BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

Brookland Middle School

Neighbor Group Meeting

July 16, 2014

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

AGENDA / GOALS

• Introductions / Rules

• Construction Updates

• Design Update

• Mascot

• Public Art Selection

• Local Business Utilization

• DCPS Update / Expanding the SIT

• Next Steps / Q&A

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

SITE PLAN

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

CONSTRUCTION UPDATES

• ONGOING & UPCOMING WORK

• Building Envelope

• Exterior Brick and Masonry

• Glass Installation

• Interior Drywall and Ceiling Grids

• Water and Sewer Connections at Shepherd Street

• Upcoming: Interior Finishes

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

CONSTRUCTION UPDATE

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

CONSTRUCTION UPDATES

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

CONSTRUCTION UPDATES

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CONSTRUCTION UPDATE

PARK USAGE

WORK ACTIVITY TIMEFRAME

Ongoing DPR modernization of Turkey Thicket park COMPLETE

Baseball field and track closed during geothermal well drilling and

field restoration

COMPLETE

Basketball courts closed during expansion of Turkey Thicket

parking lot and basketball court relocation (*pending permits)

October –

December 2014

Two (2) Tennis courts closest to school not in use during school

structure and façade work

Present –

October 2014

All eight (8) tennis courts closed during court re-surfacing October 2014

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

CONSTRUCTION UPDATE

CONSTRUCTION ACTIVITY

INTERIORS

May 2013 – January 2015

Tennis courts get resurfaced

in October 2014

Parking lot expanded and basketball

courts relocated during Oct & Nov 2014

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

DESIGN UPDATE - INTERIORS

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

DESIGN UPDATE - INTERIORS

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

DESIGN UPDATE - GYM

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

DESIGN UPDATE – PERFORMANCE HALL

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

DESIGN UPDATE – OUTDOOR CLASSROOM

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

DESIGN UPDATE – MASCOT SELECTION

• Presented Mascot options to 4th

, 5th

, 6th

grade

students at: Brookland Educational Campus,

Burroughs, Langdon, Noyes at lunchtime

meetings .

• Students voted to rank the options in order of

preference

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

PUBLIC ART

• 97 Entries from 52 artists. 21 selected as semi-finalists

• Semi finalists announced for each area

• Entry Plaza (Community) - 8 semi finalists

• Atrium – likely hanging (Diversity) – 4 semi-finalists

• Outdoor Classroom (Sustainability) – 6 semi finalists

• Michigan Ave (Brookland) – 4 semi finalists

• Main Lobby (Performing Arts) – 6 semi finalists

• Semi-finalists toured the school in early May and proposals have

been submitted.

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

PUBLIC ART - ATRIUM SEMI-FINALISTS (SAMPLES)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

PUBLIC ART – MICHIGAN AVE SEMI-FINALISTS (SAMPLES)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

PUBLIC ART – ENTRY PLAZA SEMI-FINALISTS (SAMPLES)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

PUBLIC ART – MAIN LOBBY SEMI-FINALISTS (SAMPLES)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

PUBLIC ART – OUTDOOR RM SEMI-FINALISTS (SAMPLES)

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

CBE AND WORKFORCE

• Local Business Participation (CBE)

• $22.4 out of $37.5M (60% ) of construction subcontracts have

been awarded to District CBE firms

• 16 CBE firms currently working on project

• 7 of those firms are located in Ward 5

• Local Workforce Utilization

• Approximately 40% of all workers to date DC residents

• 10 workers hired from jobsite walk-ups!!

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

DCPS UPDATE

• Academic Planning Team and Office of Teaching and

Learning ramping up educational planning.

• Outreach to students and families to begin Fall 2014.

• School Improvement Team (SIT) to be expanded to

include staff and parents from four feeder schools

• Brookland @ Bunker Hill EC

• Burroughs EC

• Langdon EC

• Noyes EC

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

BROOKLAND MIDDLE SCHOOL

NEXT STEPS

• The next “Community Meeting” will be held in September

with a focus on Academics. Place and time TBD.

• The “Envelope Group” will meet again in September.

• Jobsite tours for SIT, envelope group, and community.

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013

Questions & Answers

BROOKLAND COMMUNITY MEETING – MARCH 23, 2013