an assessment of cost escalation in building
TRANSCRIPT
* Corresponding author, tel: +234 – 812 – 002 – 0020
AN ASSESSMENT OF COST ESCALATION IN BUILDING
CONSTRUCTION PROJECT
A. Nazif1,*, A. K. Mustapha2 and F. Sani3 1, 2, 3, QUANTITY SURVEYING DEPARTMENT, KADUNA POLYTECHNIC, TUDUN WADA, KADUNA STATE, NIGERIA
Email addresses: 1 [email protected], 2 [email protected], 3 [email protected]
ABSTRACT
Estimating of cost for building construction projects with minimum error at the conceptual stage
of project development is quite essential for planning. This study seeks to evaluate factors
responsible for cost escalation of building construction projects. Questionnaires were
administered to examine and assess these factors. Subsequently, the mean score value of each
factor was determined. In addition, Correlation and Linear regression analyses were used to
establish the relationship between these factors. Factors responsible for cost escalation in
projects were examined as well as the impact of those factors, and occurrence of those factors
on project cost. The result of the analysis showed that, the most agreed factors responsible for
project cost escalation were; inadequate supervision, irregular payment, and design error,
having high mean values of 4.25, 4.20, and 4.15, respectively. Also, correlation analysis result
established that the factors responsible for cost escalation and the impact of cost escalation had
significant R and R2 of 0.81 and 0.70 respectively. Addressing these factors would go a long way
in reducing the escalation of building project cost. Never the less, an effective cost management
strategy is absolutely necessary to safeguard and sustain the construction industry.
Keywords: cost escalation, building project, construction, regression analysis
1. INTRODUCTION
The construction industry plays a vital role in the
welfare of most economies; this includes providing
shelter, infrastructure, and employment [1].
Similarly, the construction sector and construction
activities are considered to be one of the major
sources of economic growth, development and
economic activities [2].
In Nigeria, the construction industry plays a
dominant role in the economic activities of the
country. The construction industry accounts for
about 60 % of the Nation's capital investment and
30 % of the Gross Domestic Product (G.D.P) [3].
Furthermore, the construction industry is said to
have contributed about half of the total stock of
fixed capital investment in the Nigerian economy
[4]. The construction industry also generates
employment opportunities, which place it second to
the Government in the employment of labour [5].
However, there are various problems associated
with the construction industry, particularly during
the construction project process, amongst them is
cost escalation.
Cost escalation is the increase in the amount of
money required to construct a given project above
the initially budgeted sum. It also arises, if the
actual cost of construction is in excess of the
originally estimated amount [6]. Some projects are
being completed at a cost higher than the initial
budge, hence, creating an unsuccessful project
delivery [7]. It was also established that poor
contract could be attributed to the manner in which
the contract was awarded. In some cases, projects
are awarded to the lowest bidder, which results into
various degrees of problems [8]. Some of these low
bidders may have inadequate management skills
and have less regard for contract plans; cost
control; overall site management; and resource
Nigerian Journal of Technology (NIJOTECH)
Vol. 39, No. 4, October 2020, pp. 1029 – 1034 Copyright© Faculty of Engineering, University of Nigeria, Nsukka,
Print ISSN: 0331-8443, Electronic ISSN: 2467-8821
www.nijotech.com
http://dx.doi.org/10.4314/njt.v39i4.8
AN ASSESSMENT OF COST ESCALATION IN BUILDING CONSTRUCTION PROJECT, A. Nazif, A. K. Mustapha & F. Sani
Nigerian Journal of Technology, Vol. 39, No. 4, October 2020 1030
allocation. In some situations, added cost has been
established to have obvious negative implications to
the key stakeholders in particular, and the industry
at large. To the client, high cost implies added costs
over those initially agreed upon at the onset,
resulting in less return on investment. The added
costs are passed on to the end users as high
rental/lease costs or prices. Also, these added costs
will result in the inability to deliver value-for-money
by consultants; this could tarnish their reputation
and lead to loss of confidence reposed on them by
clients. On the side of the contractor, there could
be loss of profit through penalties for non-
completion, and negative comments that could
jeopardize his/her chances of winning further jobs,
if at fault [9]. Cost management system is a
process that should be carried out throughout the
lifecycle of a project, from the inception to the final
completion and final payment to the contractor. In
the light of this, the timelines and cost effectiveness
of various operations and decisions carried out will
determine to an extent the magnitude of cost that
could be saved on the project [10]. This study aims
at identifying and examining the factors responsible
for cost escalation.
2. MATERIALS AND METHODS
For this study, questionnaires were administered to
respondents that work in various consulting and
contracting organizations that are involved in
various construction projects. A total of 100
questionnaires were administered and 80 were
returned. The questionnaires returned comprised of
60 and 20 questionnaires from consulting and
contracting firms, respectively. In addition, 64 of
the respondents handled both public and private
projects, 12 respondents handled private projects,
while, 4 respondents handled public projects. The
questionnaires were administered to professionals
including; Quantity surveyors, Structural Engineers,
Architects, and Builders. The respondents
comprised of top level management, middle level
management and lower level management staff.
Subsequently, statistical mean scores and standard
deviation were used to analyse the data acquired,
the Likert’s five – point scale was used to analyse
the responses of the respondents.
The formula for mean is:
𝑀 =∑ 𝑓𝑥
∑ 𝑓 (1)
Where: f x = Total frequency and f = Frequency
2.2 Regression Analysis
The relationship between the factors responsible for
cost escalation, the impact of the factors
responsible for cost of escalation, and the
occurrence of factors responsible for cost escalation
were determined using Correlation and Linear
regression analysis. The regression analyses used
for this study are as follows;
2.2.1 Correlation coefficient (R)
Measures the linear association between two
variables. Usually, values of the correlation
coefficient are between -1 and +1. A correlation
coefficient of +1 identifies that two variables are
significantly related in a positive linear logic; a
correlation coefficient of -1 identifies that two
variables are significantly related in a negative
linear sense, and a correlation coefficient of 0
indicates that there is no linear relationship
between the two variables [8].
2.2.2 Linear Regression Analysis (LR)
The general form of LR analysis is as follows:
Yi = β0 + β1X1i + εi (2)
Where Y is the dependent variable (predictant), β0
is a constant coefficient, β1, is referred to as
regression coefficients while X1, (predictor) is the
independent variable and ε is the residual error
(difference between observed and predicted
values) [12].
2.2.3 Coefficient of Determination (R2)
R2 is used to signify how well the model results fit
to the observed data points; it can also be used to
indicate the similarity between the model tendency
and the observed concentration [12].
𝑅2 = [∑ ( 𝑂𝑖 − �̅�)2. (𝑃𝑖 − 𝑃)̅̅ ̅𝑛
𝑖=1
𝑛. 𝜎0. 𝜎𝑝
]
2
(3)
Where, n is total number of annual measurements,
Pi is predicted values, Oi is observed values, �̅� is
the mean observed values, �̅� is mean of the
predicted values, 𝜎𝑝 is standard deviation of the
predicted values, and 𝜎𝑜 is standard deviation of the
observed values.
AN ASSESSMENT OF COST ESCALATION IN BUILDING CONSTRUCTION PROJECT, A. Nazif, A. K. Mustapha & F. Sani
Nigerian Journal of Technology, Vol. 39, No. 4, October 2020 1031
Table 1: Five Likert Rating Scale Strongly Agree Agree Undecided Disagree Strongly Disagree
Grade Point 5 4 3 2 1
Range 4.5 – 5.0 3.5 – 4.4 2.5 – 3.4 1.5– 2.5 0.5 – 1.4
3. RESULTS AND DISCUSSION
3.1 Mean score Analysis
3.1.1 Factors Responsible for Cost Escalation
in Building Construction Projects
From Figure 1, the main factors responsible for cost
escalation in building construction projects were
assessed using mean score and Likert rating scale.
The factors agreed by the respondents were
inadequate supervision with the highest mean value
of 4.25 and a ranking of 1st, followed by irregular
payment and fraudulent practice and kickbacks
which have the same ranking of 2nd and a mean
value of 4.2, next was differing site condition and
design error having the same mean value of 4.15
and a ranking of 4th, respectively. While the least
favorable factor is adjustment of prime cost sum
with mean value of 3.05 and a ranking of 17th, as
shown in Figure 1. This is in agreement with
previous study that suggested that fraudulent
practices and kickbacks occasioned by greed are
perpetuated by some major players in the
construction industry [10].
3.1.2 Level of Occurrence of Factors
Responsible for Cost Escalation
Figure 2 showed that the irregular payment is a
frequently occurring factor in building construction
projects with a mean value of 4.05 and a ranking of
1st, followed by inadequate supervision with mean
value of 3.70 and a ranking of 2nd, lack of cost
control has a mean value of 3.65 and a ranking of
3rd, and fluctuation of price of materials and
contract management having the same mean value
of 3.45 and a ranking of 4th respectively. While the
least factor is wastages on site which had a mean
value of 2.60 and a ranking of 17th. Therefore, the
data obtained highlighted the factors that bring
about cost escalation in building construction
projects.
3.1.3 Impact of Factors Responsible for Cost
Escalation
Based on the findings in Figure 3, the most
significant factors that are responsible for cost
escalation are design error, extensive variation,
wrong method of estimation, irregular payment,
fluctuation, differing site condition, fraudulent
practice, and kickbacks with mean value of 4.00,
3.80, 3.70, 3.65, 3.65, 3.65, 3.65 and a ranking of
1st, 2nd, 3rd, 4th, respectively.
Figure 1: Factors responsible for Cost escalation
00.5
11.5
22.5
33.5
44.5
Me
an S
core
Factors responsible for cost escalation
AN ASSESSMENT OF COST ESCALATION IN BUILDING CONSTRUCTION PROJECT, A. Nazif, A. K. Mustapha & F. Sani
Nigerian Journal of Technology, Vol. 39, No. 4, October 2020 1032
Figure 2: Occurrences of Factors Responsible for Cost Escalation
While the most insignificant and least factor is
adjustment of prime cost sum with mean value of
2.50 and a ranking of 17th. In a previous study it
was also established that design error was one of
the factors responsible for cost escalation [12].
Furthermore, the analysis showed that quite a
number of cost escalation factors have been agreed
upon by the respondents in various professions.
The result also revealed that some factors have
significant level of occurrence and influence in
building construction project; this includes irregular
payment, inadequate supervision, and lack of cost
control and fluctuation of price of materials.
Similarly, the result further indicated the most
significant factors which need to be focused more
carefully on so as to mitigate the rise in cost of
building construction projects. These factors include
design error, extensive variation, and wrong
method of estimation, irregular payment,
fluctuations, differing site condition and inadequate
supervisions. In a previous study irregular payment
was also ascertained as a factor that causes cost
escalation in projects [13].
3.2 Regression Analysis Result
3.2.1 Relationship between Factors and
Impact of factors
Based on the linear regression model in Figure 4
and Table 2, a significant relationship was
established for factors responsible for cost
escalation and impact of factors responsible for cost
escalation, having R and R2 result of 0.81 and 0.70,
respectively. These results established that the
factors that have influence on cost escalation and
their impact are significantly related. Also, the linear
regression analysis established that the factors that
influence cost escalation can explain their impact on
cost with 70 % certainty. Also, the P-value was
<0.00 confirming that the analysis is significant.
Moreover, the correlation result for factors
responsible for cost escalation and occurrence of
factors responsible for cost escalation was
significant, having R result of 0.7, however, the
linear regression result was not significant, having
R2 result of 0.45. The P-value was 0.01 which is
>0.00 suggesting that the relationship between the
variables was not significant. Also, the analyses
result for Occurrence of factors responsible for cost
escalation and impact of factors responsible for cost
escalation were not significant both having R and R2
of 0.47 and 0.23, respectively. The P-value also
confirmed the insignificance of the analyses with a
P-value of > 0.06 which is > 0.00.
4. CONCLUSION
The study assessed factors responsible for cost
escalation in building construction project by
identifying factors that leads to cost escalation and
examining the factors that lead to escalation of cost
in building construction projects.
Based on the study findings, the major factors
responsible for cost escalation obtained from the
00.5
11.5
22.5
33.5
44.5
Me
an S
core
Factors responsible for cost escalation
AN ASSESSMENT OF COST ESCALATION IN BUILDING CONSTRUCTION PROJECT, A. Nazif, A. K. Mustapha & F. Sani
Nigerian Journal of Technology, Vol. 39, No. 4, October 2020 1033
professionals in the construction industry were;
inadequate supervision, irregular payment, design
error, differing site condition, and lack of cost
control. Furthermore, it was determined that
irregular payment, inadequate supervision, lack of
cost control and fluctuation were the most
frequently occurring factors in building construction
that causes cost escalation. In addition, the result
also revealed that, design error, extensive variation,
wrong method of estimation, fluctuation of price of
materials and irregular payment were the most
significant factors leading to cost escalation in
building construction project. Also, Regression
analysis established a significant relationship
between factors responsible for cost escalation and
impact of cost escalation, having R and R2 result of
0.81 and 0.70, respectively.
Furthermore, the correlation result of factors
responsible for cost escalation & occurrence of cost
escalation was also significant, having an R result of
0.7, however, the linear regression result was not
significant, having R result of 0.45. More so, the
regression analyses result for occurrence of cost
escalation and impact of cost escalation was not
significant, both having R and R2 of 0.47 and 0.23,
respectively.
Escalation of construction cost can be reduced to a
bearable level by adhering to the following; at the
construction stage, a clear and thorough client brief
should be taken from inception of project to avoid
or minimize excess variation. Others include;
prompt payment of certificate, and employment of
competent contractors and consultants. Also,
constant cross checking of estimates based on
updated price information to avoid any wrong
estimate. More so, proper assessment of details
should be done before embarking on a project and
lastly, professional integrity.
Cost escalation in building construction projects can
be solved or minimized when the factors examined
in this study have been addressed; it will go a long
way in minimizing cost escalation of building
construction projects.
Figure 3: Impacts of Factors Responsible for Cost Escalation
Table 2: Regression Analyses Result
Analyses
Factors Responsible and Impact of Factors
Responsible for Cost Escalation
Factors Responsible and Occurrence of Factors
Responsible for Cost Escalation
Occurrence and Impact of
Factors Responsible for Cost Escalation
Linear
regression model
y= 0.878x + 0.7011 y = 0.7051x + 1.4811 y = 0.4713x + 1.5565
R 0.81 0.70 0.47
R2 0.70 0.45 0.23
P-value 0.000 0.01 0.06
00.5
11.5
22.5
33.5
44.5
Me
an S
core
Factors responsible for cost escalation
AN ASSESSMENT OF COST ESCALATION IN BUILDING CONSTRUCTION PROJECT, A. Nazif, A. K. Mustapha & F. Sani
Nigerian Journal of Technology, Vol. 39, No. 4, October 2020 1034
Figure 4 Linear Regression Model for Factors Responsible and Impact of Factors Responsible for Cost
Escalation
5. REFERENCES
[1] Anaman, K.A. and Osei-Amponsah, C. Analysis of the Causality Links Between the Growth of
the Construction Industry and the Growth of the Macro Economy in Ghana Construction Management and Economics, 25(9),951–961,
2007.
[2] Khan, R.A. Role of Construction Sector in Economic Growth: Empirical Evidence from Pakistan Economy. First International
Conference on Construction in Developing
Countries (ICCIDC–I) “Advancing and Integrating Construction Education, Research
& Practice” August 4-5, Karachi, Pakistan, 2008.
[3] Olowo - Okere, E.G. Problems of Construction Management in Nigeria', Paper presented to the workshop on National Construction Policy, ASCON, Badagry - Lagos, Nigeria, 1988.
[4] Olaloku, F.A. The Quantity Surveyor, the second
tier Foreign Exchange Market and the Construction Industry in Nigeria; Options and
Challenges', Construction in Nigeria. Journal of the Federation of Building and Civil Engineering Contractors in Nigeria 4 (I) 4-8,
2007.
[5] Hussein, A.A. Construction and the National
Economy. The Nigerian Quantity Surveyor. 20-21, 1991.
[6] Majid, M. Z. A., Zakaria, W. Z., Lamit, H.,
Keyvanfar, A., Shafaghat, A., and Bakti, E. B.
Construction Information Systems for
Executive Management in Monitoring Work Progress. Journal of Advanced Science Letter. 15(PP): 169–171, 2012.
[7] Anosike, P. Nigerian Groans Under High Cost of
Building Material. The Daily Sun. 38–39, 6th
April 2009.
[8] Mansfield, N.R. , Ugwu, O.O. and Doran, T.
Causes of Delay and Cost Overruns in Nigeria Construction Projects. International Journal of Project Management 12 (4) 254 – 260, 2011.
[9] Mbachu J. I. C. and Nkado, R.N. Reducing
Building Construction Costs; The Views of
Consultants and Contractors. COBRA, 2004.
[10] Kerzner, H. C. Project Management. 6th Edition.
John Wiley and Sons. Incorporated Canada, 2005.
[11] Hox, J. J., Moerbeek, M., and Van de Schoot,
R. Multilevel Analysis: Techniques and Applications 3rd Edition. Routledge Press.
2017.
[12] Devi, V. and Jegan R. Cost Escalation in
Construction Projects International Journal for Research in Applied Science & Engineering Technology 5(1), 271-277, 2017
[13] Ogunlana. S., Krit, P., and Vithool, J. Construction Delays in a Fast-growing
Economy; Comparing Thailand with other Economies. International Journal of Project Management 14 (1) 37 – 45, 2013.
y = 0.878x + 0.7011R² = 0.6981
2.5
3
3.5
4
4.5
2.5 2.7 2.9 3.1 3.3 3.5 3.7 3.9 4.1
Fact
ors
re
spo
nsi
ble
fo
r co
st
esc
alat
ion
Impact of factors responsible for cost escalation