design and challenges for the ship target complex
DESCRIPTION
First SHIP Workshop – 10-12 June 2014 - Zurich. Design and challenges for the SHIP target complex. M. Calviani , A. Ferrari, R. Losito, A. Perillo-Marcone, R. Folch, V. Venturi Engineering Department (EN) Sources, Targets and Interactions (STI) Group . Outline. SHIP target station design - PowerPoint PPT PresentationTRANSCRIPT
Design and challenges for the SHIP target complexM. Calviani, A. Ferrari, R. Losito, A. Perillo-Marcone, R. Folch, V. Venturi Engineering Department (EN)Sources, Targets and Interactions (STI) Group
First SHIP Workshop – 10-12 June 2014 - Zurich
M. Calviani - Design and challenges for the SHIP target complex
3
Outline SHIP target station design
Preliminary thoughts and challenges SHIP production target
Issues and present conception Conclusions and perspectives
11th June 2014
M. Calviani - Design and challenges for the SHIP target complex
4
Target areas at CERN CERN target areas are generally halls, pits or long tunnels,
far from the access points Activated air has enough time to decay and stray radiation is not
a problem for the public Neutrino ones are generally deep in the molasses (e.g. CNGS)
11th June 2014
beam
WANF & CNGSAntiproton target
n_TOF (neutrons)TCC2
M. Calviani - Design and challenges for the SHIP target complex
5
SHIP target station design The SHIP TS
preliminary design takes advantage of the activities for CENF
Shallow target installation, multi-compartment solution
Underground areas accessible from the target hall
11th June 2014
Due to the shallow depth of the beam line (~14 meters), a target area approach based on long tunnels (i.e. CNGS, WANF, etc.) is not applicable
A multi-compartment solution similar to T2K/NuMI has been therefore developed, taking into account the specificities of CERN
M. Calviani - Design and challenges for the SHIP target complex
611th June 2014
M. Calviani - Design and challenges for the SHIP target complex
7
Features of the SHIP target station Production target installed inside an
underground Fe shielded bunker, accessible from the top
11th June 2014
Iron shielding to be water cooled (~O(100 kW))
M. Calviani - Design and challenges for the SHIP target complex
8
Features of the target station Fully remote handling/manipulation of the
target and shielding from the target hall High residual dose rate (~tens of Sv/h!)
Helium environment enclosing the target and the shielding Reduction of air activation and corrosion
Ventilation system according to ISO17874 The idea is to have a pressure dynamic
confinement
11th June 2014
M. Calviani - Design and challenges for the SHIP target complex
911th June 2014
M. Battistin (EN/CV)
M. Calviani - Design and challenges for the SHIP target complex
1011th June 2014
This is what happens w/o control of the air chemistry (~at 20 kW)
M. Calviani - Design and challenges for the SHIP target complex
1111th June 2014
Target hall above ground level Outside area shall be non-designated during target
manipulation Ground-filled around target hall or heavy concrete walls
An additional (smaller) service building needed Safety racks, EL cabinets (EBD, etc.), transformers,
water treatment area, access, etc.
M. Calviani - Design and challenges for the SHIP target complex
1211th June 2014
View of the target hall and service buildings
Radioactive areas, no access
Radioactive areas, accessible in shutdown
Access for transport and various additional services (EL, secondary water loops, etc.)
38 m
35 m
M. Calviani - Design and challenges for the SHIP target complex
13
Target station summary Target station shall be designed for a MW-
class spallation target Specific attention to radioprotection &
environmental releases – well mastered and evaluated for CENF CE works adapted to minimize water infiltration
and in case treatment with evaporators Shall be designed for long-term operation Minimize time for target exchange in case of
failure (physics downtime)
11th June 2014
Challenging… but feasible
M. Calviani - Design and challenges for the SHIP target complex
14
Target design The production target is the single most
critical aspect of the target complex As required by the experiment, W-based (i.e.
high-Z) target Long term reliability is a key factor in the
design Reduction of “waste” Reduce downtime to minimum
11th June 2014
M. Calviani - Design and challenges for the SHIP target complex
15
(Spallation) source
11th June 2014
One of the most technologically challenging aspects of the proposed installation In terms of average beam power on target would be
similar to SNS (USA) or MLF (JP) However, power during pulse would make it closer to
ESS (almost 3 MW) Baseline UltimateBeam protons protonsMomentum [GeV/c] 400 400Beam Intensity [1013 p/cycle] 4.5 7.0Cycle length [s] 7.2 8.4Spill duration [s] 1.0 2.2Expected r.m.s. spot size (H/V) [mm] 6/6 6/6Average beam power on target [kW] 400 530Average beam power on target during spill [kW] 2900 2030B
eam
par
amet
ers
M. Calviani - Design and challenges for the SHIP target complex
16
Analysis method
11th June 2014
Analysis assumes nominal operation, with both the baseline and ultimate beams Steady state with transient analysis
Worst case scenario, i.e. target reaches steady state and then receives a high intensity pulse
Main preliminary results: Full W cylinder will not withstand the
compressive stresses (>2 GPa) and temperatures (>1200 °C) – target would fail
Target segmentation mandatory to allow decrease of temperatures and thus stresses
M. Calviani - Design and challenges for the SHIP target complex
17
Energy deposition and checks
11th June 2014
FLUKA/ANSYS/CFX coupled calculations Pure tungsten, 19.3 g/cm3
60 cm length, 20x20 cm2
Beam on target:1. Uniform circular sweep 3
cm radius, 1s 6 mm2. Archimedean spiral, 5-35
mm radius (1s 6 mm) 80% energy deposited in
the target (300-400 kW)
Target must be actively cooled(H2O considered for the
moment)
M. Calviani - Design and challenges for the SHIP target complex
1811th June 2014
Preliminary
Preliminary
Optimisation of the plate thickness still ongoing Longitudinal gap of
~O(10-15 cm) Peripheral + radial
cooling to increase HTC
High tangential velocities (5-10 m/s)!
M. Calviani - Design and challenges for the SHIP target complex
19
Thermo mechanical calculations Considering the poor properties of W heavy alloys
to high temperature and radiation we baselined pure W
~780 °C, 900 MPa (worst case) R&D needed!!!
11th June 2014
Caveat: Conservative
assumptions Still lots of margins
for improvement!
M. Calviani - Design and challenges for the SHIP target complex
20
Accident scenario (no sweep)
11th June 2014
3000 °C (below melting point at ~3400 °C)
~4.4 GPa compressive stress
The target would not melt... But will fail!
M. Calviani - Design and challenges for the SHIP target complex
21
Radiation damage Design shall assume that a target withstands the
whole proposed POTs (2*1020) ~1.2 DPA (displacement per atom) at 2*1020 POT
Big impact on the evolution of mechanical properties!
11th June 2014
M. Calviani - Design and challenges for the SHIP target complex
22
Evolution of mechanical properties with radiation (and temperature)
11th June 2014
S. A. Maloy et al., ICANSXX workshop (2012) S. A. Maloy, Materials Transactions, Vol. 43, No. 4 (2002)
Yield stress increases with irradiation and decreases with temperature
Reduction of ductility with irradiation
M. Calviani - Design and challenges for the SHIP target complex
23
Crack formation on pure W samples under irradiation
11th June 2014
S. A. Maloy et al., ICANSXX workshop (2012)S.A. Maloy et al. / Journal of Nuclear Materials 343 (2005) 219–226
The central core of the SHIP target might potentially develop internal cracks due to radiation embrittlement, swelling and high temperature
M. Calviani - Design and challenges for the SHIP target complex
24
Target design preliminary assessment
11th June 2014
The target must be segmented to reduce temperatures and compressive stresses
Very high flow rate required (cavitation, erosion/corrosion...) Need to check “water hammer” effect on target/cooling
circuits Full control of water chemistry (à-la-n_TOF) Vigorous R&D should be launched on material
properties and their evolution with radiation and temperature Ta-cladded W, WRe alloys, K-doped W alloys, etc.
M. Calviani - Design and challenges for the SHIP target complex
25
Possible other uses? We are considering a 500 kW (3 MW
pulsed) class spallation source Possible additional uses with minor
additional investments: Neutron/photon irradiation close to the target
~100-200 MGy/y lateral, 400 MGy/y downstream Neutron beam(s) for different applications (i.e.
neutron radiography) laterally outside of the He vessel (@500 cm or more)
…
11th June 2014
M. Calviani - Design and challenges for the SHIP target complex
26
Conclusions
11th June 2014
Target design is very challenging (but feasible!), significant R&D required on material and technical work for CFD and code optimization
Target station design needs to account the high average power (hence radioprotection and handling aspects) Profit from CENF studies but a dedicated WG
will be needed towards the DR
We are looking forward for this project!
M. Calviani - Design and challenges for the SHIP target complex
27
BACKUP
11th June 2014
M. Calviani - Design and challenges for the SHIP target complex
2811th June 2014