baragoola 7 may 2011 baragoola... · the blog site has closed and now redirects to our “works”...
TRANSCRIPT
Baragoola 7th May 2011
In attendance: Nick, Peter C, Geoff E, Glen, Ernie, Gary, Mark T & Mark R Visitors: None This week we gathered donations of $110 and managed outlays of $0. So keep those (tax deductible
donations) coming in!
The blog site has closed and now redirects to our “Works” page – no more messiness! The blog was
simply the “guts” picked out of these newsletters with a few pictures and tended to be a month behind
anyway so this is better in the long run.
The first of the renewal forms have now gone out – you’ll be getting yours this week or next week, so
keep an eye out for them.
Unfortunately I couldn’t attend this weekend, so the information is “second hand” – thanks to Glen for
the pics and to Gary for some of the information provided.
I’m told Saturday started very cold but improved somewhat – maybe not too much as the guys are all
wearing sloppy joes! Not a bad turn-out for an off weekend either – thanks to all those who attended.
On to the work – Gary installed a small piece of electrical equipment that we purchased a few weeks
ago; small but very, very important. High on our wish list for some time has been an isolation
transformer for the shore power supply.
Simply, an isolation transformer does not have a direct electrical path from the power input side (shore)
to the power output side (Baragoola). This has several advantages and for the Baragoola the benefits
include increased safety for the volunteers whilst working on board and also minimising the potential
for stray galvanic currents causing hull corrosion and degradation of the protective anodes.
Some months ago quotes to source an isolation transformer were gathered but at over $1000 it was
determined in the order of importance that the transformer would have to wait. We were fortunate and
lucky to source an unused unit to our exact specification for approximately $350. The amount to
purchase this unit was generously donated by a member.
This weekend the unit was installed and proper reconfiguration of our power distribution system (to
MEN downstream of the isolation transformer with earth/hull bonding) means that all sub-circuits on
the Baragoola are now fitted with and protected by RCD's. Correct function with an RCD tester was
confirmed. As it also happened, a faulty fluorescent lamp unit was later plugged in and tripped the
corresponding RCD. This fluorescent unit may have proven either dangerous or a nuisance; previously a
faulty unit may have tripped the main shore protection, disabling supply to the Baragoola and also the
Cape Don, with a complicated reset procedure. Now it just tripped our sub-circuit.
The isolation transformer installed in its new home
It’s actually quite small – about the size of a case of wine but bloody heavy at 60kg – the weekend
before when it was bought onboard entailed the efforts of four men to bring it up.
All worth it in the long run however.
Also 'down-graded', rather than upgraded, this weekend was the main isolation switch at the shore inlet
fitting. Another previous inconvenience was the nuisance overload tripping of the breaker at our point-
of-supply aboard the Cape Don. Though manageable but annoying to the Cape Don volunteers when
they were present, it was always a possibility that if we 'tripped out' whilst the Cape Don was
unattended, we may have remained without supply. The scenario has been mitigated by downgrading
our main isolator breaker with a 16A unit so that peak loading will now trip on the Baragoola and not
elsewhere.
We had numerous 'tests' performed today that strangely coincided with cups of tea - with all below-
decks lighting on for a work day, each time the electric jug was turned on it would eventually trip the
main isolation breaker. Which is the desirable outcome, it is able to be reset by us. Gary had made a test
ammeter to measure our loads and this corroborated the tripping. Whilst we remain on the current
supply, we will always be limited to what we can operate at once. At least now we have the ability to
rapidly recover from these situations.
There is also on the agenda a change of the shore and auxiliary supply connections; a consolidated
switching arrangement to allow selection of the shore power or, in the event of its failure, the auxiliary
generator. It will also allow the auxiliary generator to be switched between supplying either the
Baragoola directly and accessories such as the hot water heater, welder or compressor - all without the
need to disconnect/reconnect any supply cables.
Glen set to complete the painting in the Ladies Salon; this area now has all its second coat of colour and
a trim applied and is finally looking like it used to forty odd years ago. The deck head remains to be done
in white – this will occur after repairs are effected to it upon which lighting will be installed as in the
main cabin.
Detail of Ladies Salon, starboard entrance showing colour scheme
The varnish on the windows remains to be done and brass handles re-installed on some of the windows.
As well, some work needs doing on some of the floor boards but overall a large amount of work has
been completed in here. Wiring is also temporary at this stage and will be done properly at a later date.
However, the changes are amazing compared to what it looked like a year ago – grubby and decrepit.
As it was in April last year
As it is now
Nick was at work in the shower – this was created from the removal of a toilet that once existed in this
area many years ago and the floor is uneven and didn’t drain properly. As a result the steel has been
damaged by rust along the bottom edges. A bag of cement was mixed up and applied to even the floor
out and allow water to drain properly once back in use. There may be a bit more to do but once
completed the damaged steel work will be repaired and the concrete floor painted up.
Original floor of the shower showing rust damage and wooden “plug” of old toilet pedestal
We haven’t done a huge amount of work up here beyond a little bit of remediation and some painting
but an effort will need to be made once we have our black water tank installed to re-plumb the out of
service toilets, trough and shower. So a bit of work for someone with plumbing skills!
Upstairs Mark R got stuck into oiling the loading ramps – some of these will require replacement wood
but as much as possible we’ll keep the original material, therefore we need to preserve these and the oil
will do that job for us. Mark also began the cream external painting in this area – we’ve “neglected” the
starboard side somewhat so this is good news as it means that people who look at our ferry from the
coal loader will have a much more pleasing view rather than old paintwork! This side has weathered less
well than the other side as it tends to not get as much sun to keep it dry. Conversely, the hull is in better
condition on this side as it doesn’t cop the waves.
Maybe we should turn her around!
Mark oiling the deck
What also hasn’t helped is that these ramps take a lot of the water run-off from the roof, at some stage
the original downpipes have been removed and replaced with ones in a different position. No doubt it
seemed like a good idea at the time but it has introduced problems. The PJ Company left nothing to
chance (and that’s evident throughout the boat) so in time we’ll have to reinstate the original drain
locations.
In the meantime much ongoing damage can be eliminated by careful preservation of the existing
material – we are replacing very, very little on the Baragoola and have been very fortunate thus far. You
may recall that NSW Heritage claimed that up to 65% of material on the boat would need to be
replaced, thus resulting in a “replica”. Fortunately this statement is patently and monstrously incorrect
and thus far nothing has had to be replaced – a fine testament to the skill of her builders and the quality
of the material used back in 1922.
Equally we have been fortunate in that much of the original paint colours are still there under layers of
latter paints which has aided us in having the tones faithfully reproduced – although it has to be said
that this one topic has produced much discussion and debate at times! Fortunately for us, Geoff E is a
stickler for the details and has been able to determine what needs to be used and more importantly,
exactly where it needs to be used as well.
As usual work was also done downstairs with Geoff plugging away at cleaning back the hull. He used this
weekend to also apply another coat of Rustmaster in the battery compartment – an area that he
vacated and was taken over by Ernie for use as his workshop. And Ernie looks completely at home down
there working on some piece of equipment or another.
This week Geoff had some assistance from Mark T with the cleaning up work, great to see others helping
out with this all-important work.
Geoff in the control room
The above picture also shows some of Baragoola’s steam heritage; immediately to the right of Geoff’s
head is a round patch – this is a blanking plate over the old space where an outlet pipe used to go. There
are many of these reminders in the under deck areas scattered throughout the ship and we are
fortunate that her conversion was done “on the cheap” as they give us much material that can be used
to interpret her various phases.
Other locations on the bulkheads also show where various pipes used to be that are no longer there and
of course the biggest reminder is in the engine room where the old coal bunkers are now the diesel
tanks.
Mark cleaning in the control room, note the partially disassembled air compressor beside him
Ernie continues to do amazing work and has done some absolutely meticulous restorations of
Baragoola’s electrical equipment, he very obviously enjoys his time on the boat and it’s wonderful to
have him there doing the work he does. Mostly he and the other engine crew disappear for the day and
only surface during lunch and cuppa breaks and this weekend was no different with he, Peter and Gary
working to solve the mysteries of the vintage switchboard – a job now made a little easier as I’ve
managed to get access to the ferry’s operations manuals and have started transcribing them for the
guys – in fact these came in useful this weekend as Peter was able to use the information in one of them
to solve a problem he’d noted with one of the generators.
You may recall that some attention has been given to the air compressor. We are planning on removing
the old tank as it’s suspect, but the motor and starting equipment will remain in place and be put back
into service – the tank is one of the rare items where we have decided to replace an existing item; it has
been left to the elements for over twenty years and represents a safety risk so it has to go.
The new tank will be slightly smaller and installed in the same place – this will have to go through the
access hatch in the deck above and the old tank will go out the same way – the logistics of doing this will
be rather interesting when the time comes but I have faith that our ever ingenious work crew will work
it out – they always do!
One of the things that Ernie has recently restored is the controller for the air compressor – here are the
shots.
Before….
…. and after
All in all a good day with much accomplished by the team.
Next working day is next Saturday, 21st of May which is an “on” weekend for us, so we’re looking for a
good turnout.
Contact Nick, myself or Glen for pickup on the day from our usual spots at Greenwich and Waverton..
If you’re coming don’t forget to bring lunch – we provide tea, coffee, cold drinks and fresh fruit to all
volunteers on board.
Don’t forget – all donations above two dollars are now tax deductible – see our website for details on
how to donate.
That’s it for this week – don’t forget you can keep up with all the latest on our forums at
http://www.savethebaragoola.com/forum/index.php and you can see our old newsletters at
http://www.savethebaragoola.com/works.html
Show your support!
We’re pleased to announce some additions to our range of collectable items.
All items can be ordered by sending an email to [email protected] with the following details:
Your name Postal address Size (for clothing) and quantity Your contact phone number All items will be sent with an invoice payable within 30 days.
White T-shirt, printed with Baragoola’s build year and our web address, available in white cotton only in
sizes S, M, L, XL & XXL. Price is $22 including delivery.
SS Baragoola – Baragoola as built in 1922, white coffee mug.
Price $25.80 including delivery – available now.
SS Binngarra (class vessel), white coffee mugs.
Price $25.80 including delivery – available now.
MV Baragoola – Baragoola near the end of her public life, white coffee mug.
Price $25.80 including delivery – available now – limited edition.
Coming soon will be a range of mugs featuring the current four Manly ferries. The price for these is the
same as the current stock and you can pre-order if you wish.
Specify which you want – Freshwater, Narrabeen, Queenscliff or Collaroy.
These should arrive between four to six weeks from now.
Designs will be the same as our current range.
And also coming soon – a new range of calendars similar to those released last year but for the financial
year 2011-2012.
These are printed on high quality thick glossy A4 card and will feature several views of the internal and
exterior of Baragoola. Only twenty were printed last time and they went quickly so it would be a good
idea to pre-order now to avoid disappointment!
Price will be $30 including postage.