    HEATH ROBINSON S WEB HOSTING COMPANY

    Project Plan - Heath RobinsonsNetwork Installation

    Submission DateAssignment (60%)

    Sefff

    1

  • 8/6/2019 Project Planning - Dissertation Project

    2/23

    Table of ContentsProject Summary: Introduction..................................................................................3

    My Role: As Project Manager......................................................................................3

    The Objective: Scope of Work.....................................................................................4

    Tasks to be completed...............................................................................................5

    Assumptions:...........................................................................................................5

    Construction / Refurbishing - Construction Managers Activity................................6

    Work Breakdown Structure..................................................................................6

    Activity List..........................................................................................................6

    Activity List with Dependency..............................................................................7

    Planning the Network and Telecomm access Point (Structured Cabling)................8

    Work Breakdown structure...................................................................................8

    Activity list...........................................................................................................9

    Activity List with Dependency..............................................................................9

    Equipment/Material Requirement Cost Estimate................................................10

    The Cost of materials required for structured cabling is as follows.......................11

    Network Design.....................................................................................................11

    Resource Roles and Responsibility & Cost Estimate...........................................12

    The Team consists of 10 members, the roles and the associated cost is as follows

    ..............................................................................................................................12

    Total Project Costing.............................................................................................14

    The Project cost is divided into..............................................................................14

    The Total Cost for the Project is as in the table below:.........................................15

    Project Plan and Task Execution timelines............................................................16

    ROI , Payback Period & Breakeven Point...............................................................18

    2

  • 8/6/2019 Project Planning - Dissertation Project

    3/23

    Project Summary: Introduction

    Heath Robinson Web Hosting Company has acquired second floorin a building, in East Anglia Industrial Estate. There are 8 rooms

    all together on the floor, each of which is large enough to

    accommodate 5 web hosting servers, 1 computer for server

    maintenance and 1 for development work.

    The Purpose of the Project is to design and Implement the

    Network Infrastructure for the new premises. The Project Planningneeds to be planned extensively to cover the following important

    aspects:

    Cost Estimation

    Resourcing - Roles & Responsibility

    Budget

    Milestones and Timelines

    Technology & Process Adoption

    My Role: As Project Manager

    The role played here will of a Project Manager, managing the

    overall project activity, responsible for the project deliverables,

    stick to time lines and lead a team of 10 people.

    The Roles and Responsibility of the 10 individuals is as follow

    1 computer hardware specialist responsible for hardware-

    related task

    3

  • 8/6/2019 Project Planning - Dissertation Project

    4/23

    1 financial advisor responsible for control financial resources

    available to the project

    1 network designer responsible for designing the network for

    the company

    2 software developers for developing software required by

    the new installation

    2 office assistants, one in charge of purchasing computers

    and other hardware equipment and the other dealing with

    paperwork in the office and produce project-related

    documents

    1 construction manager responsible for building and

    refurbishment work

    1 software testing engineer

    1 hardware testing engineer.

    The Objective: Scope of Work

    The objectives of this project limits to the following scope of Work

    Equipment Requirement analysis - Equipment installations,

    network cables and software needed for running the networksystem

    Manage Sub-contacted project of Constructing / refurbishing

    Second floor where equipments will be installed

    Designing the network based on the business requirements

    4

  • 8/6/2019 Project Planning - Dissertation Project

    5/23

    Investigate and purchase appropriate hardware and other

    equipment

    Developing the software required for the network system

    Installing the network and computers in the new building

    Testing hardware and software

    Tasks to be completed

    Define Work Break down structure (WBS)

    Estimate Activity Resources

    Estimate Activity Duration Estimate Cost

    Calculate Net Profit, ROI and RTR

    Risk Assessment

    Assumptions:

    30 Employees - 5 users in each room

    Cash Inflow and Cash Outflow Values are assumed Year onYear

    Resource availability, sufficiency and priority of assignment

    are assumed to readily available.

    Define Work Break down structure (WBS)

    The work Break down structure (WBS) is one of most important

    aspect of a project. It becomes the hub of information for the

    project, and arguably the most important component of project

    plan. The WBS should include procurement decisions, cost, quality

    5

  • 8/6/2019 Project Planning - Dissertation Project

    6/23

    attributes, Risk and serves as the primary tool for verifying and

    controlling the Project

    The work break down structure for the project is as follow

    Construction / Refurbishing - ConstructionManagers Activity

    Construction planning is a fundamental and challenging activity in

    the management and execution. It involves the choice of

    technology, the definition of work and the estimation of required

    resources and duration of individual task.

    The Primary focus here will be on cost control, even though

    control on the schedules defined would have realistic. The WBS

    and activity lists for the construction/Refurbishing activity is as

    follows. The type of activities comprise Production Activities and

    Procurement activities

    The Construction Manager would be responsible for planning the

    construction activity and over look all the activities.

    Work Breakdown Structure

    Design Floor plan (space plan)

    Masonry and Plumbing

    6

  • 8/6/2019 Project Planning - Dissertation Project

    7/23

    Provide Water, Electrical, Pressure air and gas services

    Repair and Paint floor, Walls and Ceiling

    Activity List

    Strip Room

    Repair Wall and Ceilings

    Repair Floor

    Lay Vinyl Floor

    Rough in Plumbing & Electricals &Finish Plumbing &

    Electrical

    Install Cabinets

    Install Wall Cabinets

    Paint Cabinet

    Paint Walls & Ceilings

    Activity List with Dependency

    Activity List with DependencyActivi

    ty Activity Description

    Depends

    on

    1 Strip Room -2 Repair Walls & Ceilings 1,53 Repair Floor 1,54 Lay Vinyl Floor 3,12,13

    5

    Rough-in Plumbing &

    Electrical 1

    6

    Finish Plumbing &

    Electrical

    2,3,5,9,10

    ,147 Install 1/3 Base Cabinets 2,3,128 Install Wall Cabinets 2,3,7,129 Paint Cabinets 6,7,8,13

    7

  • 8/6/2019 Project Planning - Dissertation Project

    8/23

    10 Paint Walls and Ceilings

    2,3,6,7,8,

    13

    11

    Obtain Vinyl Floor

    Coverings -12 Obtain Cabinets -

    13

    Painter, Plumber &

    Electrician Availability -14 Install 2/3 Base Cabinet -

    Construction Cost Estimate

    Considering industry standard pricing and costing list the cost

    estimate for the construction activity is as follows

    Construction M

    Per da Cost (8

    Planning the Network and Telecomm access Point

    (Structured Cabling)

    Modern Computer LAN (Local area Network) wiring has the

    concept of structured cabling. Structured cabling is the design

    and management of Physical layer in OSI Model. With todays high

    speed networks, the networking system must be broken up into

    shorter chunks with the cable length short enough to support the

    high data rate.

    8

  • 8/6/2019 Project Planning - Dissertation Project

    9/23

    The New floor requires Voice, Data and Video wiring and

    electronic facilities to support newest form of

    telecommunications. The Switch room, which houses the Servers,

    Networking equipments (Switches, Routers, and Firewalls)

    connects to the each terminal (Desktop) via Horizontal Cabling.

    The option for Vertical Cabling can be enabled in future for

    connecting multiple switch rooms

    Work Breakdown structure

    Design Network and Telephone point -Floor Plan

    Horizontal cabling Desktop to Patch panel wiring

    Switch room cabling

    Rack Mounting and Server wiring

    Pathway planning cable trays, conduits and hangers to

    support cable from IDF

    Activity list

    Running cable from the Network/Telecom Point to wiring

    closet

    Cable connector punching

    Wall jack mounting

    Cabling pulling

    Building Entrance cabling Connectivity to external

    network(ISP)

    Horizontal cabling Individual desktop connection to

    Switch(Hub)

    Work Area cabling for Printers, scanner and other devices

    Switch room cabling

    9

  • 8/6/2019 Project Planning - Dissertation Project

    10/23

    Obtain Cat5e cables For Data transmission

    Obtain Cat5 Cables For Voice transmission

    Activity List with Dependency

    Activity list with Dependency

    Activity Activity Description

    Dependson

    1Running cable from the Network/TelecomPoint to wiring closet 9,10

    2 Cable connector punching 11,1,3 Wall jack mounting 9,10,124 Cabling pulling 1,9,10

    5

    Building Entrance cabling Connectivity toexternal network(ISP) 9,10,11

    6Horizontal cabling Individual desktopconnection to Switch(Hub)

    1,4,9,10,11

    7Work Area cabling for Printers, scanner andother devices

    1,4,9,10,11

    8 Switch room cabling 9,10,119 Obtain Cat5e cables For Data transmission -

    10 Obtain Cat5 Cables For Voice transmission -11 Obtain Cable connectors - RJ45 7 RJ11 -

    12 Obtain Face Plates -

    Equipment/Material Requirement Cost Estimate

    The List of Network & Server Equipment/Materials required to

    execute the project is as follow. The parametric cost estimation

    technique (linear scalable estimation)

    10

  • 8/6/2019 Project Planning - Dissertation Project

    11/23

    NetwoDell PowerEdge 2900

    The Cost of materials required for structured cabling is as follows

    Network Design

    The Network has been designed based on Industry best practices.

    The aim is to design and build the best network for Heath

    Robinsons, with highest degree of functionality at the lowest

    reasonable cost. The network design is developed with an

    understanding that real-time applications like voice and video

    travel across the network.

    11

  • 8/6/2019 Project Planning - Dissertation Project

    12/23

    The Network is designed using industry standard Star topology.

    The configuration covered in the guide include layer1 and layer2

    design. The idea is to reduce the possible number of problems

    that can arise and increase the chances that each IT network

    engineer is sufficiently trained to deal the most potential problem.

    The devices have the capability to scale up twice the current

    capacity

    12

  • 8/6/2019 Project Planning - Dissertation Project

    13/23

    Resource Roles and Responsibility & CostEstimate

    The Team consists of 10 members, the roles and the associated

    cost is as follows

    Computer Hardware specialist:

    The Hardware engineer would be responsible for all hardware

    installation , routine maintenance and attend and close any kind of

    service request from the employees

    Hardware specification & Installation Daily Maintenance of the Setup

    Handle Service Request from End Users

    Network Engineer:

    The Network Engineers primary role would be designing the Network,

    scalable for the company present and future expansion. The smooth

    running of running of the Network, on daily basis is also the primary

    focus of this resource. The Primary role of the network engineer

    would be as follows:

    Manage Desktop Incidents

    Configuration of the PCs and connections to a network

    Setup and connection of a printer

    Setup of file and print sharing

    Telephone access to all cabin

    Software Developers:

    13

  • 8/6/2019 Project Planning - Dissertation Project

    14/23

    The 2 Software Developers would be responsible for design and

    development of the software required by the company. The software

    would be tailor designed based on very specific needs of the

    company. The developers would be using the standard coding

    languages like JAVA & .Net Frame work to develop the software.

    Office Assistant:

    The 2 Office assistant were appointed for essentially do whatever

    office tasks are needed so that the professional doesnt have to. One

    office assistant will purchase hardware needed to the office and otherwill do paper works

    Testing Engineers:

    One hardware testing engineer and software testing engineer were

    appointed their responsibilities is to setup of test processes including

    hardware and software deployment, provide technical support and

    training when required advanced testing, performing complex

    diagnostic tests on faulty computer. Software testing technician

    execute test plans to evaluate the performance of software

    applications and information and telecommunication systems.

    The Total Resource cost per month is as follows

    14

  • 8/6/2019 Project Planning - Dissertation Project

    15/23

    Total Project Costing

    The Project cost is divided into

    Capital Expenditure

    Operational Expenditure

    Capital Expenditure

    The Capital expenditure (Capex) is the cost incurred for

    procurement of the required Hardware and Equipments and the

    Materials used for the construction purpose. The Capex is one

    time cost and is not a recurring.

    The following table gives the Capital expenditure

    Ca italOperational Expenditure

    The Operational Expenditure (Opex) is the cost incurred to run the

    operations and is the Monthly/Yearly recurring cost. Opex is

    15

  • 8/6/2019 Project Planning - Dissertation Project

    16/23

    further classified as Direct and Indirect cost. The following table

    provides the Estimated Operational cost for next 5 years

    Opertional Cost (

    Direct Cost

    Server Maintenance

    Hardware Maintenan

    Antivirus Annual SubsIndirect Cost

    Rent

    Staff Salary (taking 30

    The Total Cost for the Project is as in the table below:

    Land Lease (per

    ConstructionCos

    Project Plan and Task Execution timelines

    The Project Planning and the associated tasks with time lines are

    as follows

    The Project is subdivided into

    Construction

    Structured Cabling

    16

  • 8/6/2019 Project Planning - Dissertation Project

    17/23

    Network Installation

    Server Configuration

    Software Development

    Software Testing

    Hardware Testing

    Desktop Configuration

    The time lines proposed is 20 working day ( 4 Weeks). The Tasks

    and the associated time lines are defined in the project plan.

    17

  • 8/6/2019 Project Planning - Dissertation Project

    18/23

    ROI , Payback Period & Breakeven Point

    As per the development and production cost we have calculated

    the benefit of this year. The following table will show you the total

    benefits of this year

    Total Cost Vs Total Benefit

    Total Cost incurred

    Total Opex Cost Total Benefit

    NPV (Net Present Value) and ROI (Return on Investment):

    The difference between the present value of cash inflows and the

    present value of cash outflows. NPV is used in capital budgeting toanalyse the profitability of an investment or project. Here the NPV

    and ROI are calculated. The following tables show you the NPV and

    ROI value.

    18

  • 8/6/2019 Project Planning - Dissertation Project

    19/23

    Net profit / total investment 100 = Return on Investment

    Total Benefit Total Cost

    ROI = ------------------------------------

    Total Cost

    = 1,610,400 - 8, 80,591

    --------------------------------

    8, 80,591

    = 0.828%

    Break Even Point for the First year

    First year Sales - 2, 41,535

    First year Cost (Direct + indirect) - 68,462

    Yearly Net Cash Flow Cumulative Net Cash Flow

    = --------------------------------------------------------------------

    Yearly Net Cash Flow

    19

  • 8/6/2019 Project Planning - Dissertation Project

    20/23

    231,537 - 68462

    = ---------------------------

    231,537

    = 1.32 BEP (1 and half year)

    Return on Investment (ROI) analysis is one of several approachesto evaluating and comparing investments. ROI compares

    investment returns and costs by constructing a ratio, or

    percentage. In most ROI methods, an ROI ratio greater than 0.00

    (or a percentage greater than 0%) means the investment returns

    more than its cost.

    ROI and other financial metrics that take an investment view of

    an action or investment compare investment returns to

    investment costs. However each of the major investment metrics

    (ROI, internal rate of return IRR, net present value NPV, and

    payback period), approaches the comparison differently, and each

    carries a different message.

    Here the case flow over a period of 5 years is assumed for ROI

    calculation. The Net Cash flow data assumed is as follows

    20

  • 8/6/2019 Project Planning - Dissertation Project

    21/23

    The table below shows the figures for the investment, including

    cumulative cash flow and ROI for the investment at the end of

    each year.

    ROI: The ROI figures Year on Year is as shown in the above table

    Future Performance: The cumulative curves above only cover 5

    years, but if the investments inflows and outflows are expected to

    continue beyond 5 years.

    Payback Period: The cumulative cash flow curves above show

    roughly the point in time when the cumulative cash flow "breaks

    even," that is, when cumulative incoming returns exactly balance

    cumulative outflows. This point in time (point on the horizontal

    axis) is Payback period .The payback period is 1.5 years

    RISK ASSESSMENT

    The initial Risk Assessment identify those risks which can be

    identified before starting the project are listed in the below page.

    The risk assessment will be continuously monitored and updated

    throughout the life of the project

    INITIAL PROJECT RISK ASSESSMENT

    21

  • 8/6/2019 Project Planning - Dissertation Project

    22/23

    Project scope

    Estimated project sche

    Knowledge level of staff

    Regardless of how close you come to reality, a committee will be

    much happier if your project comes in below budget than over it,

    however towards the end of the project due to high risk and

    inexperience make the project become unlikely to meet both the

    deadline and the budget. So, the committee decided to extent the

    project for eight weeks to finish this project.

    A Study in the Project Failure:

    22

  • 8/6/2019 Project Planning - Dissertation Project

    23/23

    Due to over budget with no clear end in site the project got

    unsuccessful. To get back on track, as a project manager I have

    to take further steps to overcome this problem. The first thing I

    need to do is to work out how far off-track and exactly how many

    days are behind the schedule and what is the percentage of

    project timeline and also I need to calculate the percentage of

    overall budget, by changing some task allocations and try to

    reassign people to tasks and check out the task dependencies is a

    better way to go on the track. And to assign the best people to

    the critical tasks and try to get those done earlier.

    Conclusion:

    The Project make or break decision is with the project

    manager. Its the responsibility of the PM to ensure that all the

    Project related activities are in line to the timeline and any delayin the deliverables are adjusted by adding extra resources or

    increasing the time line. Every project can only be achieved

    satisfactorily through a comfortable working relationship between

    very many people and with many different personal or collective

    objectives. Projects are within organizations to support

    temporary endeavours that create unique products or services.

    The Management committee will be ultimately responsible for

    taking any kind of decision on the make or break of the project in

    addition to the details provided by the project manager.

    23