new lrfd design of precast concrete pipe pipe... · 2016. 3. 1. · lrfd design of precast concrete...

57
LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16 th 2010 September 16 , 2010 www.concrete-pipe.org

Upload: others

Post on 02-Sep-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

LRFD Design of Precast Concrete Pipe

Josh Beakley – ACPA Director of Technical ServicesSeptember 16th 2010September 16 , 2010

www.concrete-pipe.org

Page 2: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

22

Design Options12 10 Reinforced Concrete Pipe12.10 Reinforced Concrete Pipe• 12.10.1• “The structural design of the type of

pipes indicated above may proceed p p y pby either of two methods.”

www.concrete-pipe.org

Page 3: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

3

12 10 Reinforced Concrete Pipe12.10 Reinforced Concrete Pipe• “The direct design method at the g

strength limit state as specified in Article 12.10.4.2 or

• The indirect design method at the service limit state as specified in Article 12.10.4.3”

www.concrete-pipe.org

Page 4: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

4

Indirect Design MethodIndirect Design Method

Page 5: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

5

Direct Design per AASHTO Section 12Section 12

Page 6: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

6

Load FactorsLoad Load Factor

Standard LRFDMinimum MaximumMinimum Maximum

Dead 1.3 0.90 1.25Water 1.3 1.0 1.0E th V ti l 1 3 0 90 1 30Earth – Vertical 1.3 0.90 1.30Earth -Horizontal

1.3 0.90 1.35

Live 1.3 x 1.67 = 2.17 0.0 1.75*

* A multiple presence factor is included in the total load A multiple presence factor is included in the total load

Page 7: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

7

www.concrete-pipe.org

Page 8: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

8

Per AASHTO LRFD

www.concrete-pipe.org

Page 9: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

9

Per AASHTO Standard Specifications

www.concrete-pipe.org

Page 10: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

10

Reason for Differences Between LRFD and Standard SpecificationLRFD and Standard Specification Allowable Fill Heights• Increase in live load concentration 1.15H versus 1.75H distribution

• Increase in impact factor 0.33 to 0 at 8 feet versus 0.30 to 0 at 3

feet• C-wall used in the LRFD tables

versus B-wall in the Standard tables

www.concrete-pipe.org

Page 11: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

LRFD Fill Height Example

www.concrete-pipe.org

Page 12: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

12

Gi enGiven:• Di = 48 in.i

• t = D/12 + 1.75= 5 75 in5.75 in.

• Do = Di + 2t= 59 5 in= 59.5 in.

• H = 5 ft.120 f• w = 120 pcf

• Type 2 Installation

Page 13: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

Soil Load

www.concrete-pipe.org

Page 14: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

14

Page 15: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

15

AASHTO LRFD 12 10 2 1AASHTO LRFD 12.10.2.1• WE = Fe w Bc HE e c Fe = Soil-structure Interaction Factor w = unit weight of soil (pcf)u t e g t o so (pc ) Bc = outside diameter of pipe (ft) H = height of fill over the pipe (ft)H height of fill over the pipe (ft)

www.concrete-pipe.org

Page 16: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

16

AASHTO LRFD 12 10 2 1AASHTO LRFD 12.10.2.1• “Standard installations for both

embankments and trenches shall be designed for positive projection, embankment loading conditions where Fe shall be taken as the vertical arching factor VAF specifiedvertical arching factor, VAF, specified in Table 12.10.2.1-3 for each type of standard installation ”standard installation.

www.concrete-pipe.org

Page 17: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

17

AASHTO LRFD 12.10.2.1

Page 18: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

18

Embankment InstallationEmbankment Installation

FrictionalSoil Prism

ForcesPrism

N t l G dNatural Ground

Page 19: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

19

Calculate soil load on the pipe:Calculate soil load on the pipe:

• Prism loadPrism load PL = w[H + (Do(4 –π))/96] Do/12 PL = 3292 lbs/ftPL 3292 lbs/ft

• Vertical Arching Factor Fe = 1 4 Fe = 1.4

• Soil loadW F * PL WE = Fe * PL WE = 4608 lbs/ft

Page 20: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

Fluid Load

www.concrete-pipe.org

Page 21: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

21

AASHTO LRFD 12.10.2.2 – Pipe Fluid WeightFluid Weight• “The unfactored weight of fluid, WF, in g , F,

the pipe shall be considered in design based on a fluid weight of 62.4 lb./ft3, unless otherwise specified.”

www.concrete-pipe.org

Page 22: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

22

Calculate fluid load in the pipe:U it i ht f t• Unit weight of water γw = 62.4 pcf

• Volume of water V = π[Di/(2*12)] 2 * 1 V = 12.56

• Fluid load WF = γw * V WF = 784.1 lbs/ftF

Page 23: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

Live Load

www.concrete-pipe.org

Page 24: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

24

AASHTO HL-93 Load

• Per Article 3.6.1.2.1, vehicular live ,loading on roadways or bridges shall consist of a combination of the: Design truck or design tandem Design lane load

• Per article 3.6.1.2.2, Design truck = 32 kip axles

• Per article 3.6.1.2.2, Design tandem = 25 kip axleskip axles

Page 25: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

25

AASHTO LRFD 3.6.1.2.5 – Tire Contact AreaContact Area• “The tire contact area of a wheel

consisting of one or two tires shall be assumed to be a single rectangle, whose width is 20.0 in. and whose length is 10.0 in.”

www.concrete-pipe.org

Page 26: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

26

Page 27: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

27Calculate the Live Load Distribution through Pipe andDistribution through Pipe and Soil

Page 28: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

28

www.concrete-pipe.org

Page 29: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

29

www.concrete-pipe.org

Page 30: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

30

Critical Live Load ParametersCritical Live Load Parameters

www.concrete-pipe.org

Page 31: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

31

Live Load SpreadLive Load Spread

www.concrete-pipe.org

Page 32: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

32Live Load Distribution for Select Granular FillFill

• For a vehicle traveling perpendicular:2 05 1 15D H 5 5 2.05 – 1.15Do < H < 5.5

From calculation above P 32 000 lb• P = 32,000 lbs

• Spread a = a + 4 + 1.15H • Spread a = 20/12 + 4 + 1 15(5 0 ft ) = 11 42 ftSpread a = 20/12 + 4 + 1.15(5.0 ft.) = 11.42 ft• Spread b = b + 1.15 H• Spread b = 10/12 + 1.15(5.0 ft.) = 6.58 ft.

Spread wheel load area at outside top of pipe• A = Spread a * Spread b =11.42 ft * 6.58 ft• A = 75.18 ft2

Page 33: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

33

Pressure at Top of Pipe

www.concrete-pipe.org

Page 34: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

34

Calculate Average Pressure IntensityIntensity• Impact Factorp IM = [33 (1 - .125(5 ft.)] / 100 = .124

• Average pressure intensity w = [P (1 + IM)] / Aw [P (1 + IM)] / A w = [32,000 lbs( 1+ .124)] / 75.18 ft2

w = 478 4 lbs/ ft2w = 478.4 lbs/ ft

Page 35: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

35

www.concrete-pipe.org

Page 36: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

36

Live Load Above the PipeLive Load Above the Pipe

www.concrete-pipe.org

Page 37: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

37

Total Live Load Calculation

• Dimension of area parallel to longitudinal axis of pipe L = Spread a = 11 42 ft L = Spread a = 11.42 ft.

• Lesser of the outside horizontal span, Do, or spread wheel load perpendicular to longitudinal axis of pipeaxis of pipe SL = Do = 4.96 ft.

• Total Live Load WT = wLSL = 478.4 lbs/ft * 11.42 ft. * 4.96 ft. WT = 27,089 lbs.

Page 38: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

38

Distribution of Live Load Through the Pipest but o o e oad oug t e pe

www.concrete-pipe.org

Page 39: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

39

Total Live Load per Linear Foot ota e oad pe ea ootCalculation

Eff ti ti l th f i• Effective supporting length of pipe Le = L + 1.75(.75*Ro) Le = 11.42 ft. + 1.75(.75 * 4.96 ft.) =

17.93 ft.

• Total live load in pounds per feet WL = WT / Le = 27089 lbs. / 17.93 ft. WL = 1,511 lbs./ft.

Page 40: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

40

D-Load Equation

www.concrete-pipe.org

Page 41: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

41

Extra Safety Factor for Type 1 Installations

www.concrete-pipe.org

Page 42: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

42

Extra Safety Factor for Type 1 Installations

www.concrete-pipe.org

Page 43: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

43

E th L d B ddi F tEarth Load Bedding Factor

Interpolate for 48 in pipe BFE = 2.867

Page 44: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

44

Live Load Bedding Factor

For 48 in pipe @ 5.0 ft of cover BFLL = 2.2

Page 45: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

45

Calculate the D-load per Equation 12 10 4 3 1 112.10.4.3.1-1

• D0.01 = (12/D)*{[(WE + WF) / BFE] + [WL / 0.01 ( ) { ( E F) FE LBFLL]}

• D0.01 = (12/48)*{[( 4,608 + 784.14) / 2.867] + [1,511 /2.2]}

• D0.01 = 641.9 lbs./ft./ft.

Page 46: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

46

Per AASHTO LRFD

www.concrete-pipe.org

Page 47: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

Direct Design of Concrete Pipe Using PIPECARPIPECAR

www.concrete-pipe.org

Page 48: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

48

www.concrete-pipe.org

Page 49: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

49

www.concrete-pipe.org

Page 50: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

50

12.4.2.7 – Yield stress limited to 65 ksi for smooth wire and 70 ksi for deformed welded wire fabric

www.concrete-pipe.org

5.4.2.1 – concrete strength limited to 10 ksi

Page 51: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

5151

www.concrete-pipe.org

Page 52: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

52

www.concrete-pipe.org

Page 53: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

53

www.concrete-pipe.org

Page 54: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

54

www.concrete-pipe.org

Page 55: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

55

WE= 4608 lbs/ft

Indirect Design Method

WE 4608 lbs/ft

WF = 784.1 lbs/ft

W 1 511 lb /ftwww.concrete-pipe.org

WL = 1,511 lbs./ft.

Page 56: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

56

48 Inch Class II (1000 lbs/ft/ft) Pipe – C-wall( ) p

Asi = 0.14 SQ. IN./FTAso = 0.08 SQ. IN./FT

www.concrete-pipe.org

so

Page 57: New LRFD Design of Precast Concrete Pipe Pipe... · 2016. 3. 1. · LRFD Design of Precast Concrete Pipe Josh Beakley – ACPA Director of Technical Services September 16September

The End

Transfer Site - http://xfer.concrete-pipe.org/Transfer Site http://xfer.concrete pipe.org/Password – “LRFDPipe”

www.concrete-pipe.org