demand, capacity, activity and queue (dcaq): a case … adp dcaq final - … · demand, capacity,...

29
Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP) Biba Brand, National ADP Delivery Advisor, Scottish Government Fiona Doig, ADP Strategic Co-ordinator, Borders ADP

Upload: lykhanh

Post on 16-Mar-2018

218 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

Demand, Capacity, Activity and Queue

(DCAQ):

A Case Study in Borders Alcohol & Drug

Partnership (ADP)

Biba Brand, National ADP Delivery Advisor, Scottish Government

Fiona Doig, ADP Strategic Co-ordinator, Borders ADP

Page 2: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

2

Acknowledgements

With thanks to:

• Scottish Government Quality & Efficiency Support Team (QuEST) for their

support;

• Service Managers and staff who participated in the use of QuEST’s Demand

Capacity Activity Queue (DCAQ) Tool in their organisations;

• Susan Walker (Borders ADP) and Rachel Tatler (Scottish Government) for

their help in preparing this document.

Page 3: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

3

Table of Contents

1 Introduction 4

2 Background 4

2.1 Overview of the Investment Review 4 3 Delivering the Investment Review – Examination of the local system 5

3.1 The ‘project team’ 5

3.2 Data and evidence collection 6

4 Review of service uptake data 6

5 Using the DCAQ Tool 7

5.1 Areas for agreement 8

5.2 Timing 8

5.3 Data collection 8

5.4 Other areas of clarification 9

5.5 Data Management 9

6 Case Study 10

6.1 Data Gathering 10

6.2 Demand 10

6.3 Capacity 10

Figure 1 – DCAQ Data 13

6.4 Analysis 15

Figure 2 – DCAQ – Summary Data Analysis 18

7 DCAQ Projecting Hypothetical Impact 20

Figure 3 – Demand vs. Capacity (Actual vs. Scenario) 21

Figure 4 - Time Lost by the Service Due to DNAs (Actual vs. Scenario) 22

Figure 5 - Overall Balance between Capacity and Demand (Actual vs. Scenario) 22

8 Setting Improvement Goals 23

9 Learning Points 24

10 Impact of QuEST 25

11 Conclusion 26

References 27

Appendix 1 – Mental Health DCAQ Tool 28

Page 4: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

4

Demand, Capacity, Activity and Queue (DCAQ) – Case Study in Borders

Alcohol & Drugs Partnership (ADP) Services

1 Introduction

This paper presents a case study in the use of the Scottish Governments Quality and

Efficiency Support Team (QuEST) Demand, Capacity, Activity and Queue (DCAQ)

tool in Borders ADP. The DCAQ Tool was used to collect data during the Borders

ADP Investment Review. The paper outlines a short overview to the Investment

Review and outlines the overall data collection process for capacity and demand

analysis which took place during the second phase of the review. Section 4 onwards

concentrates on the use of the DCAQ Tool and using data from one service to

illustrate opportunities for improvement. Section 5 reflects on future role of the Tool

in Borders.

2 Background

In July 2012 the Borders ADP commenced work on an Investment Review. Borders

ADP cover a co-terminus local authority and NHS Board. Its population is 114,000.

The ring-fenced ADP budget for 2013-14 is £1,342,790.

The Investment Review was a response to the shifts in emphasis towards prevention

and early intervention and a recovery focussed system of care. Alongside these

shifts in emphasis are the constraints on public spending and awareness that public

sector services are expected to improve quality while at the same time ensuring

efficiencies.

The aim of the Investment Review was to review and make recommendations about

future investment of funding for Interventions and Services, as part of this, the use of

information on service demand and capacity was felt to be useful to the Review

process.

2.1 Overview of the Investment Review

There were three stages to the review:

Page 5: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

5

i) External consultancy – this highlighted gaps in local knowledge relating to

need and service uptake

ii) Examination of the local system - in terms of need and services/interventions

in place to respond. It was as part of this requirement that the QuEST Tool was

used. These findings were reported in the Investment Review Report, May 2013.

ADP Investment Review Report - Final, May 2013.pdf

iii) Consultation on Review Recommendations and development of Border’s ADP

Future Model - based on this second round of consultation the ADP Executive Group

developed a Future Model which was approved by the ADP in August 2013.

ADP Future Model of Investment- August 2013.pdf

3 Delivering the Investment Review – Examination of the local system

3.1 The ‘project team’

The Executive Group identified that additional skills and experience would be crucial

in ensuring a robust examination of the local system. Scottish Borders Council

Social Work Department therefore identified capacity from a Business Analyst to

provide support relating to data collection and analysis.

The Scottish Government’s National ADP Delivery Advisor agreed to offer support to

this phase of the Review.

The other members of the team were the ADP Strategic Co-ordinator and ADP

Development Officer with an ‘as required’ attendance from the Social Work Group

Manager for Mental Health and Addictions.

Page 6: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

6

In addition, Scottish Drugs Forum Quality Team provided support to deliver Service

User focus groups.

3.2 Data and evidence collection

A plan of data and evidence sources and range of approaches was identified to

inform a ‘whole system approach’ to reducing harm from alcohol and drugs including:

i) Review of existing and available data sets relating to prevalence and need

ii) Review of service data: analysis of demand and capacity data, number of

clients, planned and unplanned discharges. During development of this plan the

National ADP Delivery Advisor discussed with the Project Team that the Mental

Health QuEST DCAQ Tool could be a potential method for analysing demand and

capacity. At that time the Tool had only been used within mental health services.

Permission was sought from QuEST to allow use of the DCAQ Tool. It was agreed

to approach Service Managers via one of the scheduled meetings to seek

agreement to use the Tool in their services.

iii) Stakeholder evidence and involvement: including themed Focus Groups with

colleagues, stakeholder interviews, substance misuse services managers meetings

and service user Focus Groups.

iv) Review of key policies and guidance notes.

Findings from all these sources were then used to develop recommendations for

each of the themed areas. These recommendations aimed to inform the way

forward.

4 Review of service uptake data

Data was gathered via Services monitoring reports and the Drug and Alcohol Waiting

Times Database. This included:

• Number of referrals

• Numbers offered assessment but never attend

Page 7: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

7

• Did not attend (DNA) rates for assessment appointments

• Numbers commencing treatment (following completion of assessment)

• Retention over 12 weeks

• Rates of planned and unplanned discharge

The QuEST team amended the DCAQ Tool to change the wording from ‘patient’ to

‘client’ to reflect its use in health and social care settings.

5 Using the DCAQ Tool

In Appendix 1 the data sheet for the Mental Health DCAQ Tool developed by the

Scottish Government’s Quality and Efficiency Support Team (QuEST) is displayed

for measurement of capacity, demand, activity and any queue. This was amended

for the purposes of work with Borders ADP, where not only NHS but local authority

and third sector social care support would be involved.

At a Service Managers’ meeting all services were asked if they would be willing to

complete the questionnaire. There was agreement in principle for this and a further

two hour meeting was arranged.

At this meeting in February 2013, the National ADP Delivery Advisor met with ADP

staff and Borders ADP services (five organisations, eight services). There had been

several previous meetings with ADP staff in the lead up period.

The purpose of this meeting was to achieve the following points:

1. Explain the thinking behind the tool as an improvement model,

2. Explain and agree consistent definitions,

3. Explain any questions and

4. Gain agreement to proceed,

5. Agree which 12 week period to use for capturing data retrospectively, and

6. Agree a timescale for reporting back.

Page 8: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

8

5.1 Areas for agreement

There were various areas for agreements raised by service managers at the

meeting. The following section is a summary of the key points:

5.2 Timing

Two of the services had recently experienced staffing vacancies which had severely

impacted on their capacity to deliver. There was concern from those services that

collection of data in the most recent quarter would not reflect ‘normal’ service activity.

Services were also concerned about the agreed timescales for feedback on the

Tools (1.4.13).

5.3 Data collection

DNA’s: Not all services routinely collected data on DNA’s and there was concern

about how they would achieve this. The ADP Development Officer agreed to use the

Drug and Alcohol Treatment Waiting Times (DATWT) Database to elicit DNA rates

for assessment appointment on behalf of the adult services. Following discussion,

agreement was reached on how to gather information on follow-up appointment DNA

rates.

Mileage: Not all services felt confident they could readily access mileage information.

However, on exploring this all agencies identified methods for gathering this data, for

example through staff expenses claim forms.

Allocation meetings: there was not agreement about what should be defined as an

‘allocation meeting’ as some services incorporated some elements of allocation

meetings into team business meetings. Therefore further discussion was required to

keep consistent definitions.

Clarity had to be agreed for services or staff which were, for example, multi-

component and where staff may be deployed in different ways e.g. proportion of time

for clinical versus time for development or management work. It was therefore

agreed that in some circumstances services or staff could be ‘split’ into parts. A

single Tool could be completed for each part of the service. Staff with dual roles,

such as team leaders with half a full caseload should be treated as 0.5 Whole Time

Equivalent (WTE) in respect of the Tool based on their pro-rata direct client contact.

Page 9: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

9

5.4 Other areas of clarification

There was scepticism from one service in particular about the value of using the

Tool. However, all services agreed to participate in the DCAQ work and did manage

to collect the required data from their existing service information and the DATWTs

Database.

All six expectations were met and all organisations were represented by their

manager or in one case with a manager representative. All services were content to

proceed and agreed the reporting quarter Dec 2012 – Feb 2013 for retrospectively

gathering data. Managers felt they could achieve this within a month’s time period.

Meanwhile, to gain deeper insight in reasons for DNAs, further information was

sought by the ADP Development Officer. This involved undertaking a short study on

barriers to accessing alcohol and drugs services. This involved distributing paper

questionnaires to Service Users (SUs) and also to staff. SUs were also offered the

opportunity to receive a follow-up phone call. Five SUs took this offer up.

5.5 Data Management

Once data was collated it was sent to the ADP co-ordinator, and forwarded to the SG

National ADP Delivery Advisor. Another month was spent cleaning data to keep

consistent and agreed definitions.

The SG Advisor met with the QuEST staff to ensure accurate data analysis and with

ADP staff to go through data and clarify understanding and potential improvements.

SG Advisor and ADP staff then met individually with service managers to confirm

data accuracy and jointly develop service improvement goals.

The following section will focus on one service to illustrate use of the DCAQ tool.

Page 10: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

10

6 Case Study

6.1 Data Gathering

The data from services was inputted to the DCAQ tool, one for each service. For one

service, Service X, this is outlined in Figure 1 which shows a display of demand,

queue, capacity, activity in the service, and these overlap to show the overall

balance between capacity and demand in Service X.

6.2 Demand

In the agreed 12 week reporting period there were 108 referrals, of which 1 was

referred elsewhere due to an inappropriate referral, 26 individuals waiting for

treatment and care at the end of the reporting period and no service users opted-out

during this period. However, it was noted that a number of these clients had been

seen for an assessment appointment but the assessment had not been completed.

Therefore, they were not strictly on a waiting list.

6.3 Capacity

As part of service capacity, information on DNAs, group and individual work, and the

number and length of appointments is displayed.

DNAs

DNA information was collected and showed that in the reporting period the DNA rate

was 20% for assessment appointments and 30% for follow-up or treatment

appointments. Services agreed prior to data gathering that the first assessment

appointment would constitute the assessment and any subsequent appointments

would be treated as follow-up.

DNA rate for assessment is measured by: the number of first assessment slots

missed divided by number of assessment slots offered, multiplied by one hundred.

DNA rate for follow-up is measured by: the number of follow-up slots missed divided

by number of follow-up slots offered, multiplied by one hundred.

Page 11: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

Individual and Group Work Appointments

In terms of the kind of appointment, individual appointments were received by 75%

of SUs, group work sessions were received by 10% of SUs and both group work and

individual appointments were received by 15% of SUs.

In each group work session or series there was on average 5 group work meetings,

attended on average by 7 service users and facilitated by 1 staff member.

Length of Appointment

On average first assessment appointments lasted 1 hour and took 1 hour of

administrative time for updating files. Similarly follow-up or treatment and care

appointments lasted 1 hour but required 20 minutes administrative time. For each

SU there are on average 8 follow-up or treatment and care appointments in any

given 12 week period.

Group work meetings lasted on average 1 hour and required 30 minutes of

administrative time for updating files.

Staffing

There were four WTE staff in this service each working a 37.5 hour week.

Time Allocation for Staff

This section shows how much time each staff member spends, on average, for

example on annual leave (per year), on sickness leave (per year), in supervision

meetings (per month), travelling (per week), at meetings regarding direct SU

engagement or other meetings (per week), and in SU/patient allocation meetings to

assign new clients to a staff member. Allocation meetings would also include the

number of staff attending these.

Allocation meetings were a key area for improvement in mental health services

where these meetings took up significant time. In this latter context capacity was

freed up by the mental health managers taking on this function and allocating new

service users directly to relevant staff members, without the requirement of a

meeting.

Page 12: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

12

In Service X the full staff team (4.0 WTE) attended two 1.5 hour allocation meetings.

Staff in Service X spend on average 3 hours per week travelling to appointments in

this rural area.

In general, services in Borders had quite a few hours spent on ‘other meetings’ due

to a smaller staff pool and still tasked with strategic and operational cross sectoral

work between substance use and related areas such as homelessness, mental

health, offending, etc. However this service, in the 12 week period, did not have any

hours spent under this heading.

Scenario

A further column has been displayed by the DCAQ tool which is optional, but for

discussion purposes a hypothetical improvement goal was set for DNAs to improve

both assessments and follow-up or treatment and care appointment DNAs, to reduce

to 15% for assessments and 20% for follow-up appointments. A further improvement

goal was set by hypothetically seeking to reduce the number of allocation meetings

from two to one (1.5 hour) meeting per week.

Inserting these scenarios creates a modelling effect to project the impact on waiting

times (queues), staff time freed-up, etc.

More information on this will be provided in Section 5 - DCAQ Projecting

Hypothetical Impact.

Page 13: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

13

Figure 1 – DCAQ Data 1.1 Time Period for Demand Data

Enter number of weeks you wish to calculate Demand and for (recommended minimum of 12 weeks) 12

1.2 Referral Information - Please enter the data for the time period specified above

ACTUALNumber

Enter number of referrals received in time period 108

Enter number of opt-outs in time period

Enter number of people referred elsewhere as inappropriate for your service in time period 1

Enter number of individuals still on waiting list for assessment at end of snapshot time period 26

Select

Does your service run a separate waiting list for treatment? No

If yes, enter number of individuals on waiting list for treatment at end of snapshot time period

1.3 Did Not Attend (DNA)

Number

DNA rate for 1st assessment slots

calculate as (no. of 1st assessment slots missed/ no. 1st assessment slots offered)*10020.0%

DNA rate for individual follow-up slots

calculate as (no. of follow-up slots missed/ no. of follow up slots planned)*10030.0%

1.4 Group Work

Select

Does your service do group work? Yes

If you selected No, please go to section 1.5

If you selected Yes, please fill in the following:

Number

Percentage of people who only go into individual work 75%

Percentage of people who only go into group work 10%

Percentage of people who receive both group and individual work 15%

Percentages should total 100%, if not, please check your figures ----------- check total: 100%

Average number of sessions per group intervention 5

Average number of people per group session 7

Average number of staff per group session 1

1.5 Slot length, Clinical/Client Admin, and Follow-up

Slot length & Associated Clinical AdminHours

Average clinical/client contact time taken per first assessment 1.00

Average clinical/client admin time taken per first assessment 1.00

Average clinical/client contact time taken per follow-up 1.00

Average clinical/client admin time taken per follow-up 0.20

Average clinical/client contact time taken per staff member per group session 1.00

Average clinical/client admin time taken per staff member per group session 0.30

Follow-Up

Number

Average number of follow-up visits per client 8

Sections 1.3 - 1.5 require you to enter a number of variables in order to calculate the time

needed to respond to the information you have entered above. Use data that best reflects what

usually happens in your service. For guidance and suggestions on how to calculate a

representative value for each variable, contact QuEST via the details provided on the Introduction

worksheet.

Page 14: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

14

Figure 1 – DCAQ Data (continued)

CAPACITY1.6 Staff Allocation - Per Week

Staff Group <please specify below> Staff WTE

Hours per

WTE Staff WTE

Hours per

WTE

Staff Group 1

Staff Group 2 4 37.5 4 37.5

Staff Group 3

Staff Group 4

Staff Group 5

Staff Group 6

Staff Group 7

Staff Group 8

Staff Group 9

Staff Group 10

1.7 Time Allocation per Person

ACTUAL SCENARIO

Days Days

Annual Leave (average days per person, per year) 36 36

Training (average days per person per year) 6.0 6.0

Percentage Percentage

Special Leave (average over minimum of 12 weeks) 0.00% 0.00%

Sickness Absence (average over minimum of 12 weeks) 3.00% 3.00%

Hours Hours

Supervision (average hours per person, per month) 1.5 1.5

Hours Hours

Time spent travelling (average hours per person, per week) 3.0 3.0

Meetings (average hours per person per week at all meetings, e.g. allocation, team business meetings etc) 2.5 2.5

Other e.g. projects (per person per week)

Hours Hours

Average length of allocation meeting 1.5 1.5

(please note this should also be included in total time spent in meetings)

Number Number

Average number of allocation meetings per week 2 1

Number Number

Average number of team in attendance at allocation meetings 4 4

ACTUAL SCENARIO

Page 15: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

15

6.4 Analysis

This section explains the findings in the Summary Data (see Figure 2) in terms of

actual hours and equivalent percentage of time spent on various activities, including

time lost to DNA appointments. The following sections take each area of capacity

and demand analysis in turn:

Time Spent by Activity

In Service X time spent directly with the client or patient constitutes 19.8 hours per

week or 53 % of frontline staff’s week spent directly with SUs.

The average level of sickness in Service X during the 12 week reporting period was

3%, which is lower than the NHS Scotland average level of sickness of 4%.

Time spent travelling was 7% of the working week, i.e. 2.5 hours per week for each

frontline staff member.

Annual and special leave amounted to 14% of the working week, i.e. 5.2 hours per

week per staff member.

Demand

The average weekly demand by clients for treatment and care is 2.7 WTE staff per

week including administrative time, or 2.1 WTE staff per week not including

administrative time.

DNAs

The total time lost to DNAs for first assessment appointments only in the 12 week

reporting period was 32 hours or 2.7 hours per week. Time lost to DNAs for follow-up

treatment and care appointment over the 12 week period was 203 hours or 16.9

hours per week. In total 19.6 hours per week was being lost in Service X due to

missed appointments, amounting to almost 3 days within a service of four frontline

staff (this is unlikely to include DNAs for group work).

Page 16: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

16

Capacity

The capacity of the service available for direct client work is 79.1 hours per week or

2.1 WTE staff. If we were to include administrative time, this would mean there is

capacity for 102 hours per week and 2.7 WTE staff.

Total number of staff hours spent at allocation meetings is 12 hours per week or 0.3

WTE staff.

Balancing Capacity and Demand

To balance capacity with demand and change nothing else, there is a small excess

of 3 hours per week or 0.1 WTE staff in this service - assuming all data is correct.

The figures in demand and capacity paragraphs above are equal, however the

DCAQ Tool calculations involve some rounding of figures and greater detail here in

looking at the balance between each theme.

Queue

During the 12 week reporting period there had been a high waiting time in the

Borders area and through additional staff in another part of the system the queue

was cleared and the problem rectified for the future through additional prescribing

capacity (posts were filled and there was additional nurse prescribing). However

addressing this system blockage created additional referrals seen in Service X with

26 service users waiting to be assessed.

To clear the queue of 26 people, based on the calculations of the QuEST DCAQ tool

there would need to be 237 hours or 32 days of staff time focused on this piece of

work. Bearing in mind each assessment takes 2 hours, including administrative time,

plus travel, etc. and 53% of available ‘time for direct client contact’ (from Time By

Category in Figure 2, line 2).

However the DCAQ Tool is not about giving additional resources to problem solve,

instead the approach is about finding solutions i.e. new procedures and approaches

to fix problems in the system. Once these changes have been made, additional

resources can be added to address any remaining queue. In Borders ADP the

additional prescribing capacity fixed the issues creating a queue, using existing

Page 17: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

17

budgets, and additional funds were given to NHS and local authority to clear the

waiting list speedily. The knock on effect which was not resourced is seen here in

Service X where a secondary queue developed.

System Balance

To create system balance within the service the DCAQ tool has projected that the

service should optimally receive 9 new service users each week, provide 67 follow-

up appointments per week across the service (by the 4 staff), or 7.5 follow-up

appointments for each new SU received per week. This would prevent a waiting list

developing and enable staff to meet the service user demand with the designed

assessment and follow-up programme of support.

Page 18: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

18

Figure 2 – DCAQ – Summary Data Analysis

Hours per Week % of hours per w eek

Average WTE hours per staff member 37.5 100%

Time left for Direct Client Contact 19.8 53%

Time left for Clinical/Client Admin (applying ratio from data input) 5.8 16%

Sickness Absence 1.1 3%

Time spent travelling 2.5 7%

Training 0.7 2%

Meetings (average hours per person per week at all meetings,

e.g. allocation, team business meetings etc) 2.1 6%

Supervision (average hours per person, per week) 0.3 1%

Other e.g. projects (per person per week) 0.0 0%

Annual & Special Leave 5.2 14%

Hours per week Hours per week

Your average weekly demand: Incl Clin Admin Excl Clin Admin

Your average weekly demand for first assessments: 18 9

Your average weekly demand for follow ups: 80 67

Your average weekly demand for group work: 2 2

Your average weekly demand for all client work (hours) 100 77

Your average weekly demand for all client work as WTE 2.7 2.1

TIME LOST TO DNA Total Hours Average Hrs per week

Time allocated for first assessments not used due to DNA 32 2.7

Time allocated to follow-ups not used due to DNA 203 16.9

Your average capacity per week: Hours per week WTE

Capacity available for direct client work 79.1 2.1

Capacity available for direct client work and clinical/client admin 102 2.7

Capacity spent on all other activities 34 0.9

Total no. of staff hours per week spent at allocation meeting: 12.0 0.3

Hours per week WTE

Difference between time needed and time available for direct

client work (including clinical/client admin): -2

If you change nothing else - additional hours and WTE needed

to match demand with capacity: -3 -0.1

ACTUAL SUMMARY

ACTUAL

CAPACITY

ACTUAL

DEMAND vs CAPACITY

TIME BY CATEGORY

ACTUAL

DEMANDACTUAL

ACTUAL

Page 19: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

19

Figure 2 – DCAQ – Summary Data Analysis (continued)

QUEUE

ACTUAL -

Assessment

Queue

Number of people on the waiting list 26

Total hours needed to clear queue 237

Days needed to clear queue (based on 7.5 hour day) 32

ACTUAL

Number

No of New Slots per week 9

No of F/Up Slots per week 67

Number of F/Ups for each new per week* 7.5

SYSTEM BALANCE

Page 20: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

20

7 DCAQ Projecting Hypothetical Impact

The DCAQ tool has the ability to forecast the impact of different scenarios in a

service, for example to assess the impact of increased staffing to reduce an urgent

waiting times issue, or the impact of increased group work and reduced individual

work on capacity and demand.

To project a scenario in a service, there should be a high degree of confidence in the

information entered on the data sheet in the first instance. Additionally users of the

DCAQ tool should be cautious that realistic and achievable scenarios are being set

for or by a service. Support can be provided from QuEST at Scottish Government

and potentially from National ADP Delivery Team with experience of using this tool.

Figure 3 shows the capacity available to address current demand for the service if

the service was able to make three improvements:

1. Reduce DNAs from 20% - 15% at Assessment appointments;

2. Reduce DNAs from 30% to 20% at Follow-up appointments, and;

3. Reducing the number of Allocation meetings from two to one meeting per

week.

Practically, these improvements mean exploring DNAs in the service, understanding

SUs opinions and satisfaction levels about appointment times, venues, notice

periods, methods for arranging appointments, travel requirements, travel

reimbursement, and for the assessment or intervention received. Some of this was

explored in the DNA analysis delivered by the ADP Support Team. Additionally, to

reduce the number of Allocation Meetings it would need to be possible for all (most)

staff to meet at one point in the week.

The learning gained from a DNA analysis would then need to be applied in the

service to make the necessary improvements, which should result in reduced DNAs.

Furthermore it may be possible to stop having Allocation Meetings altogether if this

takes too much time and if it is possible for the manager/team leader to allocate and

then communicate directly with individual staff about new SUs on their caseload. In

Page 21: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

21

the mental health setting for which this tool was originally developed, reducing

allocation meetings was a key area of improvement. However this was not felt to be

a beneficial option for staff in Service X due to the outreach nature of the service and

the need for staff to meet more often as a team, rather than for allocations per se.

Figure 3 – Demand vs. Capacity (Actual vs. Scenario)

0 20 40 60 80 100 120

Actual

Scenario

Hours

Demand vs Capcity (average per week)

Capacity - average hours per week available for all client work

Demand - average hours per week for all client work

Overall these three improvements would create significant increased capacity in the

service overall. This is due to less staff hours per week lost to DNAs and Allocation

meetings, as shown in Figure 4. Here the demand has reduced from the current

situation compared with the improvement scenario, due to fewer appointments being

required, since more SUs would keep their appointments. Staff capacity (available

hours) would increase in the improved scenario because staff would now have extra

hours available due to less wasted time from missed appointments.

This can be broken down in terms of Time Lost to DNAs, comparing an average of

16.9 hours lost per week currently (in excess of two days of staff time), with the

improved scenario losing an average of 9.0 hours per week (in excess of one day of

staff time).

Page 22: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

22

In the current situation capacity and demand are almost balanced, with just 0.1 WTE

extra capacity (see Figure 5), but we know there are 20-30% DNAs for

appointments. In reducing DNAs, we see that staff time is now freed up with almost

one full time post (0.9 WTE) available per week or 34 addition hours per week.

The purpose of the DCAQ tool is not about financial savings or ‘harder working’ but

about moving resources and improving practice so that staff time is freed up. This

gives service users and patients increased contact with staff, and would improve the

likelihood of greater service user outcome improvements.

Figure 4 - Time Lost by the Service Due to DNAs (Actual vs. Scenario)

TIME LOST TO DNA Total Hours Average Hrs per week Total Hours Average Hrs per week

Time allocated for first assessments not used due to DNA 32 2.7 24 2.0

Time allocated to follow-ups not used due to DNA 203 16.9 108 9.0

ACTUAL SCENARIO

Figure 5 - Overall Balance between Capacity and Demand (Actual vs. Scenario)

Hours per week WTE Hours per week WTE

Difference between time needed and time available for direct

client work (including clinical/client admin): -2 -23

If you change nothing else - additional hours and WTE needed

to match demand with capacity: -3 -0.1 -34 -0.9

SCENARIOACTUAL

DEMAND vs CAPACITY

As a continuous improvement model we would want to improve the scenario figure

once reached, but at the same time take account of the human dimension i.e. that

this is a hard-to-reach client group and we would always expect some level of DNAs.

Page 23: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

23

8 Setting Improvement Goals

The findings from the data showed that there appeared to be some capacity

available within the system, there was also a lack of consistency in appointment

lengths in similar services. It is also the case that A11 means waiting lists are

addressed in treatment services but this may not be so closely managed in other

services, with no HEAT Waiting Times compliance.

Following submission and analysis of the DCAQ, data managers from all services

were invited to attend an individual meeting with the ADP Co-ordinator and National

Advisor. This meeting was used to review the data sheets and to develop areas for

improvement. These areas for improvement were then communicated by letter with

timescales to services.

Examples of areas for improvement were:

• Confirm data accuracy

• Consider referral and engagement/DNA rates by source of referral

• Safe disengagement from one service was explored due to caseload and

funding pressures

• Agreement to explore alternative health centres sites closer to service users

• Deliver some group based work with this more stable service user group

which has as not yet been explored

• Calculate waiting times for service outwith the HEAT standard

• Consider referral and engagement/DNA rates by source of referral

• Review the process of arranging first appointment

• Patient information to be sent out with appointment letter

• Review DNA rates for assessment on a quarterly basis

• Work with referrers to raise awareness of the service and its referral criteria.

• Explore early discharge from service

• Explore alternative Service User feedback methods that support anonymity

There were some challenges to the implementation of the Improvement Letters.

While the Tool identified some areas for potential improvement and allowed some

level of estimation of capacity within the system the timing of its use before a

procurement process means that some of the learning will be built into future

Page 24: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

24

services rather than existing ones. On reflection, the Tool would be of most benefit if

used within services where there is an ongoing length to the contract.

Two of the services recently had new managers/team leaders appointed so the

services were already experiencing a process of change.

Despite the above contextual issues, progress on the improvements is reported via

the regular monitoring meetings with services.

9 Learning Points

There have been several learning points relating to use of the DCAQ Tool:

i) Size of project

One service was very small with some part-time hours allocated within a bigger

project. The DCAQ Tool was therefore not very helpful for this service as it could not

reflect where people might receive an element of support work elsewhere within the

service. The DCAQ Tool is not designed to analyse services with very small

caseloads since the findings may be unreliable.

ii) Multi-faceted roles

The Tool does not easily allow for roles which are multi-faceted where a role will be

planned to have client facing/clinical as well as development time. For example, a

Support Worker may have direct client time but may also be leading a project or

have significant time dedicated to training or capacity building. It may be that such

roles are more common in small Board areas like Borders as individual staff may

cover a variety of responsibilities. It is possible to resolve this problem relating to

development time by apportioning this separately and only using the QuEST Tool for

the remaining hours of a post.

iii) Use of available data

One service in particular was very experienced in this way of working and the data

was readily available. For others, although some data is available, it was not used

until applying the Tool locally. For example, the DATWT database contains data

Page 25: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

25

relating to DNA rates but services (and the ADP Support Team) has not accessed

this data until 2013.

None of the service contracts at time of writing had performance indicators relating to

DNA rates. It appeared to be the case that for this reason some services felt it was

not important to collect DNA data. One service queried the ‘status’ of the data

collected by QuEST as, since it was not in the contract, how could services be held

accountable for it. However, this was still information which had been made

available to the ADP therefore it was not possible to ignore it and, given that such

information is useful, it would be helpful to use it.

iv) Balancing process and outcome measure

It is challenging to correlate activity with quality and also how to compare process

measures with outcomes measures. Within the ADP and Scottish Government it is

recognised that there is a need for a balance between reporting both on activity,

outcomes and indeed exploring the quality of interventions and SU satisfaction levels

with service provision.

10 Impact of QuEST

At the stage of writing Borders ADP is undertaking a procurement exercise for all

commissioned services. The Tool does appear to have utility for setting

improvement goals in existing services.

It has however informed local thinking and for new services which are currently being

procured monitoring and evaluation requirements will include DNA rates for all new

services, rates of planned/unplanned discharges and 12 week retention rates for

services delivering treatments. The ADP was unable to benchmark performance on

DNA and planned/unplanned discharge, however, a request to ISD has supplied

data to Borders ADP enabling benchmarking against Scotland average. At a recent

Scottish Government Drug and Alcohol Data Action Group a request was made by

the National Delivery Advisor on behalf of Borders ADP to all ADP’s to allow sharing

of this data. As a result information is expected imminently to enable benchmarking

against similar ADPs for DNAs and (un)planned discharges.

Page 26: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

26

All new Service Specifications now have a clause which says that targets may be set

and reviewed based on capacity and demand. The ADP envisages this will allow an

open two way process to look at what is a reasonable expectation of a service to

ensure quality.

A method for assessing demand and capacity has not been confirmed within the

Service Specifications.

11 Conclusion

For Borders ADP and for substance misuse services the use of the Tool was

challenging. It was done at a time of considerable uncertainty for the future and

although Service Managers were supportive of the Investment Review process it

was an unanticipated task.

The Tool has been useful. Borders ADP and substance misuse services are now

more aware of some of their demand and capacity issues. It has led onto other work

regarding barriers to access and helped improve our understanding of our alcohol

and drugs system.

Going forward the learning will continue to be of great use. As highlighted earlier, we

are building in DCAQ data into future monitoring alongside outcomes reporting.

Borders ADP believes this will allow us to more accurately support service

improvement and evaluate our investment profile.

We are very interested to explore further the benchmarking data which ISD is

developing and this will allow us to monitor our local performance.

Page 27: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

27

References

Doig, F., Walker, S. (2013) ADP Investment Review – Findings and Recommendations: Report from ADP Executive Group; Doig, F. (2013) Borders Alcohol & Drugs Partnership (ADP): Future Model of Investment.

Page 28: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

28

Appendix 1 – Mental Health DCAQ Tool

QuEST Mental Health: DCAQ Tool

[Enter Team & Date here]

DEMAND1.1 Time Period for Demand Data

Enter number of weeks you wish to calculate Demand and for (recommended minimum of 12 weeks)

1.2 Referral Information - Please enter the data for the time period specified above

ACTUAL SCENARIONumber Number

Enter number of referrals received in time period

Enter number of opt-outs in time period

Enter number of people referred elsewhere as inappropriate for your service in time period

Enter number of individuals still on waiting list for assessment at end of snapshot time period

Select Select

Does your service run a separate waiting list for treatment?

If yes, enter number of individuals on waiting list for treatment at end of snapshot time period

1.3 Did Not Attend (DNA)

Number Number

DNA rate for 1st assessment slots

calculate as (no. of 1st assessment slots missed/ no. 1st assessment slots offered)*100

DNA rate for individual follow-up slots

calculate as (no. of follow-up slots missed/ no. of follow up slots planned)*100

1.4 Group Work

Select Select

Does your service do group work?

If you selected No, please go to section 1.5

If you selected Yes, please fill in the following:

Number Number

Percentage of people who only go into individual work

Percentage of people who only go into group work

Percentage of people who receive both group and individual work

Percentages should total 100%, if not, please check your figures ----------- check total: 0% 0%

Average number of sessions per group intervention

Average number of people per group session

Average number of staff per group session

1.5 Slot length, Clinical/Client Admin, and Follow-up

Slot length & Associated Clinical AdminMinutes Minutes

Average clinical/client contact time taken per first assessment

Average clinical/client admin time taken per first assessment

Average clinical/client contact time taken per follow-up

Average clinical/client admin time taken per follow-up

Average clinical/client contact time taken per staff member per group session

Average clinical/client admin time taken per staff member per group session

Follow-Up

Number Number

Average number of follow-up visits per client

Sections 1.3 - 1.5 require you to enter a number of variables in order to calculate the time

needed to respond to the information you have entered above. Use data that best reflects what

usually happens in your service. For guidance and suggestions on how to calculate a

representative value for each variable, contact QuEST via the details provided on the Introduction

worksheet.

Fill scenario cells with actual data

Hide Scenario Cells

Unhide Scenario Empty scenario

Page 29: Demand, Capacity, Activity and Queue (DCAQ): A Case … adp dcaq final - … · Demand, Capacity, Activity and Queue (DCAQ): A Case Study in Borders Alcohol & Drug Partnership (ADP)

29

Appendix 1 – Mental Health DCAQ Tool

CAPACITY1.6 Staff Allocation - Per Week

Staff Group <please specify below> Staff WTE

Hours

per WTE Staff WTE

Hours per

WTE

Staff Group 1 37.5 37.5

Staff Group 2 37.5 37.5

Staff Group 3 37.5 37.5

Staff Group 4 37.5 37.5

Staff Group 5 37.5 37.5

Staff Group 6 37.5 37.5

Staff Group 7 37.5 37.5

Staff Group 8 37.5 37.5

Staff Group 9 37.5 37.5

Staff Group 10 37.5 37.5

1.7 Time Allocation per Person

ACTUAL SCENARIO

Days Days

Annual Leave (average days per person, per year)

Training (average days per person per year)

Percentage Percentage

Special Leave (average over minimum of 12 weeks)

Sickness Absence (average over minimum of 12 weeks)

Hours Hours

Supervision (average hours per person, per month)

Time spent travelling (average hours per person, per week)

Meetings (average hours per person per week at all meetings, e.g. allocation, team business meetings etc)

Other e.g. projects (per person per week)

Hours Hours

Average length of allocation meeting

(please note this should also be included in total time spent in meetings)

Number Number

Average number of allocation meetings per week

Number Number

Average number of team in attendance at allocation meetings

ACTUAL SCENARIO