project risk management - session 3
TRANSCRIPT
DR. D.N.S.KUMAR
Project Risk Management
WHAT IS RISK ?
Something THAT MAY HAPPEN and if it does, will HAVE ADVERSE impact on a project
Risk Vs Uncertainty
Risk - when the decision maker knows the probability of each and every state of nature and thus each and every outcome. An expected value of each alternative action can be determined
Uncertainty - when a decision maker has information that is not complete and therefore cannot determine the expected value of each alternative
Types of Project Risks
Approaches to Risk Analysis
Approaches that consider the stand-alone risk of project (sensitivity-analysis, scenario analysis, break-even analysis, Hiller mode, simulation analysis, and decision tree analysis).
Approaches that consider the contextual risk of a project (corporate risk analysis and market risk analysis).
Corporate Risk Analysis
A projects corporate risks is its contribution to the overall risk of the firm. Put differently, it is reflects the impact of the project on the risk profile of the firm’s total cash flows. On a stand-alone basis a project may be very risky but if its returns are not highly correlated- or, even better, negatively correlated-with the returns on the other projects of the firm, its corporate risk tends to be low.
Sources of Risk
Size of the investment
Reinvestment of cash flows
Variability of cash flows
Life of the project
Risk Analysis
Principal contribution of risk analysis is to focus the attention on understanding the nature and extent of the uncertainty associated with some variables used in a decision making process
Usually understood to use financial measures in determining the desirability of an investment project
Pre Construction Risks
Construction Contract Penalties
Arbitration Process
Technology Risk
Market Demand Risk
Structural Risk
Opening of a Project Risk
During Construction
Construction Delay
Cost overrun
Zoning and Regulatory Risk
Permitting Risk
Environmental Risk
Title Risk
Contractor Risk
During Construction….contd.,
Design and Engineering Risk Materials Risk Labor Risk Natural Hazard Risk Political Risk LitigationsWorkmanship Risk
Post Construction
Management Experience Economic Conditions Demand GapCatastrophic Events Concession Risks O&M Risk Flow of Funds
MANAGEMENT / MITIGATION OF RISK INVOLVES
Risk identification in the selected domain of interestAllocation of risk to various competent partiesRisk quantificationRisk monitoringResponse and controlComprehensive contractual frameworkAdequate insurance coverageKeeping risk within acceptable limits
RISK CATEGORIES
Risk Category Significant Risks Phase of Predominance
Statutory and Regulatory Risks
Right to collect, retain and appropriate user charge
Right to fix the user charges Obtaining approvals and
clearances from authorities Land acquisition/right of way
Project Development period
Design & Development Risk
Design defect Construction difficulties
Project development/ construction period
Completion Risk Cost overrun Time overrun Fund Mobilisation Institutional Arrangement
Construction period
Performance and Operation Risk
Failure to meet performance criteria
Operating cost overrun
Operation period
Revenue Risk Changes in user charge Changes in chargeable volume
Operation period
Contd..
Risk Category Significant Risks Phase of Predominance
Finance Risk Interest rates Change in tax regime Forex rate fluctuation
Operation period
Force Majeure Risk Acts of God (non political event) viz. flood, earthquake etc.
Political event, viz. changes in law, breach or cancellation of contract
Throughout the project period
Social Risk Resettlement and Rehabilitation
Project development/ construction period
Environmental Risk Environmental incidents Construction and Operation period
Insurable Risk Casualty
Third Party Liability
Workmen’s compensation
Through the period from project development, completion and operation period
RISK CATEGORIES
RISK ANALYSIS
RISK MANAGEMENT / MITIGATION
MANAGEMENT / MITIGATION PLANRisk Category / Description
Risk Mitigation Instrument / Allocation
Failure to obtain Approvals and Clearances from the concerned Authorities
CA necessitates prior clearance from the GOI/GOWB, failure of which will result in termination of agreement and financial losses to be borne by the Authority
Instrument:- Concession Agreement (CA)
Allocation:- The Authority
Delays in Land Acquisition and Right of Way
Allotment of physically encumbrance-free land achieved through prior Social Assessment studies by identifying the project affected land and adequate cost estimates.
Instrument:- Concession Agreement, Lease Deed
Allocation:- The Concessionaire
Delay in Project Development activities
The onus of expeditious completion of the project falls on the Concessionaire
Instrument:- Concession Agreement
Allocation:- The Concessionaire
Time over-runs due to Contractor’s default
Being an equity partner, the onus of early completion of the project lies on the Concessionaire.
Levy of penalty and liquidated damages in case of default
Instrument:- Construction Contract
Allocation – The Concessionaire
Contd…
Management / Mitigation PlanRisk Category /
Description Risk Mitigation Instrument/
AllocationCost overruns Carry out detailed engineering
surveys & investigations during Project Development Phase
Extension in the Concession period till the desired rate of return is achieved
Instrument:-Concession Agreement
Allocation:-the Concessionaire Contractor
Non realisation of Operation Revenue because of lower offtake, user charge leakage and avoidance
Accurate demand projections in Project Report
Proper monitoring and reporting mechanism as well as independent audits of user charge operations
Instrument:-Concession Agreement
Allocation:- the Concessionaire, O&M Contractor
Force Majeure Political / Termination Risk
Adequate compensation in case of imposition of new laws and tax structure, withdrawal of tax holidays or restrictions on Forex transfer
Reimbursement of outstanding dues to the project lenders and a pre-agreed return to the equity investors in case of termination because of policy change by the government
Instrument:-Concession Agreement
Allocation:-The Concessionaire
Contd…
Management / Mitigation Plan (Contd…)
Risk Category / Description
Risk Mitigation Instrument/ Allocation
Financial Risk due to drastic change in the interest and tax rates
Project to be financed through an optimal mix of fixed rate and floating rate instruments
Instrument:- Lender’s Agreement
Allocation:- The Concessionaire
Financial Risk – Exchange rate risk
Financing arrangement to be made to swap the Forex debt for equivalent Rupee debt when exposed to the risk of currency devaluation
Instrument:- Financing Agreements
Allocation:- The Concessionaire
Financial Risk – Inflation Risk
Provision for inflation adjustment of costs in CA. The Concessionaire would bear the inflation risk accordingly
Instrument:- Concession Agreement
Allocation:- the Concessionaire
The attractiveness of a PPP project depends on the risk perception of the private sector
Risks may be analysed and mitigated using available technological, human and organizational resources
If risks can be reasonably allocated and an effective management and mitigation plan built into the agreements, then private sector participation in infrastructure projects can be ensured.