statewide auto-dr planning meeting · pre-cooling cooling valve limit turn off light dimmable...

50
Statewide Auto-DR Planning Meeting Lawrence Berkeley National Laboratory Akua Controls C&C Building Automation Global Energy Partners Demand Response Research Center November 13, 2006 Research and Project Sponsors California Energy Commission PIER Program Pacific Gas and Electric San Diego Gas and Electric

Upload: others

Post on 28-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Statewide Auto-DR Planning Meeting Lawrence Berkeley National Laboratory

Akua ControlsC&C Building Automation

Global Energy Partners

Demand Response Research Center

November 13, 2006

Research and Project Sponsors• California Energy Commission PIER Program• Pacific Gas and Electric• San Diego Gas and Electric

Page 2: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Presentation Overview

10:00 – 10:15 Welcome and Introductions10:15 - 10:30 Meeting Goals and Objectives10:30 – 11:30 AutoDR Project Background11:30 – 12:30 2007 PG&E Program Design12:30 – 1:00 Lunch (Provided)1:00 – 1:30 Discussion on 2007 Programs for

Southern California1:30 – 2:00 Future Directions/PIER Activities2:00 – 3:00 Next Steps3: 00 Meeting Adjourn

Page 3: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Meeting Goals and Objectives

• Provide overview of AutoDR technology, field tests, and program results

• Assist in AutoDR Implementation Plans• Discuss AutoDR commercialization strategies• Obtain feedback on research plans/priorities

Page 4: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Objective

Scope

Method

Stakeholders

to develop, prioritize, conduct, and disseminate multi-institutional research to facilitate DR

technologies, policies, programs, strategies and practices, emphasizing a market connection

Partners Planning Committee, Annual R&D Plan

! Utilities! Industry Trade

Associations! Building Owners /

Operators! Building Equipment

Manufacturers! End-Use customers

! State Policy Makers! Researchers! Information and Metering

System Developers! Aggregators! Program Implementers

DR Research Center

Page 5: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

AutoDR Project Background

• Goals• Develop a low-cost, fully automated infrastructure

to improve DR capability in California• Evaluate “readiness” of (commercial) buildings

and industrial facilities to receive common signals• Evaluate capability of control shed strategies and

measurement of sheds to improve future buildings

Page 6: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

! Develop Demand Response Automation Server (annually updated)

! Develop connection to Energy Management Control Systems (EMCS)

! Field Tests – Recruit sites/ 2 to 12 events per summer2003 - 5 sites – Internet link to Energy Information Systems (EIS)2004 – 18 sites - linked to EIS and EMCS2005 - PG&E CPP collaboration2006 - PG&E, SDG&E, Planning with SCE

! Evaluate with weather normalized baseline (data from Interact)! Interview site after each event

# Sites DRAS Site Communications Utility2003 5 Infotility XML Gateway Software None2004 18 Infotility XML - Internet Relay None2005 11 Akua XML - Internet Relay PG&E2006 25 Akua XML - Internet Relay - CLIR PG&E, SDG&E2007 200? Akua XML - Internet Relay - CLIR Statewide

AutoDR Multi-Year Summary

Page 7: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

PG&EPG&E

PG&E

SCE

SDGE

0

5

10

15

20

25

30

35

40

2000 2001 2002 2003 2004 2005 2006 2007 2008~

Par

tici

pan

ts D

R S

avin

g P

ote

nti

al [

MW

]

AB970SB5X

AB29X

AB970SB5X

AB29X

EnergyCrisis

Auto-DRw/ EIS

Auto-DRw/ EIS

Auto-DRw/ moreCtrl type

Auto-DRw/ moreCtrl type

AutoCPPw/ PG&EAutoCPPw/ PG&E

AutoCPPAutoDBPw/ 3 IOUs

AutoCPPAutoDBPw/ 3 IOUs

EISStudies

EISStudies

Demand Bidding Program

Demand Relief Program (CaISO)

Auto-RTPAuto-RTPAuto-DRw/ 3 IOUs& CaISO

Auto-DRw/ 3 IOUs& CaISO

Real TimePricing

Total4 sites

Total18

Total12

Non-CPPcustomers

Total40

2000 MW1600 MW

1200 MW800 MW

350 MW

CPUC’s Goal of Price-triggered DR

Critical Peak Pricing

DRRCDRRC

PG&EFull-scaleAutoCPP

PG&EFull-scaleAutoCPP

Automated DR Past, Present, and Future

Page 8: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

! 22 sites evaluated over 3 years (pre-2006)! Multiple building types, control strategies, and climates

• Avg savings: 10% (3 hr event, 22 sites, 13 events); avg 15-min max: 19 %• Avg savings: 91 kW, avg max of 170

• Avg savings: 0.5 W/sqft, avg max of 0.9 W/sqft

0%

10%

20%

30%

40%

50%

60%

Ech

elon

UC

SB

OF

B

50 D

ougl

as

AC

WD

2530

Arn

old

Gile

ad 3

42

Roc

he

US

PS

Gile

ad 3

57

Tar

get

Cal

EP

A

IKE

A

Cha

bot

Alb

erts

ons

Ora

cle

300C

Mal

l

B o

f A

NA

RA

CIS

CO

OS

Isof

t

450G

G

Ave

rag

e D

eman

d S

avin

g W

BP

Site Average

Total Average10.3%

0

200

400

600

800

1000

1200

OF

B

CIS

CO

B o

f A

US

PS

IKE

A

UC

SB

Cal

EP

A

Ech

elon

300C

Mal

l

Roc

he

2530

Arn

old

50 D

ougl

as

Gile

ad 3

57

AC

WD

Tar

get

Gile

ad 3

42

Ora

cle

Alb

erts

ons

Cha

bot

NA

RA

OS

Isof

t

450G

G

Ave

rag

e D

eman

d S

avin

g k

W

Site Average

Total Average91 kW

Results by Site (2003-2005)

Page 9: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Building factors System factors Strategy factors Weather factors " Building use " Building size " Structure type " Occupancy

" HVAC type " Efficiency " Control type " Commissioning

" Depth of control " Area% controlled " Curtailment duration

" Outside Temp " Humidity " Solar radiation

0 5 10 15 20 25

Global temp. adjustment

Duct static pres. Increase

SAT Increase

Fan VFD limit

CHW temp. Increase

Fan qty. reduction

Pre-cooling

Cooling valve limit

Turn off light

Dimmable ballast

Bi-level switching

# of sites

Fully-Automated Manual or Semi-Automated

Strategies and Factors Influencing Savings

Page 10: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Report:Guide to DR Strategies

Web:On-Line Tutorialhttp://drrc.lbl.gov/Strategy

Acknowledgements .......................................................................................................... iii

Executive Summary ......................................................................................................... iv

1. Introduction............................................................................................................... 1

1.1. Objectives and Report Organization................................................................... 1 1.2. Objectives and Report Organization................................................................... 2 1.3. Building Operations and Energy Management................................................... 2 1.4. Terminologies and Concepts............................................................................... 5

2. Demand Response Strategy Overview .................................................................... 7

2.1. HVAC System .................................................................................................... 7 2.2. Lighting Systems .............................................................................................. 11 2.3. Miscellaneous Equipments ............................................................................... 12 2.4. Advanced Control Strategies ............................................................................ 12 2.5. Strategies Used in Case Studies........................................................................ 12

3. Demand Response Strategy Detail ........................................................................ 15

3.1. HVAC Systems................................................................................................. 15 3.1.1. Global Temperature Adjustment............................................................... 15 3.1.2. Passive Thermal Mass Storage ................................................................. 18 3.1.3. Duct Static Pressure Decrease .................................................................. 19 3.1.4. Fan Variable Frequency Drive Limit ........................................................ 20 3.1.5. Supply Air Temperature Increase ............................................................. 21 3.1.6. Fan Quantity Reduction ............................................................................ 22 3.1.7. Cooling Valve Limit ................................................................................. 23 3.1.8. Chilled Water Temperature Increase ........................................................ 24 3.1.9. Chiller Demand Limit ............................................................................... 25 3.1.10. Chiller Quantity Reduction ....................................................................... 26 3.1.11. Rebound Avoidance Strategies ................................................................. 27

3.2. Lighting Systems .............................................................................................. 28 3.2.1. Zone Switching ......................................................................................... 28 3.2.2. Fixture/Lamp Switching ........................................................................... 29 3.2.3. Step Dimming ........................................................................................... 31 3.2.4. Continuous Dimming................................................................................ 32

3.3. Miscellaneous Equipments ............................................................................... 33 3.3.1. Fountain pump .......................................................................................... 33 3.3.2. Anti-sweat heater ...................................................................................... 33 3.3.3. Electric vehicle charger............................................................................. 33 3.3.4. Industrial process loads............................................................................. 33 3.3.5. Cold storage .............................................................................................. 34 3.3.6. Irrigation water pump ............................................................................... 34

3.4. Non-Component-Specific Strategies ................................................................ 35 3.4.1. Demand Limit Strategy............................................................................. 35 3.4.2. Signal-level Response Strategy................................................................. 36

Page 11: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

• Alameda Count

2530 Arnold: Sep-22

0

50

100

150

200

250

300

350

400

450

500

0:00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00

9:00

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Who

le B

uldi

ng P

ower

[kW

]

Actual LBNL Baseline CPP Baseline

IKEA: Oct-13

0

500

1000

1500

2000

2500

0:00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00

9:00

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Who

le B

uldi

ng P

ower

[kW

]

Actual LBNL Baseline CPP Baseline

Sample Results

Page 12: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Building use

Totalconditioned

area# ofbldg 2003 2004 2005 2006 G

loba

l tem

p. a

djus

tmen

t

Duc

t sta

tic p

res.

Inc

reas

e

SAT

Inc

reas

e

Fan

VFD

lim

it

CH

W te

mp.

Inc

reas

e

Fan

qty.

red

uctio

n

Pre-

cool

ing

Coo

ling

valv

e lim

it

Chi

ller

dem

and

limit

Chi

ller

qty.

red

uctio

n

Slow

rec

over

y

Ext

ende

d sh

ed p

erio

d

Tur

n of

f lig

ht

Dim

mab

le b

alla

st

Bi-

leve

l sw

itchi

ng

Ant

i-sw

eat h

eate

r sh

ed

Foun

tain

pum

p of

f

Non

-cri

tical

pro

cess

she

d

Ele

vato

r cy

clin

g

Shut

off

col

d st

orag

e

Ww

ater

pum

p pe

ak s

hift

300 CapMall Office 383,000 1 ● X X X X XACWD Office, lab 51,200 1 ● ● X X X X X XAlbertsons Supermarket 50,000 1 ● X XB of A Office, data center 708,000 4 ● ● ● ● X X X X XChabot Museum 86,000 2 ● ● X XCal EPA Office 950,000 1 ● X X XCETC Research facility 18,000 1 ● XCisco Office, tech lab 4,466,000 24 ● X X2530 Arnold Office 131,000 1 ● ● ● X X50 Douglas Office 90,000 1 ● ● ● X XMDF Detention facility 172,000 1 ● XEchelon Hi-tech office 75,000 1 ● ● ● X X X X X XGSA 450 GG Federal office 1,424,000 1 ● XGSA NARA Archive storage 202,000 1 ● XGSA Oakland Federal office 978,000 1 ● ● XGilead 300 Office 83,000 1 ● ● XGilead 342 Office, Lab 32,000 1 ● ● X XGilead 357 Office, Lab 33,000 1 ● ● X XIrvington Highschool 186,000 1 ● ● X XCenterville Junior Highschool - 1 X XIKEA Emeryville Retail 274,000 1 ○ XIKEA EPaloAlto Retail 300,000 1 ● ● XKadent Material process - 1 ● XLBNL OSF Data center, Office 70,000 1 ● X XMonterey Office 170,000 1 ● XOracle Rocklin Office 100,000 2 ● ● X XOSIsoft Office 60,000 1 ● XRoche Cafeteria, auditorium 192,000 3 ● ● XSafeway Stockton Supermarket - 1 ○ XSolectron Office, assembly 499,000 9 ○ X XSybase Hi-tech office 425,000 2 ○ XSvenhard's Bakery 101,000 1 ● XTarget Antioch Retail 141,000 1 ● X XTarget Bakersfield Retail 144,000 1 ● X XTarget Hayward Retail 130,000 1 ● ● X X XTarget ChulaVista Retail 126,000 1 ● X XUCSB Library Library 289,000 3 ● ● X X XUSPS San Jose Distribution center 390,000 1 ● ○ ○ X XWholeFoods Hillcrest Supermarket 28,000 1 ○ XWholeFoods LaJolla Supermarket 36,000 1 ○ X

LightHVACParticipation Other equipment

40 Sites over 4 Years

Page 13: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

2006 Auto-CPP Procedures1. Develop Program (Done by PG&E and LBNL)

• Site Requirements/Basic Procedure – Automate CPP

2. Recruit Sites (LBNL and PG&E)3. Communications Systems Development (LBNL and Akua)

• CLIR Box Development• Develop and Host DRAS• LBNL and Akua developed and implemented at Co-Lo

4. Implement/Configure Communications (LBNL and Tech Coordinator)

• Technical assistance to connect site EMCS to DRAS• Technical assistance selecting & implementing shed strategies• Apply for $100/kW Technology Incentives (SLOW PROCESS)• Shed event testing • Optimization and troubleshooting

5. Run Program/Evaluate Results (LBNL)• Post event shed “problem” interview• Weekly emailed newsletter• Post event shed data analysis• Multiple baselines evaluated, Feedback provided to sites• Evaluate individual and aggregated sheds

Page 14: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

kW Avg kW Max % Avg % Max Avg MaxACWD 96 147 30% 42% 11 13,324$ 138$ 90$ B of A 316 644 6% 12% 11 2,900$ 9$ 5$ Chabot 3 148 0% 56% 6 6,010$ n/a n/a2530 Arnold 96 168 20% 37% 11 3,500$ 12$ 6$ 50 Douglas 65 114 15% 27% 11MDF 123 322 21% 54% 11Echelon 98 169 23% 38% 11 3,620$ 37$ 21$ Gilead 300 11 57 5% 23% 9 4,500$ 71$ 14$ Gilead 342 39 101 11% 30% 9Gilead 357 13 163 3% 26% 9IKEA EPaloAlto 88 219 8% 20% 9 6,360$ 73$ 29$ Oracle Rocklin 91 180 23% 34% 11 1,875$ 21$ 10$ Target Hayward 65 107 16% 24% 11 3,312$ 51$ 31$ Total / Avg 1105 2540 14% 32% 130 5,045$ 51$ 26$

Site nameDemand Saving Achievement # of 2006

eventsSetupcost

Cost $/kW

Preliminary results of LBNL / PG&E Auto-CPP Summer 2006

(High Price Period, 3 – 6 PM)

This data is based on previous 20 non-event business days OAT regression baseline model result. Morning adjustment (shift up baseline to match morning load 3 hours prior to DR operation) is applied to all sites except Museum, where applied pre-cooling strategy. The aggregated average is calculated as {�(% saving)}/n. (NM, 11/06/2006)

Page 15: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Max Ave Max Ave Max AveMod. Price 678 608 0.44 0.39 8% 8%High Price 1192 1113 0.77 0.72 14% 13%

Price Level kW W/ft² WBP%

Aggregated Demand, 6/21/2006 (OAT: 97 °F) - Zone 2, 9 sites

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.00:

00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00

9:00

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Pow

er [M

W]

Target HaywardOracle RocklinIKEA EPaloAltoGilead 357Gilead 342Gilead 300EchelonMDF50 Douglas2530 ArnoldChabotB of AACWDCPP BLAdj Avg BLOAT Reg BLAdj OAT Reg BL

Moderate Price High Price

Page 16: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Max Ave Max Ave Max AveMod. Price 541 474 0.35 0.31 7% 6%High Price 1069 932 0.69 0.60 13% 11%

Price Level kW W/ft² WBP%

Aggregated Demand, 6/22/2006 (OAT: 99 °F) - Zone 2, 9 sites

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.00:

00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00

9:00

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Pow

er [M

W]

Target HaywardOracle RocklinIKEA EPaloAltoGilead 357Gilead 342Gilead 300EchelonMDF50 Douglas2530 ArnoldChabotB of AACWDCPP BLAdj Avg BLOAT Reg BLAdj OAT Reg BL

Moderate Price High Price

Page 17: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Max Ave Max Ave Max AveMod. Price 836 726 0.42 0.36 8% 7%High Price 1336 1150 0.67 0.58 13% 11%

Price Level kW W/ft² WBP%

Aggregated Demand, 6/23/2006 (OAT: 84 °F) - Zone 1&2, 13 sites

0.0

2.0

4.0

6.0

8.0

10.0

12.00:

00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00

9:00

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Pow

er [M

W]

Target HaywardOracle RocklinIKEA EPaloAltoGilead 357Gilead 342Gilead 300EchelonMDF50 Douglas2530 ArnoldChabotB of AACWDCPP BLAdj Avg BLOAT Reg BLAdj OAT Reg BL

Moderate Price High Price

Page 18: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Max Ave Max Ave Max AveMod. Price 669 540 0.56 0.45 12% 9%High Price 955 852 0.80 0.71 16% 15%

Price Level kW W/ft² WBP%

Aggregated Demand, 7/24/2006 (OAT: 95 °F) - Zone 1&2, 11 sites

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.00:

00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00

9:00

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Pow

er [M

W]

Target HaywardOracle RocklinIKEA EPaloAltoGilead 357Gilead 342Gilead 300EchelonMDF50 Douglas2530 ArnoldChabotB of AACWDCPP BLAdj Avg BLOAT Reg BLAdj OAT Reg BL

Moderate Price High Price

Page 19: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Max Ave Max Ave Max AveMod. Price 689 483 0.47 0.33 8% 6%High Price 1175 1106 0.81 0.76 13% 13%

Price Level kW W/ft² WBP%

Aggregated Demand, 7/25/2006 (OAT: 101 °F) - Zone 2, 8 sites

0.0

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

9.0

10.00:

00

1:00

2:00

3:00

4:00

5:00

6:00

7:00

8:00

9:00

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

Pow

er [M

W]

Target HaywardOracle RocklinIKEA EPaloAltoGilead 357Gilead 342Gilead 300EchelonMDF50 Douglas2530 ArnoldChabotB of AACWDCPP BLAdj Avg BLOAT Reg BLAdj OAT Reg BL

Moderate Price High Price

Page 20: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Aggregated Demand Saving, 7/24/2006 (Max OAT: 103 °F)7 Buildings (Zone 2), Total 0.75 million ft²

-0.2

0.0

0.2

0.4

0.6

0.8

1.010

:00

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

Ag

gre

gat

ed D

eman

d S

avin

g [

MW

]

Moderate Price High Price

Page 21: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

People did not like lighting reduction and some turned zones back on as CPP days continued. (manual DR)

Sybase

Comfort complaints so plan to implement pre-cooling, more gradual temperature changes and changes in programming to exclude corner offices with double sun exposure

Oracle

Occupants realized it is not getting cooler in the afternoon but no complaints Contra Costa

Too cool in the morning, hot in the afternoonChabot

Some comfort concernsB of A

Some complaints of high temperature but company found innovative ways to reduce complaints. Manual pre-cooling in some zones.

ACWD

Comfort IssuesSite

DR savings too small. Realized need to refine DR strategies to avoid demand charges.

Echelon

DR savings too small for hassle they have endureContra Costa

DR savings too smallB of A

Surprised by high utility bill.ACWD

Program/Tariff IssuesSite

IKEA, Gilead and Target worked fine – no complaints or issues report.

Feedback from Facility Managers

Page 22: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

What is AutoDR? • Enabling technology & processes• Can automate any DR program• Facility managers are notified, but not required for

automated sheds to occur.• Defines standard interfaces for many parties to use.

• Individual Sites• Multi-Site Energy Managers• Aggregators• EMCS Companies

• Reliable, Secure, Scalable, Open

What is NOT AutoDR?

• Doesn’t change decision making processes within utility• Doesn’t compete with aggregators (lowers their costs)

Page 23: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

AutoDR Technical Developments 2003 – present

• AutoDR was created as part of the DRRC effort to remove impediments to DR in commercial facilities. Cost effectiveness, process development & scalability were overriding principals.

• Barrier: HVAC strategies complicated and ineffective • Solution: Global Temperature Adjustment (GTA) strategy.

• Slated for Title 24 code in 2008. • Enable DR in commercial building at no additional cost. • Proven to be simple, effective & minimally objectionable

• Barrier: Too labor intensive • Solution: Automated DR with pre-planned strategies

Page 24: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

AutoDR Technical Developments 2003 – present

• Barrier: Auto-DR signal transmission infrastructure too expensive.

• Solution: DRAS leverages existing Internet and WAN connections in commercial buildings.

• Barrier: Internet signals not standardized • Solution: DRRC is working with CA PCT, NIST and

BACnet toward signal standardization

Page 25: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

AutoDR Technical Developments 2003 – present

• Barrier: Internet signals and protocols too complicated to transfer into existing EMCS

• Solution: Internet relays are easily read by all existing EMCS. • Can be used for direct load control as well

• Barrier: Internet relays are difficult to configure and are inherently insecure.

• Solution: DRRC developed self configuring, secure Internet relay device; CLIR Box (Client, Logic, w/ Integrated Relay). • Prototyped in 2005

Page 26: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Background: DR Automation Server ver. 1

• Used in 2003 & 2004 Auto-DR Tests• Served research needs• No formal design process was used• Limitations became apparent in 2004

• Not flexible • Not scalable• High latency• Not reliable

Page 27: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

DR Automation Server ver. 2 & 3

• Used in the PG&E / LBNL pilots in 2005 & 2006• Financial transactions based on the functionality• Needed to meet IT industry standards for

• Flexibility - variety of Auto-DR programs• High availability/reliability – Specified Goal: 99.99% • Scalability – 100,000 + • Security - A security breech could become a major public

relationship setback to the industry.

Page 28: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Web Browser Interface to DR Automation Server (DRAS)

What does it look like?

Page 29: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline
Page 30: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline
Page 31: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline
Page 32: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline
Page 33: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Electric Loads

CC C

EMCS Protocol

GTWY

Internet

PG&EDR Automation

Server

Individual Sites

Nacio Hosting Facility

Novato, CA

`

PG&E DR Event

Notification System (Itron)

XML SoftwareGateway

ElectricLoads

CC C

EMCS Protocol

GTWY

CC C

EMCS Protocol

C

CLIRBox

Electric Loads

CC C

EMCS Protocol

GTWY

Electric Loads

CC C

EMCS Protocol

GTWY

Multi-Site Organization(Target, Ikea, CC Gov’t)

Multi-Site Energy Mngr. (Target, CC Gov�t)

ElectricLoads

XML SoftwareGateway

Page 34: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Electric Loads

CC C

EMCS Protocol

GTWY

Internet

EdisonDR Automation

Server

Individual Sites

Nacio Hosting Facility

Novato, CA

`

Edison DR Event

Notification System (System X)

XML SoftwareGateway

ElectricLoads

CC C

EMCS Protocol

GTWY

CC C

EMCS Protocol

C

CLIRBox

Electric Loads

CC C

EMCS Protocol

GTWY

Electric Loads

CC C

EMCS Protocol

GTWY

Multi-Site Organization

Multi-Site Energy Mngr.

(EnerNOC, Comverge, EnergyICT,

Target)

ElectricLoads

XML SoftwareGateway

Page 35: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline
Page 36: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Nacio Inc. Hosting Facility(aka: Server Farm)

Page 37: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Multi-Layer Physical Security

•Intrusion (5 layer)

•Fire

•Earthquake

Redundant:

•Internet Feeds

•Power-Supplies, Generators

•HVAC

•Servers, RAID arrays

24/7 Staffing

•Network Management “hooks” into DRAS Application

Nacio Facilities

Page 38: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Nacio Co-Location

Page 39: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Nacio Control Center

Page 40: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Program Mngr.

AutoDR 2006 Task Chronology 2 MW (13 sites)

Figure Version 9-20-06

Rec

ruitm

ent

Phas

eSt

rate

gy

Def

initi

on P

hase

Impl

emen

taio

n Ph

ase

Recruiter

Program Mngr. Tech

Coord.

IOU Acct. Mngr.

Sr. Owner Rep.

Program Mngr. Tech

Coord.

Contract

Facility Mngr.

Facility Mngr.

EMCS Contractor

Spec for EMCS

Tim

e Ti

me

Tim

e

EMCS Contractors � Install CLIR boxes, perform �hands-on� programming & other upgrades to implement DR Strategies at the site. Typically, EMCS Contractor with existing relationship with owner and site must be used. Payment via site owner using TI funds.

Tech Coordinators must be able to support technical aspects of �connecting� sites to the DRAS. They assist the site facility mngr in directing the local EMCS contractor to perform necessary upgrades. Tech coordinators evaluate sites for �ease of AutoDR� and help suggest shed strategies. They also coordinate with the site IT mngr. to hook-up the CLIR box or XML software gateway. LBNL and C&C in 2006

Recruiters: Provide focused effort to secure sales targets. Must be able to convince senior property management to sign-up for AutoDR program(s). Need some technical knowledge but more importantly, must be motivated to successfully close deals. Works in concert with IOU account rep. to the degree that they require. Gets leads from utility and other sources. Two LBNL recruiters started late and brought on less than 5 new sites in 2006.

Sr. Owner’s Rep: Decision maker for energy purchases. Owner�s reps with decision-making power for multiple sites should be

targeted. . 5X?

IT ManagerDRAS Manager

IT Manager � Typically on-site personnel and their network implementers (cable to CLIR box etc.)

DRAS Manager � Assign passwords to new DRAS accounts. Connect to proper automation channel etc. LBNL in 2006

Facility Manager: Day to day operations at the site. Works w/ tech coord to define strategies. Lets subcontracts to EMCS contractor and IT implementers.

Program Manger (LBNL): Provides marketing strategies, collateral material, subcontractor management. Responsible for meeting overall project goals.

IOU Account Manager: �Owns� customer relationship. Assists LBNL recruiter with providing leads, internal IOU paperwork etc. However, AutoDR is not the primary focus of their job.

10x5x

5x 20x

EMCS installed base

Trade orgs & other

Yellow Performed by LBNL in 2006

Tech Coord. Performed by LBNL and C&C Automation in 2006

Page 41: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Rec

ruitm

ent

Phas

eSt

rate

gy

Def

initi

on P

hase

Impl

emen

taio

n Ph

ase

Tim

e Ti

me

Page 42: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

AutoDR Implementation 2007

• Ready for deployment• Technology

• Effective• Secure• Reliable

• Processes• Well defined • Scalable

• Standard Interfaces• Designed for flexibility

• Multiple programs• Multiple user types

Page 43: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Future Directions/PIER Activities

• Research Topics• Analysis of sheds by building type, end-

use, market segment, climate• DR shed prediction tools and guides• Improving links between efficiency and DR• Economic analysis • DR Automation System enhancements

• Retail Chains, property managers etc. would like a statewide view the DR status of all of their stores

Page 44: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Compare/Confirm Field Data with HVAC Theory

Page 45: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Electric Loads

CC C

EMCS Protocol

GTWY

Internet

EdisonDR Automation

Server

Individual Sites

Nacio Hosting Facility

Novato, CA

`

Edison DR Event

Notification System (System X)

XML SoftwareGateway

ElectricLoads

CC C

EMCS Protocol

GTWY

CC C

EMCS Protocol

C

CLIRBox

Electric Loads

CC C

EMCS Protocol

GTWY

Electric Loads

CC C

EMCS Protocol

GTWY

Multi-Site Organization

Multi-Site Energy Mngr.

(EnerNOC, Comverge, EnergyICT,

Target)

ElectricLoads

XML SoftwareGateway

Electric Loads

CC C

EMCS Protocol

GTWY

Internet

SDGEDR Automation

Server

Individual Sites (Whole Foods)

Nacio Hosting Facility

Novato, CA

`

SDGE DR Event

Notification System(Power Measurement Corp)

XML SoftwareGateway

ElectricLoads

CC C

EMCS Protocol

GTWY

CC C

EMCS Protocol

C

CLIRBox

Electric Loads

CC C

EMCS Protocol

GTWY

Electric Loads

CC C

EMCS Protocol

GTWY

Multi-Site Organization

Multi-Site Energy Mngr.

(Target, GSA?)

ElectricLoads

XML SoftwareGateway

Statewide Views:Trans-Utility Energy Manager •Retail Chains, Gov’t Bldgs, Property Managers

Research for 2007

Page 46: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

! Ideal start - good commissioning, retro-commissioning, advanced/new controls! HVAC - Direct digital control (DDC)

global temperature adjustment • In process for Title 24 2008• Closed loop

! Lighting Continuum - Zone Switching, Fixture Switching, Lamp Switching, Stepped Dimming, Continuous Dimming

! Maybe you “can” use a strategy every day?

Desire to tryDR

Global temp.adjustment

DDC zonecontrol?

Y N

Global temp.Adjustmentcapability?

Y N

Central plantcontrol

Airdistribution

control

Air distributionSystem DDC?

Y N

Can program GTA?

Y N Central plantDDC?

Y N

Do not try DRat this time

Desire to tryDR

Global temp.adjustment

DDC zonecontrol?

Y NDDC zonecontrol?

Y N

Global temp.Adjustmentcapability?

Y NGlobal temp.Adjustmentcapability?

Y N

Central plantcontrol

Airdistribution

control

Air distributionSystem DDC?

Y NAir distributionSystem DDC?

Y N

Can program GTA?

Y NCan program GTA?

Y N Central plantDDC?

Y NCentral plantDDC?

Y N

Do not try DRat this time

Linking DR and Energy Efficiency

Page 47: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

! Objective – Embed DR strategies in advanced controls

! New York Times Building designed for efficiency simulated to develop DR strategies

• Efficient features: Integrated movable, Shading & dimming, Under floor air systems

• Commissioning in mockup

! Demand Response Strategies• Dimming lights beyond daylighting, • Reset zone temperatures (gradient)• Reduce perimeter fan speed

Predicted Annual Savings from 400 kW Shed

Program Predicted Annual Savings*

Independent Capacity Program $17,632.00 Emergency DR Program $1,440.00 Distribution Load Relief Program $1,600.00

Best Practices in New Construction

Page 48: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Questions???Comments???

Page 49: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Utility AutoDR FundsUtility TI Funds

CEC/PIER Funds

Site 1

Program Mngr

Recruiter & Tech Coord

Johnson

DRRC (LBNL)

Tech Coord Consultant

Tech Coord 3

Tech Coord X-Co EMCS

Tech Coord

DRAS Scale-up

CLIR Boxes

Site 2

Honeywell

Site 3

Vertical Market

Sites 41-80

Johnson

Sites 81-120

Johnson

Sites 121-160

Johnson

Sites 161-200

Johnson

Site A

Johnson

Sites 4-40

EMCS X, Y & Z

Sites 41-80

EMCS X, Y & Z

Sites 81-120

EMCS X, Y & Z

Sites 121-160

EMCS X-Co Sites

Sites 161-200

EMCS X, Y & Z

Recruiter

Recruiter X-Co

Recruiter 4

DRAS Hosting

Utility TI funds to each site for 1) EMCS mods2) Customer incentives 3) Recruiter or Tech Coord bonus?

PG&E AutoDR 2007 Funding Flow 15 MW (~ 200 sites)

Figure Version 9-20-06

Recruiters & Tech Coordinators work for the

Program Mngr. as employees or subs.

EMCS Contractors

Other Vendor Sites

Vendor Existing

Sites

Recruiter 4

Own and Other

Vendor Sites

Page 50: Statewide Auto-DR Planning Meeting · Pre-cooling Cooling valve limit Turn off light Dimmable ballast Bi-level switching # of sites ... Whole Bulding Power [kW] Actual LBNL Baseline

Automated DR Definition• Automated Demand Response for commercial and industrial facilities can be

defined as fully automated DR initiated by a signal from a utility or other appropriate entity and provide full automated connectivity to customer end-use control strategies.

• Signaling – The AutoDR technology should provide continuous, secure, reliable, two-way communication with end-use customers to allow end-use sites to be identified as listening and acknowledging receipt of DR signals.

• Industry Standards - Automated DR consists of open, interoperable industry standard control and communications technologies designed to integrate with both common energy management and control systems and other end-use devices that can receive a dry contact relay or similar signals (such as internet based XML).

• Timing of Notification - Day ahead and day of signals are provided by AutoDR technologies to facilitate a diverse set of end-use strategies such as pre-cooling for "day ahead“ notification, or near real-time communications to automation "day of" control strategies. Timing of DR automation server (DRAS) communications must consider day ahead events that include weekends and holidays.