accr case studies presentation 1-22-13 (1)
TRANSCRIPT
3M™ Aluminum Conductor Composite Reinforced (ACCR)
More Amps,
More Confidence
for your most challenging
applications
3M ACCR
Case Studies
1/22/13
3M™ ACCR
2
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: Shanghai Electric Power Company Ltd
• Project: YangGao to XinZhou (Yangxing line)
• Location: Shanghai, China
• Year Installed: 2007
• Length: • Conductor length: 60 miles (96.6 km)
• Line length: 10 miles( 16.1 km);
• Voltage: 220 kV
Solution: 3M ACCR 795-T16 Drake (418 mm2)
Results:
• Doubled capacity to meet growing demand in the World
Expo area of Central Shanghai
• Eliminated need for new towers
• Provided fast, cost-effective option for delivering additional
energy in a time-sensitive project
• Installed in 18 days
“Based on the October 14 line energizing, 3M ACCR
works well. After passing a real project’s running test,
we believe 3M’s ACCR will have a brilliant future in field
application and will help us enhance the city
transmission network.” – Mr. Pan, Shanghai Power
Yanggao Project designer.
3M™ ACCR
3
Project Profile: Long-span Water Crossing
Project Overview:
• Customer: BC Hydro/BCTC
• Project: Vancouver Island Transmission Reinforcement
(VITR)
• Location: Vancouver Island
• Year Installed: 2008
• Length: • Conductor length: 13.6 miles (21.89 km)
• Line length: 2.2 miles (3.5 km)
• Voltage: 230 kV
Solution: 3M ACCR 788-T26 custom (400 mm2)
Results:
• Avoided major construction including extensive use of
helicopters, barges, and road construction by using
existing towers
• Upgraded with minimal disturbance to environmentally
sensitive waterway and provincial park
• Preserved the existing sightline
• Successfully installed conductor across 5,800 ft (1.5
km), single-span with no additional towers and no tower
in the waterway
3M™ ACCR
4
Project Overview:
• Customer: Xcel Energy
• Project: Black Dog to Blue Lake
• Location: Minneapolis, MN
• Year Installed: 2005
• Length: • Conductor length: 30 miles (48.3 km),
• Line length: 10 miles (16 km),
• Voltage: 115 kV line
Solution: 3M ACCR 795-T16 Drake (418 mm2)
Project Profile: Challenging Timeline
“ Without 3M ACCR we would have had to replace
existing towers to accommodate larger sized
conventional conductors. Use of the new conductor
allowed us to boost capacity on the line while avoiding
major construction in an area with sensitive wetlands”.
– Doug Jaeger, transmission vice president for Xcel
Energy
Results: • Boosted capacity by 80% on the line for peaking plant
upgrade coming on-line
• Used only existing towers,
• Avoided major construction in National Wildlife Refuge,
sensitive wetlands area
• Solved difficult installation challenges on site, and used single
pull across protected area
• Provided fast, cost-effective option for delivering energy by
saving months of permitting compared to ACSR/ACSS
3M™ ACCR
5
Project Profile: Challenging Timeline
Project Overview:
• Customer: Chongqing Electric Power Corporation
• Project: Shuinian to Shuangshan (Shuishuang line)
• Location: Chongqing, China
• Year Installed: 2008
• Length: • Conductor length: 24 miles (38.6 km)
• Line length: 4 miles (6.4 km)
• Voltage: 220 kV line
Solution: 3M ACCR 680-T19 Custom (346 mm2)
Results:
• More than doubled transmission capacity using only
existing towers
• Provided operational reliability in a sub-tropical region
with high humidity and extreme summer heat
• Completed in 2 weeks, just one month before the start
of the Olympics
“This is one of the hottest cities of China, with monsoonal
weather, and we required a conductor that could be
relied upon to carry more current under those conditions,
and could be installed quickly and reliably within the
existing infrastructure. Installation required only two
weeks.” – Wang Xinkuan, chief design engineer for
Chongqing Electric Power Corporation
3M™ ACCR
6
Project Profile: Densely Populated or Underbuilt Area
Project Overview:
• Customer: Arizona Public Service
• Project: Phoenix Metro Trunkline Upgrade
• Location: Phoenix, AZ
• Year Installed: 2006
• Length: • Conductor length: 16 miles (25.8 km)
• Line length: 5.5 miles (8.9 km)
• Voltage: 230 kV
Solution: 3M ACCR 1272-T13 Pheasant (642 mm2)
Results:
• Provided capacity to serve the fast-growing, congested area,
including airport, and downtown sports stadium
• Used existing medium-duty structures without any tower
modifications
• Avoided siting, acquiring rights-of-way, and environmental
permitting
• Minimized installation time (3 weeks)
• Minimized disruption to neighborhoods and facilities near the line
I don’t even want to think what the overload
would have been, or the impact of that, if we
were still using the old lines,” – Paul Richards,
construction projects manager for APS, in The
Arizona Republic, 9/25/06
3M™ ACCR
7
Project Profile: Densely Populated or Underbuilt Area
Project Overview: • Customer: Allegheny Power
• Project: Bedington Nipetown
• Location: West Virginia
• Year Installed: 2008
• Length: • Conductor length: 6 miles (9.7 km)
• Line length: 2 miles (3.2 km)
• Voltage: 138 kV line
Solution: 3M ACCR 1033-T13 Curlew (525 mm2)
Results:
• Increased transmission capacity using only existing
towers
• Sagged neatly with an adjacent 954 kcmil (490 mm²)
ACSR conductor on the same structure
• Minimized impact on under-built lines and allowed them
to remain in service during installation
“By using the 3M ACCR, the money and time saved was
invaluable on this fast-paced project. The design and
ordering process was a simple task because of 3M’s
sales and technical staff which demonstrates a service
culture of which 3M should be proud.” - Richard Hoch –
Engineer for Allegheny Power.
3M™ ACCR
8
Project Profile: Reliability
Project Overview:
• Customer: Silicon Valley Power
• Project: Center Loop Reconductor
• Location: Santa Clara, California
• Year Installed: 2008
• Length: • Conductor length: 23 miles, (37 km)
• Line length: 4 miles (6.4 km)
• Voltage: 60 kV
Solution: 3M ACCR 715-T13 Stilt (365 mm2)
Results:
• Provided a highly reliable solution to sensitive high-tech
customers
• Increased capacity using existing towers and maintained
existing right of way
• Matched existing sag and tension without adding additional
stress to existing towers
• Minimized disturbance to neighborhood and high-tech
industrial customers, including re-energizing the line at the
end of work each day for sensitive server farms and
electronic wafer manufacturers
“We needed a way to significantly increase
transmission capacity without the extra cost of
making major structural changes. 3M ACCR fit
our needs exactly and at quite a savings over
other alternatives.” - Kevin Keating, manager
of engineering for Silicon Valley Power
3M™ ACCR
9
Project Profile: Reliability
“The Timberline-Harmony line is an important
part of the grid between Denver and
Cheyenne, and we chose 3M ACCR as a way
to safeguard against overloading when
demand is high.” – Mike Dahl, Division
Manager Electric Operations, Platte River
Power Authority
Project Overview:
• Customer: Platte River Power Authority (PRPA)
• Project: Timberline-Harmony
• Location: Fort Collins, Colorado
• Year Installed: 2007
• Length: • Conductor length: 15 miles (24 km)
• Line length: 5 miles (8 km)
• Voltage: 230 kV
Solution: 3M ACCR 954-T13 Cardinal (490 mm2)
Results:
• Increased transmission capacity to meet the N-1 reliability
requirements
• 3M ACCR performed as required in heavy loads and
emergency conditions during 2008 tornado
• Used only the existing, relatively new towers
• Eliminated the need for permitting and other requirements
which would have been necessary for new towers
• Preserved the sightline
• Avoided impacting nearby bike path and railroad
3M™ ACCR
10
Project Profile: New Construction
“This has been an eagerly anticipated event that opens
the door to a much greater level of new economic
development. We’re very pleased to be the first tribal
power company to apply this technological advance in
electricity transmission.” - William Cyr, general
manager of Aha Macav Power Services.
Project Overview: • Customer: Aha Macav Power Services & Western Area
Power Administration (WAPA)
• Project: Firehouse – No Name Reliability Interconnect
• Location: Needles, CA
• Year Installed: 2008
• Length: • Conductor length: 15 miles (24 km)
• Line length: 5 miles (8 km)
• Voltage: 69 kV line
Solution: 3M ACCR 300-T16 Ostrich (150 mm2)
Results:
• Increased transmission capacity to meet growing demand,
which caused reliability issues in nearby community
• Provided operational reliability in severe desert conditions
and peak periods
• Installed double circuit with towers same height as previous
single circuit
• Met environmental permitting restrictions
3M™ ACCR
11
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: Western Area Power Administration (WAPA)
• Project: Topock-Davis
• Location: Near Bullhead City, Arizona
• Year Installed: 2007
• Length: • Conductor length: 60 miles (97 km)
• Line length: 20 miles (32 km)
• Voltage: 230 kV line
Solution: 3M ACCR 795-T16 Drake (418 mm2)
Results:
• Increased capacity on the line, as well as overall path
rating
• Used the existing structures
• Minimized environmental impact
• Cost savings from significantly reduced permitting and
environmental study requirements
“You can put the 3M ACCR on the same structures
as the existing conductor, which mitigates the overall
cost, and gets a large increase in capability” – Tony
Montoya – assistant regional manager for the federal
Western Area Power Administration, as quoted in The
Arizona Republic, September 25, 2006
3M™ ACCR
12
Project Profile: Large Ampacity Upgrade, Changing Clearances
Project Overview:
• Customer: Pacific Gas & Electric (PG&E)
• Project: Northern Receiving Station (NRS) to Scott
• Location: Santa Clara, CA
• Year Installed: 2005
• Length: • Conductor length: 0.7 miles (1 km)
• Line length: 0.25 miles (0.40 km)
• Voltage: 115 kV
Solution: 3M ACCR 477-T16 Hawk (238 mm2)
Results:
• Gained necessary capacity
• Maintained all clearances at higher capacity with existing
structures
• Increased clearance requirements in substation with
confined space.
• Avoided the need to replace 2 towers
3M™ ACCR
13
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: Alabama Power
• Project: Miller Substation
• Location: Birmingham, AL
• Year Installed: 2008
• Length: • Conductor length: 9 miles (14.5 km)
• Line length: 3 miles (4.8 km)
• Voltage: 230 kV
Solution: 3M ACCR 1033-T13 Curlew (525 mm2)
Results:
• Achieved capacity increase for future load growth
• Maintained all clearances by reconductoring on existing
structures
3M™ ACCR
14
Project Overview
• Customer: Hawaii Electric Company (HECO)
• Project: Pole 810 to Pole 818, Kahuku
• Location: Hawaii
• Year Installed: 2002
• Length: • Conductor length: 1 mile (1.6 km)
• Line length: 0.32 miles (0.5 km)
• Voltage: 46 kV line
Solution: 3M ACCR 477-T16 Hawk (238 mm2)
Results:
• Used same tension on existing towers as old conductor
• Eliminated need for intersets
• Continuously operating for several years beyond the
expected life of steel or polymer core conductors in salt
water environment
Project Profile: Harsh Environment
3M™ ACCR
15
Project Profile: Harsh Environment
Project Overview:
• Customer: Western Area Power Administration
(WAPA)
• Project: Jamestown to Fargo
• Location: Fargo, North Dakota
• Year Installed: 2002
• Length: • Conductor length: 2.5 miles (4 km)
• Line length: 0.8 miles (1.3 km)
• Voltagte: 230 kV line
Solution: 3M ACCR 795 T-16 Drake (418 mm2)
Results:
• Operated over several years with at least 2 heavy
ice loading events with no failures or measurable
degradation
• Operated through extreme cold and hot ambient
conditions and high winds
3M™ ACCR
16
Project Profile: Reliability
Project Overview:
• Customer: Alabama Power
• Project: Bynum to Anniston
• Location: Anniston, Alabama
• Year Installed: 2008
• Length: • Conductor length: 28 miles (45 km)
• Line length: 9 miles (14.5 km)
• Voltage: 230 kV
Solution: 3M ACCR 1033-T13 Curlew (525 mm2)
Results:
• Upgraded to meet contingency requirements
• Increased transmission capacity to serve summer
peak loads
• Eliminated need to replace existing transmission
structures and install 8 additional structures
• Reduced time required to fit available outage window
“The use of the 3M ACCR Conductor for this project
allowed us to avoid the replacement of 22 transmission
structures and the installation of eight additional
structures. This will significantly reduce our construction
time frame and allow the line to be taken out of service
for this project without impacting the reliability of our
grid.” Andy Wallace, Transmission line manager for
Alabama Power.
3M™ ACCR
17
Project Profile: Environmentally Sensitive Area
Project Overview:
• Customer: Companhia de Transmissao de Energia
Eletrica Paulista (CTEEP)
• Project: Jup-Tri Paraná River crossing
• Location: Border of São Paulo and Mato Grosso do
Sul States, Brazil
• Year Installed: 2009
• Length: • Conductor length: 12 miles (19 km)
• Line length: 2 miles (3.2 km);
• Voltage: 138 kV
Solution: 3M ACCR 300-T16 Ostrich (150 mm²)
Results: • Increased capacity by 220%
• Completed the river crossing using only existing
towers, and avoided major construction in
environmentally sensitive area
• Accommodated required span lengths
• Provided operational reliability in high winds and
ambient temperature
• Installed conductor in 6 days
“The 3M ACCR unique features were essential for us to
choose 3M as the supplier for this transmission line. We
needed a product that could accomplish the TL needs,
while being reliable and cost effective.” says CTEEP
engineering manager Caetano Cezario Neto.
3M™ ACCR
18
Project Profile: Densely Populated or Underbuilt Area
Project Overview:
• Customer: CPFL Piratininga
• Project: Ramal Duratex
• Location: Jundiaí-SP, Brasil
• Year Installed: 2009
• Length: • Conductor length: 12 miles (19 km)
• Line length: 2 circuit miles (3 km)
• Voltage: 88 kV
Solution: 3M ACCR 336-T16 Linnet (171 mm²)
Results:
• Increased capacity by 50%
• Avoided need for new towers in densely populated
urban area
• Left residences along narrow right-of-way
undisturbed during and after installation
“We studied several options and decided that 3M ACCR provides
the most reliable, cost-effective solution for delivering more power
through a dense neighborhood without creating numerous logistical
problems. We were impressed by its high performance in other
applications where new tower construction was undesirable. We
were also pleased that the installation process went smoothly and
everything is working as designed”. Paulo Ricardo Bombassaro,
engineering and planning manager for CPFL Energia.
3M™ ACCR
19
Project Profile: Large Ampacity Upgrade and Underbuilt Area
Project Overview:
• Customer: TATA Power
• Project: Borivali to Malad and Salsette to Saki
• Location: Mumbai, India
• Year Installed: 2009
• Length: • Conductor length: 120 miles (193 km)
• Line length: 10 miles (16 km)
• Voltage: 110 kV
Solution: 3M ACCR 300 T-16 Ostrich (150 mm²)
Results:
• Increased capacity from 900 amps to 2,000 amps just
2 years after last upgrade
• Resolved sag issue affecting hutments built under the
power lines
• Completed installation without disturbing residences
3M™ ACCR
20
Project Profile: Reliability
Project Overview:
• Customer: Silicon Valley Power
• Project: Palm Sub Project
• Location: Santa Clara, California
• Year Installed: 2009
• Length: • Conductor length: 17.6 miles (28 km)
• Line length: 3 miles (4.8 km)
• Voltage: 60 kV
Solution: 3M ACCR 715 T-13 Stilt (365mm2)
Results:
• Increased ampacity by 84% for growing substation loads
• Used only existing towers and right of way for existing line
• Matched tower heights with existing line for 2 new sections
• Re-energized existing portion of line every evening to
maintain reliable service
• Worked around railroad crossings and highways to install
• Delivered a reliable solution for sensitive high-tech
customers
“Using the cutting-edge aluminum matrix conductor mini-
mized disturbance for our customers while accommodating
the growing demand for power capacity in the area. Employ-
ing the latest technology also means less maintenance and
more reliability and we have plenty of capacity for rapid
response to customers’ increases in load requirements over
the next 15 to 20 years.” - John Roukema, Director of SVP.
3M™ ACCR
21
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: Chitaenergo
• Project: Kharonorskaya Hydro station to Turga (Line 64 – 65)
• Location: Siberia, Russia
• Year Installed: 2008
• Length: • Conductor length: 7.3 miles (11.0 km)
• Line length: 1.3 miles ( 1.7 km)
• Voltage: 110 kV
Solution: 3M ACCR 477-T13 Flicker (238 mm²)
Results:
• Increased ampacity by 100% to service railroad
• Reused existing towers without affecting under-built
facilities
• Provided a reliable solution in extreme ambient
temperatures and strong winds
“No problems that required any repair were recorded on this
section of power line during three years of operation of the
conductor . That allows to speak about the high quality of the
product and good economical affect of this project.“ – Dmitry
Popkov, Line Department Manager of Chitaenergo
3M™ ACCR
22
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: MOESK
• Project: Ochakovo-Odintsovo
• Location: Moscow, Russia
• Year Installed: 2008
• Length: • Conductor length: 51.1 miles (83 km)
• Line length: 8.26 miles (13.2 km);
• Voltage: 115 kV
Solution: 3M ACCR 477-T16 Hawk (238 mm²)
Results:
• Increased ampacity 98% by replacing ACSR 240/32
with 3M ACCR 477-T16 Hawk (238 mm²)
• Saved time
• Reused existing towers
• Provided a reliable solution for area with extreme
temperatures and heavy ice and wind loads
3M™ ACCR
23
Project Profile: Long-span Water Crossing
Project Overview:
• Customer: CPFL Paulista
• Project: Iacanga Substation
• Location: Sao Paulo, Brazil
• Year Installed: 2010
• Length: • Conductor length: 3.8 miles (6.1 km)
• Line length: 0.62 miles (1 km)
• Voltage: 138 kV
Solution: 3M ACCR 336-T16 Linnet (171 mm²)
Results:
• Eliminated need for tower on island submerged during
flooding of the Tietê River
• Avoided the delay of waiting until mid-year for river to
possibly subside
• Improved control over the overall project costs
• Lowered construction risks and environmental impacts
• Maintained same ampacity as ACSR Hawk 477 kcmil
(238 mm²) which is installed on the rest of the line
• Standard maintenance (no need for boats)
“Building the foundation and tower on submerged land
would have posed engineering difficulties; waiting until
mid-year for the river possibly to subside would have
caused unreasonable delay. Using 3M ACCR was a far
more desirable alternative - less costly, and safer for the
construction team.” - Paulo Ricardo Bombassaro,
engineering and planning manager for CPFL Energia.
3M™ ACCR
24
Project Profile: Validation at 400 kV
Project Overview: • Customer: Réseau de Transport d’Electricité (RTE)
• Project: Avoine – Distré
• Location: France
• Year Installed: 2010
• Length: • Conductor length: 9.3 miles (15 km)
• Line length: 0.75 miles (1.2 km)
• Voltage: 400 kV
Solution: 3M ACCR 1033 TW T-28
Results:
• Provided ampacity increase as a pilot on thermally limited, 400 kV line
• Installed in close quarters near Distré substation
• Passed intensive customer testing, including corona, strength, short circuit, resistance and thermal-mechanical testing, for use on extra-high voltage applications
3M™ ACCR
Project Profile: Permitting Environmentally Sensitive
Project Overview:
• Customer: Grays Harbor Public Utility District
• Project: Chehalis River Estuary Crossing
• Location: Aberdeen, Washington
• Year Installed: 2010
• Length: • Conductor length: 2.9 miles (4.6 km)
• Line length: 0.95 miles (1.5 km)
• Voltage: 115 & 69 kV
Solution: 3M ACCR 300 T-16
Results: • Avoided permitting and other potential delays by using
existing right-of-way and towers
• Avoided tower construction on the banks of the Chehalis River in an environmentally sensitive area
• Increased clearances by 44 ft. enabling GHPUD to raise the fiber optic line over the river to meet Army Corps of Engineers clearance requirements
• Increased capacity
• Upgraded 3 circuits on same crossing without
enlarging towers
“It is a significant advantage to be able to upgrade three circuits on
the same crossing, together with the under-built fiber optics, without
having to enlarge the towers. This allows us to avoid the permitting
and other potential delays that we are likely to have faced with a
construction project along the river” – Phil Penttila, System
engineering supervisor for Grays Harbor PUD.
3M™ ACCR
Project Profile: Densely Populated Area
Project Overview:
• Customer: Manila Electric Company (MERALCO)
• Project: Novalishe-Kaybiga Line
• Location: Manila, Philippines
• Year Installed: 2010
• Length: • Conductor length: 7.22 miles (11.55 km)
• Line length: 2.1 miles (3.4 km)
• Voltage: 115 kV
Solution: 3M ACCR 795 T-16 (418 mm2)
Results: • Avoided right-of-way issues
• Allowed significant savings and faster line construction
• Eliminated need for new wood poles compared to original plan using bundled 795 ACSR
• Increased line capacity to meet growing demand
• Minimized disturbance in highly crowded major thoroughfare
3M™ ACCR
Project Profile: Load Growth at 380 kV from Renewables
Project Overview: • Customer: Amprion GmbH (TSO of RWE)
• Project: BL 4307, Hannekenfähr - Gersteinwerk
• Location: Lingen, Germany
• Year Installed: 2009
• Length: • Conductor length: 5.2 miles (8.4 km)
• Line length: 2.6 miles (4.2 km)
• Voltage: 400 kV line
Solution: 3M ACCR 470 kcmil (238 mm2)
Results: • Operating successfully since installation on 380 kV line
• Increased ampacity to cover the expected load growth due to renewable energy expansion
27 © 3M 2010. All Rights Reserved.
ACCR
3M™ ACCR
Project Profile: Load Growth from Renewables
Project Overview: • Customer: E.ON Netz GmbH
• Project: Ostermoor - Marne
• Location: Brunsbüttel, Germany
• Year Installed: 2009
• Length: • Conductor length: 1.70 miles (2.70 km)
• Line length: 0.6 miles (0.9 km)
• Voltage: 110 kV line
Solution: 3M ACCR 470 kcmil (238 mm2)
Results:
• Increased capacity to support load growth created by renewable energy (on-shore wind farms)
• Preserved clearance on underbuilt 20 kV line owned by other utility
28 28 © 3M 2010. All Rights Reserved.
ACCR
3M™ ACCR
29
Project Profile: Ampacity Upgrade
Project Overview: • Customer: EDP Bandeirante
• Project: Ramal Cesar de Sousa
• Location: Mogi das Cruzes, Brazil
• Year Installed: 2010
• Length: • Conductor length: 21.7 miles (32.5 km)
• Line length: 3.1 miles (4.9 km)
• Voltage: 88 kV
Solution: 3M ACCR 267-T16
Results: • Avoided lengthy permitting delays and logistical
problems involved in expanding right of way
• Minimized environmental impact in an environmentally protected area
• Saved costs by not needing to acquire new right of way
“ We originally considered a conventional ACSR upgrade, but
the problems posed by construction in the protected area were
significant. The innovative 3M ACCR solution saves us a lot of
time and expense, allowing us to improve service about one
year sooner on a line that is already operating at full capacity”.
Vitor Luiz G. Gardiman, Bandeirante Energia’s executive
operations manager for high tension.
3M™ ACCR
Project Profile: Wetlands and Environmentally Sensitive Area
Project Overview:
• Customer: CPFL Piratininga
• Project: Henry Borden Jabaquara 1-2 and 3-4
• Location: Cubatão, São Paulo, Brazil
• Year Installed: 2010
• Length: • Conductor length: 50 miles (80 km)
• Line length: 7.5 miles (12 km)
• Voltage: 138 kV
Solution: 3M ACCR 780-T10
Results:
• Installed conductor with the same mechanical
characteristics as the old conductor
• Avoided environmental impacts of building a new
line through a marshy flood plain
• Reduced installation time to upgrade ampacity
• Performed the upgrade while keeping one circuit live
• Minimized crew time in places with challenging
access or critical areas
“We would have required two sets of foundations in that
difficult terrain, taking an estimated 10 months to complete.
The ACCR stringing needed only 4 months, with no
Construction time”. – Paulo Ricardo Bombassaro
Engineering Director of CPFL Piratininga
3M™ ACCR
31
Project Profile: Environmentally Protected Area
Project Overview:
• Customer: Georgia Power
• Project: Kraft-McIntosh
• Location: Savannah, GA
• Year Installed: 2011
• Length: • Conductor length: 106.2 miles (161.3 km)
• Line length: 34.3 miles (53.8 km)
• Voltage: 230 kV
Solution: 3M ACCR 1622 TW-T13 (823mm2)
Results: • Doubled capacity of lines while maintaining clearance
• Used existing towers with few modifications
• Maintained existing right of way (additional right-of-way was not available)
• Minimized impact on wet land
• Installed quickly within the outage window (Only one circuit could be out at a time - 10 weeks in the spring and 10 weeks in the fall)
• Saved several million dollars
3M™ ACCR
32
Project Profile: New Clearance Limits
Project Overview:
• Customer: National Grid
• Project: A127/B128
• Location: Massachusetts
• Year Installed: 2011
• Length: • Conductor length: 400 miles (640 km)
• Line length: 67 miles (107 km)
• Voltage: 115 kV
Solution: 3M ACCR 477-T16 Hawk (238mm2)
Results: • Replaced vintage 1920’s copper conductor
• Increased ampacity by approximately 20%
• Eliminated potential clearance violations
• Minimized tower reinforcement and replacement
• Reduced construction outage duration
• Minimized environmental and abutter impact
3M™ ACCR
33
Project Profile: Dense Population
Project Overview:
• Customer: AES Eletropaulo
• Project: Bandeirantes - Itaim
• Location: Sao Paulo, Brazil
• Year Installed: 2011
• Length: • Conductor length: 6.88 miles (11 km)
• Line length: 1.00 miles (1.6 km)
• Voltage: 138 kV
Solution: 3M ACCR 795-T13 TW
Results: • Increased capacity by more than 100%
• Used existing towers and right of way in a fast-growing, densely populated area
• Provided operational reliability in a tropical region with high humidity and extreme summer heat
• Installed without disrupting highway traffic or disturbing the adjacent river bed
3M™ ACCR
34
Project Profile: Cost Savings
Project Overview:
• Customer: Guadalupe Valley Electric Co-op
• Project: Schertz – Parkway T-361
• Location: San Antonio, TX
• Year Installed: 2011
• Length: • Conductor length: 9.10 miles (14.63 km)
• Line length: 3.00 miles (4.73 km)
• Voltage: 138 kV
Solution: 3M ACCR 680-T19
Results: • Increased ampacity by more than 60%
• Installed without the need to replace existing towers or add new towers
• Afforded additional capacity at a substantial savings
“3M ACCR conductor was chosen after an extensive review of the transmission load issues,
and the economics regarding replacement and addition of steel transmission structures. The
higher ampacity conductor afforded GVEC the additional capacity needed to meet the
planning requirement at a substantial savings to the GVEC membership.” - Rene Hernandez,
system engineer for GVEC.
3M™ ACCR
35
Project Profile: Long-span Water Crossing
Project Overview:
• Customer: EDP Escelsa
• Project: Rio Doce Crossing
• Location: Linhares, Espírito Santo, Brazil
• Year installed: 2011
• Length: • Conductor length: 3.6 miles (5.8 km)
• Line length: 0.574 miles (918 meters)
• Voltage: 138 kV double circuit
Solution: 3M ACCR 131-T58 (66.8 mm²)
Results:
• Eliminated need to replace towers on Doce River
border
• Improved clearance by 8.4 meters (27.5ft.)
• Avoided possible clearance issues during the rainy
season
• Lowered the overall project cost
• Reduced construction risks and environmental impacts
“The use of 3M ACCR conductor helped us to improve
our clearance before the rainy season, when the water
level in the river goes very high.” Luiz Tadeu Murad –
EDP Escelsa´s Transmission Line Projects and
Construction Engineer.
3M™ ACCR
Project Profile: Reliability
Project Overview • Customer: Irkutsk Energo
• Projects: Cimlyanskaya-Irkutsk HPP
Cimlyanskaya-Kirovskaya
• Location: Irkutsk, Russia
• Year Installed: 2010
• Length: • Conductor length: 36.0 miles (57.94 km)
• Line length: 6.21 miles (10.0 km)
• Voltage: 110 kv
Solution: 3M ACCR 427-T13 (215 mm2)
3M ACCR 636-T16 (320 mm2)
Results • Saved time and money
• Avoided having to acquire additional right-of-way in urban area
• Increased ampacity to 1240 – 1600 amps, providing reliable power during contingencies
36
37
Project Profile: Reliability
Project Overview: • Customer: Vologdaenergo (VSEP)
• Project: Centralnaya 1,2
• Location: Vologda
• Year installed: 2011
• Length: • Conductor length: 10.8 miles (17.38 km)
• Line length: 1.74 conductor miles (3 km)
• Voltage: 110 kV double circuit
Solution: 3M ACCR 300-T16 (150 mm2)
Results: • Increased capacity by 50% on existing towers
• Improved area reliability while reducing imports from neighboring regions
© 3M 2011. All Rights Reserved. Electric Markets Division
ACCR
“A five-year investment program that began in 2011 will
include additional infrastructure upgrades, of which ACCR
will be an important component,” Anatoly Pinizhaninov,
chief engineer.
3M™ ACCR
38
Project Profile: Long River Crossing
Project Overview:
• Customer: BC Hydro
• Project: Fraser River Crossing
• Location: British Columbia, Canada
• Year Installed: 2012
• Length: • Conductor length: 2.7 (4.35 km)
• Line length: .87 miles (1.40 km)
• Voltage: 230 kV
Solution: 3M ACCR 588-T73 (283 mm2)
Results: • Successfully installed conductor 4,600 ft across
river .
• Installed 3M ACCR without having to replace tower which had been damaged by erosion to the foundations at the river’s edge
• Installed in 7 days, so line could be re-energized as quickly as possible
3M™ ACCR
39
Project Profile: Ampacity Upgrade
Project Overview:
• Customer: Henan Ping Mine Company
• Project: Yueshang Line
• Location: Pingdingshan, China
• Year Installed: 2011
• Length: • Conductor length: 1.92 miles (3.2 km)
• Line length: . circuit miles ( km)
• Voltage: 35 kV
Solution: 3M ACCR 267-T16
Results:
• Saved upgrade time using existing towers
• Doubled capacity
• Provided reliable power for mine company
3M™ ACCR
40
Project Profile: Challenging Timeline
Project Overview:
• Customer: Shenzhen Power Utility
• Project: Liyue Line
• Location: Shenzhen, Guangdong Province, China
• Year Installed: 2012
• Length: • Conductor length: 16.67 miles (26.83 km)
• Line length: 2.8 circuit miles (4.5 km)
• Voltage: 220 kV
Solution: 3M ACCR 477-T16 (238 mm2)
Results: • Saved upgrade time
• Increased capacity by almost 200% using existing towers
• Provided reliable power for highway and railway crossing
3M™ ACCR
41
Project Profile: Clearance Requirements
Project Overview:
• Customer: Central Maine Power
• Project: Penobscot River Crossing
• Location:. Bucksport, ME
• Year Installed: 2011
• Length: • Conductor length: 1.48 miles (2.38 km)
• Line length: 0.48 miles (.77 km) circuit length
• Voltage: 115 kV
Solution: 3M ACCR 788-T26 (400mm2)
Results: • Increased clearances for the river to meet Army
Corp of Engineers requirements
• Minimized environmental impact
3M™ ACCR
42
Project Profile: Dense Population & Underbuilds
Project Overview: • Customer: Georgia Power
• Project: Grady to Moreland
• Location: Atlanta, Georgia
• Year Installed: 2012
• Length: • Conductor length: 11.80 miles (18.99 km)
• Line length: 3.82 miles (6.15 km)
• Voltage: 115 kV
Solution: 3M ACCR 636-T16 (323 mm2)
Results: • Increased ampacity by 58%
• Required minimal structure work
• Avoided significant real estate acquisition costs
3M™ ACCR
43
Project Profile: Load Growth From Renewables
Project Overview:
• Customer: 50 Hertz
• Project: Pilot – UW Güstrow
• Location: Güstrow, Germany
• Length: • Conductor length: 0.30 miles (0.48 km)
• Line length: 0.09 miles (0.14 km)
• Voltage: 110 kV
Solution: 3M ACCR 1033-T13
Results:
• Proved ease of installation
• Installed and operating without any problems and fully in-line with expectations
• Energized since June 2011
• Replaced a slightly larger ACSR, twin bundle (right circuit in upper picture) with a single Curlew ACCR (left circuit in upper picture)
1 or 2 Photos of installation
3M™ ACCR
44
Project Profile: Ampacity Upgrade
Project Overview:
• Customer: TransnetBW
• Project: Daxlanden-Eichstetten Pilot
• Location: Baden-Baden, Germany
• Length: • Conductor length: 0.40 miles (0.64 km)
• Line length: 0.35 miles (0.56 km)
• Voltage: 220 kV
Solution: 3M ACCR 715-T13
Results: • Proved ease of installation
• Installed and operating without any problems and fully in line with expectations
• Energized since November 2011
• Replaced a twin bundle of ACSR 240/40
3M™ ACCR
45
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: PEPCO
• Project: Dickerson-Quince Orchard &
Dickerson-Pleasantview
• Location: Maryland/Suburban D.C.
• Year Installed: 2011
• Length: • Conductor length: 108.2 miles (173.8 Km)
• Circuit length: 18.0 miles (28.9 Km)
• Voltage: 230 kV
Solution: 3M ACCR 1590 T-11 &
3M ACCR 1033 T-13
Results: • Increased ampacity by approximately 84%
• Minimized environmental impacts and permitting issues by reconductoring on existing towers
• Saved time – timing was an issue
3M™ ACCR
46
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: PSE&G (Public Service Enterprise Group)
• Project: Branchburg to Readington
• Location: Branchburg, New Jersey
• Year Installed: 2010
• Length: • Conductor length: 14.93 miles (23.89 km)
• Line length: 4.98 miles (7.96 km);
• Voltage: 230 kV
Solution: 3M ACCR 1590-T11 (807 mm2)
Results: • Increased ampacity
• Used existing towers
3M™ ACCR
47
Project Profile: Large Ampacity Upgrade
Project Overview • Customer: Perm Energo
• Project: Perm - Tets-6
• Location: Perm, Ural region, Russia
• Year Installed: 2010
• Length: • Conductor length: 32.53 miles (52.35 km)
• Line length: 5.16 miles (8.3 km)
• Voltage: 110 kV
Solution: 3M ACCR 300-T16 - Ostrich
Results: • Increased ampacity from 450 A to 700 A to
serve an expanded combined cycle power plant
• Used exiting rights of way to avoid logistical and permission issues in a crowded urban area
“In cooperation with IDGC of the Ural, we have found the best power output option, which is cheaper and more effective by its implementation at the same time. It was very vital for us to timely receive lines with enhanced capacity, so network companies successfully managed this challenge and performed their obligations at a high-quality level and right on time”,
Andrey Vagner, First Deputy General Director of IES
3M™ ACCR
48
Project Profile: Densely Populated or Underbuilt Area
Project Overview • Customer: MOESK
• Project: Cheremushki - Yujhnaya
• Location: Moscow, Russia
• Year Installed: 2011
• Length: • Conductor length: 13.4 miles (21.6 km)
• Line length: 2.05 miles ( 3.3 km)
• Voltage: 110 kV
Solution: 3M ACCR 477-T16 Hawk (238 mm2)
Results:
• Increased ampacity from 450A up to 1000A
• Used exiting towers and existing right of way to avoid logistical and permitting issues in urban area
• Avoided disrupting multilane highways and railroad tracks
• Installed in one month
3M™ ACCR
49
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: PEPCO
• Project: Palmers Corner to Burches Hill
• Location: Clinton, MD (near Washington, D.C.)
• Year Installed: 2012
• Length: • Conductor length: 80.34 miles (129.29 km)
• Line length: 6.50 miles (10.46 km)
• Voltage: 230 kV
Solution: 3M ACCR 1590-T11 (807 mm2)
Results: • Increased ampacity by over 80%
• Minimized environmental impacts and permitting issues by reconductoring on existing towers
• Saved time
3M™ ACCR
50
Project Profile: Large Ampacity Upgrade
Project Overview:
• Customer: Meralco
• Project: Zapote-Kamagong-Legazpi
• Location: Philippines
• Year Installed: 2012
• Length: • Conductor length: 32.40 miles (52.14 km)
• Line length: 10.50 miles (16.90 km)
• Voltage: 115 kV
Solution: 3M ACCR 795-T16 (403 mm2)
Results: • Used existing structures
• Avoided right-of-way issues in an urban area
• Allowed significant cost savings and faster line construction
• Installed at night so heavily loaded line could be re-energized during the day
3M™ ACCR
51
Project Profile: Environmentally Sensitive Area
Project Overview:
• Customer: CPFL Piratininga
• Project: Port of Santos new transmission line
• Location: Santos, Sao Paulo, Brazil
• Year Installed: 2012
• Length: • Conductor length: 1.4 miles (2.25 km)
• Line length: 0.23 miles (0.38 km)
• Voltage: 138 kV
Solution: 3M ACCR 267-T16 (135 mm2)
Results: • Minimized environmental impact in mangrove area
by enabling use of smaller foundations and shorter towers
• Reduced cost compared to conventional solution
3M™ ACCR
52
Project Profile: New Construction in an Environmentally Sensitive
Area and River Crossing
Project Overview:
• Customer: CTT (Cross Texas Transmission)
• Project: Red River Crossing
• Location: Texas
• Year Installed: 2012
• Length: • Conductor length: 8.14 miles (13.10 km)
• Line length: .74 miles (1.19 km)
• Voltage: 345 kV
Solution: 3M ACCR 1622-T13 TW (823 mm2)
Results: • Kept tower height low enough to avoid FAA compliance
issues
• Avoided new towers and larger foundations in the floodplain, because longer spans could be used
• Avoided permitting issues
• Part of CREZ (Competitive Renewable Energy Zone) projects to enable renewable energy development in Texas
3M™ ACCR
53
Project Profile: Challenging Timeline
Project Overview:
• Customer: Yinchuan Power Utility
• Project: Yinchuan Substation Part 1 & 2
• Location: Yinchuan, Ningxia Province, China
• Year Installed: 2012
• Length: • Conductor length: .81 miles (.1.3 km)
• Line length: .27 circuit miles (.43km)
• Voltage: 220 kV
Solution: 3M ACCR 795-T13 and 591-T13
Results: • Doubled capacity within existing substation frame
• Installed in 9 days
3M™ ACCR
54
Project Profile: Large Ampacity Increase
Project Overview:
• Customer: City of Palo Alto
• Project: Park Blvd. – Encina
• Location: Palo Alto, CA
• Year Installed: 2012
• Length: • Conductor length: 5.7 miles (9.17 km)
• Line length: 1.78 miles (2.86 km)
• Voltage: 60 kV
Solution: 3M ACCR 636-T10 (323 mm2)
Results: • Increased ampacity by 80% on line in a highly
developed urban area
• Matched the existing sags and tensions
• Maintained clearance from underbuilt line
• Enabled the use of existing towers along narrow right of ways and city streets
“With 3M ACCR we were able to avoid replacing all of the
structures along the route of our sub-transmission reconductoring
project. 3M’s technical staff made the procurement easy and
error free,” Jim Bujtor, Sr. Electric Engineer, CPAU.
3M™ ACCR
55
Current Installations Name Reason for Installation Year
Xcel Energy Minneapolis/St. Paul Riverside Installation validation 2001
HECo Oahu Waialua-Kahuku Oahu Corrosive environment 2002
Western Fargo Jamestown to Fargo Heavy ice/wind loads 2002
BPA Washington State Pasco High temp operation 2004
Western Phoenix Liberty Substation Installation validation 2004
SRP Phoenix Santan Generating Plant High current operation 2004
PG&E Santa ClaraNorthern Receiving
Station to ScottHigh temp operation 2005
SDG&E San Diego EPRI test EPRI test 2005
Xcel Energy Minneapolis/St. Paul Blue Lake to Black Dog
Environmentally sensitive
area
River crossing
2005
APS Phoenix Phoenix Metro TrunklineDense population and
underbuilds2006
Western AZ/CA border Topock to Davis High growth 2007
Shanghai Power Shanghai YangGao to XinZhou Cost and time savings 2007
Platte River Fort Collins Timberline to Harmony Reliability 2007
Aha Macav Needles Firehouse to No Name Reliability 2008
Allegheny Power West Virginia Bedington to NipetownUnderbuilt facilities
Cost and time savings2008
British Columbia Transmission Company
(BC Hydro)
Sansum and Montague
CrossingsRiver crossing 2008
Dominion Virginia Power West Virginia Loudon to Brambleton Underbuilt facilities 2008
Alabama Power Alabama Miller SubstationUnderbuilt facilities
Load growth2008
3M ACCR Commercial Installations
3M™ ACCR
56
Current Installations Name Reason for Installation Year
Silicon Valley City of Santa Clara Center Loop
Environmental and
aesthetics
Reliability
2008
Chongqing Grid Co. Chongqing Shuinian to ShuangshanLoad growth
Time savings2008
MOESK Moscow Ochakovo-Odintsovo Load growth 2008
OAO ChitaEnergo Chita Line 64-65 Load growth 2008
Alabama Power Bynum to Anniston Cost and time savings 2008
Silicon Valley City of Santa Clara Palm Sub Environmental and
aesthetics
2009
CTEEP Sao Paulo Jup-Val Cost, time and
environmental impact
2009
Tata Power Mumbai Salsette to Saki Load growth 2009
Tata Power Mumbai Borivali to Malad Load growth 2009
CPFL Varzea Paulista Ramal Duratex Load growth
Cost and time savings
2009
RWE Service GmbH Europe Lab Test Line Test 2009
Chongqing Grid Co. China Lishuwan Substation Link to substation 2009
Xcel Energy St. Paul 3M Center LineLoad growth
Cost savings2009
Chongqing Grid Co. China
Qinan substation, Yuntai
substation, Youngchuan
substation, Songlin
substation
Substations 2009
Yunnan Dai Electric China Jianchuan Substation Substations 2009
E.ON Netz GmbH Germany Ostermoor-Marne Pilot line 2009
Amprion GmbH GermanyHanekenfähr-
GersteinwerkPilot line 2009
City of Palo Alto Palo AltoHoover Pavilion 60 kV
Relocation Project
New clearance issue
Maximum amps2009
3M ACCR Commercial Installations
3M™ ACCR
57
Current Installations Name Reason for Installation Year
Grand Bahamas Power/Barkley
TechnologiesGrand Bahamas
Maximum amps
Corrosive environment
Heavy winds
2009
Silicon Valley Power City of Santa Clara Kenneth Project Relationship 2009
RTE France Avoines-Distré Pilot line 2010
CPFL Iacanga, SPIacanga Substation Tietê
River Crossing
Tight timeline
Environmental impacts
Risk of construction
problems
2010
American Electric Power CompanySporn-Muskingum River
Relocation Project
Maximum amps
Reduce number of towers2010
Henan Zhengzhou Power Utility Henan Province Helu Line Maximum amps. 2010
EDP BandeiranteMogi das Cruzes,
BrazilCesar de Souza
Environmental impacts
Permitting
Maximum amps
2010
Gray's Harbor PUD1 Washington State Chehalis River Crossing Environmental impacts 2010
Hubei Huangshi Power Utility Hubei Daye LineTime savings
Reliability2010
CPFL Brazil Henry Borden Jabaquara Environmental impacts
Cost and time savings2010
Meralco Philipines Kaybiga-Novalishe Maximum amps 2010
Eletropaulo São Paulo Bandeirantes - ItaimDense population and
cost2010
Irkutsk Energo IrkutskIrkutsk Hydro to
KirovskayaCost savings 2010
Sinkiang Dushanzi Petrochemical Corp. Xing Jiang Du Shan Zhi (Xing Jiang) 2010
PSE&G New Jersey Branchberg-Readington Maximum amps 2010
3M ACCR Commercial Installations
3M™ ACCR
58
Current Installations Name Reason for Installation Year
National Grid Massachusettes Section 1 Cost savings 2010
Shanghai Power Utility Shanghai Sanlin Line Maximum amps. 2010
Irkutsk Energo IrkutskCimlyans-Irkutsk HPP
Part 1 and 2
Cost savings
Permitting Issues2010
Irkutsk Energo Irkutsk
Cimlyans - Irkutsk
Kirovskaya Circuit 1 and
2
Densely populated area 2010
PepCo Washington D.C.Dickerson-Quince
OrchardMaximum amps 2011
EDP Escelsa Brazil Rio Doce Crossing River Crossing 2011
Alabama Power AlabamaMontgomery -
Montgomery SubstationMaximum amps. 2011
Georgia Power GeorgiaBlandford-Little
OgeecheeOther 2011
Georgia Power GeorgiaKraft-McIntosh (part 1 of
2 - black)
Maximum amps.
Cost savings2011
Henan Ping Mining Co. Henan Yueshang ProjectMaximum amps., Delivery
time2011
Guangdong Shenzen Power Utility* Guang Liyue LineMaximum amps.,
Challenging timeline2011
Guadalupe Valley Elec. Co-op North America Schertz - Parkway T-361 Total project cost 2011
National Grid Massachusettes Section 2 Maximum amps 2011
PepCo Washington D.C. Dickerson-Pleasant View Clearance requirements 2011
Volgdaselenergoproekt Vologda, Russia Centralnaya 1,2 Maximum amps 2011
3M ACCR Commercial Installations
3M™ ACCR
59
Current Installations Name Reason for Installation Year
Georgia Power Georgia Grady-MorelandDense Population,
Underbuild2012
Central Maine Power Co USA Penobscot River Xing Heavy ice 2011
BC Hydro Canada2L22 230 kV Fraser River
Crossing
Long River Crossing
Critical line issues2011
Meralco Philipines Zapote Paco Malibay Maximum amps 2012
EnBW GermanyDaxlanden-Eichstetten
PilotMaximum amps. 2011
50 Hertz GermanyGuestrow 50 Hertz Pilot
UWPilot line 2011
Yinchuan Power Utility ChinaYinshuan Substation Pt.
2Short Timelines 2012
Yinchuan Power Utility ChinaYinshuan Substation Pt.
1Short Timelines 2012
CTT - Cross Texas Transmission USA Red River Crossing
Environmentally sensitive
area
River crossing
2012
PEPCO USA Washington D.C.Palmers Corner - Burches
Hill2012
CPFL Brazil Santos Port Crossing
Environmentally sensitive
area
River crossing New
clearance limits
2012
Meralco Philippines Zapote Paco Malibay Maximum amps 2012
Perm Russia TETS 1,2 Cost savings 2010
City of Palo Alto USA Park Blvd. Sub - Encina
Dense Population,
Underbuilds
Maximum Amps
2012
3M ACCR Commercial Installations