pmp exam preparation course: 05 project time management
TRANSCRIPT
www.wizardea.com | [email protected]
B. M. Shahrier Majumder, PMPPMP® Exam Preparation
Project Time Management
www.wizardea.com | [email protected]
Learning Objectives
Upon completion of this topic you will learn about
– The processes, activities and documentation items for Project Time Management
– Elements (and deliverables) for Project Time Management– Tools and techniques of the key activities of the Project Time
Management
3
www.wizardea.com | [email protected]
Time Management
Project Time Management includes the processes required
to accomplish timely completion of the project.
4
www.wizardea.com | [email protected]
Key Activities of Time Management
• Define Activities: The process of identifying the specific actions to be performed to produce the project deliverables.
• Sequence Activities: The process of identifying and documenting relationships among the project activities.
• Estimate Activity Resource: The process of estimating the type and qualities of material, people, equipment, or supplies required to perform each activities.
5
www.wizardea.com | [email protected]
Key Activities of Time Management
• Estimate Activity Duration: The process of approximating the number of work periods needed to complete individual activities with specific resources.
• Develop Schedule: The process of analyzing activity sequences, durations, resource requirements, and schedule constrains to create the project schedule.
• Control Schedule: The process of monitoring the status of
the project to update project progress and managing changes to the schedule baseline.
6
www.wizardea.com | [email protected]
Define Activities | Data Flow Diagram
7
7
Diagram Source | PMBOK 4th Edition
www.wizardea.com | [email protected]
Define Activities
Inputs Tools & Techniques Outputs
Scope baselineEnterprise environmental factorsOrganizational process assets
DecompositionRolling wave planningTemplatesExpert judgment
Activity listActivity attributesMilestone list
8
8
www.wizardea.com | [email protected]
Define Activities > Tools and Techniques
Rolling Wave Planning Rolling wave planning is a form of progressive elaboration planning
where the work to be accomplished in the near term is planned in
detail at a low level of WBS, while work far in the future is planned for
the WBS components that are at relatively high level of the WBS.
Templates A standard activity list or a portion of activity list from a
previous project is often usable as a template for new project.
9
www.wizardea.com | [email protected]
Define Activities > Outputs
Activity List Activity list is a comprehensive list including all schedule activities required on the project.
Activity Attributes Activity attributes extend the description of the activity by identifying the multiple
components associated with each activity.
The component of each activity evolve over time.
During the initial stages of the project they include the Activity ID, WBS ID, and activity
name, and when completed may include activity codes, activity description, predecessor
activities, successor activities, logical relationships, leads and lags, resource
requirements, imposed dates, constrain and assumptions.
Milestone List A milestone is a significant point or event in the project.
10
www.wizardea.com | [email protected]
Sequence Activities | Data Flow Diagram
11
11
Diagram Source | PMBOK 4th Edition
www.wizardea.com | [email protected]
Sequence Activities
Inputs Tools & Techniques Outputs
Activity listActivity attributesMilestone listProject scope statementOrganization process assets
Precedence diagramming method (PDM)Dependency determinationAppling leads and lagsSchedule network template
Project schedule network diagramProject document (updates)
12
12
www.wizardea.com | [email protected]
Sequence Activities > Tools and Techniques
ActivityA
ActivityB
Finish to Start (FS) Relationship
ActivityA
ActivityB
Start to Start (SS) Relationship
ActivityA
ActivityB
Finish to Finish (FF) Relationship
ActivityA
ActivityB
Start to Finish (SF) Relationship
• Precedence diagramming method (PDM)
• PDM is a method used in Critical Path Methodology (CPM) for constructing a project
schedule network diagram that uses boxes or rectangular, referred to as nodes, to
represent activities and connect them with arrows that show the logical relationships
that exists between them.
13
www.wizardea.com | [email protected]
Sequence Activities > Tools and Techniques
Dependency Determination Mandatory dependency
Discretionary dependency
External dependency
Appling Leads and Lags A lead allows an acceleration of a successor activity
A lag directs a delay in the successor activity
14
ActivityA
ActivityBL=3
FS Relationship: The Start of B must lag (L) the Finish of A by 3 days
ActivityA
ActivityB
L=4
SS Relationship: The Start of B must lag (L) the Start of A by 4 days
ActivityA
ActivityB
L=5
FF Relationship: The Finish of B must lag (L) the Finish of A by 5 days
ActivityA
ActivityB
L=6
SF Relationship: The Finish of B must lag (L) the Start of A by 6 days
www.wizardea.com | [email protected]
Sequence Activities > Outputs
Network Diagram
Any schematic display of the logical relationships of Project Activities. Always
drawn from left to right to reflect project chronology. Often incorrectly referred to
as a “PERT Chart”.
Network Diagram Rules of Thumbs
There is a starting point
There is an ending point
There are predecessors for all activities
There are successors for all activities (no hangers!)
There are no loops
15
www.wizardea.com | [email protected]
Estimate Activity Resources | Data Flow Diagram
16
16
Diagram Source | PMBOK 4th Edition
www.wizardea.com | [email protected]
Estimate Activity Resource
Inputs Tools & Techniques Outputs
Activity listsActivity attributesResource calendarsEnterprise environmental factorsOrganizational process assets
Expert judgmentAlternative analysisPublished estimation dataBottom-up estimatingProject management software
Activity resource requirementsResource breakdown structureProject document updates
17
www.wizardea.com | [email protected]
Estimate Activity Resource > Inputs
• Resource Calendars• A calendar that documents the working and nonworking days that
determine the dates that a resource is available or not.
18
www.wizardea.com | [email protected]
Estimate Activity Resource > Outputs
• Activity Resource Requirement• An identification and description of the types of quantities of
resources required for each schedule activity in a work package
• Resource Breakdown Structure• A hierarchical structure of identified resources by resource category
and type
19
www.wizardea.com | [email protected]
Estimate Activity Duration | Data Flow Diagram20
Diagram Source | PMBOK 4th Edition
www.wizardea.com | [email protected]
Estimate Activity Durations
Inputs Tools & Techniques Outputs
Activity listsActivity attributesActivity resource
requirementResource calendarProject scope statementEnterprise
environmental factorsOrganizational process
assets
Expert judgmentAnalogous estimationParametric estimatingThree point estimatesReserve analysis
Activity duration estimates
Project document updates
21
21
www.wizardea.com | [email protected]
Estimate Activity Durations
• Activity Effort and Duration
Total Time = Duration
Not working Time on Tasks
Actual Working on Tasks = Effort
22
22
www.wizardea.com | [email protected]
Estimate Activity Durations > Tools and Techniques
Analogous Estimating Top down estimating, uses actual duration of activities from previous projects
Parametric Estimating Top down estimating, activity duration can be uses a mathematical model to
determine estimates
Estimating the basis for activity duration can be quantitatively determine by multiply
the quantity of work to be performed by the productivity rate. e.g. Function Point
Estimation, Use Case Estimation.
Three Point Estimating Estimating an average of the most likely, optimistic, pessimistic estimated duration.
23
www.wizardea.com | [email protected]
Estimate Activity Durations > Tools and Techniques Multi Point Estimating (PERT)
Program Evaluation and Review Technique (PERT)Calculation:
Mean = (P + 4M + O)/6 Standard Deviation = (P-O)/6 Variance = ((P-O)/6)2
Here, P = Pessimistic Estimation, O = Optimistic Estimation and M = Most likely Estimation
Reserve AnalysisCalled time reserve, contingency, or bufferPurpose – To add time to individual activities or the overall project
duration for schedule risksAccumulated for the project and included in the project contingency
fund or management reserve
Note: Authors discourage adding time to individual activities since this is a form of padding
24
www.wizardea.com | [email protected]
• Complete the table using the formulas of PERT
25
Activity O M P Expected Duration
Activity Standard deviation
Range of the Estimates
A 14 27 47
B 41 60 89
C 39 44 48
D 29 37 42
www.wizardea.com | [email protected]
• What do you need before you try to develop a schedule for your project?
26
www.wizardea.com | [email protected]
Develop Schedule | Data Flow Diagram27
Diagram Source | PMBOK 4th Edition
www.wizardea.com | [email protected]
Develop Schedule
Inputs Tools & Techniques Outputs
Activity listsActivity attributesProject schedule
network diagramsActivity resource
requirementResource calendarActivity duration
estimatesProject scope statementEnterprise
environmental factorsOrganizational process
assets
Schedule network analysis
Critical path methodCritical chain methodResource levelingWhat-if scenario
analysisAdjusting leads and
lagsSchedule compressionSchedule model
Project scheduleSchedule baselineSchedule dataProject document
updates
28
28
www.wizardea.com | [email protected]
Develop Schedule > Tools and Techniques
• Critical Path Method (CPM)• Critical Path Method (CPM), is a procedure for using network analysis
to identify those tasks which are on the critical path: ie where any delay
in the completion of these tasks will lengthen the project timescale,
unless action is taken.
• For all tasks off the critical path, a degree of tolerance is possible (eg.
late start, late completion, early start, etc.).
• Network charts and CPM analysis used to be carried out by hand.
• Software is now available which requires the user only to enter the tasks,
duration of each task and dependencies upon other tasks; a network
chart and CPM is then automatically created.
29
www.wizardea.com | [email protected]
Develop Schedule > Tools and Techniques
• Why Critical Path Method (CPM)• The CPM formally identifies tasks which must be completed on time
for the whole project to be completed on time
• Identifies which tasks can be delayed for a while if resource needs to
be reallocated to catch up on missed tasks
• It helps you to identify the minimum length of time needed to
complete a project
• The CPM determines both the early start and the late start date for
each activity in the schedule.
30
www.wizardea.com | [email protected]
Develop Schedule > Tools and Techniques
• How to Use CPM
SAMPLETask ID Duration Dependency
A 7B 3C 6 AD 3 BE 3 D, FF 2 BG 3 CH 2 E, G
31
31
www.wizardea.com | [email protected]
Develop Schedule > Tools and Techniques
• Calculating the Forward Pass
32
32
www.wizardea.com | [email protected]
Schedule Development >> Tools and Techniques
• Calculating the Backward Pass
33
33
www.wizardea.com | [email protected]
Develop Schedule >> Tools and Techniques
• Calculating the Critical Path
34
34
www.wizardea.com | [email protected]
Develop Schedule > Tools and Techniques
• Critical Chain Method (CCM)• Critical Chain Method (CCM), is a schedule network analysis
techniques that modifies the project schedule to account for limited
resources.
• Initially, the project schedule network diagram is built using duration
estimates with required dependencies and defined constrains as input.
The critical path is then calculated. After the critical path is designed,
resource availability is entered and the resource-limited schedule result
is determined. The resulting schedule often has an altered critical path.
35
www.wizardea.com | [email protected]
Control Schedule | Data Flow Diagram36
Diagram Source | PMBOK 4th Edition
www.wizardea.com | [email protected]
Control Schedule
Inputs Tools & Techniques Outputs
Schedule management planProject ScheduleWork performance informationOrganization process assets
Performance reviewsVariance analysisProject management softwareResource levelingWhat-if scenario analysisAdjusting leads and lagsProgress reportingSchedule compression Scheduling tool
Work performance measurementsOrganizational process assets updatesChange requestsProject management plan updatesProject document updates
37
37
www.wizardea.com | [email protected]
Control Schedule > Tools and Techniques
• Progress reporting• Actual Start and Finish Dates
• Remaining duration for unfinished tasks
• Percent completion (from Earned Value Analysis)
• Schedule Change Control System• Part of Integrated Change Control
• Performance Measurements• Schedule Variance (SV), Schedule Performance Index (SPI) (from Earned Value
Analysis)
• Schedule Comparison Bar Charts• Tracking Gantt
38
Get FR
EE Templates at w
ww
.wizardea.com