pmp exam preparation course: 06 project cost management

Download PMP Exam Preparation Course: 06 Project Cost Management

If you can't read please download the document

Upload: b-m-shahrier-majumder-pmp

Post on 16-Apr-2017

2.188 views

Category:

Education


5 download

TRANSCRIPT

Click to add title

B. M. Shahrier Majumder, PMPPMP Exam Preparation

www.wizardea.com | [email protected]

PMP Exam Preparation - Project Cost Management1

Project Cost Management

www.wizardea.com | [email protected]

PMP Exam Preparation - Project Cost Management2

Learning ObjectivesUpon completion of this topic you will learn about

The processes, activities and documentation items for Project Cost ManagementElements (and deliverables) for Project Cost ManagementTools and techniques of the key activities of the Project Cost Management3

www.wizardea.com | [email protected]

Cost Management

Project Cost Management includes the processes involved in planning, estimating, budgeting and controlling costs so that the project can be completed within the approved budget.4

www.wizardea.com | [email protected]

Key Activities of Cost Management

Estimate Cost: The process of developing an approximation of the monetary resources needed to complete project activities.

Determine Budget: The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

Control Cost: The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline. 5

www.wizardea.com | [email protected]

Estimate Cost | Data Flow Diagram

www.wizardea.com | [email protected]

Estimate CostInputsTools & TechniquesOutputsScope baselineProject scheduleHuman resource PlanRisk registerEnterprise environmental factorsOrganizational process assetsExpert judgmentAnalogous estimatingParametric estimatingBottom-up estimatingThree point estimatingReserve analysisCost of qualityProject management estimating softwareVendor bid analysisActivity cost estimatesBasis of estimatesProject document updates

www.wizardea.com | [email protected]

Estimate > InputsEnterprise Environmental FactorsMarket place conditionCommercial database

Organizational Process AssetsCost estimating policiesCost estimating templatesHistorical informationProject knowledge databaseLesson learn database8

www.wizardea.com | [email protected]

Estimate Cost > Tools and TechniquesBottom-up estimatingEstimates made at the work-package of the WBS and rolled upVery accurateNeeds sufficient information to make an accurate estimateVendor Bid Analysis Analysis of what the project should cost, based on the responsive bids from qualified vendors. Where project are awarded to a vendor under competitive processes , additional cost estimating work can be required of the project team to examine the price of individual deliverables and to deliver the cost that supports the final total project cost.9

www.wizardea.com | [email protected]

Determine Budget | Data Flow Diagram

www.wizardea.com | [email protected]

Determine BudgetInputsTools & TechniquesOutputsActivity cost estimatesBasis of estimatesScope baselineProject scheduleResources calendarsContractOrganization process assetsCost aggregationReserve analysisExpert judgmentHistorical relationshipsFunding limit reconciliation

Cost performance baselineProject funding requirementsProject document updates

www.wizardea.com | [email protected]

Determine Budget > Tools and TechniquesCost Aggregation

12

www.wizardea.com | [email protected]

Determine Budget > Tools and TechniquesFunding Limit ReconciliationThe expenditure of funds should be reconciled with any funding limit of the commitment of funds for the project.A variance between funding limits and the planed expenditures will sometimes necessitate the rescheduling of work to level out the rate of expenditures. 13

www.wizardea.com | [email protected]

Determine Budget > OutputsCost Performance BaselineA time-phased budget that is used to measure and monitor cost performance on a projectThe approved cost estimatesDisplayed graphically as cumulative costs over timeDisplayed as an S-Curve14Funding RequirementsTotal and periodic funding requirements, are derived from the cost baseline and can established to exceed, usually by a margin to allow for either early progress or cost overrun.

www.wizardea.com | [email protected]

Control Costs

www.wizardea.com | [email protected]

Control CostsInputsTools & TechniquesOutputsProject management planProject funding requirementsWork performance informationOrganizational process assetsEared value managementForecastingTo complete performance indexPerformance reviewsVariance analysisProject management softwareWork performance measurementsBudget forecastsOrganizational process assets updatesChange requestsProject management plan updatesProject document updates

www.wizardea.com | [email protected]

Control Cost > Tools and TechniquesEarned Value Management (EVM)EVM in its various forms is a commonly used method of performance measurement. It integrates project scope, cost and schedule measures to help project management team assess an measure project performance and progress.EVM develops and monitors three key dimensions of each work package and control account. These are Planned Value (PV), Earned Value (EV) and Actual Cost (AC).

17

www.wizardea.com | [email protected]

Control Cost > Tools and TechniquesTerms to be remember:

18Abbr.NameFormulaBACBudget at CompletionHow much did we budget for the TOTAL project effort?PVPlanned ValueWhat is the estimated value of the work planned to be done as of now?EVEarn ValueWhat is the estimated value of the work actually accomplished as of now?ACActual CostWhat is the actual cost incurred for the work accomplished?CVCost VarianceCurrently project is over budgeted or under budgeted? SVSchedule VarianceCurrently project is ahead of schedule or behind of schedule?CPICost Performance IndexHow much worth of work we are getting out of every $1 spent.SPISchedule Performance IndexWhat is our progress at percent of the rate originally planned? EACEstimate at CompletionWhat do we currently expect the TOTAL project to cost?VACVariance at CompletionHow much over or under budget do we expect to be at the end of the project?ETCEstimate to CompleteFrom this point of now, how much more do we expect it to cost to finish the project?

www.wizardea.com | [email protected]

Control Cost > Tools and TechniquesEarned Value Analysis

19Abbr.NameFormulaGoodBadEVEarn ValueBAC x Percent CompleteNANAPVPlanned ValueBAC x Percent DurationNANACVCost VarianceEV-AC+ve-veSVSchedule VarianceEV-PV+ve-veCPICost Performance IndexEV/AC>11 Tools and TechniquesExerciseTotal Budget = $2975% Duration complete: 60%% Complete = 59%Actual Cost = 1575

Find out the all values as per EVM formula table.

20

www.wizardea.com | [email protected]

Project Selection MethodPresent ValueNet Present ValueIRR (Internal Rate of Return): The rate at which the project inflows (revenue) and outflows (cost) are equal.Payback PeriodBenefit Cost Ratio

21

www.wizardea.com | [email protected]

Cost Management > Some Important DefinitionPresent Value: The value of future cash flowsFormula (PV = (FV/(1+r)n [ Here, PV = Present Value, FV = Future Value, r = Interest Rate, n = Number of time periods]

Net Present Value: The difference between the present value of cash inflows and the present value of cash outflows.

IRR (Internal Rate of Return): The rate at which the project inflows (revenue) and outflows (cost) are equal.

22

www.wizardea.com | [email protected]

Cost Management > Some Important DefinitionPayback Period: The number of time periods it takes to recover your investment in the project before you start accumulating profit.

Benefit Cost Ratio: Benefit cost ratio > 1 means the benefits are grater than the costs.

Sunk Cost: Money already spent and permanently lost.

23

www.wizardea.com | [email protected]

PMP Exam Preparation - Project Cost Management23

Questions24

[[email protected]]http://bd.linkedin.com/in/shahrier

www.wizardea.com | [email protected]