it with monitoring at the system/ loop level as construction advances towards mechanical completion/ pre-commissioning/ commissioning stages. To meet this objective, the following schedules/deliverables shall be prepared by LSTK Contractor.

6.4.1 SUB CONTRACTOR SCHEDULE

LSTK Contractor shall ensure preparation of detailed schedules for all works in the scope of each subcontract awarded by them within two weeks of award of sub-contract, for monitoring of construction progress. These schedules shall have quantity/work load details of all work items and “S” curve for each of the sub contracts. The LSTK Contractor shall ensure updation of the same on fortnightly basis. Client/ PMC reserve the right to check these schedules at any time.

6.4.2 MONTHLY PROGRAMME

LSTK Contractor shall prepare monthly quantitative programmes in line with functional schedules for all the functions. These programmes shall be made keeping in view the cumulative targets as set in the schedules backlog and work front available in terms of vendor inputs, drawings, materials and access as applicable. The programmes for construction shall be accompanied by list of resources (Manpower & machinery) planned to be deployed to achieve the programmes. Current hold ups (Drawing, Materials, etc. if any) required to be resolved for the execution of the programmes made, shall be indicated with proposed action plan for resolution.

Monthly programmes other than Construction shall be submitted to Client/PMC Design Office within three calendar days of monthly progress report cut-off date. In case of Construction, monthly programme shall be finalised in consultation with Client/PMC’s site representative and submitted within two calendar days of monthly progress report cut-off date. In all matters concerning the extent of targets set out in monthly programme, the decision of Client/PMC shall be final and binding.

The monthly programmes shall be further broken down into weekly programmes and indicated in weekly reports for closer monitoring of progress.

Page 9: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 9 of 15

6.4.3 LOOPWISE PIPING COMPLETION SCHEDULE

LSTK Contractor shall prepare micro-level schedule for completion of piping activities and submit to Client/PMC for review at least two months before the start of hydrotesting as scheduled in Unit wise Construction schedules. The schedules shall cover unit wise/ system wise/ loop wise, the following activities remaining as of the date of preparation:

a) Status of balance piping materials (Details of items, quantities, vendors, POs and

expected date of receipt at site to be indicated) b) Status of balance equipment and in-line instrument items (Details of tags, vendors and

POs and expected receipt to be indicated) c) Welding (inch dia) workload separately for shop fabrication and field welding. d) Erection and supporting (inch meter) e) Radiography (number of joints) f) Stress relieving (number of joints)

g) Hydrotesting (inch meter) 6.4.4 SYSTEMWISE COMPLETION SCHEDULE

After preparation of loop wise micro-level schedule for completion of piping activities, LSTK Contractor shall prepare Unit wise/ System wise micro-level schedule for completion of remaining activities. The schedules shall be submitted by LSTK Contractor to Client/PMC for review, 6 weeks before scheduled system completion as per Unitwise Construction Schedules. The schedules shall cover disciplinewise remaining activities as mentioned below

a) Balance civil and structural work itemwise

b) Balance Mechanical erection work tagwise c) Alignment of Rotating Equipment d) Balance Electrical work e) Balance Instrumentation works including loop checking

f) Schedule for issue of prescribed formats for handing over of system such as Format I : Information regarding system completion Format II : Checklist

Format III : Ready for pre-commissioning / Mechanical completion certificate Format IV : Ready for commissioning certificate Format V : Completion of commissioning certificate

The description of the system and loop numbering mentioned in the schedules at 6.4.3 & 6.4.4 above shall be as agreed with Client/PMC (Construction / Commissioning group). The schedule shall be resource based and shall indicate total and remaining workload for each activity.

6.4.5 PRE-COMMISSIONING/COMMISSIONING SCHEDULE

LSTK Contractor shall prepare unitwise / systemwise pre-commissioning/ commissioning micro-level schedule. These schedules shall be submitted by LSTK Contractor to Client/PMC for review two months before the Mechanical Completion milestone or one month before starting pre-commissioning activities, which ever is earlier.

Page 10: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 10 of 15

The schedules shall be developed after considering the pre-commissioning/ commissioning priorities & interface requirements and identify requirement of licensor’s/ vendor’s representatives stay at site. The description of system/ sub system mentioned in the schedule shall be as agreed with Client/PMC (Construction/ Commissioning groups).

6.5 CATCH-UP SCHEDULE

The LSTK Contractor shall generate and submit catch-up schedule for completion of all balance activities without change in contractual completion date with detailed resource reinforcement as and when asked by Client/PMC. The catch-up schedules shall be submitted to Client/PMC for review. Accordingly the “S” curves for catch-up schedules shall be made and shown along with the original schedules and actual “S” curves. During updation of overall project schedule, the catch-up schedules shall be shown in bar charts along with the original schedule.

7.0 UPDATION OF PROJECT SCHEDULES

The various schedules as described herein shall be updated for submission to Client/PMC. Updation of the schedule is to determine the project trend, with the objective of taking preventive/ corrective action. The reflection of delayed / anticipated completion by way of current trend does not in any manner absolve the LSTK Contractor of his contractual obligations as per the contract.

7.1 OVERALL PROJECT SCHEDULE 7.1.1 Overall Project Schedule Network (Detailed)

The schedule shall be updated on monthly basis and submitted in linked bar chart form in A4 size in soft form (native format). The updation shall be compared with the original schedule.

While updating, the following shall be considered:

- Actual date of start and completion for the activities. - Contractual completion dates for vendors and sub-contractors/turnkey agencies, any

change of duration due to offloading of vendors/sub-contractors/turnkey agencies to be reflected.

- Duration of activities not yet started shall remain the same as per the original schedule. - Anticipated dates of activities in progress. - Addition/deletion of any activity if required or any change on job logic. - Any change in drawing/material availability or change in activity duration. - Any change in resource planning. - Change in philosophy/strategy in execution of balance works, keeping in mind the

actual status of the project.

7.1.2 Overall Project Schedule Network (Summarised)

The schedule shall be as derived from the updated Overall Project Schedule Network (detailed) as above on monthly basis and submitted in linked bar chart form in A4 size with monthly progress report. The updation shall be compared with the original schedule. Format for updated schedule will be as per Attachment-III page 31 of 37.

Page 11: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 11 of 15

7.2 FUNCTIONAL SCHEDULES

The updated functional schedule trend and original schedule shall be shown together and submitted to client / PMC on monthly basis, as part of Monthly Progress Report.

While updating, the following aspects shall be considered:

- Actual dates of start and completion for the activities. - Actual work progress/balance work - Contractual completion date for sub-contractors and vendor delivery not reflected

earlier. - Any change in estimated activity durations - Material and drawing availability - Interfaces of one agency with other agencies

- Various statutory reviews/approval - Interfaces between unit & offsite / utilities i.e. permanent power & water, waste

disposal etc. - Any change in execution logic/philosophy and engagement of number of agencies/

sub-contractors and resource planning/ offloading if resorted to.

7.3 OTHER SCHEDULES

The following schedules shall be updated on a weekly basis and submitted to Client/PMC before the weekly review meeting at site in bar chart format. The updated schedule trend shall be compared with original schedule.

- Loopwise piping completion schedule - Systemwise completion schedule - Pre-commissioning/commissioning schedule

8.0 REVIEW MEETINGS

The LSTK Contractor shall present project status, project highlights and action plan as applicable at various review meetings as described below. The presentation materials shall be submitted by LSTK contractor to Client/PMC at least two days before the date of the meeting for management level review meetings and Monthly/ Fortnightly review meetings.

8.1 Management level Review Meeting Level of participation : Senior management of client, PMC and LSTK contractor.

Agenda frequency and venue : to be decided by Client/PMC.

8.2 Monthly/Fortnightly Review Meeting

Level of participation: Client, PMC and LSTK Contractor Agenda: 1) Status against various commitments made during the previous review meetings 2) Monthly programme v/s Progress Status/Statistics 3) Project Completion Outlook

4) Areas of concern with action plan

Page 12: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 12 of 15

5) Catch-up schedule.

Venue and timing of the meeting shall be decided by Client/PMC. Frequency of Meeting (Monthly or Fortnightly) shall also be decided by Client/PMC, based on criticality of the project status.

8.3 Weekly Review Meeting 8.3.1 For LSTK Design Office activities

Level of participation: Client, PMC & LSTK Contractor

Agenda: 1) Weekly programme v/s progress status/Statistics for Residual Basic Engineering, Detailed Engineering, Ordering, Manufacturing & Delivery and Sub-contracting.

2) Action taken for slippages. 3) Programme for next week 4) Status of various resources deployed Vs planned

8.3.2 For Site Activities

Level of participation: Client, PMC & LSTK Contractor

Agenda: 1) Work front availability

2) Weekly programme v/s Achievement 3) Resource mobilisation 4) Reasons for shortfall 5) Catch-up Schedule 6) Progress statistics 7) Programme for next week. 8) Status of resources deployed v/s planned.

Venue and timing of Weekly Review Meetings for shall be decided by Client /PMC.

9.0 PROGRESS REPORTING

The LSTK Contractor shall submit the following reports on regular basis for Client/PMC’s information/ review.

9.1 Monthly Progress Report

The report shall be submitted on monthly basis within 5 calendar days from cut-off date covering overall scenario of the project. A copy of the specified formats for the report is enclosed as Attachment – III.

9.2 Weekly Progress Report (Overall)

This report shall be prepared by LSTK Contractor and issued on weekly basis to Client/PMC with in three days of the cut off date. The report shall include the following:

• Executive Summary • Project highlights with dates of achievements.

Page 13: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 13 of 15

• Project exception (work programmed but not achieved with reasons for non-achievement) and work programmed for next week

• Critical areas • Action taken / to be taken for slippages • Progress statistics • Activities planned for next week • Status of Outstanding Documents from Licensor/PMC

This shall cover both for LSTK Contractor’s Design Office activities and construction activities at site.

9.3 Weekly Progress Report (Construction)

This report shall be prepared by LSTK Contractor and submitted on weekly basis within 2 calendar days from cut off date. The report shall cover following items:

• Progress statistics • Work item wise quantity completed against programme for the week including

reasons for shortfall • Programme for next week • Front available • Constraints, if any. • Resources deployed against planned with reasons for shortfall in resource

deployment • List of equipment/materials received at site during the week

9.4 Daily Progress Report (Construction)

LSTK Contractor shall submit (daily before noon), for status of previous working day a daily report including the following

Programme v/s Progress for the day Programme for next day Important achievements for the day Materials / Equipment receipt for the day. Man power / Machinery deployment report - Required v/s Deployed.

9.5 Expediting Report

LSTK Contractor shall submit fortnightly expediting reports based on his representative’s visit to vendor’s work for orders where delivery of materials is critical to project completion. A list of such critical items/vendors shall be specified by Client / PMC during the kick off meeting or at a later date.

In addition to the above, Client / PMC may request expediting report based on visit of LSTK Contractor’s representatives in case of orders which though not critical at the time of order placement become subsequently critical during project execution due to any reason.

10.0 BULK MATERIAL CONTROL

The LSTK Contractor shall follow an integrated material control system for the project. The system shall be such that material identification in the design office, procurement and

Page 14: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 14 of 15

allocation, are all channelised and controlled in an orderly manner. The LSTK Contractor shall follow material identification like unitwise/system wise/area wise/zone wise/Linewise, and shall give construction orientation to material control. The LSTK Contractor, right from the beginning, at the design office stage, shall start identifying materials system wise or area wise as indicated above. The system shall be based upon tracking of material requisitioning, placement of purchase order, manufacturing at vendor’s shop up to receipt at site for making the material available for performing planned and sequential construction work.

Through periodic reviews, the LSTK Contractor shall have a system of generating Hold up reports well in advance to identify exception on material availability and to track such material by the expeditors through a systematic follow up procedure from the vendors.

The LSTK contractor shall make a presentation on the bulk material control system proposed to be implemented by them for the project during the kick-off meeting.

LSTK Contractor shall submit the following reports on monthly basis for each unit as well as summary level.

• Bulk Material Status Report • Material hold up/shortage report.

11.0 PLANNING PACKAGE

Details of time of submission, frequency of submission and tentative number of copies required for all documents to be submitted by the LSTK contractor are tabulated in attachment IV.

Once the majority of the schedules are finalized, the LSTK contractor shall compile the same and submit in the form of a Planning Package. (Not later than 12 weeks of award of the job). The Planning Package shall consist of the following:

- Introduction - Overall Project Schedule Network (Summarised) - 90 days front end schedule - Project WBS/ Work load - Progress measurement methodology - Overall Project schedule Network (Detailed) - Functional schedules - Progress ‘S’ curves - Sample reporting formats - Manpower and Machinery deployment schedule LSTK Contractor shall submit reports, updated schedules, programmes etc. as described herein till the completion of all work in the scope of the contract. No chapter/annexure of any report shall be deleted without prior written approval of Client/PMC.

12.0 CONTROL ROOM DISPLAY

LSTK Contractor shall have conference room at site to display charts featuring salient static information of the project, schedules, status of progress, resource deployment, rainfall

Page 15: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Template No. 5-0000-0001-T2 Rev. 1 Copyrights EIL – All rights reserved

PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM

FOR LSTK CONTRACT

Document No. 8-2744-1003 Rev. No. 1

Page 15 of 15

record, block flow diagram, plot plan, work break down structure etc. The status shall be updated at least on weekly basis. The objectives of the control room are to provide information at a glance to project personnel including the management of clients and PMC.

13.0 SOFTWARE PACKAGES

For schedule preparation and updation, The LSTK contract shall use Internationally acclaimed network analysis package such as Primavera Project Planner, Project Scheduler, MS Project etc. compatible with that being used by Client/PMC and submit the backup of the schedules (native format) along with the hard copy whenever submission of the schedules are called for. The electronic files for all other deliverables shall be compatible with Microsoft Office.

14.0 PROVISION OF COMPUTER FACILITIES

LSTK Contractor shall provide the following facilities for use by PMC at LSTK Contractor’s design office:

A. PC with latest hardware, A3 size colour laser jet printer and Internet Connection. B. Software:

i) Network Analysis Package such as Primavera Project Planner, Project Scheduler, MS Project etc.

ii) MS Office iii) E-mail and internet facilities

Page 16: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

ATTACHMENT - I

A B C DSUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR

SUB-CONTRACTORSCHEDULE SCHEDULE SCHEDULE SCHEDULE

(UNITWISE)

SUB-CONTRACTOR SUB-CONTRACTOR SUB-CONTRACTOR

UNITWISE/DISCIPLINEWISE UNITWISE/DISCIPLINEWISE DELIVERY (UNITWISE)FOR ENGINEERING FOR ORDERING MANUFACTURING & FOR SUB CONTRACTING

FUNCTIONAL * FUNCTIONAL *SCHEDULE SCHEDULE SCHEDULE FOR SCHEDULE

(UNITWISE)

FUNCTIONAL * FUNCTIONAL *

PROJECT SCHEDULE HIERARCHY (TO BE GENERATED BY LSTK CONTRACTOR)

OVERALL PROJECT SCHEDULE

CONSTRUCTION SCHEDULE (UNITWISE)

90 DAYS FRONT END SCHEDULE(UNITWISE)

PACKAGE CONTRACTOR

CATCH UP SCHEDULE(AS APPLICABLE)

CATCH UP SCHEDULE(AS APPLICABLE)

LEVEL - II

LEVEL - I

LEVEL - III

Page 17: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

ATTACHMENT- II

WORK BREAKDOWN STRUCTURE (TYPICAL)

UNIT - 1 (CAPACITY,

LICENSORS NAME) VESSELS/ HEATREACTORS COLUMNS DRUMS EXCHANGER HEATERS COMPRESSORS

(HEAT DUTY)

NOS. NOS. NOS. NOS. NOS. NOS.MATL MATL MATL MATL MATL STR STEEL KW RATINGSIZE & WT MAX. WT & HT MAX. SIZE & WT INDG/IMP REFRACTORY MOTOR/TURBINE DRIVENINDG/IMP INDG/IMP INDG/IMP TUBES M/ IN DIA INDG/IMP

BURNER/SOOT BLOWERS

CIVIL/PUMPS PIPING STRUCTURAL ELECTRICAL INSTN.

NOS. A/G & U/G RCC IN FDN NOS. OF PANELS INSTRNS. IND/IMPKW RATING (RANGE) KM ----- RCC IN S/STR TRANSFORMERS CONTROL CABLEMOTOR/TURBINE " DIA BRICK WORK MCC/PCC TUBES DRIVEN " MTR STRL STEEL CABLES HT &LT CONTROL PANELSINDG/IMP MATL LIGHTING

INDG / IMP

UNIT - 2 (CAPACITY,

LICENSORS NAME)

SIMILAR TO UNIT - 1PROJECT/PLANT

(CAPACITY)

UNIT - 3 (CAPACITY,

LICENSORS NAME)

SIMILAR TO UNIT - 1

UTILITY /OFFSITES

RAW WATER COOLING FIRE DM WATER STEAM NON PLANTSYSTEM WATER WATER SYSTEM SYSTEM BUILDINMGS

(CAPACITY) SYSTEM SYSTEM

PUMPS NO OF CELLS PUMPS CAPACITY BOILER CAPACITY NOS.PIPES PUMPS PIPE QUANTUM OF PIPE WORK COOLING TOWER

CWTP

STORAGE CIVIL/ YARD CONTROL OTHER UTILITYW.W.T.P. YARD STRUCTURAL PIPING ELECTRICAL ROOM SYSTEMS INCLUDING

(SIZE) C.P.D. (IF ANY)

TANKAGES RCC A/G SWITCH GEAR CONTROL PANELS SPHERES STRL STEEL MATERIAL TRANSFORMERS KM/IM CABLES NO. OF S/STN.

NOTE : ACTUAL QUANTUM / NOS. TO BE WRITTEN.

Page 18: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

ATTACHMENT - III

CLIENT

PROJECT LOCATION

P R O J E C T UNIT (IF APPLICABLE)

PMC :- M/s. ENGINEERS INDIA LTD., NEW DELHI.

MONTHLY PROGRESS REPORT PROGRESS REPORT NO. XX

UPTO____ (DAY) ______ (MONTH)_______ (YEAR) (REPORTING CUT-OFF DATE)

PREPARED BY : LSTK CONTRACTOR

PAGE 1 OF 37

INFORMATION/ACTION

DATE ISSUED FOR PREPD BY REVIEWED BY APPVD BY

DOCUMENT NO ___________

Page 19: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR PROJECT

MONTH & YEAR CLIENT PMC EIL PAGE 2 OF 37

TABLE OF CONTENTS

SECTION DESCRIPTION PAGE NO. I INTRODUCTION 3 II EXECUTIVE SUMMARY 4 III DETAILED STATUS 5 IV AREAS OF CONCERN WITH ACTION PLAN 6 V PROGRESS STATISTICS 7 VI MILESTONE STATUS 9 VII PROBLEMS / HOLD-UPS 10 ANNEXURES I PROGRESS CURVES 11 II STATUS REPORTS A CHRONOLOGICAL ACHIEVEMENTS 12

B.1 SUMMARY STATUS OF ENGINEERING DRAWINGS 13 B.2 DRAWING / DOCUMENT RELEASE SCHEDULE (DCI) 14 B.3 MATERIAL CONTROL INDEX (MCI) 15 C VENDOR/PACKAGE CONTRACTOR DRAWINGS AND DOCUMENTS STATUS 16 D.1 ORDERING STATUS (SUMMARY) 17 D.2 ORDERING STATUS (DETAILED) 18 E.1 EQUIPMENT DELIVERY STATUS (SUMMARY) 19 E.2 EQUIPMENT RECEIPT AND ERECTION STATUS (DETAILED) 20 E.3 BULK MATERIAL STATUS (SUMMARY) 21 E.4 MANUFACTURING / DELIVERY STATUS 22 F SUB CONTRACTING STATUS 23 G1 UNITWISE STATUS OF CONSTRUCTION QUANTITIES RELEASED 24 G2 QUANTITATIVE MONTHLY CONSTRUCTION PROGRESS STATUS 25 H STATUS OF CONSTRUCTION 26 I LOOPWISE HYDROTESTING STATUS 27 J SYSTEM HANDING OVER STATUS 28 K.1 UNITWISE DEPLOYMENT OF LSTK PERSONNEL AT CONSTRUCTION SITE 29 K.2 UNITWISE RESOURCE DEPLOYMENT STATUS - EQUIPMENT AND MACHINERY 30 L UPDATED OVERALL PROJECT SCHEDULE 31 M STATUTORY APPROVAL STATUS 32 N INVOICING STATUS 33 O STATUS OF WAIVER / DEVIATIONS 34 P DELAY ANALYSIS 35-36 Q PROJECT PHOTOGRAPHS 37 III OTHER REPORTS OTHER REPORTS SUCH AS - QUALITY REPORT - HEALTH, SAFETY AND ENVIRONMENT REPORT - COST REPORTS ETC. AS CALLED FOR IN THE OTHER SECTION OF THE BID PACKAGE. DISTRIBUTION AS PER DISTRIBUTION LIST IN CONTRACT.

Page 20: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR PROJECT

MONTH & YEAR CLIENT PMC : EIL Page 3 of 37

I - INTRODUCTION CLIENT : PROJECT LOCATION : PMC : M/s. EIL, NEW DELHI DESIGN CAPACITY :

UNIT CAPACITY LICENSOR

CONTRACT VALUE : _____Rs.(IN CRORES) SCOPE OF WORK : PROJECT TARGET DATES (UNIT WISE) EFFECTIVE START DATE : TARGET COMPLETION DATE : CONTRACTUAL COMPLN DATE : CONTRACTUAL COMMNG DATE : (If Applicable) ANT. MECH COMPLN DATE : ANT. COMMG DATE : (If Applicable) PROJECT DURATION :_________ MONTHS TIME ELAPSED :__________MONTHS

Page 21: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR PROJECT

MONTH & YEAR CLIENT PMC : EIL Page 4 of 37

II - EXECUTIVE SUMMARY

EXECUTIVE SUMMARY SHALL SERVE AS SYNOPSIS OF THE PROJECT. IT NEEDS TO FOCUS ON THE FOLLOWING : - OVERALL SCHEDULE AND ACTUAL PROGRESS TO BE SPECIFIED

(CUMULATIVE AND DURING THE MONTH)

- LIMIT IT TO ONE PAGE AS FAR AS POSSIBLE. - MAJOR MILESTONES ACHIEVED DURING THE MONTH. - CONTINGENCY/ CRASH ACTION PLAN FOR MOST CRITICAL AREAS, IF ANY,

BEING FORMULATED / IMPLEMENTED. - SIGNAL FOR THE AREAS LIKELY TO BECOME CRITICAL. - ANY OTHER ISSUE NOT LISTED ABOVE.

Page 22: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR PROJECT

MONTH & YEAR CLIENT PMC : EIL Page 5 of 37

III - DETAILED STATUS (UNITWISE / DISCIPLINEWISE)

A. RESIDUAL BASIC ENGINEERING - ACTIVITIES COMPLETED DURING THE MONTH - ACTIVITIES PLANNED FOR THE NEXT MONTH B. DETAILED ENGINEERING - ACTIVITIES COMPLETED DURING THE MONTH - ACTIVITIES PLANNED FOR THE NEXT MONTH C. PROCUREMENT i) ORDERING - ACTIVITIES COMPLETED DURING THE MONTH

- ACTIVITIES PLANNED FOR THE NEXT MONTH

ii) MFG/DELIVERY - ACTIVITIES COMPLETED DURING THE MONTH - ACTIVITIES PLANNED FOR THE NEXT MONTH D. SUB-CONTRACTING - ACTIVITIES COMPLETED DURING THE MONTH - ACTIVITIES PLANNED FOR THE NEXT MONTH E. CONSTRUCTION /PRE-COMMISSIONING & COMMISSIONING - ACTIVITIES COMPLETED DURING THE MONTH - ACTIVITIES PLANNED FOR THE NEXT MONTH F. PACKAGE SUB-CONTRACTOR STATUS

PACKAGE SUB-CONTRACTORWISE STATUS TO BE GIVEN FUNCTIONWISE AS APPLICABLE) i) ENGINEERING ii) ORDERING iii) MANUFACTURING & DELIVERY iv) CONSTRUCTION - ACTIVITIES COMPLETED DURING THE MONTH - ACTIVITIES PLANNED FOR THE NEXT MONTH

Page 23: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT

PROJECT PMC : EILPAGE 6 OF 37

IV - AREAS OF CONCERN WITH ACTON PLAN (UNITWISE / DISCIPLINEWISE)

SR. IMPACT ON ACTION TARGET NO. AREAS OF CONCERN CONSTRAINTS SCHEDULE ACTION PLAN BY DATE

(IN MONTHS)

NOTE 1. THIS SHALL CONTAIN ONLY CRITICAL ITEMS/ISSUES WHICH ARE DIRECTLY AFFECTING THE PROJECT SCHEDULE

OTHER ITEMS CAN BE PLACED IN PROBLEMS & HOLD UPS CHAPTER.2 TARGET DATES SHALL BE FURNISHED WITH ACTION PLAN.

Page 24: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR PROJECT

V - PROGRESS STATISTICS

A OVERALL PROJECT PROGRESS DESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVE

COMPLEX SCHEDULE ACTUAL SCHEDULE ACTUALRESIDUAL BASIC ENGINEERINGDETAILED ENGINEERING ORDERINGMANUFACTURING/DELIVERYSUB-CONTRACTINGCONSTRUCTION COMMISSIONING

OVERALL PROGRESS - PHYSICAL Σ Α=100%B. PROCESS UNIT (UNITWISE)B.1 UNIT NAME

DESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVECOMPLEX UNIT SCHEDULE ACTUAL SCHEDULE ACTUAL

RESIDUAL BASIC ENGINEERINGDETAILED ENGINEERING ORDERINGMANUFACTURING/DELIVERYSUB-CONTRACTINGCONSTRUCTIONCOMMISSIONING

PHYSICAL PROGRESS UNIT- A1 A1 % 100

B.2 UNIT NAME

B.3 UNIT NAME

B.4 UTILITIES /OFFSITESDESCRIPTION WTD % AGE DURING THE MONTH CUMULATIVE

COMPLEX UNIT SCHEDULE ACTUAL SCHEDULE ACTUALRESIDUAL BASIC ENGINEERINGDETAILED ENGINEERING ORDERINGMANUFACTURING/DELIVERYSUB-CONTRACTINGCONSTRUCTION #COMMISSIONING

PHYSICAL PROGRESS UTILITIES /OFFSITES A4 % 100

MONTH & YEARCLIENT PMC : EILPAGE 7 OF 37

Page 25: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR

PROJECT

C. SUB CONTRACTED PACKAGES (PROCESS UNIT,UTILITIES & OFFSITES) C.1 PACKAGE - 1

DESCRIPTION WTD %AGE DURING THE MONTH CUMULATIVEw.r.t U/OFF UNIT SCHEDULE ACTUAL SCHEDULE ACTUAL

RESIDUAL BASIC ENGINEERING

DETAILED ENGINEERING ORDERING

MANUFACTURING & DELIVERY

CONSTRUCTION

COMMISSIONING

PHYSICAL PROGRESS RWTP X1 100

C.2 PACKAGE - 2

C.3 PACKAGE -3

D. MAJOR REASONS FOR SHORTFALL

NOTE:

3. UNIT WISE ALL SUBCONTRACTED PACKAGES TO BE REPORTED UNDER SUBHEADING "SUB CONTRACTED PACKAGE". 4. # CONSTRUCTION INCLUDES %AGE PROGRESS OF SUB-CONTRACTED PACKAGES IF ANY IN THE RESPECTIVE UNIT / OFFSITES & UTILITIES AS DETAILED IN THE ANNEXURE TO CONSTRUCTION PROGRESS.

1. WHEREIN THE GAP BETWEEN SCHEDULE & ACTUAL %AGE PROGRESS IS MORE THAN 5 % , EXPLANATION FOR THE BACK LOG/GAP REQUIRED TO BE FURNISHED IN THIS SHEET. 2. ALL COMPONENTS OF THE PROJECT IN LSTK CONTRACTOR'S SCOPE AS PER THE CONTRACT, SHOULD BE REPORTED IN IN THE PROGRESS STATISTICS.

MONTH & YEARCLIENTPMC : EILPAGE 8 OF 37

Page 26: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTORPROJECT

VI. MILESTONE STATUS (CURRENT + 2 MONTHS)

STATUS AS ON :

S. MILESTONE DESCRIPTION SCHEDULE LATEST ACTUAL FORECAST STATUS/

NO.DATE ALLOWABLE

DATE DATE DATE REMARKS

1 GENERAL

2 UNIT

2.1 RESIDUAL BASIC ENGINEERING

2.2 DETAILED ENGINEERING

2.3 PROCUREMENT

a) ORDERING

b) MANUFACTURING & DELIVERY

2.4 SUB-CONTRACTING

2.5 CONSTRUCTION

2.6 PRECOMMISSIONING

2.7 COMMISSIONING

NOTE :ALL MILESTONES (UNIT WISE AND FUNCTION WISE) AS AGREED DURING KICK OFF MEETING ARE TO BE LISTED.

MONTH & YEARCLIENT PMC : EILPAGE 9 OF 37

Page 27: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT PROJECT PMC : EIL

PAGE 10 OF 37

VII - PROBLEMS / HOLD-UPS

(UNIT WISE / DISCIPLINE WISE)

SR. NO. PROBLEM / HOLD-UPS ACTION PLAN ACTION BY TARGET DATE

1

2

3

4

5

NOTE : ONLY POINTS WHICH AFFECT THE PROGRESS BUT MAY NOT HAVE THE IMPACT ON THE PROJECT SCHEDULE SHALL BE LISTED HERE.

Page 28: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT PROJECT P P MC : EIL

PAGE 11 0F 37 ANNEXURE - I (A)

NOTE :

2. OVERALL (AT CONTRACT LEVEL) SEPARATELY FOR EACH FUNCTION AND ONE CURVE FOR PHYSICAL PROGRESS

1. UNIT WISE SEPARATE CURVE FOR EACH FUNCTION AND CURVE FOR PHYSICAL PROGRESS

PROJECT - (Name of contract)FUNCTION / PHYSICAL

0

10

20

30

40

50

60

70

80

90

100

CU

MU

LATI

VE

% P

RO

GR

ES

S

0

5

10

15

20

25

30

35

40

45

MO

NTH

LY %

PR

OG

RE

SS

SCH DURING THE MONTH 0 10 42.5 14.5

ACT. DURING THE MONTH 0 15 24 19

CUMM. SCH 5 15 57.5 72 80 85 90 95 100

CUMM. ACT 3 18 42 61

D'00 J'01 F'01 M'01 A'01 M'01 J'01 J'01 A'01

Page 29: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT

CONTRACTOR

PROJECT

ANNEXURE - II (A)

CHRONOLOGICAL ACHIEVEMENTSS. NO. DESCRIPTION OF KEY MILESTONES SCH. DATE ACTUAL DATE OF

OCCURRENCE

1. GENERAL

2. UNITWISE (AS APPLICABLE)

2.1 RESIDUAL BASIC ENGINEERING

2.2 DETAILED ENGINEERING

2.3 ORDERING

2.4 MANUFACTURING & DELIVERY

2.5 SUB-CONTRACTING

2.6 CONSTRUCTION

2.7 SUB-CONTRACTED PACKAGES

2.8 PRECOMMISSIONING

2.9 COMMISSIONING

NOTE : MECHANICAL COMPLETION & COMMISSIONING DATES SHALL ALSO BE RECORDED.

MONTH & YEARCLIENTPMC : EILPAGE 12 OF 37

Page 30: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEAR

CONTRACTOR CLIENT PROJECT PMC : EIL

PAGE 13 OF 37

ANNEXURE :II (B.1)

SUMMARY STATUS OF ENGINEERING DRAWINGS (SUMMARY LEVEL & UNIT WISE SEPARATELY)

TOTAL DRAWINGS RELEASED (NOS.) REVIEW STATUS (NOS.) SUBMISSION PROGM.

DISCIPLINE DRAWINGS DURING THE MONTH CUMULATIVE TOTAL DRGS. CODE 1 CODE 2 CODE 3 FOR NEXT MONTH REMARKS

NOS. SCH. ACT. SCH ACT FOR REVIEW FRESH CODE 3

ARCHITECTURAL

GENERAL CIVIL

STRUCTURAL

PIPING

GAD's

ISO's

ELECTRICAL

INSTRUMENTATION

TOTAL

Page 31: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR

PROJECT

PROJECT NAME

USE WTD. DRAFT CHECK IST % WTD REV.CODE VALUE COMPL. COMPL. SUBM. CODE 2 CODE 1 PROG. PROG. CODE

* * * * *SCH.A/F

SCH.A/F

SCH.A/F

SCH.A/F

SCH.A/F

SCH.A/F

SCH.A/F

SCH.A/F

LEGEND I: INFORMATION R: REVIEW A : APPROVALS : STUDY A: STATUTORY / CLIENT REVIEWP: PURCHASE C: CONSTRUCTIONT: TENDERING L: CALCULATION

NOTE : 1. INDICATE A/F (ACTUAL / FORECAST)AS APPLICABLE WITH THE DATES.2. * PERCENTAGE FOR AGREED MILESTONES AS PER PROGRESS MEASUREMENT METHODOLOGY.3. THIS INCLUDES PROCESS / BASIC ENGG. DELIVERABLES.

REMARKS

CATEGORY (CAT.):-

USE CODE :-

DRAWING / DOCUMENT TITLEDRG. NO. CAT.REV

. NO.

MILESTONESREVIEW

DISCIPLINE : PROCESS

DRAWINGS / DOCUMENTS RELEASE SCH. (DCI) (UNITWISE / DISCIPLINEWISE)

ANNEXURE - II(B.2) STATUS AS OF : DD/MM/YYYY

MONTH & YEARCLIENTPMC : EILPage 14 of 37

Page 32: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

MONTH & YEARCLIENTPMC : EILPAGE : 15 OF 37

MCI: MATERIAL CONTROL INDEX (UNIT WISE / DISCIPLINE WISE) ANNEXURE : II (B.3)

STATUS AS ON: DD/MM/YY

ISSUE OF MR PREPARE TBA PREP OF PR

APPROVAL OF PR / 1ST REVIEW

OF VENDOR DRGS

APPROVAL OF VENDOR

DRGS/DOCSREMARKS / REASONS FOR DELAY

20% 30% 10% 10% 30%

<DISCIPLINE>1 SCH

ACT/FORECAST

2 SCH

ACT/FORECAST

3 SCH

ACT/FORECAST

4 SCH

ACT/FORECAST

5 SCH

ACT/FORECAST

6 SCH

ACT/FORECAST

7 SCH

ACT/FORECAST

8 SCH

ACT/FORECAST

9 SCH

ACT/FORECAST

10 SCH

ACT/FORECAST

11 SCH

ACT/FORECAST

12 SCH

ACT/FORECAST

13 SCH

ACT/FORECAST

14 SCH

ACT/FORECAST

15 SCH

ACT/FORECAST

TOTAL SCH ______%

ACT/FORECAST ______%

LEGEND: CATEGORY (CAT.) : I : INFORMATION R : REVIEW A : APPROVALS : STUDY A : STATUTORY / CLIENT REVIEW

USE CODE :- P : PURCHASE C : CONSTRUCTIONT : TENDERING L : CALCULATION

NOTE : 1. INDICATE A/F (ACTUAL / FORECAST) AS APPLICABLE WITH THE DATES.2. * PERCENTAGE FOR AGREED MILESTONES AS PER PROGRESS MEASUREMENT METHODOLOGY.3. THIS INCLUDES PROCESS / BASIC ENGG. DELIVERABLES.

S. NODRAWING/DOCUMENT NUMBER

NAME OF LSTK CONTRACT : CONTRACTOR : PROJECT :

WEIGHTED PROGRESS

CATERGORY

(A/R/I)

WTD VALUE

DRAWING / DOCUMENT DESCRIPTION

PLEASE REFER ANNEXURE :

II (C)

Page 33: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR

PROJECT

ANNEXURE - II(C) PROJECT NAME

SL WTD. REV. NO. REVIEW PROG REMARKS &NO VALUE CODE Ist SUBM. REV. CODE-2 CODE-1 (%) STATUS

* * *

NOTE :2. ALL VENDOR / PACKAGE CONTRACTOR DRAWINGS DOCUMENTS TO BE LISTED.1. * - AGREED MILESTONE PERCENTAGE

DRG. NO. DESCRIPTIONDATE

VENDOR / PACKAGE CONTRACTOR NAME : ……………………….

VENDOR/PACKAGE CONTRACTOR DRAWINGS & DOCUMENTS STATUS (UNITWISE / DISCIPLINEWISE)

STATUS AS OF : DD/MM/YYYY

MONTH & YEARCLIENT PMC : EILPAGE 16 OF 37

Page 34: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR

PROJECT

UNIT NAME / SUMMARY LEVELANNEXURE : II (D.1)

ORDERING STATUS (SUMMARY)(LOCAL(INDIAN) & FOREIGN PROCUREMENT SEPARATELY)

TOTAL MR ISSUE BIDS FOI/TOI PO

CATEGORY MRs ISSUED ENQUIRY DUE ISSUED ISSUED

SCH ACT SCH ACT SCH ACT SCH ACT SCH ACT

EQUIPMENT

COLUMNS

EXCHANGERS

TOTAL

BULK

TOTAL

NOTE :

2. SEPERATE STATUS FOR EACH UNIT AND AT PROJECT SUMMARY LEVEL.

1. NUMBER OF MRs SHALL BE PROVIDED FOR EACH MILESTONE AGAINST EACH EQUIPMENT CATEGORY AS COLUMN, EXCHANGERS, PUMPS ETC. AND BULK MATERIAL.

MONTH & YEARCLIENT PMC : EILPAGE: 17 OF 37

Page 35: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT

PMC : EIL PROJECT PAGE: 18 OF 37

UNIT_______________

DESCRIPTION WTD. CAT MR ISSUE RECV TBA FOI/TOI PO L/C % VENDOR/ PO NO. PR REV. REV. CDD

MR NO. ITEM NO. VAL. RELS ENQ. BIDS ISSUED ISSUE ISSUE OPEN PROG LOCATION /DATE REVIEW CODE 2 CODE REMARKSDATE

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

1. INDICATE A/F (ACTUAL/FORECAST) AS APPLICABLE WITH THE DATES

2. CONTRACTUAL DELIVERY DATE (CDD) IS TO BE QUALIFIED IN REMARKS COLUMN (I.E EX WORKS, FOT, FOB, AT SITE ETC.)

NOTE :

MECHANICAL

ORDERING STATUS (DETAILED) (DISCIPLINEWISE FOR EACH UNIT)

ANNEXURE - II(D.2)

Page 36: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT

CONTRACTOR

PROJECT

UNIT / SUMMARY * ANNEXURE: II(E.1)

EQUIPMENT DELIVERY STATUS (SUMMARY)

EQUIPMENT TOTAL QTY IN DELIVERY FORECAST AT SITE FOR BAL. EQPT.DESCRIPTION NOS DESPATCHED TRANSIT CALENDAR MONTHS --------->

SCH. ACT. (NOS.) SCH. ACT (NOS.) 1 2 3 4 5 6 COLUMNS

VESSELS

REACTORS

EXCHANGERS

AIR COOLERS

PUMPS

COMPRESSORS

FANS

MISC. (MAJOR CRITICAL ITEMS)

TOTAL

NOTE 1. STATUS FOR INDEGENOUS AND IMPORTED EQUIPMENT SHALL BE FURNISHED SEPARATELY

2. * SEPARATE STATUS FOR EACH UNIT AND AT SUMMARY LEVEL.

QUNTITY ORDERED (NOS.) RECEIVED AT SITE (NO.)

MONTH & YEARCLIENT PMC : EILPAGE: 19 OF 37

Page 37: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR

PROJECT

UNIT / SUMMARY * ANNEXURE: II(E.2)EQUIPMENT RECEIPT AND ERECTION STATUS (DETAILED)

(UNITWISE/DISCIPLINEWISE))

PO NO. EQPT EQUIPMENT ERECTION VENDOR NAME, C.D.D DESPATCHED RECEIVED SITE FDN STRL. ERECTION HYDROTESTING

TAG NO. DESCRIPTION WT. LOCATION, ON AT SITE ASSEMBLY READY READY DATE DATE PAINTING INSULATION FIRE

(MT) COUNTRY (IF ANY) DATE DATE PROOFING

COLUMNS

a)

b)

VESSELS

REACTORS

EXCHANGERS

AIR COOLERS

PUMPS

COMPRESSORS

FANS/BLOWERS

OTHER ITEMS

ELECTRICAL EQUIPMENTS

NOTE : 1. ALL EQUIPMENT TO BE COVERED. TAGGED ITEMS WITH MULTIPLE SUFFIXES TO BE MENTIONED SEPARATELY. e.g 701-E-03A, 701-E-03B 701-E-03C 2. * SEPARATE STATUS FOR UNIT AND AT SUMMARY LEVEL.

REQD. AT SITE (SCH,)

MONTH & YEARCLIENT PMC : EILPage: 20 of 3

Page 38: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT

CONTRACTOR

PROJECT

UNIT NAME / SUMMARY LEVEL * ANNEXURE - II (E.3)

BULK MATERIAL STATUS (SUMMARY) ( LOCAL (INDIAN) AND FOREIGN PROCUREMENT SEPARATELY) STATUS AS OF : _______

QUANTITY FORECAST FORS.NO. ITEMWISE DESCRIPTION UOM TOTAL ORDERED RELEASED RECEIVED BALANCE STATUS/PROBLEMS

REQUIREMENT AT SITE DELIVERY1 2 3 4 5

1 PIPES M

2 FITTINGS No.

3 FLANGES No.

4 VALVES No.

5 ELECTRICAL ITEMS (ALL)

ALL ITEMS

6 INSTRUMENTATION ITEMS

ALL ITEMS

NOTE : 1. SEPARATE STATUS FOR EACH UNIT AND AT SUMMARY LEVEL.

2. STATUS TO BE GIVEN SEPARATELY FOR LOCAL (INDIAN) AND IMPORTED PURCHASE.

MONTH & YEARCLIENT PMC : EILPAGE: 21 OF 37

Page 39: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT

PMC : EIL PROJECT PAGE : 22 OF 37

ANNEXURE - II(E.4)PROJECT NAME STATUS AS OF : DD/MM/YYYY

TAG NO./ DESCRIPTION WTD PO VENDOR/ INSPN ORDER RELSD RECD VENDOR RAW RAW MFG MFG FINAL CDD FOB/EX ARRIVAL ARRIVAL SITE %

ITEM OF ITEM VAL NO. LOCATION/ CAT QTY QTY QTY DRG MATL. MATL START FINISH INSPN WORKS INDIAN AT REQD PROG REMARKS

& COUNTRY REV. S/O RECPT DELY PORT SITE DATE

DATE * * * * * * * * *SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

* - AGREED MILESTONE PERCENTAGEINSPECTION CATEGORY ;- AS DESCRIBED IN INSPECTION METHODOLOGY. A/F :- ACTUAL / FORECAST

NOTE : 1 INDICATE A/F AS APPLICABLE WITH THE DATES (A/F :- ACTUAL / FORECAST)2 BULK ITEMS LIST SHOULD INCLUDE PIPING, ELECTRICAL AND INSTRUMENTATION ITEMS.3 IN CASE OF IMPORTED SHIPMENT NAME OF THE VESSEL AND PORT OF BOARDING TO BE INDICATED.4 CONTRACTUAL DELIVERY DATE (CDD) IS TO BE QUALIFIED IN REMARKS COLUMN

(I.E. EX WORKS, FOT, FOB, AT SITE (AS APPLICABLE) ETC.)

INSPN. CAT.-

LEGEND

(LOCAL (INDIAN) AND FOREIGN PROCUREMENT SEPARATELY)

MANUFACTURING / DELIVERY STATUS (UNITWISE / DISCIPLINEWISE/ TAGWISE)

Page 40: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT

PMC : EILPROJECT PAGE: 23 OF 37

ANNEXURE - II(F)UNIT :

DESCRIPTION WTD ISSUE OF PREPARATION TENDER RECEIPT AWARD NAME DURATION CONTRACTUAL INTERMEDIATE

OF WORK VALUE TENDER OF TENDER ON OF BIDS OF %AGE OF OF COMPLETION CONTRACTUAL REMARKS

SPECS DOCUMENT SALE WORK PROGRESS AGENCY CONTRACT DATE MILESTONES* * * * * (IF ANY)

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

SCH.

A/F

A/F :- ACTUAL/FORECASTNOTE : 1. INDICATE A/F AS APPLICABLE WITH THE DATES.

* - AGREED MILESTONE PERCENTAGE

STATUS AS OF : DD/MM/YYYY

SUB-CONTRACTING STATUS

Page 41: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR

PROJECT UNIT ______________ ANNEXURE : II(G.1)

UNITWISE STATUS OF CONSTRUCTION QUANTITIES RELEASED ( DISCIPLINEWISE FOR EACH UNIT)

S. DISCIPLINE & LIKELY CUM BALANCE PROGRAMME FOR BALANCE QTY UNDER HOLDNO. MAJOR WORK ITEM UOM QTY RELEASED QTY TO BE MONTHS AND REASON FOR THE SAME

QTY RELEASED 1 ST 2ND 3RD 4TH 5TH 6TH

UOM : UNIT OF MEASUREMENT.

MONTH & YEARCLIENT PMC : EILPAGE: 24 OF 37

Page 42: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR

PROJECT UNIT : ____________

QUANTITATIVE MONTHLY CONSTRUCTION PROGRESS STATUS ( UNITWISE/DISCIPLINEWISE)

ANNEXURE :II(G.2) WORK ITEM UNIT OF TOTAL QUANTITY PROGRAM

DESCRIPTION MEASU- CUMMULATIVE DURING THE MONTH FOR NEXTREMENT WORKLOAD FRONT COMPLETED PROGRAMME COMPLETED BACKLOG MONTH

EXCAVATION CM

BACK FILLING CM

RCC WORKS CM

BRICK WORK CM

A/G PPG - FAB ID

A/G PPG - ERN IM

U/G PPG - FAB ID

U/G PPG - ERN IM

INSTRUMENTATION

- LOOPCHECKING NOS

PERCENTAGE PROGRAMMED DURING THE MONTH :PERCENTAGE ACHIEVED DURING THE MONTH : FRONT:PERCENTAGE PROGRAMMED FOR NEXT MONTH : ACTUAL:

CUM. PERCENTAGE PROGRESS SCHEDULE :

MONTH & YEARCLIENT PMC : EILPAGE: 25 OF 37

Page 43: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT

PMC : EIL PROJECT

PAGE : 26 OF 37

UNIT :_______________ ANNEXURE : II (H)

SR. AGENCY DURATION CONTRACTUAL ACTUAL ACT/ANT CUM. % ACHIEVEDNO. SCOPE OF WORK (MONTHS) START COMPLN START COMPLN MONTHLY PROGRESS CONTRACTUAL FRONT* ACTUAL

DATE DATE DATE SCH. PROGM ACT. SCH AVAILABLE

SUMMARY

NOTE : 1. * FRONT INDICATES WORK THAT CAN BE TAKEN UP CONSIDERING AVAILABILITY OF DRAWINGS, MATERIALS AND ACCESS.

STATUS OF CONSTRUCTION

Page 44: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT

PMC : EIL PROJECT PAGE : 27 of 37

UNIT :__________________ ANNEXURE : II (I)

LOOPWISE HYDROTESTING STATUS

NO. OF LOOPSHYDROTESTED LOOPS UNDER HOLD REMARKS

THIS MONTH CUMULATIVE MATERIAL ERECTION TOTALSCH. ACT. SCH. ACT.

1.0 UNIT I 100 50 30 20 20 20 15 5 20 10 35 15 50

SERVICEWISE /SYSTEMWISE

2.0 UNIT II

SERVICEWISE /SYSTEMWISE

3.0 OFFSITES PART A

SERVICEWISE

4.0 OFFSITES PART B

SERVICEWISE

5.0 PACKAGES

SERVICEWISE

TOTAL

NOTE : REPORTING SHALL START AFTER PREPARATION OF LOOPWISE PIPING COMPLETION SCHEDULE

CHECK LISTED

MECH. CLEARED

RADIO- GRAPHY

CLEARED

SR CLEARED

FRONT AVAILABLE

SR. NO. DESCRIPTION

TOTAL

Page 45: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT MONTH & YEARCONTRACTOR CLIENT

PMC : EIL

PROJECT

PAGE : 28 OF 37

UNIT : ______________ ANNEXURE : II (J)

SYSTEM HANDING OVER STATUS (UNITWISE)

S.NO. SYSTEM DESCRIPTION FORMAT I ISSUE DATE FORMAT II ISSUE DATE FORMAT III ISSUE DATE FORMAT IV ISSUE DATE FORMAT V ISSUE DATE

A. SYSTEM I TARGET DATE

ACTUAL DATE

B. SYSTEM II TARGET DATE

ACTUAL DATE

C. SYSTEM III TARGET DATE

ACTUAL DATE

TARGET DATE

ACTUAL DATE

TARGET DATE

ACTUAL DATE

GRAND TOTAL TARGET (NOS.)

ACTUAL (NOS.)

LEGEND :

FORMAT I : INFORMATION REGARDING SYSTEM COMPLETIONFORMAT II : CHECKLISTFORMAT III : READY FOR PRE-COMMISSIONING \ MECH COMPLENTION CERTIFICATEFORMAT IV : READY FOR COMMISSIONING CERTIFICATEFORMAT V : COMPLETION OF COMMISSIONING CERTIFICATE

NOTE : 1. TO BE FURNISHED SEPARATELY FOR EACH UNIT

2. REPORTING SHALL START AFTER PREPARARTION OF SYSTEMWISE COMPLETION SCHEDULE

Page 46: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTORS

PROJECTANNEXURE - II(K.1)

(1) LABOUR (2) MANAGEMENT & SUPERVISION

FOR

EMA

N

CA

RPE

NTE

RS

BA

R B

END

ER

MA

SON

S

BA

TCH

PLA

NT

LAB

.

WEL

DER

S - S

TRL.

WEL

DER

S - P

IPE

RIG

GER

S

PIPE

/FA

BN

. FI

TTER

S

GA

S C

UTT

ER

GR

IND

ERS

ELEC

TRIC

IAN

INST

. FIT

TER

S

INSU

LATO

RS

OPE

RA

TOR

/ D

RIV

ER

SCA

FFO

LDER

S

STR

L. E

REC

TOR

S

PAIN

TER

S

STR

L. F

ITTE

RS

INST

R. T

ECH

NIC

IAN

S

MIL

L W

RIG

HT

FITT

ERS

MEC

HA

NIC

S

SAN

D B

LAST

ERS

CR

AN

E O

PER

ATO

RS

TAC

K W

ELD

ERS

FAB

RIC

ATO

RS

DR

ILLE

RS

GU

NIT

OR

LAG

GER

S

UN

SKIL

LED

LA

BO

UR

OTH

ERS

SUB

TO

TAL

: (1)

MA

NA

GER

S

ENG

. DEP

T.

AD

MN

. DEP

T.

PRO

JEC

T C

ON

TRO

L

QA

/ Q

C D

EPT.

SITE

EN

G.

SITE

SU

PER

VISO

RS

SAFE

TY D

EPT.

SUR

VEYO

RS

OTH

ERS

SUB

TO

TAL

: (2)

GR

AN

D T

OTA

L : (

1) +

(2)

PLAN

ACT

PLAN

ACT

PLAN

ACT

PLAN

ACT

GRAND PLAN

TOTAL ACT

NOTE : REASON FOR DEVIATION BETWEEN MONTHLY CONSTRUCTION PROGRAMME AND ACTUAL TO BE MENTIONED. (USE SEPARATE SHEET IF NECESSARY)

PLA

N /

AC

T

NAME OF UNIT

UNITWISE DEPLOYMENT OF LSTK PERSONNEL AT CONSTRUCTION SITEMONTHLY CONSTN. PROGRAMME(%):

MONTHLY CONSTRN. ACTUAL (%) :

MONTH & YEAR

CLIENT

PMC : EIL

PAGE 29 OF 37

Page 47: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRACTOR PROJECT

UNITWISE RESOURCE DEPLOYMENT STATUS ( FOR THE MONTH OF : ___________)

EQUIPMENT & MACHINERY ANNEXURE : II (K.2)

SL NO NAME OF UNITEQ

UIP

MEN

T/M

AC

HIN

ERY

EXC

AVA

TOR

S

DU

MP

LOA

DER

S

CO

NC

MIX

ERS

DO

ZER

S

WA

TER

TA

NK

S

DG

SET

S 12

5/82

.5 K

W

DW

PU

MPS

RO

LLIN

G M

AC

HIN

ES

JAC

K H

AM

MER

S

CO

MPR

ESSO

RS

CO

MPA

CTO

RS

VIB

RA

TOR

S

WEL

DIN

G M

AC

HIN

E

CO

ATI

NG

/WR

APP

ING

M/C

RO

AD

RO

LLER

S

VIB

RO

RO

LLER

S

PAY

LOA

DER

S

PIPE

BEN

DIN

G M

/C

DR

ILLI

NG

M/C

RIG

S

RO

CK

BR

EAK

ERS

WA

TER

PU

MPS

SHEA

RIN

G/G

RO

OVI

NG

M/C

BA

TCH

ING

PLA

NT

MO

TOR

GR

AD

ERS

LOR

RY/

CA

RS/

JEEP

S

CR

AN

ES/H

YD. C

RA

NES

WA

GO

N D

RIL

LER

S

TRA

CTO

RS/

TRA

ILO

RS

WIN

CH

/HO

IST

TRA

NSI

T M

IXER

S

BA

R B

END

ING

M/C

GR

IND

ING

M/C

(AG

)

OVE

NS

MO

THER

/PO

RTA

BLE

PUG

CU

TTIN

G M

/C

SCR

EW J

AC

K

MA

GN

ETIC

DR

ILL

M/C

HA

ND

CU

TTIN

G S

ETS

PAV.

BR

EAK

ERS

BA

R C

UTT

ING

M/C

CU

BE

TEST

ING

M/C

SAN

D B

LAST

ING

HO

PER

HO

T M

IX P

LAN

T

MO

BIL

E D

G S

ETS

HYD

RA

(8T)

250

MT

CR

AN

ES

REQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYEDREQUIREDDEPLOYED

TOTAL REQUIRED

DEPLOYED

PROGRAMME %AGE :-

%AGE PROGRESS ACHIEVED :-

MONTH & YEARCLIENT

PMC : EIL

PAGE 30 OF 37

Page 48: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

MONTH & YEARCLIENTPMC : EILPAGE : 31 OF 37

UPDATED PROJECT SCHEDULE ANNEXURE : II (L)STATUS AS ON: DD/MM/YY

NAME OF LSTK CONTRACT : CONTRACTOR : PROJECT :

Page 49: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT

MONTH & YEAR

CONTRACTOR

CLIENT

PMC : EIL

PROJECT

PAGE 32 OF 37

ANNEXURE : II (M) .

REQUIRED BY RECEIVED ON

1 CHIEF INSPECTOR OF FACTORIES FOR PLANT LAYOUT

a) CONSTRUCTION

b) AS BUILT

2 MUNICIPAL CORPORATION FOR VARIOUS BUILDINGS

3 CIVIL AVIATION FOR FLARE STACK OF CHARGE HEATER

4 FIRE & NUISANCE DEPARTMENT FOR FURNACE STACK ( CHARGE STACK)

5 NOC FROM MUNICIPAL CORP. FOR ALL FACILITIES

6 IBR FOR STEAM PIPING & EQUIPMENTS

7 IBR FOR CHARGE HEATER

8 TAC FOR FIRE WATER & FIRE FIGHTING SYSTEM

9 CCE FOR PLANT LAYOUT, FIRE FIGHTING SYSTEM & TANK

10 CEI APPROVAL FOR H.V ELECTRICAL DISTRIBUTION SYSTEM

11 ANY OTHER STATUTORY & GOVT. APPROVALS (LIST THE SAME)

@@ NOTE : PROBLEMS IF ANY HOLDING APPROVAL SHALL BE HIGHLIGHTED IN THE STATUS COLUMN.

STATUTORY APPROVAL STATUS (APPROVALS TO BE LISTED UNDER THE HEADS OF (A) FOR DESIGN / DRAWINGS AND (B) FOR INSTALLATION)

APPROVAL DATEREMARKS @@ STATUSAPPROVALSSL. NO.

Page 50: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

AMOUNT CERT.RECD

TOTAL 0 0 0 0 0 0

NUMBER & DATE VALUE NET AMOUNT DATE

INVOICING STATUS

SR.NOSERVICE TAX

& OTHER DEDUCTIONS

TOTAL DEDUCTIONS

REASONS FOR OTHER DEDUCTIONS/

REMARKS

DEDUCTIONSINCOME TAX

INVOICE RECEIPT

PAGE 33 OF 37

ANNEXURE - II(N)

NAME OF LSTK CONTRACT

PROJECT

MONTH & YEARCONTRACTOR CLIENT

PMC : EIL

Sheet 1 of 1

Page 51: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

MONTH & YEAR

CONTRACTOR CLIENT PMC : EILPAGE 34 OF 37 ANNEXURE - II(O)

SR. NO WAIVER/ DEVIATION PERMIT NO/ LETTER REF NO DATE SUBJECT REMARKS STATUS

A

B DEVIATION PROPOSED

STATUS OF WAIVERS/ DEVIATIONS

SUBMITTED IN FORMAT

NAME OF LSTK CONTRACT

PROJECT

Sheet 1 of 1

Page 52: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

ANNEXURE : II(P-i)

SCH ACT SCH ACT

1 HMTD

2 GENERAL CIVIL

3 ARCHITECTURE

4 STRUCTURAL

5 PIPING

6 PRESSURE VESSELS

7 ROT.EQUIPMENT

8 MECH.EQUIPMENT

9 ELECTRICAL

10 INSTRUMENTATION

TOTAL 100.0

100.0 97.4

PROJECT

NAME OF LSTK CONTRACT

DEVIATIONDURING THE

MONTH %CUMULATIVE PROGRESS %

DELAY ANALYSISANALYSIS

SR. NO REMARKSDISCIPLINE

WTD VALUE

%

MONTH & YEARCONTRACTOR CLIENT

PMC : EILPAGE 35 OF 37

Sheet 1 of 2

Page 53: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

MONTH & YEARCONTRACTOR CLIENT

PMC : EILPAGE 36 OF 37 ANNEXURE - II(P-ii)

SCH ACT

1 HMTD

2 GEN. CIVIL

3 ARCHITECTURE

4 STRUCTURAL

5 PIPING

6 ROTATING EQPT

7 MECHANICAL

8 ELECTRICAL

9 INSTRUMENTATION

NAME OF LSTK CONTRACT

PROJECT

DELAY ANALYSIS

SR. NO REMARKSDISCIPLINE ACTIVITY/ ITEM DRG NO/ MR NODEVIATION

CUMULATIVE PROGRESS %

Sheet 2 of 2

Page 54: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

NAME OF LSTK CONTRACT CONTRCTOR PROJECT

MONTH & YEAR CLIENT PMC : EIL Page 37 of 37

ANNEXURE : II (Q) PROJECT PHOTOGRAPHS

NOTE : COLOUR PHOTOGRAPHS SHOWING KEY PROJECT ACTIVITIES e.g

MANUFACTURING OF CRITICAL EQUIPMENT, TRANSPORTATION OF ODC ITEMS, CONSTRUCTION/ERECTION OF MAIN AREAS / EQUIPMENT SHALL BE INCLUDED EVERY MONTH.

Page 55: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Attachment -IV FLOW OF DOCUMENTS FROM LSTK CONTRACTOR

Page 1 of 3

Note : 1. Documents to be submitted by the bidder along with Bid are listed in clause 4.0

2. LSTK Contractor shall submit electronic file along with hard copy wherever “*” is marked below

3. Number of copies to be submitted by LSTK Contractor for each document indicated below are indicative and shall be modified

as per project requirement by Project Manager before including in the bid document.

S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT

NO. OF COPIES DOCUMENT CATEGORY CLIENT

(HO) CLIENT (SITE)

PMC (HO)

PMC (SITE)

PMC (LSTK

DESIGN OFFICE)

1. 90 Days Front End schedule With in one week of award 2 2 4* 2* 2* Review

2a.

2b.

Procedure for Planning Scheduling and Monitoring

along with sample formats.

Progress Measurement Methodology

During kick off Meeting ( To be held within two

weeks of award ) 2 1 2 2 2

Approval

Approval

3a.

3b.

Overall Project Schedule ( Unit wise ) – Detailed &

Summarised

Updation of overall Project schedules

( Unit wise )

With in four weeks of award.

Monthly summarized schedule to be submitted

with monthly progress report. Detailed schedule

to be submitted separately on monthly basis.

4

2

2

1

4*

3*

2*

2*

2*

2*

Approval

Information

4a.

Unit wise Functional Schedules in resource based

bar chart with “s” curves

- Residual Basic Engineering Schedules

- Detailed Engineering Schedules

- Ordering Schedules

- Manufacturing & Delivery Schedule

- Sub-contracting Schedule

Within 6 weeks of award

Schedules of different disciplines to be

submitted as separate documents

-

-

4*

-

1

Review

Page 56: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Attachment -IV FLOW OF DOCUMENTS FROM LSTK CONTRACTOR

Page 2 of 3

S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT

NO. OF COPIES DOCUMENT CATEGORY CLIENT

(HO) CLIENT (SITE)

PMC (HO)

PMC (SITE)

PMC (LSTK

DESIGN OFFICE)

4b. Updation of Functional Schedule and “S” Curve Monthly 2 1 2* 2* 2* Information

5a.

5b.

Construction Network (Unit wise) with contract

level, unit level and discipline “S” curves.

Updation of Construction Network and “S” curves (

Unit wise )

Within eight weeks of award or one month

before start of construction activities, which

ever is earlier.

Monthly

1

1

1

1

3*

1

2*

2*

2*

1

Review

Information

6a.

6b.

Loop wise piping completion schedule

Updation of loop wise piping completion schedule

Two months before start of hydro -testing as

scheduled in unit wise construction network

Weekly, to be submitted before review meeting

1

1

1

1

3*

1

2*

2*

2*

1

Review

Information

7a.

7b.

System wise completion schedule

Updation of system wise completion schedule

Six weeks before scheduled completion as per

unit wise construction network

Weekly, to be submitted before review meeting

1

1

1

1

3*

1

2*

2*

2*

1

Review

Information

8a.

8b.

Pre-commissioning / commissioning schedule

Updation of Pre-commissioning / commissioning

schedule

Two months before scheduled mechanical

completion or one month before starting of

Pre-commissioning activities as per unit wise

construction, whichever is earlier.

Weekly, to be submitted before review meeting

1

1

1

1

3*

1

2*

2*

2*

1

Review

Information

9. Catch up Schedules

a. For Overall Project Schedule

b. For Construction Networks

c. Updation

As desired by Client/PMC

As per 3b & 5b.

2

2

2

1

4*

3*

2*

2*

2*

2*

Review

Review

Page 57: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

Attachment -IV FLOW OF DOCUMENTS FROM LSTK CONTRACTOR

Page 3 of 3

S.NO. DESCRIPTION OF DOCUMENT FREQUENCY / TIME OF RECEIPT

NO. OF COPIES DOCUMENT CATEGORY CLIENT

(HO) CLIENT (SITE)

PMC (HO)

PMC (SITE)

PMC (LSTK

DESIGN OFFICE)

10a.

10b.

Sub-contractor schedules with “S” curves including

all Sub-Contractor Packages like Heater, DM Plant

etc,

Updation of Sub-contractor schedules with “S”

curves

To be made within two weeks of award of Sub-

Contract

To be submitted when called for by the owner /

PMC.

Fortnightly

As called for Information

Information

11. Monthly Programme

a. Design Office Activities

b. Construction Activities

Within three calendar days of monthly progress

report cut off date

Within two calendar days of monthly progress

report cut off date

As desired 2

2

2

2

2

2

Review

Review

12. Monthly Progress Report Monthly, within 5 calendar days from cut off

date

4 2 2* Files as

mentioned

above

2* Files as

mentioned

above

2* Files as

mentioned

above

Information

13. Weekly Progress Report ( Over all ) Weekly / within 3 calendar days of cut off date. 1 1 2 2 2 Information

14. Weekly Progress Report ( Construction ) Weekly / within 2 calendar days of cut off date. 1 1 2 2 2 Information

15. Daily Progress Report ( Site ) Daily / before noon of next day 1 1 2 2 1 Information

16. Expediting Report Fortnightly 1 1 2 2 2 Information

17. Planning Package Within 12 weeks of award. 2 2 2 2 2 Information

Note: All the above deliverables shall also be furnished in soft form (native format) along with hard copies.

Page 58: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

ATTACHMENT – V Page 1 of 3

INDICATIVE PROGRESS MEASUREMENT WEIGHTAGE AT VARIOUS LEVELS

I Function Level

PROCESS UNITS UTILITIES & OFFSITE Residual basic engineering 01.0 01.0 Engineering 10.0 10.0 Ordering/purchase 03.0 03.0 Manufacturing & delivery 54.0 30.0 Construction. 30.0 54.0

Pre-commg. and Commissioning 02.0 02.0 and Handing over.

II Discipline Level

ENGINEERING: Avg Range

CIVIL/ STRUCTURAL 20 (15-25) PIPING 35 (30-40) HEAT EQUIPMENT 06 (03-09) PRESSURE VESSELS 06 (03-09) MECH.EQUITMENT/SYSTEMS 12 (08-16) ELECTRICAL 08 (06-18) INSTRUMENTATION 13 (08-24) ORDERING & MANUFACTURING AND DELIVERY: PIPING 16 HEAT EQUIPMENT 19 PRESSURE VESSELS 18 MECH.EQUIPMENT/SYSTEMS 28 ELECTRICAL 07 INSTRUMENTATION 12

CONSTRUCTION (PROCESS UNITS): PILING (IF APPLICABLE) 02 CIVIL WORK 22 STRUCTURAL 03 PIPING & EQUIPMENT ERECTION 40 HEATERS 10 INSULATION 03 PAINTING 01 ELECTRICAL 06 INSTRUMENTATION 08 MISCELLENEOUS 05

Note : In case of utilities and offsites, package/system wise weight factors and then to discipline wise weight factors shall be developed. This will be more relevant in case the EPCC contractor is sub contracting some packages on turnkey basis. For example: RW System etc.

Page 59: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

ATTACHMENT – V Page 2 of 3

III Deliverable weightages PROCESS: DESIGN BASIS 05 PFD 15 PROCESS SUMMARY 05

DATA SHEETS FOR MAJOR EQUIPMENT 15 P&IDs 30 INSTRUMENT DATA SHEETS 10 LINE SCHEDULE 10 FINAL PROCESS PACKAGE 10 IV Milestone level PROCESS: FIRST ISSUE 50 RECEIVE COMMENTS 20 INCORPORATE COMMENTS 20 ISSUE FOR PROCESS PACKAGE/FEED 10

ENGINEERING: Drawings & Documents:

Appl.Cat Info.Cat. DRAFTING COMPLETE 50 50 CHECKING COMPLETE 10 10 ISSUE FOR APPROVAL 10 -- RECEIVE COMMENTS 10 -- ISSUE FOR CONST. 10 30 UPDATION & REVISIONS 10 10 Material Requisitions: Equipment Bulk ISSUE M/R 20 20 TECH.EVLN. 10 50 ISSUE PR TO PMC 10 10 REVIEW OF PR BY PMC 10 10 ISSUE P/R TO VENDOR 10 10 VENDOR DRAWING

REVIEW 40 -- ORDERING: ISSUE ENQUIRY 05 RECEIVE BIDS 15 TBA 25 RELEASE TOI 45 ISSUE PO/PR TO VENDOR 05 UNPRICED PO/PR TO OWNER 05

Page 60: PROJECT PLANNING, SCHEDULING, MONITORING & CONTROL SYSTEM ...gailtenders.in/writereaddata/Tender/a3.8 planning scheduling... · project planning, scheduling, monitoring & control

ATTACHMENT – V Page 3 of 3

MANUFACTURING & DELIVERY: Equipment: SUBMISSION OF MAJOR DRAWINGS 5.0 APPROVAL OF MAJOR DRAWINGS 5.0 SUB ORDERING OF MAJOR MATERIALS 5.0 RECEIVE MAJOR MATERIALS 25.0 FABRICATION WORK 40.0(Progressive) FINAL INSPECTION & TESTING 05.0 DESPATCH TO SITE 05.0 RECEIVE AT SITE 05.0 SUBMIT FINAL DOCUMENTATION 05.0 Bulk material: START OF WORK 10.0 DESPATCH 60.0(Progressive

Desp.qty./Total qty.) RECEIVE AT SITE 20.0(Progressive

Received.qty/Total qty.) FINAL DOCUMENTATION 10.0 CONSTRUCTION IN CASE OF CONSTRUCTION ALL ITEMS OF WORK AND QUANTITIES SHALL

BE INDICATED AND % PROGRESS AT WORK ITEM LEVEL SHALL BE BASED

ON WORK COMPLETED VS. TOTAL QTY OF THE WORK ITEM. THE EPCC

CONTRACTORS SHALL GIVE DETAILS OF ARRIVING AT TOTAL CONTENTS.