AGENDA
• Introductions
• Design Update
• Schedule & Work Hours Update
• Construction Update
• Affect on DPR Facilities
• Next Steps
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
BROOKLAND MIDDLE SCHOOL
SITE PLAN
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
DESIGN UPDATE
SCHOOL SITE
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
DESIGN UPDATE
EXTERIOR RENDERING
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
SCHEDULE & WORK HOURS
UPDATE
SCHEDULE
• Students and staff to occupy building 2015-16 school year
• Construction to complete in January 2015
WORK HOURS
• Work to take place during standard DCRA work hours
7AM-7PM Monday through Saturday
• No applications for extended work hours
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
CONSTRUCTION UPDATE
ACTIVITY SCHEDULE
COMPLETE
• Building demolition
• Ground improvements
ONGOING & UPCOMING
• Concrete foundations and
waterproofing
• Steel structure
• Geothermal Well Drilling (Requires closure of baseball
field and track from December 1, 2013 – April 15, 2014)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
CONSTRUCTION UPDATE
PARK USAGE
WORK ACTIVITY TIMEFRAME
Ongoing DPR modernization of Turkey Thicket park Present –
December 2013
Baseball field and track closed during geothermal well drilling and
field restoration
December 2013 –
April 2014
Basketball courts closed during expansion of Turkey Thicket
parking lot and basketball court relocation
April 2014 –
May 2014
Two (2) Tennis courts closest to school not in use during school
structure and façade work
Present –
October 2014
All eight (8) tennis courts closed during court re-surfacing October 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
STRUCTURE / SKIN
Present – December 2013
Two (2) Tennis courts closest to
school not in use during school
structure and façade work
(Present – October 2014)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
GEOTHERMAL & FACADE
December 2013 – April 2014
Two (2) Tennis courts closest to
school not in use during school
structure and façade work
(Present – October 2014)
Baseball field and track closed during
geothermal well drilling and field
restoration (Present – October 2014)
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
INTERIORS
May 2013 – January 2015
Tennis courts get resurfaced
in October 2014
Parking lot expanded and basketball
courts relocated during April & May 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013
NEXT STEPS
• Next SIT Meeting in December 2013
• Focus on interior finishes and design
• Resume “envelope” meetings
• Monthly updates to be e-mailed at end of each
month
• Community Meeting in February 2014
BROOKLAND COMMUNITY MEETING – MARCH 23, 2013