project planning presentation

39
@ Industria l Engineeri ng by Bopaya Bidanda David I. Cleland

Upload: samuel90

Post on 01-Nov-2014

835 views

Category:

Business


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Project Planning Presentation

@ IndustrialEngineering

byBopaya BidandaDavid I. Cleland

Page 2: Project Planning Presentation

@ IndustrialEngineering

Project Management Process

Planning

Organizing

MotivatingDirecting

Control

Page 3: Project Planning Presentation

@ IndustrialEngineering

Planning

Strategic contextPlanning processProject planning elementsProject planning work packagesProject life cycle

Page 4: Project Planning Presentation

@ IndustrialEngineering

Page 5: Project Planning Presentation

@ IndustrialEngineering

Planning Process

Develop project objectives, goals, and strategiesDevelop project “work breakdown structure” (WBS)Develop precedence diagramDevelop time-based schedulePlan on the resource support

Page 6: Project Planning Presentation

@ IndustrialEngineering

Project Planning Elements

Statement of workProject specificationMilestone scheduleWork Breakdown StructureFinancial planning

Page 7: Project Planning Presentation

@ IndustrialEngineering

Project Life Cycle4 Phases

Phase IConceptual

Phase IIPlanning

Phase IIIExecution

Phase IVTermination

Dol

lars

of

wor

ker

-hou

rs (

leve

l of

effo

rt)

Page 8: Project Planning Presentation

@ IndustrialEngineering

Phase I---Conceptual

Identify needEstablish feasibilityIdentify alternativesPrepare proposalDevelop basic budget and scheduleIdentify project team

Page 9: Project Planning Presentation

@ IndustrialEngineering

Phase II---Planning

Implement scheduleConduct studies and analysesDesign systemBuild and test prototypesAnalyze resultsObtain approval for production

Page 10: Project Planning Presentation

@ IndustrialEngineering

Phase III---Execution

Procure materialsBuild and test toolingDevelop support requirementsProduce systemVerify performanceModify as required

Page 11: Project Planning Presentation

@ IndustrialEngineering

Phase IV---Termination

Train functional personnelTransfer materialsTransfer responsibilityRelease resourcesReassign project team members

Page 12: Project Planning Presentation

@ IndustrialEngineering

Work Breakdown Structure

Divides the overall project into work elementsEach project must be subdivided into tasksProjects are planned, organized, and controlled around the lowest level of the WBS

Page 13: Project Planning Presentation

@ IndustrialEngineering

Work Breakdown Structure (Example)

Antenna Rotating System

Control Box Wiring Interface Antenna Assembly

Chassis Electrical Subassembly Antenna Mast Antenna Rotating Motor

Interconnect WiringSwitch AssemblyCapacitatorMotor AssemblyTransformer

Switch Housing Terminal Board

Page 14: Project Planning Presentation

@ IndustrialEngineering

Project Planning Work Packages

Establish the strategic fit of the projectDevelop the project technical performance objectivesDescribe the project through the development of the projectIdentify and make provisions for the assignment of the functional work packages

Page 15: Project Planning Presentation

@ IndustrialEngineering

Project Planning Work Packages (cont.)

Identify project work packages that will be subcontractedDevelop the master and work package schedulesDevelop the logic networks and relationships of the project work packagesIdentify the strategic issues that the project is likely to face

Page 16: Project Planning Presentation

@ IndustrialEngineering

Project Planning Work Packages (cont.)

Estimate the project costsPerform risk analysisDevelop the project budgets, funding plans, and other resource plansEnsure the development of organizational cost accounting system interfacesSelect the organizational design

Page 17: Project Planning Presentation

@ IndustrialEngineering

Project Planning Work Packages (cont.)

Provide for the project management information systemsAssess the organizational cultural ambienceDevelop project control concepts, process, and techniqueDevelop project teamIntegrate contemporaneous state-of-the-art project management philosophies, concepts, and techniques

Page 18: Project Planning Presentation

@ IndustrialEngineering

Project Planning Work Packages (cont.)

Design project administrative policies, procedures, and methodologiesPlan for the nature and timing of the project auditsDetermine who the project stakeholders are and plan for the management of these stakeholders

Page 19: Project Planning Presentation

@ IndustrialEngineering

Implementation of New Technology & New Concepts

Success FactorsEstablishment of clear project objectivesUse of a Human Centered philosophyEarly team member participation in planning and implementationIntroduction of technology through pilot projectsPresence of a technology implementation champion

Page 20: Project Planning Presentation

@ IndustrialEngineering

Success Factors (contd.)

Selection and training of employeesOrganization directs efforts towards overcoming resistancePerformance evaluation and rewards system changesOrganizational design changesEmpowerment of project team

Page 21: Project Planning Presentation

@ IndustrialEngineering

Techniques in Project Scheduling

Gantt ChartCritical Part Method (CPM)Project Evaluation and Review Technique (PERT)

Page 22: Project Planning Presentation

@ IndustrialEngineering

Critical Path Method (CPM)

Each activity is known with certaintyUsed to determine the length of time required to complete a projectUsed to determine how long each activity in the project can be delayed with out delaying the completion of the project

Page 23: Project Planning Presentation

@ IndustrialEngineering

Project Evaluation and Review Technique (PERT)

The duration of the activities is not known with certaintyUsed to estimate the probability that the project will be completed by a given deadline

Page 24: Project Planning Presentation

@ IndustrialEngineering

Developing Time Estimates

A probabilistic modelThe time for an activity is a random variable having the same distribution3 estimates for each activity

m = most likely timea = optimistic timeb = pessimistic time

Page 25: Project Planning Presentation

@ IndustrialEngineering

PERT

Expected Time = a + 4m + b =

Variance or 2 = (b-a)2 / 36Based on the Beta distribution which weights the most likely time 4 times more than the optimistic or pessimistic time

6

Page 26: Project Planning Presentation

@ IndustrialEngineering

Page 27: Project Planning Presentation

@ IndustrialEngineering

Managers vs. Leaders

LeadersLeadersDevelop foresight and vision for the future opportunityMaximize effectivenessDevelop and execute creative future strategyMaintain strategic awarenessSeek and see the big picturesSeek new purpose

Page 28: Project Planning Presentation

@ IndustrialEngineering

Managers vs. Leaders

ManagersManagersDevelop and maintain oversight of current operationMaximize efficiencyDevelop and execute management systemMaintain controlWatch the detailSeek constancy of purpose

Page 29: Project Planning Presentation

@ IndustrialEngineering

Good Characteristics for Leaders

CoachFacilitatorCounselorNetworkerResource providerLeaderCoordinator

Page 30: Project Planning Presentation

@ IndustrialEngineering

Good Characteristics for Managers

Self relianceGeneralistSpecialistConnected

Page 31: Project Planning Presentation

@ IndustrialEngineering

Organizing

Organizing processMatrix organization

Page 32: Project Planning Presentation

@ IndustrialEngineering

Organization Charts

Traditional ChartLinear Responsibility Chart (LRC)

Page 33: Project Planning Presentation

@ IndustrialEngineering

Matrix Organization

A network of interfaces between a project team and the functional element of an organizationThe interfaces center on work packages

Page 34: Project Planning Presentation

@ IndustrialEngineering

A Basic Project Management Matrix

Project Functional Project Functional InterfacesInterfaces

Page 35: Project Planning Presentation

@ IndustrialEngineering

The Project-Functional Interface

Project is to be done?When will the task be done?How much money is available to do the task?How well has the total project been done?

How will the task be done?Where will the task be done?Who do the task?

How well has the functional input been integrated into the project?

Project ManagerProject Manager Functional Functional ManagerManager

Page 36: Project Planning Presentation

@ IndustrialEngineering

Project Functional Interface

Describes how project manager accomplishes projectManaging of organization relationship is primarily 2 dimensions

Page 37: Project Planning Presentation

@ IndustrialEngineering

Organizing Process

Establish organizational structure for the teamIdentify and assign project roles to members of the project teamDefine management project policies, procedures, and techniques

Page 38: Project Planning Presentation

@ IndustrialEngineering

Organizing Process (cont.)

Prepare project management charter and other delegation instrumentsEstablish standard for the authority, responsibility, and accountability of the project team

Page 39: Project Planning Presentation

@ IndustrialEngineering