project planning presentation
DESCRIPTION
TRANSCRIPT
@ IndustrialEngineering
byBopaya BidandaDavid I. Cleland
@ IndustrialEngineering
Project Management Process
Planning
Organizing
MotivatingDirecting
Control
@ IndustrialEngineering
Planning
Strategic contextPlanning processProject planning elementsProject planning work packagesProject life cycle
@ IndustrialEngineering
@ IndustrialEngineering
Planning Process
Develop project objectives, goals, and strategiesDevelop project “work breakdown structure” (WBS)Develop precedence diagramDevelop time-based schedulePlan on the resource support
@ IndustrialEngineering
Project Planning Elements
Statement of workProject specificationMilestone scheduleWork Breakdown StructureFinancial planning
@ IndustrialEngineering
Project Life Cycle4 Phases
Phase IConceptual
Phase IIPlanning
Phase IIIExecution
Phase IVTermination
Dol
lars
of
wor
ker
-hou
rs (
leve
l of
effo
rt)
@ IndustrialEngineering
Phase I---Conceptual
Identify needEstablish feasibilityIdentify alternativesPrepare proposalDevelop basic budget and scheduleIdentify project team
@ IndustrialEngineering
Phase II---Planning
Implement scheduleConduct studies and analysesDesign systemBuild and test prototypesAnalyze resultsObtain approval for production
@ IndustrialEngineering
Phase III---Execution
Procure materialsBuild and test toolingDevelop support requirementsProduce systemVerify performanceModify as required
@ IndustrialEngineering
Phase IV---Termination
Train functional personnelTransfer materialsTransfer responsibilityRelease resourcesReassign project team members
@ IndustrialEngineering
Work Breakdown Structure
Divides the overall project into work elementsEach project must be subdivided into tasksProjects are planned, organized, and controlled around the lowest level of the WBS
@ IndustrialEngineering
Work Breakdown Structure (Example)
Antenna Rotating System
Control Box Wiring Interface Antenna Assembly
Chassis Electrical Subassembly Antenna Mast Antenna Rotating Motor
Interconnect WiringSwitch AssemblyCapacitatorMotor AssemblyTransformer
Switch Housing Terminal Board
@ IndustrialEngineering
Project Planning Work Packages
Establish the strategic fit of the projectDevelop the project technical performance objectivesDescribe the project through the development of the projectIdentify and make provisions for the assignment of the functional work packages
@ IndustrialEngineering
Project Planning Work Packages (cont.)
Identify project work packages that will be subcontractedDevelop the master and work package schedulesDevelop the logic networks and relationships of the project work packagesIdentify the strategic issues that the project is likely to face
@ IndustrialEngineering
Project Planning Work Packages (cont.)
Estimate the project costsPerform risk analysisDevelop the project budgets, funding plans, and other resource plansEnsure the development of organizational cost accounting system interfacesSelect the organizational design
@ IndustrialEngineering
Project Planning Work Packages (cont.)
Provide for the project management information systemsAssess the organizational cultural ambienceDevelop project control concepts, process, and techniqueDevelop project teamIntegrate contemporaneous state-of-the-art project management philosophies, concepts, and techniques
@ IndustrialEngineering
Project Planning Work Packages (cont.)
Design project administrative policies, procedures, and methodologiesPlan for the nature and timing of the project auditsDetermine who the project stakeholders are and plan for the management of these stakeholders
@ IndustrialEngineering
Implementation of New Technology & New Concepts
Success FactorsEstablishment of clear project objectivesUse of a Human Centered philosophyEarly team member participation in planning and implementationIntroduction of technology through pilot projectsPresence of a technology implementation champion
@ IndustrialEngineering
Success Factors (contd.)
Selection and training of employeesOrganization directs efforts towards overcoming resistancePerformance evaluation and rewards system changesOrganizational design changesEmpowerment of project team
@ IndustrialEngineering
Techniques in Project Scheduling
Gantt ChartCritical Part Method (CPM)Project Evaluation and Review Technique (PERT)
@ IndustrialEngineering
Critical Path Method (CPM)
Each activity is known with certaintyUsed to determine the length of time required to complete a projectUsed to determine how long each activity in the project can be delayed with out delaying the completion of the project
@ IndustrialEngineering
Project Evaluation and Review Technique (PERT)
The duration of the activities is not known with certaintyUsed to estimate the probability that the project will be completed by a given deadline
@ IndustrialEngineering
Developing Time Estimates
A probabilistic modelThe time for an activity is a random variable having the same distribution3 estimates for each activity
m = most likely timea = optimistic timeb = pessimistic time
@ IndustrialEngineering
PERT
Expected Time = a + 4m + b =
Variance or 2 = (b-a)2 / 36Based on the Beta distribution which weights the most likely time 4 times more than the optimistic or pessimistic time
6
@ IndustrialEngineering
@ IndustrialEngineering
Managers vs. Leaders
LeadersLeadersDevelop foresight and vision for the future opportunityMaximize effectivenessDevelop and execute creative future strategyMaintain strategic awarenessSeek and see the big picturesSeek new purpose
@ IndustrialEngineering
Managers vs. Leaders
ManagersManagersDevelop and maintain oversight of current operationMaximize efficiencyDevelop and execute management systemMaintain controlWatch the detailSeek constancy of purpose
@ IndustrialEngineering
Good Characteristics for Leaders
CoachFacilitatorCounselorNetworkerResource providerLeaderCoordinator
@ IndustrialEngineering
Good Characteristics for Managers
Self relianceGeneralistSpecialistConnected
@ IndustrialEngineering
Organizing
Organizing processMatrix organization
@ IndustrialEngineering
Organization Charts
Traditional ChartLinear Responsibility Chart (LRC)
@ IndustrialEngineering
Matrix Organization
A network of interfaces between a project team and the functional element of an organizationThe interfaces center on work packages
@ IndustrialEngineering
A Basic Project Management Matrix
Project Functional Project Functional InterfacesInterfaces
@ IndustrialEngineering
The Project-Functional Interface
Project is to be done?When will the task be done?How much money is available to do the task?How well has the total project been done?
How will the task be done?Where will the task be done?Who do the task?
How well has the functional input been integrated into the project?
Project ManagerProject Manager Functional Functional ManagerManager
@ IndustrialEngineering
Project Functional Interface
Describes how project manager accomplishes projectManaging of organization relationship is primarily 2 dimensions
@ IndustrialEngineering
Organizing Process
Establish organizational structure for the teamIdentify and assign project roles to members of the project teamDefine management project policies, procedures, and techniques
@ IndustrialEngineering
Organizing Process (cont.)
Prepare project management charter and other delegation instrumentsEstablish standard for the authority, responsibility, and accountability of the project team
@ IndustrialEngineering