session 11 risk analysis in cbgrd
TRANSCRIPT
-
8/13/2019 Session 11 Risk Analysis in CBgrd
1/37
Risk Analysis In Capital Budgeting
-
8/13/2019 Session 11 Risk Analysis in CBgrd
2/37
Findings from CFO Survey
Method % of companies rating it
as imp
Sensitivity analysis 90.10%
Scenario Analysis 61.60%
Risk Adjusted Discount Rate 31.70%
Decision Tree Analysis 12.20%Monte Carlo simulation 8.20%
-
8/13/2019 Session 11 Risk Analysis in CBgrd
3/37
Risk and Uncertainty
Risk is referred to a situation where the
probability distribution of the cash flow of an
investment proposal is known.
If no information is available to formulate a
probability distribution of the cash flows thesituation is known as uncertainty.
3
-
8/13/2019 Session 11 Risk Analysis in CBgrd
4/37
Sources and Perspective of Risk
Sources of Risk
Project-specific risk
Competitive risk
Industry-specific risk
Market risk International risk
Perspectives on Risk
Standalone risk
Firm risk
Market risk
-
8/13/2019 Session 11 Risk Analysis in CBgrd
5/37
Techniques For Risk Analysis
Techniques of risk
analysis
Analysis of stand-
alone risk
Analysis of
contextual risk
Sensitivity
analysis
Break-even
analysis
Simulation
analysis
Scenario
analysis
Corporate
risk analysis
Market risk
analysis
Decision tree
analysis
-
8/13/2019 Session 11 Risk Analysis in CBgrd
6/37
Certainty-Equivalent..Example If you invest in stock than there are two
possible outcomes: 0.6 probability of receiving 10,000
0.4 probability of receiving 5,000
If you keep money in fixed deposit 1.00probability of receiving 7000
Certainty equivalent is 7000/8000 = 0.875
-
8/13/2019 Session 11 Risk Analysis in CBgrd
7/37
Certainty-Equivalent
Reduce the forecasts of cash flows to some conservativelevels.The certainty-equivalent coefficient assumes a value
between 0 and 1, and varies inversely with risk. Decision-makersubjectively or objectively establishes the coefficients.
The certaintyequivalent coefficient can be determined as a
relationship between the certain cash flows and the risky cashflows.
7
=0
NCFNPV =
(1 )f
nt t
tt k
*NCF Certain net cash flow =
NCF Risky net cash flow
tt
t
-
8/13/2019 Session 11 Risk Analysis in CBgrd
8/37
Example
8
-
8/13/2019 Session 11 Risk Analysis in CBgrd
9/37
Risk-Adjusted Discount Rate Can we discount all kind of projects from same
discount rate (WACC) ?
-
8/13/2019 Session 11 Risk Analysis in CBgrd
10/37
Risk-Adjusted Discount Rate
Risk-adjusted discount rate, will allow for both timepreference and risk preference and will be a sum of the risk-free rate and the risk-premium rate reflecting the investorsattitude towards risk.
Under CAPM, the risk-premium is the difference between themarket rate of return and the risk-free rate multiplied by the
beta of the project.
10
= 0
NCFNPV =
(1 )
n t
t
t k
f rk = k + k
-
8/13/2019 Session 11 Risk Analysis in CBgrd
11/37
RADR in Practice..Example
Investment Category RADR
Replacement Investments WACC
Expansion Investments WACC + 3%
Investment in related lines WACC + 6%
Investment in new line WACC + 10%
-
8/13/2019 Session 11 Risk Analysis in CBgrd
12/37
Example
12
-
8/13/2019 Session 11 Risk Analysis in CBgrd
13/37
Example
13
-
8/13/2019 Session 11 Risk Analysis in CBgrd
14/37
Risk-adjusted Discount Rate: Merits
It is simple and can be easily understood.
It has a great deal of intuitive appeal for risk-aversebusinessman.
It incorporates an attitude (risk-aversion) towardsuncertainty.
14
-
8/13/2019 Session 11 Risk Analysis in CBgrd
15/37
Risk-adjusted Discount Rate: Limitations
There is no easy way of deriving a risk-adjusted discount rate.CAPM provides a basis of calculating the risk-adjusteddiscount rate.
It does not make any risk adjustment in the numerator for thecash flows that are forecast over the future years.
It is based on the assumption that investors are risk-averse.Though it is generally true, yet there exists a category of risk
seekers who do not demand premium for assuming risks; theyare willing to pay a premium to take risks.
15
-
8/13/2019 Session 11 Risk Analysis in CBgrd
16/37
Sensitivity Analysis
Sensitivity analysis is a way of analysingchange in the projectsNPV (or IRR) for agiven change in one of the variables.
The decision maker, while performingsensitivity analysis, computes the projectsNPV (or IRR) for each forecast under threeassumptions:
pessimistic, expected, and optimistic.
16
-
8/13/2019 Session 11 Risk Analysis in CBgrd
17/37
Sensitivity Analysis
The following three steps are involved in the use ofsensitivity analysis:
1. Identification of all those variables, which have an
influence on the projects NPV (or IRR).2. Definition of the underlying (mathematical) relationship
between the variables.
3. Analysis of the impact of the change in each of thevariables on the projects NPV.
17
Sensitivity Analysis
-
8/13/2019 Session 11 Risk Analysis in CBgrd
18/37
Sensitivity Analysis(000)
YEAR 0 YEAR 1 - 10
1. INVESTMENT (20,000)
2. SALES 18,000
3. VARIABLE COSTS (66 2/3 % OF SALES) 12,000
4. FIXED COSTS 1,000
5. DEPRECIATION 2,000
6. PRE-TAX PROFIT 3,000
7. TAXES 1,000
8. PROFIT AFTER TAXES 2,000
9. CASH FLOW FROM OPERATION 4,000
10. NET CASH FLOW 4,000
NPV = -20,000,000 + 4,000,000 (5.650) = 2,600,000 ( discount rate = 12 % )
RS. IN M IL LI ON
RANGE NPV
KEY VARIABLE PESSIM ISTIC EXPECTED OPTIM ISTIC PESSIM ISTIC EXPECTED OPTIMI STIC
INVESTMENT (RS. IN MILLION) 24 20 18 -0.65 2.60 4.22
SALES (RS. IN MILLION) 15 18 21 -1.17 2.60 6.40
VARIABLE COSTS AS A 70 66.66 65 0.34 2.60 3.73
PERCENT OF SALES
FIXED COSTS 1.3 1.0 0.8 1.47 2.60 3.33
-
8/13/2019 Session 11 Risk Analysis in CBgrd
19/37
-
8/13/2019 Session 11 Risk Analysis in CBgrd
20/37
Sensitivity Analysis: Pros and Cons
It does not provide clear-cut results. The termsoptimistic and pessimistic could mean differentthings to different persons in an organisation. Thus,the range of values suggested may be inconsistent.
It fails to focus on the interrelationship betweenvariables. For example, sale volume may be relatedto price and cost. A price cut may lead to high sales
and low operating cost.
20
-
8/13/2019 Session 11 Risk Analysis in CBgrd
21/37
Scenario Analysis
One way to examine the risk of investment isto analyse the impact of alternativecombinations of variables, called scenarios,on
theprojectsNPV (or IRR).
The decision-maker can develop some
plausible scenarios for this purpose. Forinstance, we can consider three scenarios:pessimistic, optimistic and expected.
21
-
8/13/2019 Session 11 Risk Analysis in CBgrd
22/37
Pessimistic, Normal And Optimistic Scenario
PessimisticScenario
ExpectedScenario
OptimisticScenario
1. Investment 24 20 18
2. Sales 15 18 21
3. Variable costs 10.5 (70%) 12 (66.7%) 13.65 (65%)4. Fixed costs 1.3 1.0 0.8
5. Depreciation 2.4 2.0 1.8
6. Pre-tax profit 0.8 3.0 4.75
7. Tax 0.27 1.0 1.588. Profit after tax 0.53 2.0 3.17
9. Annual cash flow from operations 2.93 4.0 4.97
10. Net present value
(9) x PVIFA (12%, 10 yrs)(1)
(7.45) 2.60 10.06
-
8/13/2019 Session 11 Risk Analysis in CBgrd
23/37
Simulation Analysis
The Monte Carlosimulation or simply the simulation analysisconsiders the interactions among variables and probabilities ofthe change in variables. It computes the probability distributionof NPV.
The simulation analysis involves the following steps:
First, you should identify variables that influence cash inflows andoutflows.
Second, specify the formulae that relate variables.
Third, indicate the probability distribution for each variable.
Fourth, develop a computer programme that randomly selects one valuefrom the probability distribution of each variable and uses these values tocalculate theprojectsNPV.
23
-
8/13/2019 Session 11 Risk Analysis in CBgrd
24/37
Simulation Analysis: Shortcomings
The model becomes quite complex to use.
It does not indicate whether or not the
project should be accepted.
Simulation analysis, like sensitivity or
scenario analysis, considers the risk of any
project in isolation of other projects.
24
B k A l i
-
8/13/2019 Session 11 Risk Analysis in CBgrd
25/37
Break-even Analysis
Accounting Break-even Analysis
FIXED COSTS + DEPRECIATION 1 + 2
= = RS. 9 MILLIONCONTRIBUTION MARGIN RATIO 0.333
CASH FLOW FORECAST FOR NAVEENS FLOUR MILL PROJECT
(000)YEAR 0 YEAR 1 - 10
1. INVESTMENT (20,000)
2. SALES 18,000
3. VARIABLE COSTS (662/3% OF SALES) 12,000
4. FIXED COSTS 1,000
5. DEPRECIATION 2,000
6. PRE-TAX PROFIT 3,000
7. TAXES 1,000
8. PROFIT AFTER TAXES 2,000
9. CASH FLOW FROM OPERATION 4,000
10. NET CASH FLOW (20,000) 4,000
Cash Break-even Analysis
-
8/13/2019 Session 11 Risk Analysis in CBgrd
26/37
DCF Break-even Analysis
Sensitivity analysis is a variation of the break-evenanalysis.
DCF break-even point is different from the accounting
break-even point. The accounting break-even point isestimated as fixed costs divided by the contribution ratio. Itdoes not account for the opportunity cost of capital, andfixed costs include both cash plus non-cash costs (such asdepreciation).
26
-
8/13/2019 Session 11 Risk Analysis in CBgrd
27/37
Simulation Analysis
Procedure
1. Choose variables whose expected values will be replaced withdistributions
2. Specify the probability distributions of these variables
3. Draw values at random and calculate NPV
4. Repeat 3 many times and plot distribution
5. Evaluate the results
-
8/13/2019 Session 11 Risk Analysis in CBgrd
28/37
Decision Trees for Sequential Investment Decisions
Investment expenditures are not an isolatedperiod commitments, but as links in a chain ofpresent and future commitments.
An analytical technique to handle the sequentialdecisions is to employ decision trees.
28
-
8/13/2019 Session 11 Risk Analysis in CBgrd
29/37
Steps In Decision Tree Approach
Define investment
Identify decision alternatives
Draw a decision tree
decision points chance events
Analyse data
29
-
8/13/2019 Session 11 Risk Analysis in CBgrd
30/37
Electric Bike Project
An automobile company is planning to develop anew product electric bike. Project will cost Rs. 20
million and will take 6 months. 70% chance that
in pilot production and testing product will be
successful. The company require to invest Rs. 150
million to built a new plant and plant will generate
Rs. 30 million for 20 years, if demand is high. If
demand is moderate than project will generate Rs.20 million. Probability of high demand is 0.4. The
discount rate is 12%.
Decision Tree Analysis
-
8/13/2019 Session 11 Risk Analysis in CBgrd
31/37
Decision Tree Analysis
STEPS
DELINEATE THE DECISION TREE
EVALUATE THE ALTERNATIVESC21: HD ANNUAL CASH FLOW
0.6 30 MILLION
D21: INV
C2 EMV (C2) = RS.194.2 m
150 m
C11: S
D2 EMV (D2) = RS.44. 2 m C22: LD ANNUAL CASH FLOW
p : 0.7 0.4 20 MILLION
D11: PILOT PROD
C1 EMV (C1) = RS.30. 9 m D22: STOP
& TEST MKTG
- RS.20 m C12: F
D1 EMV (D1) = RS.10. 9 m D3 D31: STOP
p : 0.3
D12: DO NOTHING
A l i
-
8/13/2019 Session 11 Risk Analysis in CBgrd
32/37
Analysis
1. Start at thee right hand end of the tree and
calculate the NPV at chance point C2 thatcomes first as we proceed left
-
8/13/2019 Session 11 Risk Analysis in CBgrd
33/37
Usefulness of Decision Tree Approach
Clarity: It clearly brings out the implicitassumptions and calculations for all to see,question and revise.
Graphic visualization: It allows a decisionmaker to visualise assumptions andalternatives in graphic form, which is
usually much easier to understand than themore abstract, analytical form.
33
-
8/13/2019 Session 11 Risk Analysis in CBgrd
34/37
Decision Tree Approach: Limitations
The decision tree diagrams can become moreand more complicated as the decision makerdecides to include more alternatives and morevariables and to look farther and farther intime.
It is complicated even further if the analysis is
extended to include interdependentalternatives and variables that are dependentupon one another.
34
-
8/13/2019 Session 11 Risk Analysis in CBgrd
35/37
Risk Analysis in Practice
Most companies in India account for risk whileevaluating their capital expenditure decisions.
The following factors are considered to influence
the riskiness of investment projects: price of raw material and other inputs
price of product
product demand
government policies
technological changes
project life
inflation
35
-
8/13/2019 Session 11 Risk Analysis in CBgrd
36/37
Risk Analysis in Practice
Four factors thought to be contributing most tothe project riskiness are: selling price
product demand
technical changes
government policies
Methods of risk analysis in practice are: sensitivity analysis
conservative forecasts
36
-
8/13/2019 Session 11 Risk Analysis in CBgrd
37/37
Case Exercises
Richa Foods Limited
Weston Plastic
Airways Limited