pre-feasibility report of m/s vega life sciences...

14
Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd Pashamylaram Unit Page 1 of 14 PREFEASIBILITY REPORT OF M/s. VEGA LIFE SCIENCES PVT.LTD 1. Introduction of the project M/s Vega Life Sciences Pvt.Ltd is promoted by Sri K.Venkat Reddy and Smt.K.Vasundhara. Industry proposes to expand the unit to manufactures Bulk Drugs, Intermediates, chemicals in addition to solvent recovery. At present industry is recovering only solvents. The unit is located on plot No plot No.D-22, Phase-1, IDA,Pashamylaram,Patancheru Mandal, Medak dist. a notified industrial area. M/s Vega Life Sciences Pvt.Ltd has purchased the unit from M/s Jayamahima Chem Pvt.Ltd. Total land area of the unit is 4306 SQM. 1.1 Need of the project The Indian pharmaceutical industry valued at $ 12 billion has portrayed tremendous progress with reference to infrastructure development, technology base creation and a wide range of production. The pharmaceutical industry produces bulk drugs belonging to major therapy groups. India ranks 4 th worldwide accounting for 8 percent of the world’s production (in terms of volume) and 13 th in terms of value. It is estimated that by the year 2010, the Indian pharmaceutical industry has the potential to achieve over Rs.1, 00,000 crore in formulations and bulk drug production. The industry now produces bulk drugs belonging to all major therapeutic groups requiring complicated manufacturing process and has also developed Good Manufacturing Practices (GMP) facilities for the production of different dosage forms. The pharma industry exports drugs and pharmaceuticals worth over $4.5 billion. It ranks 17 th in terms of export value of bulk actives and dosage. Indian exports cover more than 200 countries including the highly regulated markets of USA, Europe, Japan and Australia. At a growth rate of 9 percent per year, the pharmaceutical industry in India is well set for rapid expansion. As a result of the expansion, the Indian pharmaceutical and healthcare market is undergoing a spurt of growth in its coverage, services, and spending in the public and private sectors.

Upload: others

Post on 03-Apr-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 1 of 14  

 

PRE­FEASIBILITY REPORT OF M/s. VEGA LIFE SCIENCES PVT.LTD 

 1. Introduction of the project 

M/s  Vega  Life  Sciences  Pvt.Ltd  is  promoted  by  Sri  K.Venkat  Reddy  and Smt.K.Vasundhara.  Industry  proposes  to  expand  the  unit  to  manufactures Bulk  Drugs,  Intermediates,  chemicals  in  addition  to  solvent  recovery.  At present  industry  is  recovering  only  solvents.  The  unit  is  located  on  plot  No plot No.D-22, Phase-1, IDA,Pashamylaram,Patancheru Mandal, Medak dist.  a notified industrial area. M/s Vega Life Sciences Pvt.Ltd has purchased the unit from M/s Jayamahima Chem Pvt.Ltd. Total land area of the unit is 4306 SQM.  

1.1 Need of the project  

The  Indian  pharmaceutical  industry  valued  at  $  12  billion  has  portrayed tremendous  progress  with  reference  to  infrastructure  development, technology base creation and a wide range of production.  The pharmaceutical industry produces bulk drugs belonging to major therapy groups.  India ranks 4th worldwide accounting for 8 percent of the world’s production (in terms of volume) and 13th in terms of value.  It is estimated that by the year 2010, the Indian pharmaceutical industry has the potential to achieve over Rs.1, 00,000 crore in formulations and bulk drug production.  The industry now produces bulk  drugs  belonging  to  all major  therapeutic  groups  requiring  complicated manufacturing process and has also developed Good Manufacturing Practices (GMP)  facilities  for  the  production  of  different  dosage  forms.    The  pharma industry exports drugs and pharmaceuticals worth over $4.5 billion.  It ranks 17th in terms of export value of bulk actives and dosage.  Indian exports cover more  than  200  countries  including  the  highly  regulated  markets  of  USA, Europe, Japan and Australia. 

At a growth rate of 9 percent per year, the pharmaceutical industry in India is well  set  for  rapid  expansion.    As  a  result  of  the  expansion,  the  Indian pharmaceutical and healthcare market is undergoing a spurt of growth in its coverage, services, and spending in the public and private sectors. 

 

 

 

Page 2: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 2 of 14  

 

2.      Project Description 

The  proposed  industry  intends  to  produce  the  products  given  below.  The products  are  divided  into  bulk  drugs,  Intermediates,  Chemicals  and  solvent recovery  by  distillation.  The  installed  capacity  for  bulk  Drugs  and intermediates  is  65.00TPM,  for  chemicals  90TPM  and  for  solvent  recovery 450TPM. 

Industry proposes to produce 2.0 TPD either from bulk drug group or intermediate group; 3.0 TPD from chemicals group; 15.0 TPD solvent recoveries.  

2.1     Project details 

Sl.No  Description  Details I  Name of the project  Vega Life Sciences 

Pvt.Ltd II  Location     Village  Pashamylaram   Area  APIIC   District  Medak   State  Telangana III  Land use pattern of the 

industry  

  Total Land area in SQM  4306.00   Built‐up area  1989.00   Production Block  1690.00   Storage yard     300.00   Roads     800.00   Green Belt  1446.00   ETP       70.00 

  

 

 

Page 3: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 3 of 14  

 

2.1.2   List of products 

• Bulk Drugs 

Sl. No Name of the product Production TPM

1. Carvedilol phosphate 2.50

2. Citalopram Hydrobromide 10.00

3. Closantel sodium 5.00

4. Esomeprazole magnesium trihydrate 1.50

5. Fexofinadine hydrochloride 2.00

6. Fosfomycin trometamol 3.00

7. Gaba-pentin 3.00

8. Itraconozole 2.00

9. Lansoprazole 3.00

10. Lornoxicam 4.00

11. Montelukast sodium 3.00

12. Omeprazole 5.00

13. Ondansetron 3.00

14. Oxyclozanide 5.00

15. Ritonavir 3.00

16. Rosuvastatin calcium 3.00

17. Setraline hydrochloride 2.00

18. Sparfloxacin 2.00

19. Terbinafine hydrochloride 3.00

Total 65.00

 

 

 

Page 4: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 4 of 14  

 

• Intermediates 

Sl. No Name of the product Production TPM

1 Tri Chloro Salisylic Acid 3.00 2 5-AminO-2-Hydroxy Benzoic acid 2.00 3 5-Amino-2-dibenzylamino-1,6-diphenyl-hex-4-en-3-

one 2.00

4 2-Amino-6-chloro-3-nitro pyridine 3.00 5 4-Chloro butyryl chloride 3.00

 

• Chemicals 

Sl.No Name of the product Production TPM

1 Tributyl Tin chloride 90 2 L-Menthol 90

3 Dicyclo Hexylcarbomidiimide

90

 

• Solvent Recovery 

Sl.No Name of the product Production TPM

1 All solvents 450

 

Industry proposes to produce

• 2.0 TPD either from bulk drug group or intermediate group • 3.0 TPD from chemicals group • 15.0 TPD solvent recovery

            

Page 5: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 5 of 14  

 

 2.2 Project site selection 

The main reason for selecting this site is its affordability and an existing unit. Also  very  near  to  state  Highway  connecting  Hyderabad  and  Mumbai. Availability  of  the  supporting  facilities  including  skilled  man  power  is available around the area.  

There  are  no  reported  endangered,  threatened  or  rare  plant  species  at  the plant site or within the 10 kms radius of the plant that need to be conserved.  No discernible impacts on terrestrial life.  No migration route to avifauna.  The development of greenbelt will improve aesthetics in surrounding area.  

Topographical map of the Area 

 

 

 

Page 6: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 6 of 14  

 

General Location on Google Map 

 

 

 

 

 

 

 

Site index 

 

Page 7: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pa 

2.3

Acta  s

ashamyla

3 Brief M

tive rawsolvent 

aram Unit

Manufac

w materias  per

t                

cturing

als of thr  the  pr

P

                 

g proces

he resperocess 

Pre-Feasib

                 

 

 

 

 

ss 

ective prbatch  s

bility Repo

                 

 

 

 

 

roducts sheet.  A

ort of M/s

                 

are charAfter  m

s Vega Lif

                 

rged intmaintena

fe Science

          Pag

 

to reactoance  sol

es Pvt.Ltd

ge 7 of 14

 

or usinglvent  is

d

g s 

Page 8: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 8 of 14  

recovered by distillation for next batch.Thus pharma is  isolated and purified with water wash and sometimes with crystallsation with a suitable solvent. 

2.4 Typical flow chart 

Active inputSolventCatalyst

Reactor Solvent recovery

CentrifugeWater Waste water

Product  Solvent recovery

All the solvents will be first neutralized either with base or acid solution separately. Water will be removed by separation and then the same will be taken into a kettle fro distillation.

• Typical flow chart

Spent SolventSodium Chloride Reactor

Reboiler

Distillation column

Steam

Storage Tank

Organic Residue

Sodium Chloride solutionto recovery and reuse

   

 

2.5 Raw materials requirement 

Manufacturing process  involves  the use of chemicals, organic solvents either directly as reactant or for extraction of a product of interest from the reaction 

Page 9: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 9 of 14  

mixture and spent solvents. Raw materials required for the process is mostly bought  from  the  local  (indigenous) market.  Spent  solvents will  be  obtained from nearby industries. Coal is used in the proposed boiler of 2 MT/hour. The coal consumption is about 3.0 Tons per day. Diesel used for DG set of capacity 125KVA will be about 40 liters/hr at full operation load. 

2.6 Resource Re­Cycling Optimizing /Re­cycling 

All efforts will be made by the industry to carry out R& D on the isolated by‐products  /  wastes  to  minimize  wherever  possible.  However  R&  D  is  a continuous  process,  where  improvement  in  the  process  adopted  by  the industry, waste minimization etc can be worked out as the project progresses. 

 

2.7   Utilities 

Sl.No  Description   1  Coal Fired 

Boiler 2TPH 

2  Chilling Plant  200TOR3  Cooling 

Towers 400TR 

 

2.8   Water requirement 

The total water requirement of the plant is 54M3/day. The water needs for the industry will be met from public supply. 

2.9   Power requirement 

The  total  power  requirement  of  the  plant  is  150HP  and  is met  from  public supply. DG set of 125KVA will be used only as stand by. 

 

 

 

2.10    Wastewater generation & Proposed Treatment method 

Page 10: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 10 of 14  

The wastewater generated from the plant will be about 24 m3/day.  Out of this about 1.50 KLD will be domestic wastewater.  Trade effluent will be collected by gravity from all sources into a collection tanks. 

The effluent will be pumped to the above ground level R.C.C. tanks lined with Acid  proof  tiles  for  storage  and  neutralization  and  then  the  effluent will  be sent to Multiple Effect Evaporators.  Condensate will be reused appropriately.  Salts  from  the MEE  evaporation  system will  be  collected  and  sent  to  TSDF. Domestic waste water will be sent to septic tank. 

2.11 Solid waste generation & Proposed Treatment method 

Solid  waste  generated  from  the  plant  is  of  two  categories.  Inorganic  and Organic  Solid  waste.  Inorganic  solid  waste  about0.0.42TPD  will  be  sent  to TSDF for secured land fill. Organic solid waste about 0.72 TPD will be sent to cement  plants  for  incineration.  Coal  ash  from boiler will  be  sold  to  suitable buyers.    

3.   Site Analysis  Industrial  area  is  well  connected  by  Road  and  rail.  It  is  beside  to  NH9 connecting Hyderabad and Mumbai. Project area is a notified industrial area.   The  area  is well  away  from  sensitive  sites  such  as National  parks, Wild  life sanctuaries,  biosphere  reserves  and  religious  places.  Singur  Dam,  a  water source is 48 Km away from industrial area. Nearest Human Habitat is 3.5 Km   Temperatures in the region vary between 360C and 430C during day time and during  night  varies  between  230C  and  270C  in  summer  season.  During monsoon season temperatures varies between 290C and 300C during day time and  200C  and  220C  during  night  time.    In winter  season  temperature  varies between  200C  and  100C.Relative  humidity  is  between  50%  and  55%during monsoon  and  during winter  is  between  30%  and  40%.  Nearly  67%  annual rainfall  is  between  June  and  September.  A  few  showers  are  also  received during the October.     4.  Brief Planning 

Page 11: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 11 of 14  

 Industry being a multi product manufacturing unit, it works in shifts. It works round  the clock. Therefore  transportation of workers  is a not a major point. Industry will engage private operators for the purpose. Since industry is near to the human habitat, industry does not have any plans to construct houses for the employees. 

5.   Proposed Infrastructure 

 

Total Land area in SQM  4306.00

Built‐up area  1989.00Production Block  1690.00Storage yard    300.00Roads   800.00Green Belt  1446.00ETP       70.00

 

6.   Rehabilitation and Resettlement   

Since  the  industry  is  proposed  on  a  notified  industrial  area,  R  &  R  is  not required. By providing direct and indirect employment to the locals and also by facilitating the villages by conducting various developmental programs in a phased manner in association with local bodies, area will continue to develop socio‐economically. 

 7.  Post project monitoring 

The industry has definite environmental monitoring program to monitor the Ambient  Air  Quality  as  well  as  Stack  Emissions.    The  industry  will  engage recognized laboratories to carry out all necessary monitoring parameters for the  industry.   Qualified  staff will  be  appointed  for  the purpose of Operation and maintenance of the pollution control facilities.   Stand‐by  facilities will be provided to all the pumps so as to ensure fail proof treatment. 

8.   Greenbelt development 

8.1  Objective 

Page 12: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 12 of 14  

The purpose of a green belt around the plant site is to capture the fugitive emission, attenuate the noise generated and improve the aesthetics. 

The  green belt  at  the project  site will  form an effective barrier between  the plant  and  the  surroundings. Open  spaces, where  tree plantation may not  be possible, will be covered with shrubs and grass to prevent erosion of topsoil.  Adequate attention will be paid to plantation of trees, their maintenance and protection. A green belt will be developed around the periphery of the plant. Open spaces within the factory will be converted to green areas in the form of lawns or flowering plants. 

8.2  Plant species for green belt. 

A wide range of plant species will be planted  in and around the premises  to help  capture  the  fugitive emission and noise  levels  form  the plant premises. This wide range covers plants of 

• Fast growing type • With thick canopy cover • Perennial green nature • Native origin 

A  specialist  in  horticulture  may  be  appointed  to  identify  any  other  native species and also supervise greenbelt development. 

8.3  Design of Green Belt 

As far possible the following guidelines will be considered in proposed green belt development. Shrub and trees will be planted in encircling rows around the outer three rows (away from planted side) 

The short trees (<10 m height) will be planted in the first two rows (towards plant side) of  the green belt. The tall  trees (>10 m height) will be planted  in the outer three rows (away from plant side). 

• Planting of trees in each row will be in staggered orientation. • In the front row, shrubs consisting of Callistemon, Prosodies etc. Will be 

grown. • Since the trunks of the tall trees are generally devoid of foliage, it will be 

useful to have shrubs in the fronts of the trees so as give coverage to this portion. 

Page 13: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 13 of 14  

The spacing between the trees will be maintained slightly less than the normal spaces, so that the trees may grow vertically and slightly increase the effective height of the green belt. 

9. Recycle  

 All efforts will be made by the  industry to carryout R&D on the  isolated by‐products  / wastes  to  recycle  /  reuse wherever  possible. However,  R&D  is  a continuous  process,  where  improvement  in  the  processes  adopted  by  the industry, waste minimization etc can be worked out as the project progresses. 

10. Environment management cell 

The unit will provide upgraded Environment Management cell as below: 

10.1  Environment Management Cell 

The Environment Management Cell shall include: 

1. Manager (Head of Environment Cell) 2. Process  in charge  from production 3. In charge  Maintenance Department 4. In charge  Operation ETP, Air Pollution Control Division, Solid waste 

management with Chemist  5. A representative of Environmental Consultants (Adviser) 

11.   Handling of raw materials and finished materials 

The  industry  is  proposed  to  store  the  raw materials  (maximum  seven  days storages  capacity).These  raw materials  and  finished  goods will  be  the ware house as per safety norms.  

12.  Hazardous Chemical, waste and Risk Assessment 

Bulk Drug &  intermediate manufacturing  industry  has  to  handle many  such chemicals  that  are  hazardous waste  is  generated.  The  industry will  provide special  training  to  the workers  handling  Hazardous  chemical  /  wastes.  The industry  will  engage  safety  consultants  to  prepare  a  risk  assessment  and suggest safe handling and safe storage of Hazardous wastes for  the proposed project.  Only  highly  trained  personal  with  personal  projective  Equipments (PPE’s) will be allowed to handle such chemicals or under strict supervision. 

13.   Project schedule and cost estimates 

Page 14: Pre-Feasibility Report of M/s Vega Life Sciences Pvtenvironmentclearance.nic.in/writereaddata/Online/... · 2.11 Solid waste generation & Proposed Treatment method Solid waste generated

Pre-Feasibility Report of M/s Vega Life Sciences Pvt.Ltd

Pashamylaram Unit                                                                                                               Page 14 of 14  

 Industry  proposes  to  commence  the  construction  activity  as  soon  as Environmental Clearance and CFE are granted by respective authorities.  It  is estimated  that  12 months  is  required  to  complete  the  construction  and  one more month for trial production and another two months to start commercial production. 

The  Total  Gross  proposed  investment  in  Land,  Buildings  and  Plant  & Machinery is Rs.271 Lacs and the Unit has been registered under Small Scale Industry.  Industry  has  allocated  an  amount  of  about  Rs.40.00  Lacs  for Environmental Protection measures and 1.50 lacs for green belt development