ve hed me w. fey - vtechworks - virginia tech
TRANSCRIPT
MANUFACTURING SYSTEM MAINTENANCE DEVELOPMENT
by
Brennan P. Bowen
Report submitted to the Faculty of the
Virginia Polytechnic Institute and State University
in partial fulfillment of the requirements for the degree of
MASTER OF ENGINEERING
IN
INDUSTRIAL AND SYSTEMS ENGINEERING
APPROVED:
oe Gary
Prof. B.S. Blanchard, Chairman
Ve hed Me W. Fey Dr. K. P. Glllis Dr. W.J. Fabrycky
December 1996
' Blacksburg, Virginia
Keywords: Maintenance, Failure, Reliability, FMEA, RCM
MANUFACTURING SYSTEM MAINTENANCE DEVELOPMENT
by
Brennan P. Bowen
Prof. B.S. Blanchard, Chairman
Industrial and Systems Engineering
(ABSTRACT)
In this report, the Process Failure Modes and Effects Analysis (PFMEA)
and the Reliability-Centered Maintenance (RCM) analysis are used in tandem to
initialize a cost-effective maintenance plan for the Amada HFA-330 band saw.
The intent of this report is to describe and demonstrate how the two analyses
are used to develop the maintenance plan.
As part of the maintenance plan development, consideration is given to
the effects of processor down time on the throughput and profitability of the
manufacturing system. Any processor failure that decreases throughput of the
manufacturing system will create a loss in opportunity to fulfill demand.
After determining a maintenance plan, data should be collected from the
system to reaffirm or revise the maintenance decision. Data collected from the
manufacturing system may provide move accurate estimates allowing the
analyst to reiterate the procedures and improve the plan.
This methodology would be useful in the design phase to assess the life-
cycle cost of a system design. This methodology can be used to estimate the
cost of maintenance. The life-cycle cost of the system can then be estimated
from estimates of research and development, construction, start-up, operation
and maintenance, and system disposal estimates. Given multiple alternatives, a
decision on the preferred system can be made based on life-cycle costs.
Acknowledgments
The opportunities given me as an associate with the Systems Engineering
Design Laboratory (SEDL) were the source of my motivation for this project. |
took great interest in SEDL’s project with Federal Mogul Corporation in applying
the Process Failure Modes and Effects Analysis as a too! for process
improvement. While assisting the SEDL with this project, | learned of other
applications for this tool. Thank you Dr. Fabrycky and Professor Blanchard for
those opportunities. Thank you Dr. Verma for patience and guidance through
our work together. Thank you Dr. Ellis for your attention to detail and willingness
to serve on my graduate committee. Thank you Lovedia Cole for keeping the
formalities in order. | have enjoyed researching this topic.
Table of Contents
1.0 INtrOGUCTION .......:ccscccsscnsersnsnnserssnsaesonnnsessunaseeeusunseerauacsersaneasesosouauesonsegeeseneass 1
1.1 Identification of Opportunity ................. ccc cccccccsesseseeeeseeeeseeeeseesaeeseesesseeaeeeeeees 1 1.2 The Objective of the Project..................cccccccccseeesesseeeeeeeeeeeeeaaeaaeeeceeeeteeeesennenes 2
2.0 Manufacturing Systems Backgroui.........:ccsssssseeseccsscessseerecsennavereeeancenees 7
2.1 The Nature of Failure................c.cccccccccceseeecceceeeseesceecesnenesceeeesessacaeceesensaeaeees 10 2.2 Failure Assessment Through Effectiveness Measures...................::::ccee 14
2.3 Failure Assessment Through Cost Measures. .................cccccsseeeeseeeeeeneeeeeees 16 2.4 Defining the Manufacturing System.............0... cc eecceceececseeseeeeeeseeeeesseeeeees 18
3.0 Process Failure Modes and Effects Analysis (PFMEA) .............ssssssse 21
3.1 INTFOCUCTION 0.00... eecccceeeccesseceenerenscceceaseseeueeseescceeaeseceueeessaeeesensessausessaeeene 21
3.2 PFMEA Methodology ..................ccccceececceceeeeecereeeeeeeeeeeeenereeeeeeseeersteeteeeeeseeess 26 3.3 PFMEA Exa@mple.................ccccccccccccesesecceceesessececeeseenaeeceesesaaeasceeesseeaeseeeeseenees 29 3.4 Defining System Requirement ................::c:cccccceeececceeeeaeeaseseeeeeeeceeeeeneenaeees 31 3.5 Defining the Process FIOW..............ccccccccsesecccesssccneeeesecsensecessaeeecsaaaeseseeegsees 31 3.6 Functional Allocation ................cccccccsecccceseeceseecesesececesessenscsseeceseecenseeesseeess 33
3.7 Defining Failure Modes...................ccccccccccccceseseececaaseeeceeesecscsaaeseessaueeseeaaeeees 33 3.8 Defining Failure Causes ..............ccccccccccsesceseceeceeeseceseeceeeeeeeesesauegeceeeeseaaeness 37 3.9 Defining Failure Eff@cts 2.0.0.0... ccccecceccesssceeceeseceeseneeeeseensseeseeassessenanees 37
3.10 Identifying Current Controls .......... cc cccecceccccecceceeeeeceseeesseeeeseeseeeesssssaneneees 38 3.11 Defining Occurrence, Severity, and Detection. ............cccccceceeeeeseeeees 39 3.12 Determining Cost of Failure ........ 0... ccc cccccecceseeeseeesesereesessseeeneeseeessanaeees 39
4.0 Reliability Centered Maintenance Analysis ..............:ccccsscsssscsssserssreecesees 45
4.1 IMTPOGUCTION 0.00... c ccc cccnseeceeceeeesececeesesaneeeeseesauensceeeessaaaueeceeesseagaeeeeesnaes 45 4.2 Maintenance Significant ItEMS ..................cccccccccceeceeeeseeeereeseeeeteeeeeseaaenseeeeees 49 4.3 Structurally Significant IteMs 0.0.0.0... cceeceeccesceeeeeeeeeeseeeeseeeesseaaeeeeeeeeases 51 4.4 ROM DeCISION LOGIC 0.0.0.0... cee cccecceeseccceeeeseseeeeeccenensseeceeeeseaseneeeeeuenadseeeenaeaes 52 4.5 RCM Il Analysis Example ...................ccccccscecccessecseesesseseseeneeceeseseceeseeeeneeseees 54
4.6 Manufacturer's Recommended Maintenance Tasks.................cc:::csssseceeeees 57 4.7 Total-loss Lubrication Points .................ccccceeeeccesesceeseseneaeeeceseetesetseesersaes 59
4.8 Maintenance Task Decision LOGIC... cecccccsceesecseeneceeseeeeeessueeaceetan 59 4.9 ON-CONITION TASKS...............c.cccceeccccssesseeeseeeeessssesesseceenaeeesessegaeesesesssanaeeses 64 4.10 Scheduled Restoration Task................0cccccccccesescceceeeecceseeeeceeseneseeseaeseesees 65
4.11 Scheduled Discard Task................cccccccccccenseeseceeceseessececceseueaseesessesseseeesess 66 4.12 No Scheduled Maintenance (Corrective Maintenance) ......................00 67 4.13 Compulsory REdeSIGN .............cccccccccccecceseeeeseeeeeeeceseeseeeesseceeceeseaneneaeeaeaaaaes 68 4.14 Selecting the Maintenance Task..................cccccccccceceeseeneeeecsseeeeeeeesenensaaeees 68 4.15 Wallk-throughs ...0....... cc ccccceseeceeeeseeceessansaeesaeeeeeeseceseessaassensaseseeeeseeeneas 70
5.0 Maintenance Plan SUMMALPY.......:ccssssescsssssssessssesesvessessenecessenssssasorseasscenes 77
6.0 Conclusions and Recommendations ............ccssssessseseeeeeseesesonsenenseerersesens 77
Appendix A - RCM Decision Logic Diagrams. ...........:..:s:sessssssssssssessensensnenses 80
Appendix B - Maintenance Task AnalySis ................cessssenresssesssesncsssenseneensees 86
Appendix C - References and Additional Reading ............:::ssssesssssersesensers 90
Figure 1. Figure 2.
Figure 3. Figure 4. Figure 5.
Figure 6. Figure 7.
Figure 8.
Figure 9. Figure 10. Figure 10. Figure 10. Figure 11.
Figure 12. Figure 13.
Figure 15.
Figure 16. Figure 17. Figure 18. Figure 19. Figure 20. Figure 21.
Figure 22. Figure 23.
List of Figures
The PFMEA-RCM Relationship with a Feedback Loop...................... 5 Manufacturing System Throughput. ...................ccceceeeesseeeeeeeeeeeeeeeneees 9 Component P-F Interval. ............0... cc cecccccceesccceesseeeeceeseeeseaeseeessaaees 11
Reliability Profiles. ..............ccccccccssssesssseecceeeececeeaeueesseseeeeseeeeseeseeaanees 12 Manufacturing System Process FIOW. ...............:cccccccesseseeeeteeteeteeeeees 18 Sources of Information for the PFMEA. ..................:.ccccsssssseeeeeeeeeeeees 23 Identifying Production Constraints. ..................cccccccsssssceessseesenereneeeees 25
Identification of Machine Parts for Amada HFA-330. ....................0 30 Part Drawing: Incline Press Movement Arm. ..............::::ccseseeeeeeeenees 32 Band Saw Process Flow Diagram (Part 1). ..............cccccccssssssseseeeees 34 Band Saw Process Flow Diagram (Part 2). ...........::::::esssesesseeeeeeeees 35 Band Saw Process Flow Diagram (Part 3). ..............cccccceceeseneteeeeees 36 Sources of Information for the RCM. ................cccccesssseeeeeeeeeeeeeteseees 47 Eliminating Production Constraints. ..................ccccccccesesseseeeeeeneeenees 50 Classification Decision Logic for ROM Il. ...............ccceeeeeeeeeeeeeeeees 56 Maintenance Task Decision Logic for Safety/Environmental ae ee 61
Maintenance Task Decision Logic for Operational Failures........... 62 Maintenance Task Decision Logic for Nonoperational Failures. ....63 MIL-STD-2173(AS) RCM Decision Logic. ..............ccceeeeceeeeceeeeeeeeees 81 AMC-P-750-2 RCM Decision LogIc. ..............::::s:eeeeeeeeeeeeeteeeeereeeeees 82 MSG-3 RCM Decision LOGIC..............cccccccsseeeeeeeceeeeseeeesneaeeseseeesees 83 RCM II Decision LOGIC. ..............ccccccccceesececseeeceeeeseeceeseeaeeesseeeeeteees 84
Structural Significant Item Decision LOgIc. .................cccccseeeeeeeeeeeees 85 Sources of Information for the MTA...............cccccccccscssssssssseseeseeeetees 87
vi
List of Tables
Table 1. The Big Six LOSSES. ...............cccccceccccesssecceceaeeeeeeaaeeccesauseeceeaueeeeesaaeneees 14 Table 2. Processor Utilization Profile. ..................cccccccccseseeceeeesneeeseerecessaenaeeeees 19 Table 3. Functional Allocation to Process FIOWS. ...............ccccccsssseeeeeeeeneeeeeeees 37 Table 4. Band Saw PFMEA (Part 1). ...........ccccccccccccccecceceeeeeeeseeseetereeeneeeeeeneceess 41 Table 4. Band Saw PFMEA (Part 2). 20.0.0... ...cccccceceeceeeeeeeeeceeeaeneeeeseeesenateesens 42 Table 4. Band Saw PFMEA (Patt 3). .............cccccccccecescececeeeeececceceeeeeesseseeeneneeees 43 Table 5. Band Saw Annual Maintenance Costs (Part 1)..............ccccceccseeeeeeees 44 Table 5. Band Saw Annual Maintenance Costs (Part 2)...................::cceeeee 44 Table 6. Maintenance Cost Breakdown. .................ccccccsssseececceseeeeeeeeeeeeeseseeeeees 46 Table 7. Default Actions. ..............:cccccccccccessseeseenseeeseaeeeeecaueseeseaeaeeessaaeeeeseeaaeeees 55
Table 8. Manufacturer Recommended Maintenance Tasks. ..................::006 58 Table 9. Alternative Maintenance TaskS. .................cccccsssseeceeseceeceteeeeeneaneeeenees 69
Table 10. Proposed Maintenance Plan (Part 1)... cccccsssseeeeesseeeeeeeeee 72 Table 10. Proposed Maintenance Plan (Part 2).............ccccccccccsccssseresessseseeeeeees 73 Table 10. Proposed Maintenance Plan (Part 3)................eeee eeesseseeeeeeeeeeteeeeees 74 Table 10. Proposed Maintenance Plan (Part 4)................:cccccescceeeeseesseeeeeeenees 75 Table 11. Band Saw Annual Preventive Maintenance Costs..................::008 76 Table 12. Preventive Maintenance Plan Summary. ..................::c::::ssceeeeeeeeeeees 78 Table 13. Maintenance Task Analysis (Sheet 1). .............ccccsseeeseeeeeeeeeeeeeeees 88 Table 14. Maintenance Task Analysis (Sheet 2). .................:cccccccsseeeeeeeeereeeeees 89
Vii
1.0 Introduction
1.1 Identification of Opportunity
To remain competitive, organizations are attempting to simultaneously
reduce operational costs, increase throughput, and enhance product and
service quality. A cost category which significantly impacts all of these
attributes is manufacturing system maintenance.
With most modern manufacturing systems increasing in complexity,
maintenance requirements have become more significant and demanding.
Manufacturing system maintenance often has a sizable impact on an
organization's profitability, and consequently, it's competitiveness. According
to a study reported by R. K. Mobley, maintenance activities are responsible for
15% to 40%, with an average of 28%, of the total cost of finished goods."
Presently, technological advancements and a growing transition towards
automation are likely to create a system more dependent on maintenance. "T.
Wireman reports from a study conducted in 1989 that the estimated cost of
maintenance for a selected group of companies increased from $200 billion in
1979 to $600 billion in 1989." 2:5
Many manufacturers are faced with increasing customer demand and
shrinking resource availability. To meet production demand, the manufacturing
system must sustain the highest throughput possible. Consider the Just-in-
Time procedures and transfer lines becoming prevalent in many industries
such as the automobile industry. Downtime at one point in the manufacturing
system results in downtime for every process. At GM's East German
1 Mobley, R. K., Introduction to Predictive Maintenance, Van Nostrand Reinhold, New York,
1990. 2 Wireman, T., World Class Maintenance Management, Industrial Press, Inc., New York, 1990. 3 Titan Software Corporation, "Maintenance: Profit Center 2000," Plant Engineering, March
1992, pp. 101-112.
automobile assembly plant in Eisenach, downtime at one process resulted in
1,840 idle workers.* Any loss in throughput results in a loss of opportunity to
fulfill demand. Maintenance must be effective and responsive to meet
manufacturing system demands.
United States industry loses about $66 billion annually on unnecessary
maintenance of plant and equipment.5 To meet the need of high-tech support,
eliminate unnecessary maintenance, and control rising maintenance costs,
computerized maintenance management systems (CMMS) were introduced in
the early 1980s. A CMMS utilizes computers and technological advances to
assist with the management and execution of the maintenance program.
CMMS users list primary benefits of increased manufacturing asset
productivity, increased maintenance productivity, and decreased material
costs. However, these systems are not based on a methodology for
determining maintenance plan requirements. A CMMS cannot solve
maintenance problems that come from a poor maintenance philosophy. The
most successful implementations of a CMMS build on an existing framework of
sound maintenance philosophy, good maintenance practices, organization and
documentation of tasks, and an integrative equipment history.’
1.2 The Objective of the Project
The objective of this project is to describe and apply an approach to
developing a cost-effective maintenance plan to support the manufacturing
4 Hamrick, James. "Eastward With TPM and CMMS," Industrial Engineering, October 1994, pp. 17-18.
5 Maquire, Micheal, "Predictive Maintenance: What does it do?," Electrical World, Vol. 206 No. 6 June 1992, pp.11-12.
8 Titan Software Corporation, "Plant Maintenance As Profit Center: Rethinking Our Priorities," Plant Engineering, 1991 Encyclopedia, July 1991, pp. 228-230.
’ Titan Software Corporation, "How to Select and Get the Most From a CMMS," Plant Engineering, 1991 Encyclopedia, July 1991, pp. 233-235.
system of an organization. The approach should be applicable to: (1) assess
each process alternative in a life-cycle design decision in terms of operation
and maintenance requirements, (2) optimize the operation and maintenance
costs for existing manufacturing systems, and (3) provide a means of
continuously assessing and improving the maintenance plan as_ the
manufacturing system and its environment changes.
This project will describe the methodology for developing a maintenance
plan as applied to an existing manufacturing system. The decision
methodology will be applied to the Amada HFA-330 band saw in service at
Nautilus International.
This approach translates into the optimization of present and future
operation and maintenance costs. For an existing system, the first cost
associated with planning and purchasing the manufacturing system has
occurred. Regardless of whether the manufacturing system was designed for
optimal total life-cycle cost, management must consider further optimization of
the system’s operation and maintenance costs as the system’s environment
changes. Manufacturing management's attempt to further improve the system
will only affect present and future costs, not sunk costs. The decision
methodology's place in the overall optimal alternative selection process during
manufacturing systems design will be addressed in the last chapter.
This project will not invent the methodology or procedure used to
develop the maintenance plan. This project will apply existing methods
together to develop the maintenance plan. Specifically, the information within
the manufacturing system needed to develop such maintenance plans must be
identified, collected, documented, and maintained to justify a course of action.
This project will identify information sources needed for the decision logic,
identify the information’s path through the decision logic, show how the
decision logic thoroughly documents decision justification, and relate the
information to its effect on the end-result maintenance decision.
The Process Failure Modes and Effects Analysis (PFMEA) and the
Reliability-Centered Maintenance (RCM) analysis can be used in tandem as a
decision logic to develop a cost-effective maintenance plan. The PFMEA will
allow a user to map and document the manufacturing process, the failure
mode-cause sequences, and the cost of each failure. The RCM decision logic
will be used to determine the most appropriate maintenance tasks based on the
information provided by the PFMEA. A Maintenance Task Analysis (MTA) may
be used to analyze and cost the feasibility of maintenance tasks.
The PFMEA is a simple, systematic tool which identifies, quantifies, and
prioritizes system weaknesses. The PFMEA can be tailored to suit the
analyst's needs and capabilities. The PFMEA provides a powerful input to an
RCM analysis. The RCM analysis provides a structured and formal decision
logic that assists an analyst in translating PFMEA output into a effective and
justifiable maintenance plan. The RCM analysis decision logic can be tailored
to reflect the capabilities of individual manufacturing facilities and personnel.
After using the tools successively, the analyst should have countered all failure
causes with either preventive maintenance task(s), corrective maintenance
task(s), or a redesign or adjustment of the system.
Although both are intended as tools for systems design improvements
and advanced product quality planning, these analyses are easily applied to
existing systems. Both tools provide a means of continually assessing a
system and providing feedback for continuous improvement. After an iteration
of improvement, the manufacturing system or the manner in which it will be
operated will change. These changes, in turn, should be reflected in the next
iteration of the PFMEA and RCM analysis in order to identify and reprioritize
system constraints. See Figure 1.
Process Data, Process Data, Failure Data, Failure Data,
| Maintenance Task PFMEA Maintenance Task _—sif | Analysis Analysis
| Failure Data
RCM Maintenance Task ——\ Analysis
q
1
|
Preventive Corrective Redesign | Maintenance Maintenance and/or
Plan Plan Improvement
Process & Failure
Data Collection
Figure 1. The PFMEA-RCM Relationship with a Feedback Loop.
Manufacturing facilities are searching for means of increasing market
posture and securing profit. The PFMEA and RCM analysis provides a means
of identifying opportunities to meet these goals. These tools will identify
production system constraints and allow the manufacturing organization to
attack them.
2. will failure
assessment, and define parameters of the manufacturing system under
Chapter discuss manufacturing systems, failure,
analysis. Chapter 3 will discuss the PFMEA and its application to the
manufacturing system under analysis. Chapter 4 will discuss the RCM analysis
and its application to the manufacturing system under analysis. Chapter 5 will
summarize the results of the maintenance plan formed through the use of both
analysis.
2.0 Manufacturing Systems Background
A manufacturing system is a group of processors and material handlers
in a configuration consisting of serial and/or parallel relationships which
converts raw materials into a product which the company intends to sell for a
profit. The functions that a manufacturing system is intended to perform are
provided in the forms of technical drawings, bills-of-materials, process plans,
routings, process instructions, and work instructions. These items convey to
manufacturing the product functions desired by the manufacturer's customers
and the process by which it will be made. Processors within the manufacturing
system impart those specifications onto the finished product.
Throughput, inventory, and operational expense are three major
measures of a manufacturing system. Throughput is the rate at which the
system generates money through sales. Inventory is the money that the
system has invested in purchasing things which it intends to sell. Operational
expense is the money the system spends in order to turn inventory into
throughput.2 In order to maximize company profitability, throughput must be
increased while inventory and operation expense are decreased. Mechanical
resources (ultimately money) typically constrain throughput. A company's cash
flow constrains inventory and operational expenditures.
A bottleneck is the processor which dictates the throughput of the
manufacturing system. Utilizing a processor upstream of the bottleneck in
excess of the bottleneck throughput creates inventory and does not increase
the output of the manufacturing system. Processes downstream can only
process at the rate at which the bottleneck supplies work-in-process.
Downtime at a processor within the system results in a throughput loss only
when that processor is or becomes the bottleneck of the system.
8 Goldratt, Eliyahu and Jeff Cox. The Goal: A Process of Ongoing Improvement, Second Edition, North River Press, Croton-on-Hudson, NY, 1992.
An illustration of the throughput constraints for five processors in series
is shown in Figure 2. The X axis of the graph represents the processor and the
Y axis represents each processor's production rate (units per time period) for
four utilization profiles. The utilization profiles are denoted in the graph legend.
For example, Processor 1 is used to produce 60 units per period. Processor 1
does not lose any units to scrap. It loses 5 units per period to down time and it
has an unused capacity of 40 units per period. Processor 3 is the bottleneck of
the system. The maximum capacity of Processor 3 is 70 Units. Processor 3
loses 10 units per time period to down time and 6 units to scrap. Processor 3
has a throughput of 54 units per time period. (70 - 10 - 6 = 54). Since
Processor 3 is only supplying a rate of 54 units to Processor 4, Processor 4
cannot exceed a rate of 54 units. Any scrap at Processor 4 reduces the rate at
which it can supply Processor 5. Therefore, system throughput is equal to the
bottleneck processor throughput less all scrap generated by downstream
processes. Throughput for a manufacturing processor X is:
Throughput(X) = Capacity(X) - Scrap(X) - Down Time(X) - Unused Capacity(X)
where:
X = the processor's precedence in a serial relationship of n processors,
Capacity(X) = actual capacity of processor X in units,
Scrap(X) = units lost when processor X produces nonconforming parts,
Down Time(X) = the down time of processor X in units, and
Unused Capacity(X) = unused capacity of processor X in units,
‘ndyBnos] wajshs
Suunjoejnuey ‘@
eunbi-+
auijumoq |
|| Ajoeded
pesnun WY)
yndybnowyl | dens
JOSSE001¢4
©
yndyBnosys waysh
Oo Oo rN
© oO
—
Cs
ececc
|
ae r
0 0
L
O01
O CO
(INOH / SHUN) a}ey UOHONpPOsd
Throughput for a system of n manufacturing processors in series is:
System Throughput =Min( >) Throughput(X,Y)) y Scrap(X)), Y
where:
Y represents the quantity of processor X in parallel, and
b signifies the bottleneck processor, Min(” Thru(X,Y)). ¥
The bottleneck process, being responsible for system throughput
limitations, may be the most crucial system element to maintain. However,
pinpointing bottlenecks in a well-balanced system or a job shop with a diverse
product mix presents a challenge. Equipment failure, setups and adjustment,
idling and minor stoppages, reduced operational speeds, process defects, and
reduced yield 9 can cause a bottleneck to shift to other processes.
Manufacturing management has the responsibility of allocating
operational expense, which is a limited resource, to sustain system throughput.
Manufacturing management requires a means of identifying and prioritizing
system failures. The FMEA will fulfill that function, allowing manufacturing
management to focus operational expenditures wisely. This will insure that the
organization obtains the largest return on investment of their limited resource.
2.1 The Nature of Failure
A failure is the condition in which a system is unable to perform its
intended function.1° In the course of failure, a component in the system may
exhibit physical conditions of degradation and imminent failure.
9 Nakajima, Seiichi. Introduction to Total Productive Maintenance, Productivity Press, Cambridge MA, 1988.
10 Blanchard, B.S., Verma, D. and Elmer L. Peterson. Maintainability. A Key to Effective Serviceability and Maintenance Management. John Wiley & Sons, Inc. New York, New York, 1995.
10
Vibration, heat, or odors unusual to normal process baselines may
indicate that a potential failure (P) is about to occur. Examples of signs of
potential failures would be increased temperature in gearboxes, low fluid
levels, or increased vibration in bearings. Eventually, functional failure (F)
occurs. The elapsed time between signs of potential failure (P) and functional
failure (F) is known as the P-F interval. See Figure 3.
Conditio
n ——»
Time ——> F
Figure 3. Component P-F Interval."
Component reliability can be represented by a reliability curve as shown
in Figure 4. Some failures can be related to component age (as in Figure 4,
Curves A, B, and C.) Age-related failures result from component wear which
occurs during operation. Wear usually occurs when adjoining surfaces mate
and rub each other. Systems or components showing age-related failure would
be granulators, brakes, clutches, and tires. Wear associated with age-related
failure may be detectable if there is accessibility to the component.
Given comparable care, identical components exhibiting age-related
failure tend to fail around the same age, or life. In the event that a component
shows signs of aging, on-condition monitoring techniques may be able to
detect potential failure (P). The ability to establish a usable life for the
11 Moubray, John. Reliability-centered Maintenance II. Industrial Press, Inc., New York, NY, 1992.
11
SFE as - Ah
“NEN PLE oD
~spmi-
POY ORS ee RU RAR RT EF ae ne Ne Tia high) WYertiw, one ee
Figure 4. Reliability Profiles.
12
component allows maintenance to possibly schedule restoration or discard
tasks.
Not ail failures are age-related. (See Figure 4, Curves D, E and F.)
Typically electronics, hydraulics, pneumatics, and rolling element bearing do
not fail as a function of age. 12 Since there is not a useful life associated with
these items, personnel must be able to detect potential failure (P) through
some on-condition task or allow the component to fail.
Failure can occur either sporadically or chronically. Chronic failures
occur persistently and are usually a reflection of the processor's inherent
capabilities, condition, or management philosophy. The cause-and-effect
relationship associated with chronic failures is difficult to establish. Sporadic
failures are sudden changes in operating conditions which have a
straightforward cause-and-effect relationship. These failures can typically be
easily corrected by restoring the cause to its original condition. Tool wear and
the movement of adjustable processor parameters are sometimes responsible
for sporadic failure. Physical feed stops on a manual processor would be an
example of an adjustable processor parameter. They may slip after a period of
use.
Failure can be either equipment failure or function-related failure.
Equipment failure is the failure of the processor to produce conforming parts at
the standard processor operational rate. Function-related failure is the failure
of the processor or its tooling to impart its intended engineering specification or
function onto the part. Function-related failure is a function of required
engineering specifications as well as inherent processor capabilities. For
example, a band saw may have a process capability of +0.003 inches.
Although the saw can operationally perform all week, as the blade wears the
saws capabilities will fall to + 0.008 inches. Company A may use the saw to
12 Moubray, John. P. 116.
13
fulfill engineering tolerances of +0.015 inches. As the blade wears,
engineering specifications will not be compromised. In fact, the blade may dull
to the point that the saw cannot sustain the standard operational rate, hence
operational failure. Company B may use the saw to fulfill engineering
tolerances of +0.005 inches. As the blade wears, engineering specifications
will be compromised at some point in use. This will result in nonconforming
product or function-related failure. Thus, the same processor may have
different operational or utilization profiles which may create a different
maintenance requirement.
2.2 Failure Assessment Through Effectiveness Measures
Manufacturing system failure is best defined by the “Six Big Losses.” 15
These losses, listed in Table 1, are categorized into downtime, speed losses,
and defects.
Table 1. The Big Six Losses.
Downtime:
1. Equipment Failure
2. Setup and Adjustment
Speed Losses:
3. Idling and Minor Stoppages
4. Reduced Speed
Defects:
5. Process Defects
6. Reduced Yield
13Nakajima, Seiichi. Introduction to Total Productive Maintenance, Productivity Press, Cambridge MA, 1988.
14
Downtime losses include processor lost time to (1) equipment failure
from breakdown and (2) lost time due to processor setup and adjustment.
Availability or uptime of the processor is defined as follows:
Available Time - Downtime Availability = vanapuny Available Time
The measure of availability penalizes a manufacturing organization for having
an idle processor. It would not be proper to evaluate processor availability
outside the processor’s scheduled use.
Speed losses include (3) idling and minor stoppages due to sporadic
problems and (4) reduced processor speed. Within the availability of the
processor, manufacturing personnel must fully utilize the processor.
Production efficiency is defined as follows:
Standard Cycle Time x Qty Processed Production Efficiency = Operating Time
Defect losses are (5) process defects and (6) reduced yield. Reduced
yield refers to any loss of parts that may result from a setup or adjustment of
the processor for the upcoming lot. In the context of manufacturing, these two
losses are one in the same: a nonconforming part. The quality rate is defined
as follows:
Processed Amount - Scrapped Amount Quality Rate =
y Processed Amount
15
Overall Equipment Effectiveness (OEE) is a product of availability,
processor efficiency, and scrap rate. The OEE is the product of the three
because scrap rate is a function of processor efficiency and processor
efficiency is a function of processor availability.
OEE = Availability x Processor Efficiency x Quality Rate
Mean Time Between Failures (MTBF) is an effectiveness measure that
will provide a failure rate for a processor. The failure rate will allow the
calculation of expected downtime over a period of time and its cost. The MTBF
is defined as follows:
Total Operating Hours
Number of Failures MTBF =
Mean Time to Repair (MTTR) is an effectiveness measure that will
provide the amount of time needed to repair a failure. This measure will be
used to cost corrective maintenance labor, lost operational labor, and estimate
average corrective maintenance down time. The MTTR is defined as follows:
Total Maintenance Hours
Number of Failures MTTR =
2.3. Failure Assessment Through Cost Measures.
OEE as an overall benchmark measurement of a process or
manufacturing system may not suffice, alone. Throughput like OEE is a
function of availability, processor efficiency, and quality rate. There is a cost
associated with sustaining the desired throughput of the processor or
16
manufacturing system. The cost associated with sustaining the desired level of
availability, processor efficiency, and quality rate is simply all operational and
maintenance costs charged to the processor, or operational expenditures as
defined by Goldratt. Availability, processor efficiency, and quality rate can
contribute to a loss of throughput and therefore a possible loss of opportunity
to gain profit. When external market demand exceeds system throughput,
nonproduction time at a processor results in a loss of opportunity.
To determine the cost associated with the lack of capacity, the external
demand, processor capacity, and system capacity must be determined. The
cost of lost opportunity associated with the lack of capacity is a measure of the
profit forfeited from the unfulfilled demand that the system could have satisfied.
Cost of Lost Opportunity =
Profit Margin Per Unit x (Demand - System Throughput)
The production of nonconforming product not only lessens system
throughput. It creates an additional cost in the form of scrapped material or
additional labor to reclaim the material. Scrap cost includes the cost of lost
material, labor, and overhead. Rework cost includes the additional cost of
labor and overhead. The cost of the functional failure may provide incentive to
counteract the cause of failure prior to its occurrence.
F
Scrap Cost = Material Cost + >’ (Labor Cost + Overhead Cost) 1
where F signifies the failing processor in the series of processors.
Rework Cost = Rework Labor Cost + Overhead Cost
17
Each product will have a separate scrap or rework cost associated with it
which is dependent on the processor needed for rework and the nonconforming
attribute.
There is a cost associated with corrective and preventive maintenance
of the system. These costs include cost of replacement parts, consumables,
and cost of maintenance labor.
2.4 Defining the Manufacturing System
The processing line studied for this project consists of 1 Amada HFA-
330 band saw, 3 Okuma LNC8 CNC lathes, and 2 Eaton-Leonard CNC
bending machines. See Figure 5. The multiples of each processor function in
parallel to each other. At Nautilus, the band saw is used to cut raw stock to
length. The lathe is used to reduce outer diameters or produce inner
diameters. The bending machine is used to create bends in material. This
project will focus on the Amada HFA-330 band saw.
m= Lathe 1 J
— Bender 1
— Saw 1 Lathe 2 |
Bender Oe 2
! Lathe 3 — Figure 5. Manufacturing System Process Flow.
Actual information regarding Nautilus’ machine utilization, part
specifications, process parameters, and product costing are not available for
18
use in this project.14 Reasonable values for these parameters are used for the
purpose of performing the analyses which is the focus of this project.
Processors operate 24 hours per day with exceptions for preventive
maintenance, tooling adjustments, breaks, and lunch. The utilization profile of
each processor is given in Table 2. Preventive maintenance performed during
the scheduled time is performed by the operator as part of an autonomous
maintenance program aimed at extending processor life and product quality.
These autonomous maintenance items will be discussed during the RCM
analysis. Corrective maintenance is the average time lost to the processor per
day as a result of tooling adjustments and failure. Tooling adjustments are
required to prevent function-related failure. Tooling adjustments are usually
triggered by trends in SPC data.
Table 2. Processor Utilization Profile.
Processor Saw Lathe Bender Processor Quantity 1 3 2 Standard (Min / Pc) 0.33 3.00 1.50 Output Capability per Hour Uptime (Pcs) 180 60 80 Processor Availability Per Day (Min) 1,440 4,320 2,880
Scheduled Down Time (Min) 180 270 130 Unscheduled Down Time (Min) 13 15 20 Scrap per Day (Pcs) 5 15 24 Processor Time Lost to Scrap (Min) 2 45 38 Available Processing Time (Min) 1,245 3,990 2,692
Output Capability per Day (Pcs) 3,772 1,330 1,794 Demand (Pcs) 1,330 1,330 1,330 Demand (Min) 439 3,990 1,995 Excess Capacity (Pcs) 2,442 0 464
Excess Capacity (Min) 805 0 696
14Most of the information required for the analyses was not collected by Nautilus therefore the data was unavailable. Information that was available is proprietary to Nautilus International and is not intended for public knowledge.
19
All processors have excess capacity except for the CNC lathes. The
cost of lost opportunity associated with the production system can be
calculated by determining profit lost for every hour it is not performing
productive work. The average profit margin per part is $5.20. For every hour
that the system loses throughput, the company loses $306.80 in profit. System
throughput is the throughput of the lathe less the loss of throughput due to
scrap at the bender.
(60 - 1) Parts / Hour * $5.20 / Part = $306.80 / Hour
For non-bottleneck processors, the lost opportunity cost will only be
applicable when production time cannot satisfy demand. Although the saw is
not a bottleneck processor, a failure or combination of failures that exceeds
over 805 minutes of downtime per day would reduce saw production time and
create a loss of opportunity.
Scrap results from functional failure of processors. Scrap not only
wastes production time but creates a loss of material, labor, and overhead. For
this project, the average part cost of $26 will be used as the scrap cost.
Rework is not an option.
There will not be costs associated with contractual breach, loss of
customer faith, or personnel injury. The method by which these costs are
derived may differ based on the manufacturing facility and the management
philosophy.
Nautilus only keeps spare components for consumable items. These
items are saw blades, wire brushes, lubricants, and fluids. Parts are usually
available overnight from California. Additional down time due to shipping spare
parts will be 15 hours.
20
3.0 Process Failure Modes and Effects Analysis (PFMEA)
3.1 Introduction
A Failure Modes and Effects Analysis is a systematic method of
identifying failure modes, their frequency of occurrence, their causes, and their
effects within a system. The FMEA provides a logical review of the system to
determine which failures are most critical, which failures will result in hazardous
conditions for personnel, and which failures result in products that do not meet
specifications. This enables a company to identify, document, and address the
most critical production problems using limited capital resources. 15
A FMEA is an iterative and continuous analysis, and can be performed
during design, after production, on a product, or on a process. FMEA is most
effective when performed during design in order to identify and implement a
cost-effective design alternative. This analysis can improve preventive
maintenance plans, control plans, and safety procedures. The FMEA will guide
an analyst in determining the severity of a system failure, which may serve as a
ceiling to preventive maintenance costs during maintenance design.
In order to increase throughput (and consequently sales) processor
rates and scrap rates must be improved. A completed FMEA will identify those
items that reduce system efficiency. The contributors can then be addressed
through redesign or maintenance to allow the system to achieve the maximum
throughput gain at the lowest expense. Manufacturing system improvements
will not only result in an increase in throughput by decreasing downtime and
scrap; it may increase personnel safety and increase product quality.
The FMEA can be a design FMEA (product) or a process FMEA. A
FMEA consists of six major steps: (1) define the system, (2) allocate system
154 FMEA is essentially the same as a FMECA, except the FMEA does not utilize the criticality analysis. There is a process FMEA (PFMEA) and a design FMEA (DFMEA).
21
requirements to system components, (3) analyze the failure modes, effects,
and causes of the system, (4) identify the means of failure detection, isolation,
and compensation, (5) determine the severity/criticality of each sequence, and
(6) take action as indicated by analysis results in the form of redesign,
preventive action, and/or corrective action to control or eliminate risks
associated with failure.
The FMEA has been used with qualitative and/or quantitative input. The
type of input depends on the system's life cycle phase, the availability of
pertinent information, the availability of resources to perform the analysis, or
the desired accuracy of the analysis. A system in the design phase may have
no historical data or component libraries from which to derive quantitative data.
Established systems may have sufficient historical data which supports
confident quantitative input. Qualitative input is generally quicker and easier to
collect. Qualitative input relies primarily on the experience of people within the
manufacturing organization. Figure 6 diagrams information sources and
information flow through the FMEA.
The Department of Defense requires the performance of a FMECA on
system and equipment acquisitions. Many agencies within the federal
government as well as the military divisions frequently use the FMECA as an
analysis and feedback tool for systems hardware design. '®
The Surry Nuclear Power Plant uses the FMEA as an operational
improvement tool to troubleshoot and prevent the reoccurrence of failures. The
failure mode's level of severity dictates the extent of detail that is used during
the analysis. A non operational failure will receive a shallow analysis while an
operational failure will receive a full analysis.”
16 Borgovini, R., Pemberton, S., and D. Russell. “Failure Mode, Effects, and Criticality Analysis (FMECA),” Reliability Analysis Center, Rome, NY operated by IIT Research Institutue, 1992.
17 Collin Bruce, Associate Engineer, Safety Department, Surry Nuclear Power Plant. Personal Interview.
22
WOU
L
eunje-
LIM pejeioossyy
3809 ayeingjeg
"‘WAINAd
84} JO}
UONEULOJU]
JO SBDINOS
“9 ainbi4
uolPpejeqd pue
UOHEULUOJU] we}shS
‘AeAes
‘aquein[0O aouenbas syeinajeD
seouenbasg
@SNED-8j)F-OPoW) ounyle 4 JUSWINDOG
MO|4 (euolouny
ALo\sIH VO
pue soueuajuIEW
indyBnosy, ‘spsepuels
HeW 9
Joge} ‘WIW
0d
‘VLJ ‘estwedxg
Joyesad¢ ‘Alo}siH
WD pue
esueuaieEW
‘uonseBing BW
—_/
syBNOJU-yIeEMA
oO} syueWueINbexy WUAISAS
SCO} |
Noi
jeuonouny euyeq
syusuuINbay
wejsks auyeqd
‘sBunnod yonpold
‘sueld sseoolg —
_/
syBnosyy-IEM ‘sBuynos
ONpold ‘gueid
ssec0ld s6umeiq GuyeeuiBuy
‘soadg/shanuns
JOWOISND ‘GAO
23
Companies are using the FMEA to analyze product designs before
introducing them to market. Chrysler Corporation, Ford Motor Company, and
General Motors Corporation issued an instruction manual in February 1993 by
which they and their suppliers perform both product and process FMEAs.'®
The procedures as listed by the FMEA instruction manual are excellent with the
exception of its complete qualitative nature. Severity, occurrence, and
detection are measures based on scales of one to ten. Although these
automotive firms may find this sufficient, this does not provide a basis by which
to perform a break-even analysis or cost justification of redesign, preventive
actions, or corrective actions.
The FMEA is also being used as a process improvement tool. The
PFMEA is used to map the manufacturing process, identify failures, and assess
their severity. Performing a pareto analysis on the PFMEA results will identify
the areas with the highest opportunity for improvement. The company can
make efficient use of its resources by resolving the highest ranking problems.
See Figure 7.
Federal Mogul Corporation of Blacksburg has recently began the use of
the PFMEA to improve process integrity and part quality. The PFMEA has
been used to identify and prioritize failure causes so the company could attack
them as resources allowed. The PFMEA was tailored to suit the manufacturing
plant's intent of process improvement and assurance to customers of their
commitment to quality. The PFMEA procedures that Federal Mogul developed
with the assistance of the Systems Engineering Design Laboratory at Virginia
Tech are heavily based on those developed by The Big Three with a minor
influence by MIL-STD1629A.‘9
18 Chrysler Corporation, Ford Motor Company, General Motors Corporation, Reference Manual, Potential Failure Mode and Effects Analysis (FMEAA), Second Edition, February
1995. 19 Verma, D. and B. Bowen, Process FMEA Training Manual, Federal Mogul Corporation,
Blacksburg, Virginia 24060. December 1992.
24
_ opportunities
|The FMEA __ ot
3
Processor
a oS Fo O wor WN
(INOH / SHUN) syey UOI}ONPOd
Downtime
oS 3) Q. oO © a D = c > WY
Thro
ughp
ut
NWN Scrap
Figu
re
7. Identifying
Production
Cons
trai
nts.
25
There have been many computer programs designed to facilitate the
execution, information handling, and documentation associated with a FMEA.
FailMode, Failure Modes & Effects, PC - FMECA, Relex FMECA, and CARA
FMECA are five programs which perform a hardware FMEA based on MIL-
STD-1629A. Some of the programs support MIL-STD-338 and MIL-HDBK-217.
Most of these programs provide libraries of historic, quantitative figures-of-merit
for electronics and commonly-used components. These libraries help build a
reliable analysis output. FMEAPlus is a Windows-based software developed to
support the FMEA format developed by The Big Three.”
Given that the FMEA successfully identifies opportunities for
improvement, a methodology will be necessary to determine effective actions
which are responsive to those opportunities. The RCM analysis (along with a
Maintenance Task Analysis) will be used to identify effective and cost-justified
actions which will capitalize on the opportunities presented by the FMEA.
3.2 PFMEA Methodology
System requirements are process or product parameters that define the
desired results of the process. Customer specifications through Quality
Functional Deployment or engineering design documents usually provide the
system requirements. Most of the system requirements fulfill customer
requirements, while others may provide functionality to downstream processes.
A functional flow diagram is a flow chart of the process. It defines the
sequence of operations that need to be performed in order to achieve the
desired outcomes of the overall process. The functional flow diagram should
reflect quality checks, work-in-process, and other non-value added processes.
These diagrams are prepared to the detail necessary to establish an
20 See Appendix C for software references.
26
understanding of the process. The functional flow diagram can be developed
from process plans or part routings. Further, the functional flow can be
developed or validated by performing a "walk-through." During a “walk-
through," the analyst traces the steps of a part through the manufacturing plant
noting all processes, inspections, transits, and points of storage. At this point
in the analysis, the entire system should be defined.
The system requirements are then allocated to their respective
operations. If an operation can affect a requirement, the requirement is
allocated to that operation. Process plans, product routings, and "walk-
throughs" will assist the analyst with allocating system requirements.
A failure mode is defined as the inability to achieve a system
requirement. Failure modes throughout the process can be determined by
experienced operators, maintenance history, manufacturer documentation, and
quality assurance history.
A failure cause is defined as a mechanism by which the process can
experience a failure mode. Failure causes can be determined through
manufacturer documentation, Fault Tree Analysis, or experimentation.
Maintenance data may provide insight into failure causes. Quality assurance
data may provide insight into quality problems or provide a trace to root
causes.
The effect of a failure can be defined as the consequence of the failure
mode-cause sequence. External effects are effects to the customer. Internal
effects are effects to the failed process and processes down stream. Internal
effects have a relatively concrete cost whereas external effects have a cost that
is more difficult to estimate. Failure effects can be determined by the analyst’s
experience, maintenance history, or quality assurance history. At this point in
the analysis, all likely failure modes of the system has been documented.
27
Current controls are operations or process procedures that are intended
to prevent a certain effect from occurring or propagating down stream.
Examples of current controls are quality control checks, machine vision
cameras, or misprogression sensors.
The next step in the FMEA process is to determine the frequency of
occurrence, the severity of the effect, and the ability to detect the effect for
each mode-cause-effect sequence. This information will provide the severity or
cost of each failure-mode-cause sequence. To assist in the goal of developing
a cost-justified maintenance plan, these measures should be quantitative, not
qualitative. The cost of each sequence will provide the extent to which process
improvement or preventive maintenance can be justified.
Occurrence is the frequency of occurrence. Severity is the cost of
failure measured in terms of safety, quality, reputation, lost production time,
and maintenance cost. Detection is the probability that the current control will
detect the failure mode-cause-effect sequence before it causes any damage.
This measure will determine how frequently and to what extent that the severity
cost will be incurred upon failure.
A Risk Priority Number is a measure of the criticality of a failure mode-
cause-effect sequence. RPNs are the product of the relevant occurrence,
severity, and detection ratings according to The Big Three procedures. The
RPN in the context of this project will be the annualized cost of failure. For
example, a machine fails five times per year at a cost of $1,000 per failure.
Controls can preempt 50% of the costs associated with four out of five failures.
The failure sequence would cost $3,000 per year.
$1,000 / failure * 5 failures / year * (1 - (50%) * (80%)) = $3,000
28
Performing a pareto analysis of the failure costs will prioritize efforts and
resources where they can best be spent to improve system costs throughput.
The PFMEA supports the maintenance development process by
performing a formal analysis of failure modes, frequencies, causes, and effects
of the system. Further, the analysis will guide the analyst in determining the
cost of allowing a failure sequence to occur. This information is ultimately
useful when justifying process improvements or preventive maintenance
actions.
The PFMEA supports the goal of continuous improvement by increasing
the knowledge of the process so that items in need of greatest attention are
corrected. The PFMEA is an iterative process. As more reliable information
emerges from the manufacturing system or problems are reduced, the PFMEA
should be updated. These changes in the system may change the priorities of
other failure causes or create new failure modes.
3.3 PFMEA Example
The analyses demonstrated in this project will be performed on the
Amada horizontal band saw Model HFA-330. The band saw accepts any
length raw stock. It can be programmed to index and cut up to 99 different cut
lengths of any quantity from the stock. Through the use of an encoder and
hydraulics, the band saw will index and measure the programmed cut length,
then cut the stock. It will continue to index to the programmed length and cut
until the saw uses up the material or finishes the programmed lengths and
quantities. The Amada band saw is equipped with numerous system fault
detection and safety features that will automatically stop the sawing process.
29
. Jenuew sJojesadO
O€€-VAH/OEE-VH Mespueg
|eJUOZLOH], “epewly
,z
iz OCE-VAH BPewiy
10} sue Ssulyoeyy
jo UORedyHUap) “g einBi4
“OCE-WH 03
sandde
os(e pue
OCe-V4H
195 81
Guymerp siqy
(A0ssa00e [puondo)
Ja702 Gujdwep
voNesgra (As0$89998
jeuoido)
GjQe) JOHOH
(A10ssa90e jeuoydo)
BAIBA fO}UOD
GNSSAIG
BSA
(Aiossagze jeuondo)
10\Da}ap Nd
aseNbs-jo-1NO Jajuy
samod
9199/3
BINSO|OUS JBI}ND0/9 wGi
OM
yaued joUu0D
yuey piny
Gumnd duund
pin Suning
Jao
(eIU9A JOO
PGIs HIOM
JBPUAD
PII} OSIA
sedy
WUN vONDaIap UOISOd
as}, Jeay
"sajaay YDeodde
yaINO aoua;
Alayes J0|DajaP
VONOW
JOABAUOD BIND
Jojow Gund
ayNeipAY
4UB) NO
DyNeipAy JapuyAd
Buwas
JBAa{ yO
OPING apelq
MES
apind apeq
mesg JOAR_
VOISUB] BPe|Q
MES
J8ayM vaAQ
ysniq aI
peaymes JOJOW
BPEIQ MES
1934 aap
pue sadINpa:
paads
OSIA 2834
JAPUPWAD ASIA
|SIA juOY
ABs) WOM
ued piny
Gumind
{12} (oz) (61}
“(at} {zt} {91} (st) (vt) (ct) {21] fia) fou] an
Ne en ee ten ee et -NOTNOKR @ ne eee nee et ee et
(2 15) ovet
(uy) wu Wun)
SLUVd HNIHOVW
AO NOILVOMTINACI
3.4 Defining System Requirements
Most part requirements are specified to manufacturing in the form of a
part drawing. Part drawings specify the desired features and tolerances of the
part. A manufacturing process plan and routing is created based on these
desired features and tolerances. Part drawings are usually stored is a central
location by Quality Assurance. This project will focus on the production of an
incline press movement arm. See Figure 9.
The print shows a part made of two-inch diameter 1040 cold-rolled round
stock that must be five feet long with + 0.015 inches tolerance. Eight inches of
one end of this stock must have the outer diameter reduced to one inch in
diameter + 0.001 inches tolerance. The piece of stock must receive two (2)
ninety degree bends in the same plane + 0.5°.
3.5 Defining the Process Flow
Process flows are represented by part routings and by process flow
diagrams. The processor required to perform the desired part specifications is
selected by its ability to perform the function and its ability to meet required
tolerances. Machine abilities are usually defined by the manufacturer in
purchasing specifications. Process capability studies can further determine
machine capabilities given the variables on the shop floor. All machines are
capable of the parts manufacturing requirements. The Amada manual
indicates that the machine is capable of repeating 0.001 inch increments.22
This author's experience is that the Amada band saw is capable of holding
0.003 inches.
22 Amada. “Horizontal Bandsaw HA-330/HFA-330 Operator's Manual.”
31
The part must first be cut from eight foot stock to five feet. The stock
must then be lathed to achieve the smaller outer diameter. Last, the part is
bent in both places using the CNC bender.
The band saw will be responsible for indexing the part to the proper cut
length and cutting the part to tolerances. Additionally, the saw will flood the
blade with coolant. The coolant will maintain blade life, extending the saws
capability to maintain desired tolerances. The coolant will also rinse metal
chips from the cutting area so that the blade does not bind or cut out-of-square.
The process flow diagram for the band saw functions is in Figure 10.
3.6 Functional Allocation
At this point, the desired part features must be assigned to process
functions which effect the ability to meet the desired features. To do this, the
analyst must understand the process flow, the manufacturing processor, and
the part manufactured. The saw has two functions: (1) index the part and (2)
saw to specification. The results of functional allocation are in Table 3.
3.7 Defining Failure Modes
Failure modes are failures to achieve the desired system requirements
or outcomes. The failure modes for the outcomes in Table 3 are (1) part length
not indexed and (2) stock not sawed to proper specification. The column titled
“Failure Mode” in Table 4 (Part 1) will list potential failure modes for process
descriptions associated with the band saw.
33
‘() Wed) wesbeig Mo|4 sse00/4 Mespueg
‘O| ainbi-4
sdiyD —]
aysean anowey
f*
vb
cHed uojeoyioads
uOITEIyIOadS 0}
oure'] OND
Jujoury Le
0} YO0}$
MES +
yooys MEY
XApU| mes
pueg sonpoid
O'S 394
eb bb
OL ‘Jeu
—j
H90]G MEY
POH pe
Zh
BUIPIOAA 0}
yodsuel]
aBelojs yOo}S
MEY
Jepueg DND
Sue] IND
Meg pueg
oe 0c
OL
34
sdiuo
BISEAA SAOWUAY
VL Jee
uojeayoads
03 Y20Ig MES
eb yee
YOO}G
MEY PIOH
a
ob eu sa,
(Z Wed)
wesbeig
Moj-] ssa00J4
Mespueg
‘O| eunbi-
uonesyiseds 0}
yOOIS MEY
XePU]
apeid Mes
912104 fas
euze] OND peel mes esiey
z'e't HH
oneouneds
oz 3eu
cet 4
peay meg somo eb
yeu
ber
ON , 49018
400g éuj6ue7
y90]9 3
yaoig dwejun
y01S MEY
4ND 0} xepu
GWELD aa1A
JULY “eu
h yoann BIA
JUOLY dwie[g
asta seay
S21 2808
PENOH Pat
an eneel
ob ov
vit ete
eb ib
uonedyoeds
0}
yoo}g vey
XepU|
ib yee
35
auje]
ONO
O'? (J2Y
‘(© Wed)
wesbeig Mo|4
sse00j4 Mespueg
‘O} aunbi4
éHed Jaujouy gonpold
(sayejoy apeig
uayAA AUC)
apeig ysmug
sv'l
sdiy9 Aeauoy
vol
sdiyo @ISEAA
SAOWIAY
jUB|OOD J2}I4
<_—
JUBIOOD poo
—
(UO
S| jUe|OOD uayM
AjUO) yugjoosy
dung
ev'l Pb
Pl
|
36
Table 3. Functional Allocation to Process Flows.
Process Flow Outcome Retract Rear Vice Desired Part Length Indexed Rear Vice Clamps Raw Stock Desired Part Length Indexed; Desired
Raw Stock Dimensions Rear Vice Indexes Raw Stock Desired Part Length Indexed
Front Vice Clamps Raw Stock Stock Sawed to Proper Specification Saw Part Stock Sawed to Proper Specification Lower Saw Head Stock Sawed to Proper Specification Rotate Saw Head Stock Sawed to Proper Specification Raise Saw Head Stock Sawed to Proper Specification Pump/Flood Coolant Stock Sawed to Proper Specification Filter Coolant Stock Sawed to Proper Specification Convey Chips Stock Sawed to Proper Specification Brush Blade Stock Sawed to Proper Specification
3.8 Defining Failure Causes
Each failure mode is caused by the failure of a part or parts of the
system. As system components wear, they may fail, causing the entire
processor to fail. The column titled “Failure Cause” in Table 4 (Part 1) will list
potential failure causes for process descriptions associated with the band saw.
3.9 Defining Failure Effects
The effect of the failure is the consequence of the failure mode-cause
sequence. The effects of failure could be reduced process throughput, scrap
parts, rework costs, tooling damage at subsequent processes, the inability to
meet demand, the inability to meet quality requirements, or failed product in the
hands of the consumer. In any event, there are costs associated with failed
mechanisms, failure to meet demand, and failure to isolate nonconforming
products from the customer. Costs associated with immediate effects or other
effects in downstream processes within the manufacturing facility are
37
obtainable. Costs associated with effects downstream of the manufacturing
facility may be difficult to obtain. The columns titled “Immediate Failure Effects”
and “Downstream Failure Effects” in Table 4 (Part 1) and Table 4 (Part 2)
respectively will list potential failure effects for the process descriptions
associated with the band saw. Immediate effects are evident at the failed
processor. Downstream effects are evident at downstream processes or the
customer. Internal effects of nonconforming product propagating down stream
is increased rework or scrap during Incline Press assembly at a cost of $500
per incident.
3.10 Identifying Current Controls
Controls are sensors or procedures designed to detect and isolate
nonconforming product from propagating to downstream processes. For
existing processes, these items are usually listed on a control plan. These
items could be manual inspections, automated inspection systems, or go-no-go
gages. For sawed items, a long measuring gage can be used to measure
length.
The parts will be sawed in bundles of 10. The operator will check one
part of each bundle internal to the next cut. In addition, the band saw is
equipped with an out-of-square detector (OSD). The detector can stop the saw
cycle if the blade bows out-of-square a preset amount.
The band saw is equipped with a fault detection system. In most cases
when a failure occurs, the saw’s hydraulic motor will stop the sawing process
and display an error fault code. These error codes are listed under current
controls when applicable and are noted as “E-XXX.” Saw stoppage is a
process control that will preempt additional system failures or scrap production.
38
Saw stoppage is a prompt for the operator to review parts in process as
suspect nonconformance before releasing them to the next process.
3.11 Defining Occurrence, Severity, and Detection
Occurrence is the frequency of occurrence of the failure cause. For
reliability issues, occurrence is usually expressed as a Mean Time Between
Failures (MTBF) in hours. MTBF values may be provided by the manufacturer
based on reliability test or warranty data. Maintenance history of processors
may provide better MTBF estimates since the data is based on the processor in
its environment and utilization profile. Some component failures may not be
age-related. Therefore, a MTBF may not be attainable. Nautilus did not keep
historic maintenance information.
Severity of occurrence is the cost of the effect of the failure in terms of
damage or inability to isolate nonconforming parts. The severity results from
scrap, repair costs, lost throughput, inability to fulfill demand, quality reputation,
or harm to personnel.
Detection is the probability that the current controls can detect and
isolate nonconforming product from effecting downstream processes or
customers. Basically the detection probability is the assessment of a
company’s control plan. Historic information on scrap reports or return material
authorization from customers indicate the quantity of parts that get through
current controls.
3.12 Determining Cost of Failure
To determine and annualize the cost of failure, the analyst must have
the previous information developed in the PFMEA, scrap cost, cost of
39
downtime, cost for loss of opportunity, the cost of maintenance labor, the cost
of spare parts, and labor hours required to repair the failure. Maintenance
labor hours can be determined from historical data or through a Maintenance
Task Analysis (MTA). Mean corrective maintenance time (Mct) will be factored
with the maintenance labor wage to determine the corrective maintenance
labor cost. MDT may include administrative delay time or time to acquire parts
which are not in stock. Material costs are the costs of spares or consumables
which need to be replaced as a result of the failure. The cost of failure is the
sum of the following costs plus the material costs.
Scrap Cost = Pieces of Scrap * Scrap Cost
Cost of Idle Operator = MDT * Operator Wage
Cost of Lost Opportunity =
(MDT - Excess Capacity) * Hourly Cost of Lost Opportunity
Cost of Downstream Effects =
(1 - Scrap Detection %) * Pieces of Scrap * Cost of Downstream Effects
Corrective Maintenance Labor Cost = Mct * Maintenance Labor Wage
This section has described the application of the PFMEA to the Amada
band saw. Manufacturing system information has been used to determine the
cost of the failure. See Table 4 (Parts 1, 2, and 3) for the PFMEA. See Table
5 (Parts 1 and 2) for the annual corrective maintenance cost by component.
40
deios ‘ebeweq
epeig aNn|le4
JOJOW) YsMUg
OSL
deios ‘abeweq
apelg WOAA
Usnig Dads
0} paMmes
JON 490]S
epelg usg
Cpl
deiog ‘aBeweq
epejg ainie4
JOJ}OWy JOABAUOD
sads 0}
pames JON
4901S sdiy Aaauoy
vrb
deiog ‘ebeweg
epeg/pebbo/5
Jey14 pinj4
Buiyno dads
0} pames
JON 490}
JUBIOOD 19}!
ev
deios ‘eBeweq
apelg MO|-{
JUB[OOD Jo
yore] Fey
dejos ‘eBeweq
apelgpeBBojD dung
pinj4 Buiynd
Jere
deios ‘aBbeweg
apejg| aunyie4
dwing pinj4
Buiyn5 dads
0} pames
JON 4901S
JUBIOOD pooj4/duind
Leh
La aunie4
ainespApy PaMEsS
JON 190}$
Pedy Mes
asiey eel
LQ} anyle-4
JOJOW SPeig
Mes PEaMeS
JON 490}$
e@pelq MES
sj2}0Y Zeb
id einjle4
oneupAH
PaMmes JON
A90}S PES}
MES J8MO7
L’e'b La
pele seonpay
peeds PEMes
JON A90}S
Jeonpey pasds
oe
deios apelg
ueyolg aeL
deiog sdig
epeig Wel
de1og epelg
ING dads
0} PaMes
JON 490}
Wed Mes
eb
afeweq
epelg ‘deios
aunjiej oneupA}y
Eads 0}
PaMes JON
AOS
YOOIS SdUWEZID
Ssd1A JUOI4
OL
desos aunjiej
Japoouyg GL
1a aunjie4
onespAy
ach
La aousJepayu}
deiog paxepu|
JON ujybue7}
Wed yOOIS
MEY SEeXepu|
adIA JeSY
SLL
SUON| YOOIS
MeY Sdwe|oU
ed1A JUOUS
pli
desog| YyBIH
001 Buiyag
o1NeIpAH| pepo}siq
sucisuaWIG YOO}g
MEY GEL
ebeweq
epe|g ‘deiog|
Moy oo,
Buiyes oneypAH
Jeb
ia Sines
oNeipAH pexepu|
JON yjbue7]
ped] — JOO}G
MEY SdIWe|D
dA
1BOY Ebb
deiog ainjle4
Jepoouy OZ bE
1d ainjle4
o1neipAH ae
La soualepeyuj
desiog paxepu]
JON yjybue]
wed BdIA
Jeay jORI}EY
ZL
@UON| OIG MEY
sdwejoUN sdIA
Je8yY L'L'b
sjoayy aunjie4
asney asnjie4
apo; snyle4
UOHd]I9Seq SSa001d)
SDUSIBJOy
aye
pout wy
‘(, 882d)
VAWadd Mes
pueg ‘p
age]
A1
(sdojys aulyoeW|
/00-3) GSO
‘OL / |
IdA| a1quiessy
jou [IM
54 OS
FL (sdoyg
sulyoey| /00-3)
GSO ‘OL
/ |b
IdA} alquiessyy
jou |[IM
54 epeig
ysnig Cyl
(sdojs aulyoey|
J00-4) GSO
‘OL /
| IdA|
aiquiessy jou
IM OS
sdiyd Asauod
py
(sdojg auiyoey]
J00-3) GSO
‘01 /
b IdA|
eiquiessyy jou
HIM D4
JUZIOOD J9}14
ev tb
(sdojg aulyoey
400-3) GSO
‘OL /
Lb IdA|
aiquiassy jou
|IIM 54
ab PL
(sdoys aulyoey|
400-3) GSO
‘OL /
Lb IdA}
aiquiessy jou
|JIM 94
Ob yl
(sdojg auiyoey)
100-3) GSO
‘OL /
|b idA]
aiquwiessy jou
IM 54
Uz|OOD poo|4/duind
L'v'b
(SOL-3 ‘ZOL-3)
sdoyg auiyoey)
peey Mes
asiey eel
(LOL-3) sdojg
aulyoeyy OPpeig
MES a]e}0y
we |
(SOL-J ‘ZOL-3)
sdoyg auryoey
Peay MES
J8MO7 Lek
sdojs SUILSeIA
‘JOL}UO4) {ENstA
JaOnN pay peeds
OS
b
(sdoyg auryoey]
Z1 1-3)
YOUMS uu]
ebeyeaig epejg
Mes] ejquiessy
JOU |IIM
D4 gel
(sdojs sulysey
¢]|.|-3) 10}a}eq
UOKOW apeig)
ajquiessy jou
|IIM D4
WEL
(sdoysg sulyoeW
100-3) GSO
‘OL /
b IdA}
elqwessiy jou
||IM 94
Wed MeS
eh
(SOL-3 ‘ZOL-3)
sdojyg auryoep)|
eiquuassy jou
[IM 54
YOO}S SAWUIL|D
Bd1A JUO!4
OL
; OL/
LIdA! e1quiassy
jou [IM
54 OGL
(GOL-3 ‘ZOL-3)
sdoyg sulysey
aoe
(pL b-3)
sdoyg auryoey)
YOO}S MEY
Sexapu| Sd1A
1294 SLL
YOoS Mey sdwejour) GIA
JUO]4
pet
OL /
b IdA)
aiquiessy jou
JIM D4
Geb
OL/ LIGA}
e1GuWassy JOU
IM D4
Gee
(SOL-J ‘ZOL-3)
sdoys sulyoey
YOO] MEY
SALUBID 901A
JESY ebb
OL/ Lb
IdA) P1quiessy
jou |IIM
94 _
ZL
(SOL-3 ‘ZOL-3)
sdojs auiyoey
Gate
PEJEAOY S|
YOUMS WUT
PlemyoeG [NUM
BjOAD YSIU!4
JON JIA
BUulyoRY BIA
1eAY JORIOY
CLL 4Oo1IS Mey sdwejoun
SdIA JeOY
LLL
$]Ol}UOD JUSIIND
—_ spay
ounie4
uondisoseq
SS9I01d|
IOUSIjJIY
weasjsumMog
(Z aed)
VAWd4d Mes
pueg “p
a1Ge]
42
-
$ |%S6
- OSL
poy $$
|%S6 oes'l
epeig ysmg
Syl
- $
|%G6 -
sdiyo Aeauog
aa
CLE =
$ |%G6
070'Z WULIOOD
19314 ev
9sG'y $
%S6 021
Abb
€72 3=— $
| %GE 090'¢
OL VL
- $
|%S6 -
JURIOOD pooj4/duind
L vb
- $
1%0 -
peasy Mes
asiey eeb
- $
1%0 -
epeig Mes
s}e}0Oy Cel
- $
1%0 -
pesH MES
18M07 om
G6z_ $$
|%O 00Z'L9
Jaonpey peeds
Oe
- $
|%001 -
aqey -
$ |%00L
- VEL
ELL'E $
|%G6 Ove
Hed MES
cb
- $
|%G6 -
YyOo}s sdwelD
eoiA yuol4
OL
- $
|%S6 -
OS LL
- $
|%0 -
aS
bt -
$ 1%0
OZO'L YOO]S
MEY SOXSPU]
SdIA Je8y
GLb
yoo]S Mey
SALUBIOUT Bd1A
jUOI4 PLL
- $
1%S6 -
Celt
- $
| %G6 -
Deby
- $
|%0 -
YOO}S MEY
SAUD
Sd1A Jeey
ELL
- $
|%GS6 -
DCL TL
- $
1%0 -
ACL
G $
1 %0 000'9
BIA JEOY
PRIOY
CLL
yoo]S MEY
SdwejoUN asdiA
Jeey LL'h
(%) (sJH)
uondisosegd ssal01g|
aquasajay
Ajisanag | uonsejeq
| 4G
LIN
‘(¢ eBed)
WAWadd Mes
pueg ‘p
eiqey
43
Table 5. Band Saw Annual Maintenance Costs (Part 1).
MTBF |Scrap Scrap|MDT | Mct| Throughput|Scrap |Cost of Cost of Loss of
Corrective Maintenance (Hrs)|(Pcs) | Detection (%)|(Hrs) |(Hrs)| Loss (Hrs) Cost ($)|Operator |Opportun
Hydraulic Failure - 0.0 100% | 19.00) 4.00 §.6|$ - $ 285 | $ 1,718
Encoder Failure - 2.5 95%} 17.00) 2.00 3.6|$ 21|$ 255(|$ 1,104
Dull Blade 240 2.5 95%/| 0.33) 0.33 0.0|/$ 2148 5|$ -
Blade Slips - 0.0 100%| 0.33) 0.33 00;$ - $ §|$ -
Broken Blade - 2.5 100%| 0.33] 0.33 0.0/$ 21/$ 5|$ -
Speed Reducer Failure 61,200 0.0 100% | 19.00; 4.00 §.6|$ - $ 285 $ 1,718
Saw Blade Motor Failure - 0.0 100%| 17.00] 2.00 3.6|/$ - $ 255|$ 1,104
Cutting Fluid Pump Failure - 2.5 95% | 16.50} 1.50 3.1]/$ 21/$ 248|$ 951
Cutting Fluid Pump Clogged } 3,060 2.5 95%| 1.00| 1.00 0.0;/$ 21/$ 15 | $ :
Lack of Coolant Flow 120 2.5 95%| 0.25] 0.25 0.0/$ 21/$ 4|$ :
Cutting Fluid Filter Clogged 2,040 2.5 95%| 1.00] 0.50 0.0/$ 21/|$ 15 |$ -
Conveyor Motor Failure - 0.0 95%| 17.00/ 2.00 3.6|$ - $ 2551 $ 1,104
Brush Worn / Change 1,530 2.5 95%| 0.66; 0.66 0.0|/$ 21;$ 10|$ :
Brush Motor Failure - 2.5 95%| 15.50 0.50 2.1/$ 21/$ 2331 $ 644
| |
Table 5. Band Saw Annual Maintenance Costs (Part 2).
« Annual Cost
ost of Effects|of Failureto | Materlal| CMLabor| An « nual | Annuat Cost Per Task Torective Maintenance Downstream (Process Costs Costs | CM Cost of Failure; Cost of Failure
ailure $ - $ - $ 1,000 |$ 60 | $ - $ $ Encoder Failure $ 63 | $ - $ 2251 $ 30 | $ : $ - $ on ull Blade $ 631$ 2214 7 Blade Sips So es et Broken Blade $ - ($ -_ Ts 8818 TST S - ; 36 peed Reducer Failure $ - $ 196 - 5 Saw Blade Motor Failure | $ - Ts - : 750 ; 30 : ey oe 239
Cutting Fluid Pump Failure | $ 63 | $ - $ 250/$ 23 | $ - ; - ; 1 558 Cutting Fluid Pump Clogged | $ 631$ 193 |$ -|$ 151$ 29 1$ 293 : siz Lack of Coolant Flow $ 63 | $ 4,369 | $ -|1$ 4/§ 188 | $ 4,556 | $ ot Cutting Fluid Filter Clogged | $ 63/$ 2001$ Ts a(S 22(s : Conveyor Motor Failure $ - $ : $ 175 |$ 30 | $ - $ a 564 Brush Worn / Change $ 631$ 367 1/$ 151 10[$981$ wats a8 Brush Motor Failure $ 631 $ - $ 165 | $ 81$ - $ $ 1 135
Total | $ 9,564
4.0 _Reliability Centered Maintenance Analysis
4.1 introduction
Reliability Centered Maintenance Analysis is a systematic approach for
the development of an effective and documented preventive maintenance
program for an equipment or system. The RCM analysis consists of a
structured decision tree that defines effective and efficient preventive
maintenance tasks which will sustain the quality and throughput of a
manufacturing system based on maintenance and failure costs. Like the
FMEA, RCM is best used during the systems design phase. The RCM analysis
is also an effective tool for evaluating and improving existing preventive
maintenance programs.
The goals of RCM are to: (1) assess the less expensive maintenance
alternative, (2) establish the preventive maintenance schedule, (3) establish
preventive and corrective maintenance procedures, (4) establish resource
requirements, and (5) allocate maintenance task responsibility (operator,
electrician, mechanic, etc.). In general, the goal is to implement and maintain a
strategically scheduled/JIT preventive maintenance program and a responsive
corrective maintenance program which is effective and exhibits the lowest cost.
See Table 6.
In the process of developing the RCM program, extensive
documentation on the manufacturing system will be developed which will reveal
the companies current practices regarding operation, maintenance, product
quality, and safety. The structured review of the system will create the means
by which maintenance tasks are introduced and revised, failures modes,
causes, and effects are reported, and corrective maintenance actions are
defined. Maintenance actions can be recorded to provide a historical database
which can be used to improve the maintenance concept. RCM can also be
45
Table 6. Maintenance Cost Breakdown.
Cost Components Associated with Cost Components Associated with
Failure Preventive Maintenance
Labor Labor Materials Materials Diagnostic/Test Equipment Monitoring/Test Equipment Training Training Loss of Opportunity Contractual Delivery Loss of Customer Faith Scrap
Rework
Personnel Injury used to establish maintenance roles which are best performed by the machine
RCM can be
performed on all processes or on the critical processes as defined by a FMEA
operators, leading towards Total Productive Maintenance.
given limited resources.
To perform a Reliability Centered Maintenance analysis, the analyst
determines the modes by which a process will fail, failure frequency, the effects
of the failure, and the cause of the failure. The cost of the failure is calculated
based on corrective maintenance costs, scrap costs, rework costs, lost
opportunities cost, and the cost of defects reaching the customer. The analyst
also determines maintenance tasks which are technically feasible and effective
in preventing failure modes. The costs associated with the preventive
maintenance tasks must be defined. To determine the costs of each
maintenance alternative, the analyst must determine the maintenance task
procedures, material requirements, the personnel quantities and skill levels
required for performing the maintenance. Figure 11 shows the information
requirements needed for each step in the RCM analysis.
46
NON
84} JO}
UOeUOJU]
JO SeouNOS
“11 eunbi4
UONEULOJU] UB|d
SOUBLIAIUIEYy Wwa}shS
peyysnf-}soD
sjueWelINbey VLIW
SOUBUSIUIEY '
- juewinooqg
WOu
VAWd
Va
pue V.LIN
BARUSASIg
| SSE]
GAQUBBg |
JO }S0D SUIULUIS}EQ
SN
(s)yse 1,
WLIN
SAHUSADI BIGEI/
SUILLIS}EG @ANUBABI
—
UONEULOJU| Auanes VaWs
Auenes 0}
Bulpioooy eunyes
Aysse[Q
uoReULOsUy
|
USPPIH S! eunie4
JOQUCD JUELIND
ji OUILUE}EQ pue
uoloejeq Vaw4
47
The RCM analysis is best performed by an interdisciplinary group of
people with an operations, maintenance, or engineering background. The
analysts must be knowledgeable of the manufacturing system, the maintenance
concept, maintenance tasks and their effective application. The analyst's
knowledge and experiences form the major inputs to the RCM decision logic.
The RCM decision logic is flexible and should be customized to the
manufacturing and support capabilities of the manufacturing facility, if
applicable.
Four of the common RCM decision logics are: (1) MIL-STD-2173(AS) -
“Reliability-Centered Maintenance Requirements for Naval Aircraft, Weapons
Systems, and Support Equipment,"25 (2) AMC-P-750-2 - "Guide to Reliability-
Centered Maintenance,"24 (3) MSG-3, "Airline/Manufacturer Maintenance
Program Development Document,"25 and (4) Reliability-Centred Maintenance
\l.26 See Appendix A for a graphical representation of each decision logic.
Today, RCM is extensively applied within the airline industry where it
originated. Manufacturers are required to develop a maintenance program for
each new aircraft before it is introduced into service. The MSG-3 (or RCM)
analysis is an acceptable methodology for developing the maintenance
program. Presently, The United States Department of Defense uses RCM to
develop maintenance plans for systems and equipment. For these uses, RCM
was intended to optimize system reliability and insure mission success.
RCM has been used over a broad range of manufacturing industries
including railroad industries and automobile manufacturers. While mission
23 MIL-STD-2173(AS), Military Standard, "Reliability-Centered Maintenance Requirements For Naval Aircraft, Weapon Systems, And Support Equipment," AMSC No. N3769, U. S. Department Of Defense, Washington D.C., August, 1981.
24 AMC-P-750-2, U.S. Army Pamphlet, “Guide To Reliability Centered Maintenance," U.S. Department of Defense, Washington D.C.
25 MSG-3, Airline/Manufacturer Maintenance Program Development Document, Maintenance Steering Group 3 Task Force, Air Transport Association of America, March 1988.
26 Moubray, J., Reliability-Centered Maintenance - RCM-I|, Butterworth-Heinemann Ltd.,
Boston, Massachusetts, 1991.
48
success in most manufacturing applications is important, cost-efficiency of the
entire manufacturing system is paramount. John Moubray and associates have
assisted with the application of RCM at many industries including three power
generation plants, two railways, two automobile manufacturers, several food
manufacturing plants, two nuclear facilities, and mumerous_ other
manufacturers. The results of the RCM analysis as applied to an existing
manufacturing facility is a preventive and corrective maintenance plan which
will optimize system throughput and costs. See Figure 12.
Allison Gas Turbine Division of General Motors Corporation has
developed a computer program that automates the MSG-3 analysis logic.27
The program was designed to serve as a tool to present the decision logic to
the analyst and to document the analyst's responses. The analyst is
responsible for making decisions, not the software. The software prompts for
information and records it. This reduces the amount of work required to
perform the analysis as opposed to manually performing the analysis. It also
reduces the chance of error as a result of incorrectly following the decision
logic.
4.2 Maintenance Significant Items
Maintenance Significant Items are items whose failure: (1) could affect
safety, and/or (2) could be undetectable or are not likely to be detected during
operations, and/or (3) could have significant operational impact, and/or (4)
would have significant economic impact.28 They will be addressed through the
RCM analysis.
27 Callis, C.L. and F.E. David, "Automating the MSG-3 Analysis," Allison Gas Turbine Division, General Motors Corporation.
28 MSG-3, “Airline/Manufacturer Maintenance Program Development Document,” Maintenance Steering Group 3 Task Force, Air Transport Association of America, March 1988.
49
S}UIBISUOD UOHONpold
Burjeulunjyy ‘Zp
eunbi
awijumod ||
Ajoedeg pasnun
Y
yndyBnowy, | deins
JOSS9900/4
v
| 1 4 _ SOUT
ido au
u uo 5 azigides -
ae [HM. W
ow ou
jo sunsey oul
© co
Oo Oo rien
O CO
(NOH / S}UN) eByey UOI}ONPOd
001
O01
50
4.3 Structurally Significant Items
Each structural item is assessed in terms of its significance to continuing
structural stability, susceptibility to any form of damage, and the degree of
difficulty involved in detecting such damage. Once this is established, a
maintenance program is determined which will assure continued structural
integrity by providing the means to demonstrate that catastrophic failures due
to fatigue, corrosion, or accidental damage will be avoided throughout the
operational life of the structure.29
The work group must analyze the structurally significant items using two
analyses: Fatigue Damage Analysis and Accidental Damage/Environmental
Deterioration (AD/ED) Analysis. Fatigue analysis separates SSI into either
damage tolerant items or safe-life items. Items classified as damage tolerant
are routinely inspected for noticeable failure or redesigned. An example of an
SSI would be a mezzanine support or pallet rack. Accidental damage could
occur if a negligent tow motor driver collided and bent the support structure.
Fatigue from cyclic loading or corrosion could also lead to decreased structural
integrity.
AD/ED Analysis requires the analyst to determine inspection techniques
which will detect anticipated accidental damage or environmental damage.
These inspection techniques dictate where to look and what signs reveal
damage. Inspection requirements for timely detection of AD/ED must then be
determined.
Decision logic for SSI analysis is graphically represented in Figure 22 in
Appendix A. This project will not address SSIs. SSis would not be made
evident through a PFMEA.
29 MSG-3, Airline/Manufacturer Maintenance Program Development Document.”
51
4.4 RCM Decision Logic
The RCM decision diagram will pose a series of questions which will
prompt the analyst to define a maintenance plan using the information obtained
from the FMEA. The analyst will review the indicators and consequences of
failure then determine the maintenance tasks which will cost-effectively prevent
or correct the failure. Each question of the RCM decision logic will help the
analyst decide which maintenance option is less expensive, corrective or
preventive maintenance. In the decision process, the analyst must determine
which, if any, preventive maintenance actions will significantly increase process
reliability. The analyst will also establish alternative preventive maintenance
procedures, frequencies, resources requirements, and the cost associated with
each alternative.
In general, RCM decision logic first classifies failure modes by the ability
to detect them. An operator must first be able to detect the failure mode or the
effects of the failure mode before multiple failures are allowed to occur. This
consideration will guide the analyst in determining what information the
processors or work-in-process will provide in assessing the necessity and
timeliness of maintenance requirements. This information was defined in the
PFMEA current controls list.
Hidden failures are failures with no direct effects or consequences to the
operating system. Hidden failures may allow multiple failures to occur which
can impact the system catastrophically. Consider the generator in a car as an
example. A generator can fail and not be detected by the operator till the
battery fails. The system is not impacted till the battery's energy is completely
consumed. If the failure is hidden, the RCM decision logic suggests a series of
preventive maintenance tasks which may make the failure visible. Inspection
or built-in-testing are the most common form of identifying hidden failures. If a
52
preventive maintenance task is not feasible or cost-effective for unmasking the
hidden failure, a design change may be warranted if the failure consequences
are severe. Otherwise, corrective maintenance of the multiple failures is the
preferred maintenance action.
The next step in the RCM decision logic is to classify failures according
to their severity. Severity may be defined in terms of safety, quality, reputation,
lost production time, cost, or a combination thereof. In general, failures are
placed in one of four categories: Hidden, Safety/Environment, Operational,
and Non-operational. Failures which result in personnel injury or
environmental damage clearly belong to the Safety/Environment category.
Only the RCM Il logic includes environmental concerns. Although the severity
of these damages may be negligible to system operation, the company's
responsibility to personnel and the environment are unmeasurable. These
failures must be avoided at all costs since these resources are invaluable.
Determining cost-effectiveness in this category is very difficult. |The
documentation and task choices when reviewing these failure modes can
determine the extent to which the company has committed to preventing these
failures and can possibly be used as a means to declare the extent of
negligence and/or liability the company must burden, if any, in the case of a
safety/environmental failure.
Operational failures impede or halt production, which results in a
corrective maintenance cost, downtime production loss, and possibly a loss of
customer faith. These three costs can be used to cost-justify a preventive
maintenance task aimed at reliably preempting the failure.
Non-operational failures do not affect system throughput. Although non-
operational failures do not present a loss of production, management policies
may assign a value to some non-operational failures. For example, a bent car
fender would be a non-operational failure, since the fender does not affect
53
vehicle operation. Suppose a chauffeur agency had a vehicle with a bent
fender. The bent fender may degrade the clientele's perception of the
company, therefore warranting repair. Associated with each category of failure
modes is a flow diagram of questions which are designed to determine the
most effective course of maintenance.
Some preventive maintenance tasks will be determined prior to the use
of the maintenance task decision logic. In the case of a purchased system, the
manufacturer may have recommended some maintenance tasks. Total-loss
lubrication points will be listed and scheduled without analysis. The cost of
analysis of total-loss points often outweighs the cost of maintenance.
Next, the maintenance task decision logic associated with each failure
category is used to suggest maintenance tasks in order to preempt the failure.
These maintenance task categories are on-condition, scheduled restoration,
and scheduled discard. The analyst must consider if a task is technically
feasible and if the task will prolong or restore the component back to its original
reliability. The task cost will be used to answer the question of whether the
task is economically feasible as opposed to the default action. One must
ultimately consider the life-cycle cost of the failure and its impacts to the
system, personnel, and the environment. In the event that preventive
maintenance costs more than failure costs, the default action “no scheduled
maintenance” is preferred, except under the safety/environmental category.
Failures which harm personnel or the environment will require compulsory
redesign.
4.5 RCMIl Analysis Example
The RCM analysis performed in this project will utilize the RCM Il
decision logic. The RCM II decision logic is preferred instead of the other three
54
because it has been applied previously in private industry and because it
addresses environmental concerns.
The RCM II will begin with a series of questions which as a result will
classify the failure into one of the following categories: Hidden Failure,
Safety/Environmental Failure, Operational Failure, and Nonoperational Failure.
After the classification, each failure mode must proceed through the
maintenance planning decision logic associated with the classification.
The only discernible difference between the task logics is the default
action. The default action is the action the organization should take if the
failure is not technically or economically feasible to prevent. Given a hidden
failure, if multiple failures do not effect personnel safety or the environment,
there is no scheduled maintenance. Redesign is voluntary if feasible. If
personnel safety or the environment is in jeopardy as a result of a hidden
failure, the system should be _ redesigned. The default action for
safety/environmental failures is compulsory redesign. The default actions for
both operation and non-operational failure is no scheduled maintenance,
redesign if feasible. Table 7 summarizes consequences and default actions.
Table 7. Default Actions.
Consequence Default Action Hidden, Safety/environmental Compulsory Redesign Hidden, Non-safety/environmental No scheduled maintenance.
Redesign if feasible.
Safety/Environmental Compulsory Redesign Operational No scheduled maintenance.
Redesign if feasible.
Non-operational No scheduled maintenance. Redesign if feasible.
The analyst will first categorize the failure of the band saw into a
consequence category by proceeding through the decision logic in Figure 13.
55
Will the loss of function
caused by this failure mode on its own become evident to the operating crew under
normal circumstances? Yes
Does the failure mode
cause a loss of function Yes
or other damage which could hurt or kill someone?
No \
Hidden Failure
No
Does the failure mode cause a
loss of function or other
damage which could breach any known
environmental standard or
reguiation?
Yes
No
Does the failure mode have a direct adverse effect on
operational capability (output, quality, customer service or operating costs in addition to
the direct cost of repair?
Safety/Environmenta
Yes
No
Nonoperational
Operational
Figure 13. Classification Decision Logic for RCM II.%°
30 Moubray, John. Reliability-centered Maintenance - RCM II.
56
The results of the consequence analysis is in Table 10 under the column
“Consequence.” With the exception of the brush, all consequences are
operational. The brush consequences are hidden. However, the brushes
hidden consequences will not effect personnel safety or the environment.
Therefore, all default tasks in this example will be “no scheduled maintenance.”
Please note that failure causes involving hydraulic pressure settings and
scrap interference are not being pursued through the RCM analysis. Pressure
settings are made by the operator based on material configuration. High
pressure settings on the clamps will distort tubing while in the vise. These
parameters will be established in the process instructions for the operators. It
will be assumed that these settings are correct, thus not a maintenance issue.
Scrap interference is an uncommon incident where scrap slugs fall
behind the rear vice and the back stop. The scrap slug interferes with the rear
vice reaching the back stop and limit switch. Therefore the machine does not
cycle. This condition is recognized and fixed by the operator.
4.6 Manufacturer’s Recommended Maintenance Tasks
Since the Amada band saw was manufactured by an original equipment
manufacturer (OEM), the manufacturer has probably suggested certain
preventive maintenance tasks aimed at extending processor life and preventing
some failure modes. Additionally, the Operator's Manual will provide some
maintenance instructions and trouble shooting tips. Table 8 represents the
preventive maintenance tasks suggested by Amada. These items are listed in
the maintenance plan. They are denoted by “(MR)” for “manufacturer
recommended.”
57
« Jenuew S.JoyesedO
O€E-VAH/OSE-VH MEspuRg je}UOZOH,
“epewy |.
SODIA Jeal
pue UOJ
Jo Sayeyd
apis 0}
jlo Ajddy
aplis epind apeigq
Mes aseals
QOIA Jeal
JO Seq
apinb
o} |i0
Aiddy
QOIA JED BSBAIS
Sdiyd jo
Saoeyns suIyOeUW
UBA|D abuly
peaymes esealy
UOIPUOS pue
JUaWaoR|d YSNjg aJIM
YOOUD
Ja|josU0d apl|S
UOISUa} Bpe|gq
MBS aSeaIg
Ayedosd pajjeysul
si apejq
Mes duns
ayeyy
sbulugag JOoUM
USALIP aSeals)
jlo JaOnpal
paads yOayD
fio oINespAy
obueyD Jayy
duwnd piny
Burns uealo
[10 otneupAy yOaYD
jl0 Jaonpas paeds
abueuD pin
Bunino abueuD
xoq diyd
ueajD piny
Buyyns yooyD
Ajpenuuy
Ajyenuue-1was —ALWUOW
Ayreq
1¢ SUSEL SOUBUB]UIE]
PEPUEUODEY
JEUNJOBJNUeW ‘g
a1GeL
@ LO
4.7 Total-loss Lubrication Points
The analyst should list all total-loss lubrication points. Total-loss
lubrication points such as grease nipples, slides, lead-screws, and open
lubrication systems should not be analyzed as part of the RCM analysis
because maintenance costs are relatively inexpensive. Whereas analyzing
total-loss lubrication for proper maintenance intervals and costs may be
unnecessarily expensive. %2
Since these items are typically open, replacement of lubrication is
frequent. Lubrication in open systems is easily contaminated and _ lost.
Fortunately, all total-loss lubrication points on the Amada are listed in the
operator's manual and are part of the manufacturer-recommended preventive
maintenance plan. These tasks are best allocated to the operator and defined
in the process instructions.
Closed lubrication systems such as gearboxes or engines are
determined during the task decision process. These lubrication points usually
require checking fluid levels, changing fluids, and/or analyzing the condition of
the fluid.
4.8 Maintenance Task Decision Logic
Next, the analyst must proceed through the maintenance task decision
logic. The maintenance task logic is represented in Figures 14, 15, 16, and 17.
The following sections will discuss the task options in detail.
32 Moubray, John. Reliability-centered Maintenance - RCM II.
59
Will the loss of function caused by this failure mode on its own become evident to the operating crew under
normal circumstances?
No
Is a task to detect whether the failure is Yes occurring or about to
occur technicallyfeasibie and worth doing?
Scheduled
On-conditionTask
qT
Nol
Is a scheduled
restoration
task to reduce the failure
rate technically feasible and worth doing?
Scheduled
Restoration Task
No
Is a schedule discard
task
to reduce the failure rate creed’
technically feasible and worth doing?
No
\
Is a failure-finding task to detect the failure
technically feasible and worth doing?
Scheduled Failure-finding Task
No
Could multiple failure | Yes affect safety or environment?
Redesign is Compulsory
No,
| No Scheduled
Maintenance -
Redesign if Cost Effective
Figure 14. Maintenance Task Decision Logic for Hidden Failures.**
33 Moubray, John. Reliability-centered Maintenance - RCM II.
Does the failure mode
cause a loss of function | No or other damage which
could hurt or kill
someone?
Yes
Is a task to detect whether the failure is occurring or about to
occur technically feasible and worth doing?
Is a scheduled restoration
task to avoid the failure rate technically feasible
and worth doing? —__1
fo No
Is a schedule discard
task
to avoid the failure rate technically feasible and worth doing?
Does the failure mode cause a
loss of function or other
damage which could breach any known
environmental standard or regulation?
a Yes
Scheduled
On-conditionTask
Yes —
Scheduled
Restoration Task
Yes
a
No
ls a combination of task
to avoid failures
technically feasible and worth
doing?
Scheduled
Discard Task
Yes
Combination of
Tasks
No
Redesign is Compulsory
Figure 15. Maintenance Task Decision Logic for Safety/Environmental
Failures.34
34 Moubray, John. Reliability-centered Maintenance - RCM II.
Does the failure mode have a
direct adverse effect on operational Capability (output, quality, customer
service or operating costs in addition to the direct cost of repair?
|
Yes
is a task to detect
whether the failure is Yes Scheduled
occurring or about to i On-conditionTask occur technically feasible
and worth doing?
Is a scheduled restoration
task to reduce the failure rate technically feasible | Yes
and worth doing? |
——
ls a schedule discard task Yes
to reduce the failure rate technically feasible and worth doing?
Scheduled
Restoration Task
No
Scheduled
Discard Task
No Scheduled
Maintenance -
Redesign if Cost Effective
Figure 16. Maintenance Task Decision Logic for Operational Failures.5
35 Moubray, John. Reliability-centered Maintenance - RCM Ii.
Does the failure mode have a
direct adverse effect on operational capability (output, quality, customer
service or operating costs in addition
to the direct cost of repair?
No
Is a task to detect whether the failure is Yes occurring or about to
occur technically feasible and worth doing?
yn
Is a scheduled restoration
task to reduce the failure >
rate technically feasible Yes and worth doing?
Scheduled
On-conditionTask
Scheduled
Restoration Task
No
Is a schedule discard
task Yes
to reduce the failure rate
technically feasible
and worth doing?
Scheduled
Discard Task
No
| No Scheduled
Maintenance -
Redesign if Cost Effective
Figure 17. Maintenance Task Decision Logic for Nonoperational Failures.
36 Moubray, John. Reliability-centered Maintenance - RCM II.
63
4.9 On-condition Tasks
On-condition tasks involve monitoring a system or component that tends
to fail over a period of time (P-F interval). On-condition tasks are system
inspections which are used to look for potential failures. On-condition tasks
can involve inspection through human senses, monitoring of process feedback,
inspection of product quality, and condition monitoring. The inspection may
reveal a needed preventive maintenance action or estimated time to failure. To
assess a processor condition, an attribute must be measured and compared to
a control signature. The control signature(s) of the attribute are used to assess
the condition of the machinery given a condition measurement. For example, a
spectrometer analysis of a degreaser sample may provide a parts per million
(PPM) count of suspended grease. This PPM measurement would then be
compared to a control signature. In this case, the contro! signature would likely
be an upper limit grease PPM count, which when exceeded, indicates the need
to drain, centrifuge, and replace the degreaser. In the event that the PPM
count was below the upper control limit, personnel may compare the
measurement to historical data, providing an estimate of the life of the
degreaser.
Typical processor instrumentation which may indicate imminent and
approaching failure are temperature or pressure gauges. Monitoring also
involves noticing unusual physical attributes such as odor, noise, or vibration to
predict failure. These symptoms usually indicate to the operator that failure is
approaching. Predictive monitoring is a form of on-condition monitoring, where
machine conditions are tracked and assessed using a cycle counter or a time
clock.
For an on-condition task to be effective, a component condition that
exhibits potential failure (P) must be detectable and task frequency must be
64
smaller than the component's P-F interval. Based on the P-F interval, on-
condition tasks may allow maintenance to schedule Just-In-Time restoration or
discard tasks at the processor’s next convenience. This would also avoid some
or all of the cost of system down time. If the P-F interval is too short or
inconsistent, on-condition tasks are not feasible. A short P-F interval may not
afford maintenance the opportunity to perform the maintenance task when the
processor is available.
On-condition tasks have many benefits. In the event an on-condition
task can detect potential failure with age-related items, the component can be
used over its entire useful life. Whereas, scheduled tasks may recondition the
system and incur the associated cost well before actual failure of the
component. Using all of the components useful life before maintenance may
save a manufacturing organization considerable money.
On-condition tasks due require time and money. It must be technically
feasible to monitor the system. The on-condition task must clearly define a
potential failure. Developing experience or history on performance baseline
and thresholds will assist the analyst in clearly defining a potential failure
mode.
If a feasible on-condition task cannot be determined, scheduled
restoration or discard tasks can be considered for items that exhibit age-related
failure. The analyst must resort to default tasks for items that do not exhibit
age-related failure.
4.10 Scheduled Restoration Task
Scheduled restoration is the act of refurbishing a component to its
original resistance to failure at a predetermined interval. To consider a
scheduled restoration task, the component must have a useful life. If failure is
65
not age-related, then the restoration task does not preempt a failure due to
wear. In fact, unnecessary restoration may induce failures. The frequency of a
scheduled restoration task is based on the components useful life.
Typical restoration tasks are cleaning, fluid replenishments, or painting.
An example of a restoration task would be turning brake rotors to restore a
uniform surface for the brake pads.
Scheduled restoration tasks have benefits over corrective maintenance.
Restoration does not necessarily incur as much material costs as replacing the
component. Restoration would prevent costs of secondary damage that may
be caused by component failure. Restoration must be significantly less
expensive than discarding, else discarding would be preferred. The largest
benefit to any scheduled task is, to a certain degree, it can be done at the
processor’s convenience.
Teamwork between maintenance and the scheduling function could
reduce or eliminate the cost associated with down time. Administrative delays
and procurement lead times would be external to the machine down time. On
the downside, scheduled restoration will typically require additional labor and
down time to restore the item.
4.11 Scheduled Discard Task
A scheduled discard task is the scheduled restoration of the system to a
reliable condition by replacing a component which is near failure. A scheduled
discard task is very similar to a scheduled restoration task. The discard item
must have a definable useful life. A discard task is preferred over a restoration
task if it is not technically feasible to restore the component or if it is less
expensive to discard the component. The discard task interval is based on the
useful life of the component.
66
The scheduled discard task can also be done at the convenience of the
processor. The costs associated with discard tasks are comparable to those of
corrective maintenance. The only exception is that the scheduled task may
avoid costs associated with down time.
Since preventive rework and discard task frequency are determined by a
predetermined MTBF, rework/discard tasks are performed based on the cycle
clicks, hours of utilization, or calendar intervals. Condition monitoring can be
used to establish maintenance click/clock intervals or calendar intervals.
4.12 No Scheduled Maintenance (Corrective Maintenance)
In the event corrective maintenance is the preferred option, a responsive
corrective maintenance plan should be defined. A responsive corrective
maintenance plan entails equipment, indicators, and procedures for diagnosis,
disassembly, rework/replace, repair verification, data collection, and sparing.
When performing the RCM, corrective maintenance protocol (i.e. lockouts and
diagnosis) and maintenance instructions for processors will be developed.
During a corrective maintenance action, information should be collected which
would be used to develop, reaffirm, or revise maintenance standards and
policies. This information includes machine downtime, time to repair,
counter/timer readings, cause of failure, material cost, and scrap cost.
Direct costs associated with corrective maintenance include labor, parts,
diagnostic equipment, process scrap/quality rejects, contractual deadline costs,
and the lost opportunity cost of production (if it decreases bottleneck
throughput).
4.13 Compulsory Redesign
The default action for safety and environmental failures is compulsory
redesign. Redesign could entail incorporating built-in test equipment, condition
monitoring sensors, or building redundancy into the system.
4.14 Selecting the Maintenance Task
At this point, the analyst must proceed through the maintenance task
logic for each failure mode. Feasible preventive maintenance tasks are
determined by the analyst and their cost is estimated. Table 9 lists feasible
preventive maintenance tasks for age-related components and their cost
estimates.
Task PM Cost = (Material Cost + Labor Cost + Overhead Cost)
Annual PM Task Cost = Task Frequency * Task PM Cost
For on-condition PM tasks, the cost of discarding the item upon potential failure
is the same as the cost of corrective maintenance. Therefore, the cost of
corrective maintenance is used as the cost of the on-condition discard task.
This assumes that the estimated MTBF is the life of the component. Only
historical data will help define a more accurate MTBF.
When choosing which task to perform, compare the annual costs of the
proposed PM tasks versus the annual cost of failure. Consider the
manufacturing facility's maintenance philosophy in this decision. In the case of
operational failure, this analyst believes that PM tasks should be chosen over
CM tasks if the costs are comparable. Since the CM task estimations are
68
(Wid) Z9$
96¢ "SUOIJONJISU!
“SU}UOLU sseooid
Jad juaweoe}d
yooyo
g AJaAe
USNJg Jo
PueoSIp pejnpeUoS
ISNIN ‘Alie@p
J0}!UOW UO!}IPUOS-UO
rors ‘UJOM
USNdg
(Wd) 06$
‘pebbojo SUON
‘AJUJUOW UONLIO}SS1
Pa|NDeYOS
CLES Jaf
piny Bumng
(Nd) (97+POL$) OSES
“AjuJUOUW
JUBIOOD JO
PUBOSIP pajnpeuNS
SUON
‘Aylep JOPUOW UO!IPUOCD-UO
9SS'r$ ‘JUe|OOO
JO yOe 7
(WD) 2$
‘Buissaooid ‘peBbojo
‘QUON Buunp
JOWUOW UO!}IPUOS-Ud
©77$ duind
pings Buning
(Id) (Lb+29$)
82$ 66$
‘Ajjenuue
‘sueek OL
AJaAe -{LUSS
PIN|J JO
PUBOSIP pajnpeudS
Jeonpes peeds
jo pueosip
pejnpayos
‘Ajlep sjargj
jlo yOoUy
G6zs ‘gilej
JeoNpes peeds
667
L$
‘SBOM (WD)
66r'L$ OM]
AJ8A8 PJeOSIq,
painpeuos
‘Jd
Buisn soyUoOW
UOlIpPUOS-UO E1Z‘e¢
‘apeiq jing
(IND) }S0O5
JenuUuy pue
jSO4 jenuuy pue
aunjie4 jo
OM| 8AIEUI93/ Wd
BUC SAIJEUI9I|¥
Wd | 3809
jenuuy
yusuodwio4y
‘SySe | SOUBLAIUIEI
SANEUWAIY “6
BIGe 1
69
based on MTBF estimations, and on-condition tasks are feasible on most age-
related components, this analyst is willing to risk a $500 error that PM is
significantly less expensive then CM. Since this analyst is biased towards PM,
a $500 factor will be included in the task decision.
If Annual CM Cost + $500 < Annual PM Cost, perform CM, else perform PM.
When historical maintenance data defines better variable estimates, a factor
may not be desired.
If there are alternative PM selections with comparable costs, on-
condition tasks are preferred to scheduled restoration/discard tasks. This too
is a decision based on the manufacturing facility’s maintenance philosophy.
Again, this analyst prefers using components to potential failure until a reliable
and consistent life can be determined.
Maintenance items that have zero MTBF are items whose failure is not
age-related. For these items, scheduled restoration or discard is not an option.
Therefore, if condition monitoring tasks cannot be determined, “no scheduled
maintenance” is the default task.
The resulting maintenance decision based on the maintenance task
decision logic is listed under “Proposed Task” in Table 10. In the table, each
question in the maintenance task logic is answered, forming the documented
maintenance plan. Table 11 provides the cost for each PM task.
4.15 Walk-throughs
After the maintenance tasks are selected, the analyst may want to
consider scheduling walk-throughs as a maintenance task. A walk-through is
basically a walk through the plant inspecting items for accidental damage or
70
structural damage. For example, aisle traffic around the saw may have
damaged a hydraulic hose. An alternative to a walk-through is having
operators perform an overall visual inspection of their area. With proper
housekeeping, the operator should be able to spot accidental damage or leaks
during everyday use of the equipment. This author believes daily
housekeeping is essential and those activities are directed by process
instructions.
71
969
L$ Ld
UBIDUOS/5 | SEL
Jed ‘QOUBUSBJUIEW
SANDALOO UWOLAd
ynejaq
“auniley payejal-abe
JON puBosiq
“aunjie} peyeas-ebe
JON uoleio}say
OG
tL
“aiqiseay AjjeoluYyoa}
JON |
UO!IPUdd-UO
jeuoeiedO
OL
1S09 ‘1S
Aq [PAJa}U
uonjenjeag
jenuuy
powJoLlead yeni
yse{ pesodoid
yse]_ |
auenbasuos | aouasajay
Japooug
Ceol
Leh
OL|
asl t
Qe
Le
Srl$ JIUBYOSP]
| SY}UOW
Qg "Ilo
oynesipAy eBueyd |
(YIN) pueosiq
OSL t
“ajqiseay Ajjeoiuyos}
JON UOHBJOISOY
Gets
(YIN) eb
29$ JoyesadoO
Ayieq "J@AQ]
[10 SIINBIPAY
YOOUD |
UOPUOD-UO
jeuoneiado
QZ
jSO9 Sy
Ag {BAJa}U]
uonjenjeAgq
jenuuy
pawojiad
jeniuy yse]
pasodoilg
yse] | auanbasuog | asualsajay
(| Wed)
ue|q soueuaiuleW
pasodosg ‘O}
sjqeL
| wajshs
oIneipAy
¢2
syyuow LES
dIUBYOO|\ ZL
‘|l0 JaOnpas
paeds aBueuDd |
(YW) puBOsiG
"alqiseay Ayjedluyoa}
JON UOI}BJO}SOY
CHIN) L9$
Joyeiado Ayieg
‘jaAQ| [10
JaONPa’ paads
yoayuyD | UOIIPUOD-UO
jeuonessdo f1
3809 ‘JS
Aq |=
jeAsazuy uonenjeag
jenuuy pawJopad
yenuy yse,
pasodoid
ysel |
aouanbasuos |
aduajajay
| 499npay
paads
‘payejal-abe JON
pJBOSIC ‘pajejai-abe
JON UdI}BJOISaY
gel
“giqiseay Ajpeoiuyos}
JON | UOlPUdd-UO
uayolg
“alqiseay AljeO!luyo9]
JON pJeosiq
"alqiseay Aj]BOILWOU0TS
JON UOI]EJOISOY
(IA) Vel
L9$ JojeJado
Aneq Auadod
payeysul si
apeyq J1
8as 0}
yOoUD |
UOl}IpUuds-UO jeuoijesadoO
dis
‘aIqisea) A}JBOIWLIOUOD2
JON DIBISIG
"alqiseay Ajjeo1uyd9}
JON UOI}eJOISOY
667' 1S
JoyeiadO | SIH
OFZ “UOI}PUOD-U0
apeRyg ebHueyD
sued |
‘Joyesado peoualiadxe
0] JoyedIpUI
Pinos HuljnD
S| 0$
Joyesado | op
Alaag "UOHIPUOD
apeRl jo
JoyeoOIpul aHues
yONpod OgS |
UO PUOd-UO
jeuonesedo ing
1809 ‘JS
Ag | jeAsazuy
uonjenjeag jenuuy
psuopLisd jeniuy
ysel| pasodold
yse] |
aduanbasuog | aduasajay
| @peig
mes
'(Z Med)
UB|d soUeUS}UIeYW]
pesodosd
‘O} s1qeL
13
Org JoyeiedO |
syjuoW 9g
‘ping Gunns
ebueyd | (YW)
peosiq “a}qised)
Ayjeolwouods JON
UOIJBJOISAY "JUBjO0D
(MIA) POLS
Jojeisdo Ayieq
jo Junowe
sadoJd sey
wajshs }1
99S 0}
YOSYD | UOlIpPUdD-UO
jeuoneiedO JPL
}S05 '1S9
Ag |
jeasaquy uonenjeag
jenuuy palopiad
jeniuy yse|
pasodold
yse| |
aouaenbasuog |
adualajay
juR|O0D
“ainile} payejas-abe
JON pieosiq
“aunjiey payejas-abe
JON UOIIBJO}SAY
‘duind Vy
6z$ JoyesodoO |
SIH| O90'E
pabbojo e
ayeolpul Aew
MOlj JUBJOOD
pajoUjsay | UOdl}IPUdd-UO
jeuoielsdoO pabbo9
SSS‘ I$
Id uBINUIOaIQ
| ysel
Jed “QOUBUSIUIBL
SAIOSLION ULIOLAd
ynejoq ‘payeja:
abe-10N DIBdSIG
“paje|al-abe ION
Udl}elo}sey
Lr
‘aiqiseay Ajjeoluyoay
JON |
UOlPUOd-UO
jeuoheiadoO payie
}S09 ‘}S9
Ag |
jeasajzu uonenjeag
jenuuy pawopiad
jeriuy yse]
pasodoid
yse] |
aouenbasuo; |
aduaiajay
| duind
ping Buigns
6E8' L$
Ld ueBlIoNjoa|a |
ySe] Jad
SOUBUSIUIEW BANDANOD
WWOLad
ynejaq “aunile}
payejas-abe JON
pbueosIg “ainle}
peyejes-abe JON
uoleso}say
“ajqiseas AyediuYyos}
JON | UO!}!PU0D-UO
jeuoneedO
ce}
1S09 ‘Isa
Ag |
jeasaquy uonenjeag
jenuuy pawoplad
jeiziu] ysel
pasodold
ysej |
aduanbasuos |
adualajay
'(€ Ue) Ue}
soUeUAa]UIeEW pesodolsd
‘OL sjqeL
| JOJ}OW
apeig MES
14
ZL‘ LS
Ld uBIDa|y |
ysel Jed
‘QOUBUSIUIELU BANIGIION
WWOLAd
“aunjie} peyejal-abe
JON piBosiq
“ainjle) pojejas-abe
JON uoeJoOIsey
"alqiseay Aljeo1uYyos}]
JON | UOlIPUOD-UO
jeuoneledg Gr
1S04 ‘}sq
Ag} jeasajuy
uonenjeag
jenuuy pauwopad
jeijiuy yse)
pasodoid
ysey |
aouanbasuog | aouasajay
| JOJOW
USNig
“aIqISeay AjJBOILUQUODA
JON pbuBosiIg
"alqisea Aljed1Uydd}
JON UONBIO}SOY
96$ Joyesado |
suH OSs‘L
“UONIPUOD-Ud ebuBYD
“WOM S}
YSNiq jl
8as 0}
YOBYD ‘“apeiq
(YIN) 19%
JoyeladoO Ayeq
| mes
ysureBe ysniq
Jo juawaoRd
Jaedoid Jo}
yOoUD |
UOlLIPUDD-UO usppIH
Sr]
3805 }s9
Ag |
yeaAsajzu] uonenjeag
jenuuy pawJojled
jeu]
yse| pasodoig
ysel |
aouanbasuog |
souasajay
ysnig
p9S‘'1$ Id
uBIoN}Oa|/9 | YSeL
Jed "BOUBUSIUIBLU
DAIIDAIION WOLad
ynejaq “pajejal-abe
10N pieosiq
“payejel-abe JON
UdNeJOISey ‘aiqisea)
Ayjeoluyos} JON |
UOlIPUOD-UO jeuonesedoO
vr
1805 ‘sq
Ag | jeAsayuy
uonenjeag
jenuuy pawsopiad
yerysuy ysej
pesodoidg yse]
| aouanbasucs |
adualajay
| 400) JOABAUOD
‘g1qIseaj AypeoiWOU0de
JON pleosiq
(YIN) 06$
Joyesado | AjujuoW
‘JOY UBBID
UOIBJO}SOY o¢
JoyesadQ “Jay
pabbojo e Sayeoipul
MO| JUBIOOD
payoNIsey |
UOlIPUOD-UO jBUDIeJOdO
op}
1S05 "}Sq
Aq |
jeasazuy uonenjeag
jenuuy paelwojiad
jeniuy yse]
pasodoig
ysel |
aduenbasuos |
aduasajay
‘(py Wed)
Ue] Yy sOUeUaIUIEW pesodojd
‘O| sjqel
| saya
pinjy Gumgng
15
cel $
|[e}OL GQ
$| Sol
$)/ -
$1] £800
cS UO!}OSdsu!
PUNO
Y/BAA 19
$] 770
$ -
$] 9L0'0
08z ysnig
ysnipy
/ yoeuD
06 $
|) 092 $
- ${]009°0
Zh Jayi4
pinjg Buyyng
ueeD OV
$/STLL
$|]O061LL $ |
0SZ'0 cj
jue|ooD ebueyD
vOlL $|
770 $;€lO
$| 9100
08z |[9A97]
JUB|OOD YO9YD
LL $ |
O92 $!06e
$ | 0050
| IO
Jeonpay peeds
ebueyD 19
$ | 770
$ -
$1 9100
08z 10
Jeonpey peeds
yooyD 19
$ | 7Z'0
$ -
$1] 9L0°0
ogz |
uone|/e}su| Jedold
JO} epelg
YO8YD Srl
$|/002L $|002S
$1} CELL
cg pinj4
onespAy ebueyo
19 $ |
7Z0 $
- $1]
9L0°0 08z
pInj4 o1jNeIpAHy
yOeUD INd
jo 3809
s}so4 (san)
}dW | bes
YSP] POUBUDJUILW SAIJUSADId
jsOD jenuuy | JOqe7]
Wd jeusyew
‘SISOD SOUBUAIUIe SAIUBAQ,
Jenuuy Mespueg
“L] aIGeL
16
5.0 Maintenance Plan Summary
The estimated annual cost for the proposed maintenance plan as
described in Table 12 is $2,293. See Table 11 for a preventive maintenance
task summary. This methodology provides an initial maintenance plan. As
maintenance and failure data emerge from the manufacturing system (failure
rates, failure costs, preventive maintenance effectiveness, etc.), the
maintenance plan should be reviewed, evaluated, and revised as necessary
using the FMEA and RCM to ensure the most cost-effective, efficient
maintenance plan.
6.0 Conclusions and Recommendations
This project has demonstrated that the PFMEA and RCM analysis can
be used to define a maintenance plan for manufacturing processors within a
manufacturing system. The PFMEA assists the analyst in determining failure
causes. The impact of these failures can be qualified as a cost of failure with
the availability of certain system information. The RCM analysis will logically
direct the analyst towards viable maintenance tasks. The expertise of the
analyst must determine if tasks are technically feasible and effective since
those answers are situation-dependent. As the cost of alternative PM tasks are
compared to corrective maintenance tasks, a maintenance decision based on
cost can be made.
This methodology would be useful in the design phase to assess the life-
cycle cost of a system design. This methodology can be used to estimate the
cost of maintenance. The life-cycle cost of the system can then be estimated
from estimates of research and development, construction, start-up, operation
77
£6z7'c$_ |: [BIOL
96$ Joyeiadg
| suH
OSs‘} ‘UONIPUOD-UO
abueYyD | UOdl}IPUOD-UO
usMg "WOM
SI USM
Jl 88S
0} YO9UD
‘“apeig Mes
CHIN)
L9$ Joyeiado
Ajieq ysureBe
ysnig jo
juaweoRid sadoid
Jo} yOSYD
| UOINPUOI-UO
ysng Syl
(YW) Jaz
06$ JoyeiadeO
Ajujuopy “JOH
UBI]D UO}}BJO}SOY
pinj4 Buying
“JOU Jays
o$ JoyesadO
pabBbojo &
sajyeolpul MO}
}UB[OOD payOUIsaY
| UOlPIPUOD-UO
pinj4. Buiyind
or
Ors JOleladO
SUJUOW
9 ‘pins
Buns aHueuy | Qyy)
pueosiq juejooyD
"JUB|OO9 (YIN)
POLS Joyeiado
Ajieq Jo
JunoWe
Jadoijd sey
WalsAs JI
9as 0}
YOSYD |
UOIIPUOD-UO
juejoo4y JPL
— ‘duind dung
VP 6z$
Joyweiado |
su Q90'S
| paBbBojo
e ajyeolpul
ABW MOjJ
JUB]OOD pajOUsaY
| UOdlpPUOd-UO
pinj44 Buring
pabboi9 LLS
oiueyoayy |
sujyuoWw Z|]
‘jlo JaONpes
paads abueuyd |
(YIN) DJeOSIq
| JaONpay
paads
CHIN) L9¢
Joye.ieadQ Ajieq
‘[BAQ] [IO
JaONpas paads
yOSYyD |
UOIPUOD-UO | JaOnpay paeds
OL
(YW) Vel
19$ Joyeiado
Ayieq Ajsadosd
payjeysul si
apelg J!
a8as 0}
yOaYD |
UOl}TPUOD-UO apelg
Mes
dis
667 L$
JoIeIadO SIH
OFZ “UOHIPUOD-UO
ape|g ebueyD |
UOdlIPU0D-UD
apeig Mes
sued |
Joyeledo peouaiiadxs
0} JOVeEdIpul
Pinos Hunn
cL o$
JoyeJadoO OL
AJaAy |
‘UOlpUOD apelgq
Jo JoJeOIpU!
aHues ONpoOJd
Odds | UONIPUODD-UO
apejg Mes
Ind
Wa}shs Cele
Sr1$ dIUBYOsY
SYJUOW 9
“Hl ayjneupAy
aBueyd |
(YIN) Pseosiq
oyneipA}y OSL
h (YW)
Wa}SAS Cle
L9$ Jo}e18d0O
Ajieq JAA]
10 SNeIpAY
YO9YD |
UO!IPUod-UO o1neipA}
aeoLre }SO9
‘1Sq Ag
[eAsa}U| uoijenyjeag
jenuuy paeuojiad
yeiiuy yse
pasodoid
yse] yuguodwo4 |
adualajay
‘AJGUIWUNS UB] qd SOUBUSIUIEW
SANUSASIY ‘Z]
BIGeL
78
and maintenance, and system disposal estimates. Given multiple alternatives,
a decision on the preferred system can be made based on life-cycle costs.
After each iteration of the methodology, data should be collected from
the system to reaffirm or revise the maintenance decision. Data collected from
the manufacturing system may provide move accurate estimates allowing the
analyst to reiterate the procedures and improve the plan.
Further study should be performed concerning down time associated
with function-related failure. The author's experience is that down time related
to function-related failure is greater than down time related to equipment
failure. Although these failure modes may show up on the PFMEA, they are
not issues that will appear in the maintenance plan. They are process control
issues under the control of the operator. There may be a decision logic or
procedure that will assist in establishing comprehensive process instructions,
work instructions, and reaction plans for these issues from the PFMEA.
79
, ;
,Juaudinba yoddng
pu
‘swajshg uodeay,
‘Yes JEAN
JO4 SjusWaINbay
soUeUajUIEY pasajuaD-AqIqe!aM,,
‘prepues AewIW
(SV)EZLZ-GLS-IIW ye
©
ze 01607 uoIsI9Eag
WOU (SV)EZLZ-GLS-TIW
‘gL aunbi4
paninbex ubisepey
fw ¥SB)
LBARIEYS Bupuy-eunye}
pur |iqeoixdde
ys) euyeq
A) Burpuy-eunie} & 5]
fav 86%
Jo Te
pared (cane
6ySE) Jo oe
pue pj
pues aiqeoidde sxsq
6g Aey
udjsepey og
Azyy uBisepey ej
BIOYGde SYSE) JO
VORPHIGICO UYPT |
524. | Jo uogeUIqUCD B §|
pasinbey Wd ON pane
Wd ON voreuiquuoo BUyeC |
ts, yoneuiqcd e S|
is is
te {ex
esnqoeye LOAD
9 eC)
LOanoeye ¥Sey
se} ¥SE]
4Se) OWA pur
e)qeaiidde te
pue eyqeondde
ne pue
e\qeoydde pus
eigeoydde Sun Prey OUP)
A} yee oun prey e |
Sua PRY UST Ts,
ysey own prey e S| Sun PREY U
e
| so}
sey own puey e S| prey eyed
| yse} own puey e |
few ts
i ie
LeAnoey8 Leagoeye
Leanoeye vo
uo eeanoaye
ee
pue exeoiidde ¥s2] Seateg
PR] Rue sraeanide x52
ee
pue eiqeandde ¥se) eed
pue eiqeaixdde Se ued
$A | UOMIPUD-UO
Ue 5|
54] — vofpucd-u0
ue 5]
A) vonipuce-uo
ue $s}
$4) WOR
PUCO-UIO UB
S|
| ON —
| ON c
_—_— ! ON
ee
; ON
eenjoeye Lsanoeye
LOAnoo ye Lergoeye
Burp Bupyues
2) Buwies
se) Buryues
eoUan oor Pe]
Pi oneairide ase peneeuer
eued je —|
pur oqeaidde ¥S2) pon
ouyeg pue e\qeoydde xsey
oneavg eujed
pue e\eoidde 452] MOAPA
VOTE |
594} Buriases/eqny e |
et 4]
Bupyuesreqny es] mum
1 Buwieseqny e 5)
A] Buroyuesfeqny e S|
, 4
L
eAayes UAdiayes
bunesado Bun eedo
U0 peya esuaspe
UO eye eSeApS Peup
UP SAR
GINge) RQOUR © OAzY pyncd
jeg eGewep
$9) (qua Uog g
uquca
uo
| «ON
ON | Arepucoes
20 sso] jeuoNoUTy |
$2) JS
GuNER] UappAy
Oy S209)
8 OSNED
auyey Oy)
SOQ)
uapply Ayes
UaPPIH AyayeS-UON
isonrp uno feuopesedo/ajwo0ussg
seouanbasueg Ayajes
| Buruwoped
aya 20;850d0
MAD ABO REpAR
| oS
80u8I7000 GanEE;
Of}
ITWOd
- soueUajUleWy pasajusc-Ayyjiqelay
‘uYyor ‘AeIqnOW
op N
or 21607] uolsi9ag
|| WON “Lz
anbiy
SN Pasa
90D Ff
ubssapay
- SOUEUTPLESH Painpeyag
oN
f ON
UJUAUO
KRAUS
wean vera
eon pa "
SO, | one; a
dynu
ay pINCD
oN oN
@an20y 3 1809 #
AR20Y3 180D
# ese}
cbuicp yom pus agseay
ss | Bupuy-anye Bis0p
yom pus agseay ubisepey
- souRuaUEyY ubisapey
- sxueUa LEY :
feat} Ayeouanyray Soungey Prone Of
4 Aperanyoay
eunpey
ay 91a
yO Udr aug.)
PaNpAPS PeNpeDS ON
papas ON
$9, | 45m]
0 UOgeuqucD
& $2, |
04 45@ Burpuy-asnge;
@ sy
iL
oN oN
on ON
UBia0p yom Apeeuyoo
{Sxacp yom Agronn29 EBuICD
om Aysonnjoa} Ubknop
rom Ageona pay
81 PROS
816: one} ag GONPOL OF alee
ayes Ose; 4p GONPA! OF
wen pied jt]
BIR) aang 2 POAT Of
151 PROD
jee ——] yes arryny
ag sor 94
PareAPS $24 |
48m) PUEOSP epayps ws
SOA | 488) preosip ampays
#4 PAPPAPS
$94 | 18% p
sp onpaps
& 5 Panpaps
SOA | 452] PUBOSIP anpaYys
8 S
, oN ON
ON ON
Lbui0p yor pus
UBurp yom pue
Ubuiap yom pus
eBu0p yom pur
488 LoONOISaY
mqsee; Aomnpol
018) YSE)
VONBOISOY 01890;
Agno,
oie NSE
LOH RIO SOY
ng Oe
s90y Aptoruy29]
9122 SR | UO
BOIS
arg ceay Ayemunse]
918
Perpeyps “oa
BuNyray ay BONpA
OF 4 Sm
parpaps “A
eunpay Oy eanpai O15
parpeips |
Oona] HY
PROAR OF 45
Panpays “on
Gunga]
By sONpa Of Yay Wor] 820] $41 PaNPSLPS
8 sy UOIBIOLS3) PANPRE
# 5 OH G15
PANDAS 8 5}
LOyRIO|
Sau PENPALS @ 5]
j j
oN ON
ON
Oy
Ubwop YOM pus ORESEa]
LBurOp Lom pure Orgseny Ubwcp yom
pus agszay ESu0p
yom pus aqseaj
#88 | YON pLU0D-UID Agecnnypey inaco of
jnoga $8 [YON pudt-UD)
Ageon 04 IO
O4 |NOGE
SR | UOUIPUCO-UD)
Aga pay
200 Oy jnogE
348% | UOUIPUO-UQ) Agtowuypey
1200 of NOGs
panpeyps 594
10 Butuncoo © auneay og
pares
$94 19 Buwurono
& aunpay ay PHPPAPS
sa, | 72 Suurace & aunagy ay
panpayps a
30 Buunsco
5 ampey OQ SYoya JOOIap OF
ER BS
JOYA aA
OF 45]
8 4 MAQOYM POLAP
OF 48H} B S| FOYJOYA
}9919P OF ¥SAY @ S}
j ]
$a 4 ———_1___
=
On
BOO
JO 1809 Praup og
oF quoqenhas
USWOURYS
UND AD ;RULIOU
Uon ppl ur 51500 Bugesedo 10
sovues 30
PueOueys UaWUABALe
t rep
nee
Jepun mad Bugguedo
ayi Of
sawosna ‘Aygenb
yndkno) Amcadeo twanouny Aue Ye aug PyN0O Lapa
toe ay ise
cere at
JUapLAd @iv0oeg UO SY UO ON |
prUCqEuadd
UO peye suuerpe Pap Se WEP 2040 10 UOGIUNY
JO S50} oH
ap0w ag 5200
so, | spow aunges
sug Aq pesneo 8 dAzy apou
anya] ay 5909) 8 9SN6D Bpow ange)
oy Se0q]
a
uoqoury
}O $90) 3ut BAA
J JUaWNDOG JuatUdojaAeq
WeJBoJq soURUBIVIEW
JaNSeyNUeW/EUILlY, ‘C-OSW
ge 09
se D!IHo7 uolsi9ag
WON E-OSW
‘Oz anbi4
nt
UBysopey
tow Laney
eu0g 6g
TW so
rqesnad og OAL
wo a
-—| 8 aFROREH wpe
ISPRN uogmugune
ubjsepe vogsurmoceee, |
SA) On
cs
ai 8 ubssopay
Jou |
~ to.
N
signage 9 eeanogte
mere 9 appogt
su0g 9g
NW
cope erpopits
seq
seo]
om eon
on carve prong
lye} Saye
Qe ate) OG Qe. 7800)
9g aapeyg
on
|<
A! oempempen
A! awn ee
As Pre
ABW '
OnSUQUD
/)t# 2
eam y
o——Fa
ln la
———a
veri =
oo
Sairae uopesyssy
fe—_{| sen
pueond now
pmong = je
——
pea
..—8 @A|
eorpe:
a yy 7A!
a eameoen A!
Jensen
A) Senrpen
|_ Uouncnee!
© L
" ‘
tev _ -
re {
as
weug yeoman ey
vonorte voor
enone foucRouny
=o —|
pcan pap
vores —
om ory
WORE ICRSa he
on ory
UORe Ore
om Or
Monoedeuy 7)
ae
=A oorpel
a a
7, aren
mA pooh pabayeamd)
[
mn t
5 [
fa Ci
Canes
;weyD eel
ny
Wey
wan
5 Pep
aqecptis ogy
We
PM
LL
ee
aan pouopouns
_ poop
fuogoung =
ke ————
P compwive por
muopuna = fe juan re
feu0gs ede
om, ee
ee Mopoedau!
=) s—mae
proppedeuy
-. wp poy
popoedeu]
way) amon
{ —
\,
[ ~~
f
[ ON
[SN
Laney
denpeye Loney
denpeye Bupyueg
__| vennogie
Cupyusg yomorte
Buppues renee
Suppues rerporte
AoRELaT] |
ee, |
vem Qunree MORFOUIT]
ee
Aogeopgr |~
on ures mopeopar]
[~ aa, Dome
{ j
mn [=
: TrerwaR
nn -,
Ougesedo. UO pays cewps
Apes Ougaunto
as
cy| Pape my
ree eunye
any UU
CAnes
Dug dD
a omy Lop
3 900Q up pays o
UEE
Grp 2 PEL
7
fo Pup
heey a
. wate
8 '
Ory) ROLY
ay | OFWs
ORpEE wguny
enpe emmy
ON | Gugnees Damp
RUDgOUY
Wa AmpUC8S
10
= Pp Wp
ee
are pogTy
ms eg
LaPrp mu mo 900g)
—- peamunsd
og 0arp
| —_
Ouganc
08
+
WBOUEUaIUEW) PIU
Ayqelay OL
pind, ‘Jeiydwed
Au
‘S'N ‘Z-0GZ-d-OWV
g¢ ©
gc 0!B07 UOISID9q
WOW 2-0SZ-d-OWV
‘6} aunbi4
nga
1805 p
wbomuig ueag
AANO 964849 ubssog abut) wossaq
t n { oN
( oN
BNPOYZ 1802 Ht
45%] }0
esse} fo
48% vey
£4Sej JO
Le{se] JO
ATWO e6ueyg
ubsag OG PURGWOD
GUYOC) “>
A oq euquice
¥ juawecede,
BuyQ) sh,
pausceday y
UO eUNgLUOD
BUYoQ ~.
i vogeuiqwwas
y
I N —___f
oN —
oN ee
t oN
¥sa Uisq
1s vse
5m} vem
ee) Ore
yuewecedas ouyeq
50, JUeWROR de!
y ueweoerdas
ouya) $04
juewsonyda: y
IDM
BUYOQ) 59)
oma
y luewaonxdas
euyac] 594
yuswaoeda y
ye ose
i) ona
8m oer
482) er)
OMA CUYAQ
50, spomal y
syOma) GUYER “7A
oma ¥
09 PUdd-U0 eUyEQ) 50)
oR pU00-U0 Uy somal
BUyaq] S94
ypomal y
se oy
se 45%
88} Buuojow
48m Buuopuow
4a] O8a
Log pUa-LO euyeg 504
vor puce-U0 uy
YoqspUNT-UO BUya() $94,
uoYspUde-U UY
aD GUY aC)
50h many
Woq pude-uo suyeq “mA
UORIPUCD-L0 Uy
—_______}
oN Bay
A
T
88) oqoedsuy
45R) voqoadsu 1m
a 459)
Buuopuow 488]
Buvopuow uonpsedg
Aus, , —
(uoqeedo Aue,
Le
——| «
aed
58) euyag
sa) SAwS Guys
sa1, aoans
y ad
auyag 5a)
maby
' |
oN On
8
458 ose
| osm
opesed oneiedy
482 L4SR
muues
Guyed) wah
mous
y Bovuss SUuyay)
wah
eounty
yeu ouoH
ru
SOLAS suyad
5)
nus
y
4 4
bo
Nm!
A tcp sad
ado
sywousag ‘Aapes-uoH voppty “Asses
sooue heunoe args; 6900 wong haps
I oN
HA J
I ON
FA J
(vepiou jeje
Hyg) 20 poge
vosew Urapou
Aayes judy 20 poe 1B BENED
LOR Gun] 520K)
VOsShW § 85ND BIERy S200
I On
894 ]
Lemesy Poop
marnnond ues)
Define aircraft
structural itams | !
Is item No | structurally Other Structure
significant?
Yes |
__f . Accidental i t & Categorize &
Catege SSI AD/ED Analysis Damage and list as Other ; Environmental | gs
Anaiyze for FD ; ' tructure and ADIED Detenoration Analysis
FD Analysis | | | —__f ; | ts other structure |
i { similar to existing | Evsuate t , Is SSI damage ins pection j secre? | ' tolerant? fequirements for mt
| detecting AD/ED Yes Yes | No for al SSIs
| y aR
+ fp Dam : . Tolonmnt Safe-Life | Accidental | Environmental |
' Damage | Deterioration | | po : ____t__, ! 1 id | SwG
. Categorize & Est recommends | Categorize & | as SL: Mfr Inspection . and/or selects | listasDT | determines irements i maintenance |
safe-tfe Emits and require iL includes with SSI | for timety
poaab ean | ADIED forall | | airworthiness or al Is FD detection | No imitations | SSis | dependent on | L_ J a | scheduled inspections? | | \ |
{ i
Yes t ; —_——. Preliminary | |
| Adequate residual ! : ! . | strength with | ' Maintenance ec
| extensive damage | : Pian | thatls readily | ' ‘ ee nea \ detectable during ; :
| routine aircraft | ! operation; or = | | ;
| damageis | | | | indicated bya | | \ | safe malfunction | : | Overiay task
| | fromeach | _——___t___ ‘| damage |
Is scheduled N | No scheduled . i : evaluation & | fatigue related | NO a fatigue related i consolidate: | inspection inspection submit to ISC | required? required | fro approval |
Yes "and inclusion | ! , | in MRB report ;
Can FD be | Can FD by | Proposal detected by visual No detected by NDI | i
inspection at fhods at practical | practical | intervals? intervals? 7
Ave fatigue Improved access inspection No and/or redesign requirements §(_—-——————™ may be read, or
feasible according classify es to SWG? safe-ife?
Yes Fo
Figure 22. Structural Significant Item Decision Logic.*'
41 MSG-3, Airline/Manufacturer Maintenance Program Development Document.
Appendix B - Maintenance Task Analysis
A Maintenance Task Analysis will provide a structured method of
determining maintenance requirements associated with a failure mode or
preventive task. Maintenance Task Analysis will also provide the analyst with
the information necessary to determine task productivity.
The first step in defining maintenance tasks is defining the maintenance
requirement. The maintenance requirements result from the failure modes as
defined by the PFMEA. They also result as a formulation of tasks aimed at
preempting the failure modes defined by the PFMEA. After defining the
maintenance requirement, the analyst must define the tasks which will correct
or prevent the failure. This information can usually be found in the
manufacturer's documents or developed by experienced maintenance
professionals. For each task, the analyst must determine the elapsed time
needed to perform the task, tool and equipment needs, the necessary
personnel skill level, and replacement parts associated with the task. 42 This
information, along with the MTBF, will allow costing of the maintenance
requirement. Figure 23 diagrams information sources and information flow
through the MTA. Tables 11 and 12 represent a MTA on changing the
hydraulic fluid associated with the Amada HFA-330 band saw.
42 Blanchard, B.S., Logistics Engineering and Management, Prentice Hall, Englewood Cliffs, New Jersey, 1992.
86
WLIW
Su} JO}
UONEWIOJU]
JO SSDINOG
“$7 einbi4
toe a
UONEUUOJU|
VvaW weiss
sjueLUaUINDeY copepueuucoey ) |
auedg BW
‘spsepue}s
pue ajqewinsuod
Eva}
SUILIE}Eg ‘ayey
eunyres
yusuuaINbeY euoiesa
J yuewdinby
pue ‘uct
ISSBJOld
{00 | SUILLUA}EQ
oN
|
yuauasINbaY ach
JeUUOSI8¢4 8sI
SUKULIIEC} [EUCISSAJol4
SPJEPUE}S JOGe)
NW
SUONEPUELULUODOY r
By ‘esqedxg
syse] SOUeUaTUIEyY
euljeq
i
JEUOISSAJOlg
|
jusweuinbey suoyepuswwosey
By |
SOUBUaTUIEYY
| +
BS|OdOxy
[BUOISSA}Old
‘sgouanbas Suljeq
apow
aunii€s V3W4
Po
87
89 Sul]
|E}OL 989
S "UDI}ED0}
Jedoid 0}
UEdUIEIP WINeay
EL
‘Bo7] jesodsiq
oju! Ayjue
soRjq ‘JeUle}UOD
€9 Ol
JBUa}eIW snoplezey
pinbiq oyu!
piny s1iNeJPAY
pesn jo
esodsiq ch
ES S
“BNUE; Ajejes
Bu} soRidey
LL
Sr 9
"JOAOO PUN
SINeIpAY 8u}
soeides pue
‘deo s94]1}
By} US}YHI}
Ajaundes OL
‘abneb juBis
au} Jo
jeAd] Bjppiww
OV G
OU} O}
HUB} OU}
OFU! J9IIy
24} YBNoYY
PINy ayyNeJpAY
Ysa. ey}
INO
6 ce
G ‘Onid
ulejJp au}
eoe|dei ‘paulieJp
Aja}ejdLuad SI
jd DNespAY
Su} UBsU/\A
93
oe €
"10 DIINBspAY
uj jo B
njd
ulesp au}
sAowayY Z
Lo L
‘deo Jai|y
ay} eAowsay
9 92
S "JBAOD
HUN DIINeIDAU
BU} SAOWAY
S
LZ S
‘a0Ud) Ajajes
au] SAQWAY
v
"YOUIMS Jayealg
9| S
WNDJID doys
ay} PUB
YOUMS JEeyYeaJg
JINDJIIO SUIYORW
Ou] HO
WNL
©
LL €
‘UedUIeIG 389
z 8
8 CED
IO SNIISL
[lOUS JO
SUOI|BS) G°G
JOD L
(UIA) OWL
(UII) posdey
ou] 4SeL
uoldiuoseg ysel |
# ySeL
SUJUOI| 9
Aouanbel4 juawasinbay
lO aIINepAH
eBueys) |
JUeWasnbay
jo uoljduoseg
10 d1NeIpA}
"ON HE q
/aweN
Wis}|
mes
pueg epeuy
wa}sAhs
‘(| yeeus)
siskjeuy yse{
souBuejUleEW ‘|
aiqeL
88
el Cl LL OL
YOUSIAA JOH90S
,, Z/| 6
YOUSINA JOH90E
,, Z// 8
1S$ (Suo}leD
$°6) ZED
I! SNIIFL
8US Z 9
UC
UICIG ‘YDUSIAA
JOYOOS , 2/1
S
YOUSIAA JEH90§
,, Z/} v
YOUSIAA JOH90G
,, Z/L €
YOUSIAA }OH90S
,, Z/| C L
}SO9 ye,
posinboy syed
posinbay juawdinba/sjoo! |
# yseL
SUJUOI 9
- Aouenbai4 yuawasinbay
lO dIINeupAH
eBueyH =|
JUsWasINbay
Jo UONdUDSeq
1O a11INeIpPAH
"ON HEd/sweN
Wes}
MeS
pueg Bpeuy
wa}sAS
'(Z }e0uUS)
sisAjeuy yse|
soUBUdJUIEW
‘pL sIGeL
89
Appendix C - References and Additional Reading
AMC-P-750-2, U.S. Army Pamphlet, “Guide To Reliability Centered Maintenance,” U.S. Department of Defense, Washington D.C.
Author Not Listed, "Computerizing Maintenance Information,” Plant
Engineering, 1991 Encyclopedia, July 1991, pp. 218-219.
Amada, “Horizontal Bandsaw HA-330/HFA-330 Operator's Manual.”
Blanchard, B. S., Logistics Engineering and Management, 4th. Edition,
Prentice-Hall, Englewood Cliffs, N. J., 1992.
Blanchard, B.S. and W.J. Fabrycky, Systems Engineering and Analysis, Prentice Hall, Inc., Englewood Cliffs, New Jersey, 1990.
Blanchard, B.S., Verma, D. and Elmer L. Peterson, Maintainability: A Key to
Effective Serviceability and Maintenance Management, John Wiley & Sons, Inc. New York, New York, 1995.
Blanchard, B.S., Brennan Bowen, and Dinesh Verma. "A Review of Reliability Centered Maintenance (RCM) Approaches." Systems Engineering Design Laboratory, Virginia Polytechnic Institute and State University, Blacksburg, VA, 24061-0118, 1993.
Borgovini, R., Pemberton, S., and D. Russell. “Failure Mode, Effects, and Criticality Analysis (FMECA),” Reliability Analysis Center, Rome, NY operated by IIT Research Institute, 1992.
Bowen, Brennan and Dinesh Verma, "Manufacturing Process Improvement
Through the Application of the Failure Mode, Effects, and Criticality Analysis." Proceedings of the Fourth FAIM Conference, Blacksburg, Virginia, Spring 1994.
Bowles, John B., and Colon E. Pelaez, “A Comparison of Commercial FMEA/FMECA Programs," University of South Carolina, Columbia, S.C. 29208, 1991.
Callis, C.L. and F.E. David, "Automating the MSG-3 Analysis," Allison Gas Turbine Division, General Motors Corporation.
90
CARA FMECA (Software). Technica International, Suite 800, 1440 N. Harbor Blvd., Fullerton, CA 92635. (714) 447-9400.
Chrysler Corporation, Ford Motor Company, General Motors Corporation,
Reference Manual, Potential Failure Mode and Effects Analysis (FMEA), Second Edition, February 1995.
Cooper, Chris, "Desert Island Data,” Manufacturing Engineering, October 1992,
pp. 36-37.
Criswell, John W., Planned Maintenance for Productivity & Energy
Consumption. The Fairmont Press, Inc., Atlanta, GA, 1983.
Enelow, Micheal, "Go With the Flow," Manufacturing Engineering, February 1992, pp. 11-12.
Ertas, Atila and Jesse C. Jones. The Engineering Design Process. John Wiley & Sons, Inc., New York, 1993.
FMEAPlus (Software). Non-Ford Version: Adistra Corporation, 100 Union Street, Plymouth, MI 48170. Ford Version: Ford Motor Company, 1994.
FailMode (Software). Item Software Limited, Fareham, Hampshire, England, PO15 5SU.
Failure Modes & Effects Program (FME) 1.0 (Software). Powertronic Systems,
Inc., P.O. Box 29109, New Orleans, LA 70189. (504) 254-0383.
Ginzel, E. Charles and Dinesh Verma, "FMECA: Recommendations for
Improved Application." Technical_ Proceedings - The 28th Annual International Logistics Symposium, August 1993.
Goldratt, Eliyahu and Jeff Cox. The Goal: A Process of Ongoing Improvement,
Second Edition, North River Press, Croton-on-Hudson, NY, 1992.
Hamrick, James. "Eastward With TPM and CMMS," Industrial Engineering,
October 1994.
Hannan, Vince and Daniel M. Keyport, "Automating a Maintenance Work Control System,” Plant_Engineering, Vol. 45, No.2, December 1991, pp. 122-124.
91
Koelsch, James R., "A Dose of TPM: Downtime needn't be a better pill,”
Manufacturing Engineering, Vol. 110, No. 4, April 1993, pp. 63-66.
Kurz, Eberhard and Dieter Eden, "CIM-Maintenance - Information and
Document Management for the Maintenance of Aircraft," International Journal _of Flexible Automation and Integrated Manufacturing, Volume 1 Issue 1, 1993. CRC Press, Ann Arbor, pp. 1-10.
MIL-STD-1629A, “Procedures for Performing a Failure Mode, Effects, and Criticality Analysis’, Department of Defense, Washington, D.C.
MIL-STD-2173(AS), Military Standard, "Reliability-Centered Maintenance Requirements For Naval Aircraft, Weapon Systems, And Support Equipment," AMSC No. N3769, U. S. Department Of Defense, Washington D.C., August, 1981.
MSG-3, “Airline/Manufacturer Maintenance Program Development Document,” Maintenance Steering Group 3 Task Force, Air Transport Association of America, March 1988.
Maquire, Michael, "Predictive Maintenance: What does it do?,” Electrical World, Vol. 206, No.6, June 1992, pp. 11-12.
Mobley, R. K., Introduction to Predictive Maintenance, Van Nostrand Reinhold, New York, 1990.
Moubray, J., Reliability-Centered Maintenance - RCM-il, Butterworth- Heinemann Ltd., Boston, Massachusetts, 1991.
Nakajima, Seiichi. Introduction to Total Productive Maintenance, Productivity Press, Cambridge MA, 1988.
PC-FMECA Version 2.7 (Software). Management Sciences, Inc., 6022 Constitution N.E., Albuquerque, NM 87110. (505) 255-8611.
Patton, Joseph D. Jr. Maintainability and Maintenance Management,
Kingsport Press, 1980.
Reich, Hans, Maintenance Minimization for Competitive Advantage: A Life
Cycle Approach for Product Manufacturers and End Users, Gordon and
Breach Science Publishers, Langhorne, Pennsylvania, 1994.
92
Relex FMECA (Software). Innovative Software Designs, Inc. One Kimball Ridge Court, Baltimore, MD 21228. (301) 747-8543.
Smith, A.M., R.V. Vasudevan, T.D. Matteson, J.P. Gaertner, "Enhancing Plant
Preventive Maintenance Via RCM", 1986 Proceedings of the Annual Reliability and Maintainability Symposium.
Titan Software Corporation, "Maintenance: Profit Center 2000," Plant
Engineering, March 1992, pp. 101-112.
Titan Software Corporation, "Plant Maintenance As Profit Center: Rethinking Our Priorities," Plant Engineering, 1991 Encyclopedia, July 1991, pp. 228- 230.
Titan Software Corporation, "How to Select and Get the Most From a CMMS,"
Plant Engineering, 1991 Encyclopedia, July 1991, pp. 233-235.
Verma, D., "A Causal Emphasis during the Failure Mode, Effects, and Criticality Analysis", Invited Paper, International Logistics Conference, University of Exeter, Exeter, England, June 1993.
Verma, D. and B. Bowen, Process FMEA Training Manual, Federal Mogul Corporation, Blacksburg, Virginia 24060. December 1992.
Verma, D., B. Bowen, B.S. Blanchard, and L.B. Weddle, “Utilization of the
FMEA to Improve Manufacturing Process Efficiency: A Commercial Case Study,” Technical Proceedings - The 28th _ International Logistics Symposium, August 1993.
Wireman, T., Inspection and Training for TPM, Industrial Press, Inc., New York,
1992.
Wireman, T., Total Productive Maintenance: An American Approach, Industrial
Press, Inc., New York, 1991.
Wireman, T., World Class Maintenance Management, Industrial Press, Inc.,
New York, 1990.
93