© 2005 Austin Energy All Rights ReservedInformation Technology & Telecommunications For AE Internal Distribution Only

1

ITT PMO Update

Brad Ring

ITT PMO Council chair

Page 2: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

2

ITT Mission & Vision

MISSION

“To deliver quality utility solutions on-time and on-budget”

VISION

“To build a 100% online, interactive, anytime, anywhere, any device, secure, reliable, and scalable enterprise for employees,

customers, partners and vendors.”

Page 3: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

3

Part 1: History: Establish 5 Project key performance indicators (KPIs)Focus: Reactionary, firefighting, chaos theory.

Page 4: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

4

Part 1: History: 5 key performance indicators (KPIs)Focus: Reactionary, firefighting, chaos theory.

Historical KPI progress

1. Project communication: Inconsistent

2. Supporting processes: PMO On-line (BOT) Microsoft Server Project 2003

3. Resource planning: Ad hoc

4. Financial reporting: Focus on CIP projects

5. Baseline scheduling: Limited

Page 5: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

5

Part 1: History Focus: Reactionary, firefighting, chaos theory.

ITT prior Project challenges

Page 6: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

6

Part 1: History Focus: Reactionary, firefighting, chaos theory.

Resource gridlock

Schedule slippage

Low probability of success

Cost overruns

ITT Project challenges

Page 7: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

7

Part 1: History Focus: Reactionary, firefighting, chaos theory.

Resource gridlock

Schedule slippage

Low probability of success

Cost overruns

Scope creep Incomplete projects No quality control Most important project

“of the week”.

ITT Project operating environment:

Page 8: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

8

Part 2: KPI Current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability

Page 9: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

9

Part 2: KPI Current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability

KPI 1- Project communication (ITT Focus)

Established weekly project status reporting cycle includes distribution to all ITT management and BSA’s.

Established periodic detailed status reviews (DSR) for peer review, schedule review, risks, and feedback.

Page 10: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

10

Part 2: KPI Current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability

KPI 2 - Supporting Processes

Established 5 new processes & process owners:

PM Mentoring: coaching & mentoring new & existing staff.

Formal resource request process: written approval from RM.

Issue Escalation: Issues sent to all Division Managers & CIO.

Project Prioritization

On-going PM best practices (purchasing, scheduling, etc.)

Page 11: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

11

Part 2: KPI Current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability

KPI 3 - Resource Planning

Define resource utilization rate for lifecycle tasks: analysis, projects, operations, maintenance and support. (activity tracking sheet)

Established standard utilization factor of 20% for all meetings, overhead, etc.

Created accurate global resource pool

Page 12: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

12

KPI 4 - Financial Reporting

Created work orders for all active projects to capture all related projects costs (June)

Able to track resources, capital costs, labor, and related expenses in MS Project Server

Coordinating with BSA’s to establish initial work order for lifecycle mgt.

Part 2: KPI Current Accomplishments (Jan 05 to Present)Focus: Repeatability and predictability

Page 13: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

13

Part 2: KPI current accomplishments (Jan 05 to Present)Focus: Repeatability and predictability

KPI 5 - Baseline Scheduling

Snapshot: current portfolio projected workload of 42 active projects including 18 CIP projects (May)

Training: 25 staff attended formal schedule estimating techniques including PERT, WBS levels, risk mgt.

Pilot project: Service Center replacement

Page 14: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

14

Service Center Replacement Pilot

Scope:

Page 15: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

15

Service Center Replacement Pilot

Scope:

Accomplishments:

1. Document high level WBS for entire project

2. Formal cost & schedule estimate for each work package

3. Schedule in MS Project: dependencies, critical path, resources

4. Supporting PM documents: Charter, project plan, risk plan, etc.

Page 16: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

16

Service Center Replacement Pilot

Scope:

Accomplishments:

1. Document high level WBS for entire project

2. Formal cost & schedule estimate for each work package

3. Schedule in MS Project: dependencies, critical path, resources

4. Supporting PM documents: Charter, project plan, risk plan, etc.

Result: High probability of success

Page 17: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

17

Part 3: Future Strategies Focus: Integrated workload and resource management

Page 18: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

18

Part 3: Future Strategies Focus: Integrated workload and resource management

Strategy #1

A. Re-estimate & baseline all existing projects using formal estimating techniques.

B. Require formal estimating on all new proposed projects

Page 19: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

19

Part 3: Future Strategies Focus: Integrated workload and resource management

Strategy #2

Define resource utilization rate for analysis, projects, operations, maintenance and support by skill, resource, and division.

Page 20: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

20

Part 3: Future Strategies Focus: Integrated workload and resource management

Strategy #3

Prioritize and rank all projects& support initiatives within eachbusiness unit (including ITT) and across the organization

Page 21: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

21

Part 3: Future Strategies Focus: Integrated workload and resource management

Strategy #4

A. Link prioritized projectsto global resource pool.

B. Determine resource availability, conduct resource planning and forecasting. Revise project completion dates.

Page 22: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

22

Part 3: Future Strategies Focus: Integrated workload and resource management

A. Re-estimate & baseline all existing projects using formal estimating techniques.

B. Require formal estimating on

all new proposed projects

Provide resource utilization and availability rate using global resource pool by division and skill set.

Link prioritized projectsto resource plan.

Prioritize projects withineach division and across the organization

Page 23: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

23

Benefits of Integrated workload and resource management

1. Customers: realistic project delivery dates

2. Sponsors: high degree of success for all projects

3. ITT staff: manageable workload

4. ITT management: Accurate resource allocation & forecasting Resource alignment with highest priority projects Project predictability and repeatability

Page 24: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

24

Summary

A. Re-estimate & baseline all existing projects using formal estimating techniques.

B. Require formal estimating on all new proposed projects

Provide resource utilization and availability rate using global resource pool by division and skill set.

To successfully complete the Mission Statement “To deliver quality utility solutions on-time and on-budget”

The following foundation pieces must be in place:

Page 25: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

25

Acknowledgements

Page 26: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

26

Questions, comments, feedback

Contact:

Brad Ring Ext 6347 TLC 457

[email protected]

Page 27: Pmo presentation

© 2005 Austin Energy All Rights Reserved Information Technology & Telecommunications For AE Internal Distribution Only

27

DSR I TT DETAILED STATUS REVIEW DSR 3.0

Project:

Project Manager: Project Start Date:

Customer: Est. Completion Date:

Sponsor: Priority:

Project Scope:

1. Scope Yes No NA Date Notes

a. Clearly defined with customer signoff?

b. Identified in MS Project as a note?

c. PMP completed, signed, archived?

2. Schedule/ Budget Yes No NA Date Notes

a. Schedule accurate and updated?

b. Demonstrate progress of milestones & deliverables. Identify next deliverable.

c. Identify the critical path

d. I f CIP, document current cost & budget

e. Work Order established

f. Formal estimation process used

3. Remaining Schedule and Effort

Effort (hours)

Duration (days)

Date Notes

a. Estimated remaining effort

4. Risk Management Yes No NA Date Notes

a. Risk plan completed, signed, archived?

b. Identify any significant issues that may adversely affect project deliverables

5. Procurement Yes No NA Date Notes

a. RFP Requirements? Identify stage.

b. Outstanding issues?

c. Estimated procurement cost & budget ($$)

6. Resource Management Yes No NA Date Notes

a. Are all tasks and deliverables properly resourced?

b. Written commitment from Res. Mgr?

7. Dependencies – Task/ Resource/ Project

Yes No NA Date Notes

a. Any critical dependencies not identified in risk plan?

b. Part of a Program or Multi-Phase initiative?