manufacturing planning & scheduling

Upload: buntymth05

Post on 09-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Manufacturing Planning & Scheduling

    1/44

    Manufacturing Planning &

    Scheduling

    N.K.Agarwal

  • 8/8/2019 Manufacturing Planning & Scheduling

    2/44

  • 8/8/2019 Manufacturing Planning & Scheduling

    3/44

    PPC isthe organisation and planning of

    manufacturing process

    PPC

    Co-ordinatessupplyand movement of materialsand labour

    Ensures economic and balanced utilisation of machinesand

    equipments,and

    Otheractivitiesrelated with production

    To achieve the desired manufacturingresults

    Production Planning & Control(PPC)

  • 8/8/2019 Manufacturing Planning & Scheduling

    4/44

    Production Planninginvolves

    Formulation

    Co-ordination,and

    Determination ofactivities

    In a manufacturingsystem

    Production Controlinvolves

    Process of maintainingabalance between variousactivities

    involved in production planning providing

    Most effective and efficient utilisation ofresources

    Production Planning & Control(PPC)

  • 8/8/2019 Manufacturing Planning & Scheduling

    5/44

    Production Planning

    The function ofthe managementthat decides

    The resourcesthe firm willrequire forits future

    manufacturing operations,and

    Allocatingthese resourcesto produce the desired outputin

    required amountatleast cost

  • 8/8/2019 Manufacturing Planning & Scheduling

    6/44

    Production planning prepares

    Procurement plans formaterialsand personnel,

    Establisheswork proceduresand control, Preparesand issuesworkauthorisation,establishes finished

    goodsinventory control,and

    Maintainsalternative plans ofaction

    Production Planning-Procedures

  • 8/8/2019 Manufacturing Planning & Scheduling

    7/44

    Categories of production planning procedures

    Routing

    Scheduling,and Loading

    Production Planning-Procedures

  • 8/8/2019 Manufacturing Planning & Scheduling

    8/44

    Routing means determination of path orroute over

    which each piece isto travelin beingtransformed

    from raw materialinto finished product Routinggenerallyinvolvesthe following

    Whetherto make/buy

    Form and shape ofthe material

    Division ofworkto be done into operations

    Production Planning-Routing

  • 8/8/2019 Manufacturing Planning & Scheduling

    9/44

    Choice of machines/ work centers on which each operation

    should be done and its duration

    Sequence in which operationsare to be performed

    Division of operationsinto work elements

    Choice ofspecialtooling

    Economic lotsize of production orderquantity

    Estimation ofamount ofscrap

    Production Planning-Routing

  • 8/8/2019 Manufacturing Planning & Scheduling

    10/44

    Schedulingis

    Decidingwhen and where each operation in a production

    processisto be executed,and

    Establishment oftime table atwhichto begin and/or

    complete each event oroperation involved in a procedure

    Production Planning-Scheduling

  • 8/8/2019 Manufacturing Planning & Scheduling

    11/44

    Developed byreviewing market forecasts, customer

    orders,inventorylevels, facilityloading & capacity

    information regularly Plan for future production of end items overshort

    range planninghorizon

    An importantlinkbetween production and marketing

    Master Schedule

  • 8/8/2019 Manufacturing Planning & Scheduling

    12/44

    F

    unctions of MPS

    Translatingaggregate plansinto specific end items

    Evaluatingalternative masterschedules

    Generating materialrequirement Generating capacityrequirement

    Facilitatinginformation processing

    Maintaining valid priorities

    Utilising capacity effectively

  • 8/8/2019 Manufacturing Planning & Scheduling

    13/44

    MASTER PRODUCTION SCHEDULE- FLOW CHART

    FORECAST & CUSTOMER

    ORDERS

    AGGREGATE PLAN

    TENTATIVE MPS

    TRIALFIT ON

    MRP SYSTEM CRP SYSTEM

    ARE

    MATERIALSADEQUATE ?

    ARE

    CAPACITIESADEQUATE ?

    FIRM MPS

    TO MRP & CRP SYSTEM

    DOMESTIC &INTERNATIONAL

    REVISE MASTER

    SCHEDULE

    REVISE MASTER

    SCHEDULE

    END PRODUCTS &

    SERVICE PARTS /

    SPARE PARTS

    CAPACITY

    REQUIREMENTPLAN (CRP)

    YESYES

    NO NO

  • 8/8/2019 Manufacturing Planning & Scheduling

    14/44

    MPS Environment

    Make to stock

    Production bythe companyin batches

    Carries finished goodsinventory formost ofthe end items

    Mostly consumerproducts

    Orders from warehouses mostly

    Lotsizes of ordersbased on economics

    Efforts to prepare MPS are relatively less

  • 8/8/2019 Manufacturing Planning & Scheduling

    15/44

    Make to order

    Companies do not carry finished goodsinventory

    Builds customerordersas needed

    Customers expected to wait forthe design & manufacturinglead time

    Example: Buildings, Jewellary making,Ship building

    Lotsize and numberof products depends upon customer

    orders

    Many product designs, productsand ordersto be included

    Efforts required to prepare MPS are more

    MPS Environment

  • 8/8/2019 Manufacturing Planning & Scheduling

    16/44

    Assemble to order Typicalwith verylarge numberof possible end items made from

    combination ofbasic componentsand sub-assemblies

    Customerdeliverytimes often lessthan totallead times

    Flexibility maintained in manufacturing Basic componentsand sub-assemblies produced

    Finalassembliestaken up onlyagainst customerorder

    Example:Automobile manufacturing,Forkliftswith

    differentspecifications

    End items notscheduled Schedule unitsstated in planningbills of materials

    Common partsand options form the MPS planningbill

    MPS Environment

  • 8/8/2019 Manufacturing Planning & Scheduling

    17/44

    Objectives

    To plan newwork orders on the basis ofspare capacity

    available

    To balance the workload in a plant

    To maintain delivery promises

    To checkthe feasibility of production programmes

    Production Planning-Loading

  • 8/8/2019 Manufacturing Planning & Scheduling

    18/44

    PPC-Production Control

    Production Controlisthe procedure

    To regulate an orderly flow of materials,and

    Co-ordinate various production activities

    To accomplishthe objective of producingthe desired

    item

    In the right quantity of desired qualityatthe required

    time bythe bestand the cheapest method

    To attain highest efficiencyin production

  • 8/8/2019 Manufacturing Planning & Scheduling

    19/44

    PPC-Production Control

    Properco-ordination ofthe operation of varioussections/

    departmentsresponsible forproduction

    To ensure timelysupply ofraw materialatthe desired place

    and of prescribed qualityand quantityto avoid delaysin

    production

    To perform inspection ofsemi finished and finished goods

    and use of quality controltechniquesto ensure

    manufactured goods meetingrequired specifications

    Also responsible forproduct design and development

  • 8/8/2019 Manufacturing Planning & Scheduling

    20/44

    Production Control- Levels

    Three levelsin production control

    Programming

    Planningthe output of product forthe factoryasawhole

    Ordering

    Planningthe output of components from suppliersand

    production departments

    Dispatching

    Considers each processing departmentin turn and plans

    the output from the machines,toolsand otherworkcentersso asto complete the orderby due date

  • 8/8/2019 Manufacturing Planning & Scheduling

    21/44

    Orderingis

    Process of placing orders,also known aswork orders, to

    the suppliersand the processing departments forthe

    materialsand otherparts needed to manufacture theproduct,and

    To arrange the ordering quantityand deliveryschedule in

    suchaway

    Thatallitemsare delivered in time to meetthe

    production programme

    Production Control- Ordering

  • 8/8/2019 Manufacturing Planning & Scheduling

    22/44

    The decision ofassigning variousjobsto different

    machinesisknown asDispatching

    Functions To checkthe immediate availability of materials

    Ensuringavailability ofall production and inspection aids for

    use

    Obtain appropriate drawingsand specifications

    Collatejobs, operation layouts,routine etc.withthe design

    Production Control- Dispatching

  • 8/8/2019 Manufacturing Planning & Scheduling

    23/44

    Processinginformation orinspection schedule

    Assign workto definite machine,work place and men

    Issue necessary materialsand tools etc.to the required point

    foruse

    Issue production note indicatingthe startand finishtime of

    the work

    Inform progressregardingstart ofwork

    Instruction to startthe work

    Maintain all production records

    Production Control- Dispatching

  • 8/8/2019 Manufacturing Planning & Scheduling

    24/44

    Follow-up/expediting orprogressingis checking

    production activitiesso that production maybe

    carried outas perplan

    Involves measurement of outputagainst plan,analysis of

    performance forshort-fallsand following up the line

    managementto apply corrective action

    The chaserisresponsible forobservingthatany

    detailwhichis overlooked ornot properly executed issetright

    Production Control- Follow - up

  • 8/8/2019 Manufacturing Planning & Scheduling

    25/44

    Schedulingbecomes complex due to

    Delivery dateshave to be promised forwork ordersagainstcustomers orders

    Production lotstend to become small & manyrequire

    machine change over

    Possibility ofassigning / reassigningworkers & machinesto

    variouswork orders Schedulesto be specific and detailed machine wise to bring

    orderliness

    Scheduling of Process Focused

    Production Systems

  • 8/8/2019 Manufacturing Planning & Scheduling

    26/44

    Scheduling of

    Product - Focused System Relatively fewerstandard product designs

    Production usually on produce to stock & sellbasis

    Finished goodsinventoriesare maintained Production rates ofindividual products exceed their

    demand

    Muchless pre production planning concerningroute sheets,job

    instructions, process plansand product designs

    Schedulesbased on economic production runs forproductswithoutfirm delivery commitments

    Majorscheduling concernsare

    Timing of production line change over

    Length of production runs

  • 8/8/2019 Manufacturing Planning & Scheduling

    27/44

    Reduces cost of production by minimisingwastage of

    materialand economic utilisation ofresources

    Leadsto lowerinvestmentby means of efficientandbalanced utilisation ofresources

    Promotes employee morale byavoidingallsorts of

    bottlenecks

    Enhances customersatisfaction and confidence

    PPC - Importance

  • 8/8/2019 Manufacturing Planning & Scheduling

    28/44

    MPS and Shop Floor Planning &

    Control

    MPSand shop floorplanning & controlresultsin Lowinventorylevels,

    Minimise the manufacturing cycle time,

    Full utilization of production services,and

    Helpsin the development of positive customerrelations

    By meetingthe promised delivery dates

  • 8/8/2019 Manufacturing Planning & Scheduling

    29/44

    References Production Operations Management :

    Aswathappa / Bhat

    Modern Production / Operations Management:Buffa / Sarin

    Operations Management :

    Donald Waters

    Manufacturing Planning & ControlSystems :

    Vollman / Bery / Whybark

  • 8/8/2019 Manufacturing Planning & Scheduling

    30/44

    Thank You

  • 8/8/2019 Manufacturing Planning & Scheduling

    31/44

  • 8/8/2019 Manufacturing Planning & Scheduling

    32/44

    PPC - Objectives

    Determiningthe nature and magnitude of variousinput factorsto manufacture the desired output

    To co-ordinate labour, machinesand equipmentin

    the most effective and economic manner

    Establishingtargetsand checkingthese againstperformance

    Ensuringsmooth flow of materialsby eliminating

    bottlenecksin production

    Utilisation of underemployed resources

    To manufacture the desired output ofright qualityand

    quantityatrighttime

  • 8/8/2019 Manufacturing Planning & Scheduling

    33/44

    Production Planning-Objectives

    Systematic co-ordination and regulation of variousactivities

    To maintain properbalance ofthe activities for

    efficient production

    Determination ofraw materials, machines, equipmentetc.and otherinputs fordesired output

    Anticipation ofbusiness changesand reactingto

    them in propermanner

    To have optimum usage orresourceswith optimum

    costand time

    To provide alternative production strategiesin case of

    emergencies

  • 8/8/2019 Manufacturing Planning & Scheduling

    34/44

    Varioustypes of proformasto record details of

    production processat differentstagesalso to be

    designed

    In manufacturing plants,routing ofan ordercarried

    out usingRoute Sheets

    Production Planning-Routing

  • 8/8/2019 Manufacturing Planning & Scheduling

    35/44

    Route Sheet

    ManufacturingOrder no.

    Drawing no. Date of completion

    Description of

    the item

    Remarks

    No. of pieces on

    order/Economic

    lot size

    Spoilage

    allowance

    Total items to

    be produced

    Material description

    Purchase Order no.

    Time/ Piece

    Tool Description

    Quality of material allotted.

    Stores requisition no.

    Due date.

    Setup time/lot operation no.

    Time allowance

  • 8/8/2019 Manufacturing Planning & Scheduling

    36/44

    Objectives of Production control

    Provision ofraw materials, equipment, machinesand labour

    To organise production in conformitywiththe demand

    forecast

    Ensure utilisation ofresourcesin the best possible manner

    suchthatthe cost of production is minimised and delivery

    date is maintained

    Determination of economic production runswitha viewto

    reduce the setup costs

    PPC-Production Control

  • 8/8/2019 Manufacturing Planning & Scheduling

    37/44

    Production Control- Techniques

    Programming: Objectives

    Reliable deliveryto customers

    Even loading ofthe plant

    Even loading ofthe labourin total man -hours perweek

    Efficient use of capital

    Lack of production programmingin any

    manufacturingsystem resultsin late deliveryto

    customers

  • 8/8/2019 Manufacturing Planning & Scheduling

    38/44

    SCHEDULING SERVICES

    ECONOMICACTIVITIES INWHICH PRIMARYOUTPUT IS

    NEITHERA PRODUCT NORA CONSTRUCTION

    VALUE ISADDED TO THISOUTPUT THAT CANNOT BE

    INVENTORIEDLIKE CONVENIENCE, COMFORT,SECURITY,AND THEOUTPUT IS CONSUMEDAS PRODUCED

    TRANSPORTATION

    UTILITIES

    COMMUNICATIONS

    FINANCE,BANKING, INSURANCE, POST & TELEGRAPH

  • 8/8/2019 Manufacturing Planning & Scheduling

    39/44

    SERVICE OPERATIONS

    SERVICESYSTEMS

    DONOT HOLD INVENTORIES

    DEMANDON THEM HIGHLY VARIABLE

    OPERATIONSLABOUR INTENSIVE PRIMARILY PERFORMED THROUGH PERSONNEL

    ASSUCH, PERSONNELSCHEDULING BECOMES COMPLEX

  • 8/8/2019 Manufacturing Planning & Scheduling

    40/44

    SERVICE OPERATIONS

    ALSOKNOWNASNON-MANUFACTURING OPERATIONS, CAN

    BE CLASSIFIEDAS

    STANDARDSERVICES

    CUSTOMERSERVICES CLASSIFICATIONACCORDING TO THEDEGREEOF

    STANDARDISATIONOF THEOUTPUTSAND THE PROCESS

    PERFORMEDBY THESERVICESYSTEM

  • 8/8/2019 Manufacturing Planning & Scheduling

    41/44

    SERVICE OPERATIONS

    STANDARDSERVICES

    SYSTEMS MORELIKE PRODUCT-FOCUSSED MANUFACTURING

    SERVICESSTANDARDFOR MOST CUSTOMERS

    PROCESSONCEBEGUN CARRIED THROUGH TOCOMPLETIONWITHOUT MUCHDELAY

    SIGNIFICANT DIFFERENCEWITH PRODUCT-FOCUSSED

    MANUFACTURING BEING THAT SERVICES PRODUCED

    ACCORDING TO CUSTOMERORDERRATHER THANFOR

    FINISHED GOODS INVENTORY

    TRNASPORT COMPANIES,FAST FOOD

    RESTAURANTS, POSTALSERVICES,AIRLINES

    SOPHISTICATEDSCHEDULING SUCHASON-LINE

    COMPUTERBASEDSCHEDULING SYSTEMS USED

  • 8/8/2019 Manufacturing Planning & Scheduling

    42/44

    SERVICE OPERATIONS

    CUSTOMERSERVICES SYSTEMSLIKE JOBSHOPSANDHENCESCHEDULING MUCH

    LIKE JOBSHOPS

    SMALLSERVICESLIKEADOCTORS CLINIC,SMALLRETAILERS,LOCAL TRANSPORT COMPANIES

    NOFORMALSCHEDULING SYSTEMSEMPLOYED

    SIMPLESCHEDULING SYSTEMSSUCHASAPPOINTMENTSCHEDULES, TOKENSYSTEM,FIRST-COME-FIRST-SERVICEETCUSED TOASSIGN PRIORITIES TO CUSTOMERS

    PART TIMEWORKERSANDSTAND-BYEQUIPMENT FREQUENTLYUSEDDURING HIGHDEMAND PERIOD

    HOSPITALS USE MORESOPHISTICATEDSCHEDULING SYSTEM

    INCLUDINGA MOST CRITICALNEED CRITERIA ;FIRST-COME-FIRST-SERVED

  • 8/8/2019 Manufacturing Planning & Scheduling

    43/44

  • 8/8/2019 Manufacturing Planning & Scheduling

    44/44

    SCHEDULING PERSONNEL IN

    SERVICES PERSONNELSCHEDULESDEVELOPED TOALLOWSYSTEM

    CAPACITIESWHICH MATCH THE CUSTOMERDEMAND SYSTEM CAPACITY VARIEDBY VARYING NUMBEROF PERSONNEL TO

    WORKDURING EACHHOUROF THEDAY

    PART TIME PERSONNEL MAYBEEMPLOYEDDURING PERIODSOFPEAKDEMAND

    FOREMERGENCYSERVICESLIKEFIREOR POLICE,SCHEDULINGDONEFOR 24 HOURFULL CREW COVERAGE

    DURING PEAKDEMAND PERIODS,OFF-DUTY PERSONNEL CALLED INAND COMPENSATEDWITHOVERTIME PAYMENT OR TIME-OFFS