feeder trunk hardening

24
FEEDER TRUNK HARDENING A PROGRAM DEVELOPED BY IDAHO POWER

Upload: khangminh22

Post on 21-Jan-2023

1 views

Category:

Documents


0 download

TRANSCRIPT

FEEDER TRUNKHARDENING A PROGRAM DEVELOPED BY

IDAHO POWER

PRESENTATION

P Vinson Carter

• Background, Method & Scope

Brett Efaw

• Statistical Analysis of Program Benefits

Purpose: Open discussion on distribution feeder hardening ingeneral. We have an interest in benefiting from othersexperience.

Can You Sleep When the Wind Blows?

Idaho Power Reliability History

In 2006 Idaho Power was deep in the fourth quartile of the IEEEreliability rankings.

We knew that we needed to improve or we could face mandatedreliability quotas.

We after completing some regional projects for a couple of years,we started two company wide projects from a ranked list:

• Exposure Zone Reduction

• Feeder Trunk Hardening

FEEDER TRUNK HARDENING

• Listed 200 feeders with highest number of customer outages

• Created an action plan to eliminate outage causes in the maintrunk or breaker zone of these feeders.

• Began with pilot distribution feeder to get cost and constructionfeed back.

• Expanded to small group of feeders in each of five service areas.

– A lines inspector performed initial inspections and provided valuablefeed back as to the program scope.

• As we came to understand the process and costs we expandedthe project and eventually the scope.

• As the project progressed the Fielding Check list expanded to 26items.

FEEDER TRUNK HARDENING LIST

Partial Fielding Checklist

1. Replace porcelain switches with polymer.

2. Replace and position all arrestors below switch fuses.

3. Install bird guarding as per the Avian Retrofit section 11-35 of the Construction Guidelines.

4. Install disconnect switches on the line side of CSPtransformers.

5. Re-tension conductors including flying taps and slackspans.

6. Fuse lateral taps.

7. Replace wood pins and cross arms.

8. Replace or repair damaged conductor

FEEDER TRUNK HARDENING LIST

9. Replace poles if there is significant deterioration aboveground. (up to 10% on FTH WO)

10. Report inadequate third party pole attachmentclearances.

11. Retighten hardware.

12. Replace dead end bells that show deterioration.

13. Replace steel primary side brackets.

14. Check down guy clearance and add fiberglass breakers ifrequired

15. Modify unreliable riser assemblies as well as otherunreliable assemblies

16. Reroute jumpers to increase spacing and avoid animalcontact.

PHOTOS

PHOTOS

PHOTOS

PHOTOS

PHOTOS

PHOTOS

PHOTOS

PHOTOS

PHOTOS

PHOTOS

PHOTOS

PHOTOS

Notes on Data and Analysis

• Compare SAIFI of feedersbefore versus after FTH

• Compare SAIFI overbetween FTH and no FTH

• All outages on the feederversus outages for thefeeder breaker

• Exclude plannedmaintenance and loss ofsupply outages

General CauseDescription Sub-Causes

Material/DeviceFailure

Corrosion/RotElectrical FailureLoose HardwareMechanical Failure

ForeignInterference

ContaminationLightningLoading/Unloading (Snow, Ice)Tree/VegetationStructures (Signs, Buildings)Unstable EarthWildland/Building FireOther Utility

AnimalInterference

Bird NonRaptorBird RaptorSmall AnimalLarge Animal (Livestock)

Public Interference Construction/Dig-inForeign Object (Pipe, Kite, Tree Trim)VandalismVehicle Collision

Miscellaneous OtherUnknown

SAIFI Before vs. After FTH

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

Material/DeviceFailure

ForeignInterference

AnimalInterference

PublicInterference

Miscellaneous Utility Practice

SAIF

I

Major Cause Category

SAIFI - All Outages

Before After

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

Material/DeviceFailure

ForeignInterference

AnimalInterference

PublicInterference

Miscellaneous Utility Practice

SAIF

I

Major Cause Category

SAIFI - Breaker Only

Before After

All Outages

Metric - Cause

FTH

No FTHBefore After Delta

SAIFI 2.04 1.36 -33% 1.28

Material/Device Failure 0.44 0.28 -35% 0.34

Foreign Interference 0.24 0.34 46% 0.17

Animal Interference 0.25 0.21 -14% 0.14

Public Interference 0.22 0.15 -31% 0.15

Miscellaneous 0.76 0.31 -59% 0.39

Utility Practice 0.14 0.05 -62% 0.09

Breaker Only

Metric - Cause

FTH

No FTHBefore After Delta

SAIFI 1.13 0.62 -45% 0.63

Material/Device Failure 0.22 0.12 -47% 0.15

Foreign Interference 0.11 0.15 39% 0.08

Animal Interference 0.15 0.14 -7% 0.07

Public Interference 0.14 0.06 -56% 0.07

Miscellaneous 0.41 0.14 -66% 0.18

Utility Practice 0.11 0.02 -84% 0.06

SAIFI FTH vs No FTH – All Outages

$-

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

0.0

0.5

1.0

1.5

2.0

2.5

3.0

2006 2007 2008 2009 2010 2011 2012 2013 2014

Mill

ion

so

fD

olla

rs

SAIF

I

Year

Dollars (M) FTH - All Outages No FTH - All Outages

Average Delta ‘06-’10: 0.76

Average Delta ‘11-’14: 0.23

SAIFI FTH vs No FTH – Breaker Only

$-

$500,000

$1,000,000

$1,500,000

$2,000,000

$2,500,000

0.0

0.5

1.0

1.5

2.0

2.5

3.0

2006 2007 2008 2009 2010 2011 2012 2013 2014

Mill

ion

so

fD

olla

rs

SAIF

I

Year

Dollars (M) FTH - Breaker Only No FTH - Breaker Only

Average Delta ‘06-’10: 0.55

Average Delta ‘11-’14: 0.06

SAIFI IEEE Benchmarking

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

SAIF

I

Year

IEEE SAIFI Quartiles

Q4 Q3 Q2 Q1 IPC

0.0

0.5

1.0

1.5

2.0

2.5

3.0

2004 2005 2006 2007 2008 2009 2010 2011 2012 2013

SAIF

I

Year

IEEE SAIFI MedEx Quartiles

Q4 Q3 Q2 Q1 IPC