LIFE CYCLE COST (LCC)

GROUP MEMBERSAHMAD OSMAN BIN RAMELI EC10035NURNABIHA BINTI ISMAILEC10028NORAZALIA BINTI ISHAKEA10055NUR HIZA’IZZATI MUSTAZAEC10044

Page 2: Presentation maintenance (lcc)

DEFINITION• Life cycle cost is the total cost of ownership

of machinery and equipment, including its cost of acquisition, operation, maintenance and conversion.• LCC are summations of cost estimates from

inception to disposal for both equipment and projects.

Page 3: Presentation maintenance (lcc)

OBJECTIVE• The objective of LCC analysis is to

choose the most cost effective approach from a series of

alternatives to achieve the lowest long-term cost of ownership.

Page 4: Presentation maintenance (lcc)

WHY USE LCC ? REASON 1

LCC helps change provincial perspectives for business issues with emphasis on enhancing economic competitiveness by working for the lowest long term cost of ownership. Consider these typical problems and conflicts observed in most companies:

1. Project Engineering wants to minimize capital costs as the only criteria. 2. Maintenance Engineering wants to minimize repair hours as the only criteria. 3. Production wants to maximize uptime hours as the only criteria. 4. Reliability Engineering wants to avoid failures as the only criteria. 5. Accounting wants to maximize project net present value as the

only criteria. 6. Shareholders want to increase stockholder wealth as the only criteria.

Page 5: Presentation maintenance (lcc)

• LCC can be used as a management deci-sion tool

for harmonizing the never ending con-flicts by focusing on facts, money, and time.

Page 6: Presentation maintenance (lcc)

WHY USE LCC ? REA-SON 2

• The discount rate is important in order to make

economic decisions easy for engineers. Dis-count factors reflect a host of relationships and considera-tions which include very low risk investment returns.

Page 7: Presentation maintenance (lcc)

WHY USE LCC ? REA-SON 3

• To get a least negative net present value(NPV) Engineering always want a simple, single value, crite-ria for a

project.• NPV is the present value of proceeds minus present

value of spend. Projects and processes with the greatest NPV is usually the winner. Often for incremental changes on a project or within a plant, you lack enough details to arrive at a positive NPV.

• Thus many improvement projects must be selected on the least negative NPV values from many alternatives.

Page 8: Presentation maintenance (lcc)

• internal accounting reports of profit/loss and for calculating NPV.

• Straight line depreciation is based on con-sumption of a fixed percentage of the equipment cost.

• Often straight line depreciation is used for internal accounting reports of profit/loss and for calculatingNPV.

Page 9: Presentation maintenance (lcc)

STEPS

Page 10: Presentation maintenance (lcc)

BASIC TREE FOR LCC

The basic tree for LCC is combination of Acquisition Costs

and Sustaining Costs“memory jogger”

Page 11: Presentation maintenance (lcc)
Page 12: Presentation maintenance (lcc)
Page 13: Presentation maintenance (lcc)

CALCULATION METHOD

• General Formula for LCC

• LCC = Total LCC in present-value dollars of a given alternative

• Ct = Sum of all relevant costs, including initial and future costs, less any positive cash flows, occurring in year t

• N = Number of years in the study period• d = Discount rate used to adjust cash flows to

present value.

Page 14: Presentation maintenance (lcc)

CALCULATION METHOD

• Simplified Formula for LCC

• LCC = Total LCC in present-value dollars of a given al-ternative

• I = Present-value investment costs• Repl = Present-value capital replacement costs• Res = Present-value residual value (resale value, scrap

value, salvage value) less disposal costs

• E = Present-value energy costs• W = Present-value water costs• OM&R = Present-value non-fuel operating, mainte-

nance, and repair costs.

Page 15: Presentation maintenance (lcc)