TE EPC. Bulding 245 schedule update. LIU Booster Meeting 30-01-2014 Fulvio Boattini TE-EPC. Building 245 position. TE EPC. b245. MPSB Time Schedule. TE EPC. No ressources. Services Integration (EL, CV,..). GS/SE studies and procurement. Building construction. May 2016 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Bulding  245 schedule update

Bulding 245 schedule update

LIU Booster Meeting 30-01-2014Fulvio Boattini

TE-EPC

TE EPC

Page 2: Bulding  245 schedule update

Building 245 position

TE-EPC - Fulvio Boattini 2

TE EPC

b245

30/01/2014

Page 3: Bulding  245 schedule update

physics LS1 physics LS2 physics

2012 2013 2014 2015 2016 2017 2018 2019

May 2016Building ReadyNo ressources

Services Integration(EL, CV,..)

GS/SE studies and procurement

Building construction

October 2013March 2014 March 2015

FC

April 2017Start

Commissioning on dummy load

TE EPC

MPSB Time Schedule

Switching cabinets and cabling installation

30/01/2014 TE-EPC - Fulvio Boattini 3

Page 4: Bulding  245 schedule update

TE-EPC - Fulvio Boattini 4

TE EPCBuilding 245: electrical power needs

Power needs have been collected and EN/EL worked out a power network layout

30/01/2014

EN/EL needs detailed power departures from TE/EPC and EN/CV

Page 5: Bulding  245 schedule update

TE-EPC - Fulvio Boattini 5

TE EPCBuilding 245: electrical power needs

EN/EL prepared the first schematic of the LV network is now available.

Transformers:18k/0.4kV 2MVA; 800kVA

Switching cabinets

An UPS

30/01/2014

Page 6: Bulding  245 schedule update

Building 245: cooling pipes

TE-EPC - Fulvio Boattini 6

TE EPC

EN/CV proposed a path for the pipeworks

• 2 DN200 + 2DN100 pipes for PSB magnets cooling (from b245 to b361)

• 2 DN100 pipes for chilled water (from b361 to b245)

• 2 DN100 pipes for TT2 cooling (from b245 to b289)

30/01/2014

Page 7: Bulding  245 schedule update

Building 245: power cables

TE-EPC - Fulvio Boattini 7

TE EPC

BATIMENT 361 ETAGE 1 BATIMENT 271 ETAGE R

1-205

1-018

TP9

R-401

R-411

R-402

R-403

R-404

R-405

R-201

12.6 M2

CONTROL ELEMENTS

POWER ELEMENTS

CROWBAR

SWITCHBOARD

C: C11,12,13, C17,18,20

A: C9+C10+C14+C19+Control CablesB: C5÷C8+C15,16,21,22+Control Cables

D: C1÷C4

Cont

rol C

able

s

E: Dummy Load connection (from b367)

ME25

TE/EPC presented power cables paths

No spare magnets are needed anymore inside b245 as POPS spare magnets will be used for commissioning

18kV cables still to be added

EN/EL-TE/EPC shall verify the routing in a cad model

30/01/2014

Page 8: Bulding  245 schedule update

Building 245 layout

TE-EPC - Fulvio Boattini 8

TE EPC

30/01/2014

Page 9: Bulding  245 schedule update

Building 245 layout

TE-EPC - Fulvio Boattini 9

TE EPC

30/01/2014

Page 10: Bulding  245 schedule update

Building 245 layout (b271 side)

30/01/2014 TE-EPC - Fulvio Boattini 10

TE EPC

Page 11: Bulding  245 schedule update

Building 245 layout (Isolde side)

TE-EPC - Fulvio Boattini 11

TE EPC

30/01/2014

Page 12: Bulding  245 schedule update

Building 245 layout

TE-EPC - Fulvio Boattini 12

TE EPC

30/01/2014

Page 13: Bulding  245 schedule update

Building 245 layout

TE-EPC - Fulvio Boattini 13

TE EPC

30/01/2014

Page 14: Bulding  245 schedule update

Building 245 layout

TE-EPC - Fulvio Boattini 14

TE EPC

30/01/2014

Page 15: Bulding  245 schedule update

Building 245 layout

TE-EPC - Fulvio Boattini 15

TE EPC

30/01/2014

Page 16: Bulding  245 schedule update

TE EPC

MPSB Time Schedule

INTEGRATION PROJECT OPEN POINTS:• EN/CV needs to work more on layout design of the cooling part• EN/EL TE/EPC need to find a solution for the EN/EL cabinets layout.

EN/EL is starting to test two solutions on the 3D model but more detailed input from EN/CV is needed.

• Cost estimation needs to be provided by all services of the building

INTEGRATION PROJECT CRITICAL POINTS:• EN/CV announced Glen will have no time for completing the design the

cooling components. Michel will replace him during his absence, but in the whole process we take more than one month of delay.

30/01/2014 TE-EPC - Fulvio Boattini 16

Page 17: Bulding  245 schedule update

TE-EPC - Fulvio Boattini 17

THANKS FOR THE ATTENTION

QUESTIONS?

Bulding 245 schedule update

TE EPC

30/01/2014

Page 18: Bulding  245 schedule update

TE EPC

Building 245 layout

30/01/2014 TE-EPC - Fulvio Boattini 18

EN/EL proposal for Electrical Room