accr case studies presentation 1-22-13 (1)

59
3M™ Aluminum Conductor Composite Reinforced (ACCR) More Amps, More Confidence for your most challenging applications 3M ACCR Case Studies 1/22/13

Upload: deepuer

Post on 09-Feb-2016

131 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: ACCR Case Studies Presentation 1-22-13 (1)

3M™ Aluminum Conductor Composite Reinforced (ACCR)

More Amps,

More Confidence

for your most challenging

applications

3M ACCR

Case Studies

1/22/13

Page 2: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

2

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: Shanghai Electric Power Company Ltd

• Project: YangGao to XinZhou (Yangxing line)

• Location: Shanghai, China

• Year Installed: 2007

• Length: • Conductor length: 60 miles (96.6 km)

• Line length: 10 miles( 16.1 km);

• Voltage: 220 kV

Solution: 3M ACCR 795-T16 Drake (418 mm2)

Results:

• Doubled capacity to meet growing demand in the World

Expo area of Central Shanghai

• Eliminated need for new towers

• Provided fast, cost-effective option for delivering additional

energy in a time-sensitive project

• Installed in 18 days

“Based on the October 14 line energizing, 3M ACCR

works well. After passing a real project’s running test,

we believe 3M’s ACCR will have a brilliant future in field

application and will help us enhance the city

transmission network.” – Mr. Pan, Shanghai Power

Yanggao Project designer.

Page 3: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

3

Project Profile: Long-span Water Crossing

Project Overview:

• Customer: BC Hydro/BCTC

• Project: Vancouver Island Transmission Reinforcement

(VITR)

• Location: Vancouver Island

• Year Installed: 2008

• Length: • Conductor length: 13.6 miles (21.89 km)

• Line length: 2.2 miles (3.5 km)

• Voltage: 230 kV

Solution: 3M ACCR 788-T26 custom (400 mm2)

Results:

• Avoided major construction including extensive use of

helicopters, barges, and road construction by using

existing towers

• Upgraded with minimal disturbance to environmentally

sensitive waterway and provincial park

• Preserved the existing sightline

• Successfully installed conductor across 5,800 ft (1.5

km), single-span with no additional towers and no tower

in the waterway

Page 4: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

4

Project Overview:

• Customer: Xcel Energy

• Project: Black Dog to Blue Lake

• Location: Minneapolis, MN

• Year Installed: 2005

• Length: • Conductor length: 30 miles (48.3 km),

• Line length: 10 miles (16 km),

• Voltage: 115 kV line

Solution: 3M ACCR 795-T16 Drake (418 mm2)

Project Profile: Challenging Timeline

“ Without 3M ACCR we would have had to replace

existing towers to accommodate larger sized

conventional conductors. Use of the new conductor

allowed us to boost capacity on the line while avoiding

major construction in an area with sensitive wetlands”.

– Doug Jaeger, transmission vice president for Xcel

Energy

Results: • Boosted capacity by 80% on the line for peaking plant

upgrade coming on-line

• Used only existing towers,

• Avoided major construction in National Wildlife Refuge,

sensitive wetlands area

• Solved difficult installation challenges on site, and used single

pull across protected area

• Provided fast, cost-effective option for delivering energy by

saving months of permitting compared to ACSR/ACSS

Page 5: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

5

Project Profile: Challenging Timeline

Project Overview:

• Customer: Chongqing Electric Power Corporation

• Project: Shuinian to Shuangshan (Shuishuang line)

• Location: Chongqing, China

• Year Installed: 2008

• Length: • Conductor length: 24 miles (38.6 km)

• Line length: 4 miles (6.4 km)

• Voltage: 220 kV line

Solution: 3M ACCR 680-T19 Custom (346 mm2)

Results:

• More than doubled transmission capacity using only

existing towers

• Provided operational reliability in a sub-tropical region

with high humidity and extreme summer heat

• Completed in 2 weeks, just one month before the start

of the Olympics

“This is one of the hottest cities of China, with monsoonal

weather, and we required a conductor that could be

relied upon to carry more current under those conditions,

and could be installed quickly and reliably within the

existing infrastructure. Installation required only two

weeks.” – Wang Xinkuan, chief design engineer for

Chongqing Electric Power Corporation

Page 6: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

6

Project Profile: Densely Populated or Underbuilt Area

Project Overview:

• Customer: Arizona Public Service

• Project: Phoenix Metro Trunkline Upgrade

• Location: Phoenix, AZ

• Year Installed: 2006

• Length: • Conductor length: 16 miles (25.8 km)

• Line length: 5.5 miles (8.9 km)

• Voltage: 230 kV

Solution: 3M ACCR 1272-T13 Pheasant (642 mm2)

Results:

• Provided capacity to serve the fast-growing, congested area,

including airport, and downtown sports stadium

• Used existing medium-duty structures without any tower

modifications

• Avoided siting, acquiring rights-of-way, and environmental

permitting

• Minimized installation time (3 weeks)

• Minimized disruption to neighborhoods and facilities near the line

I don’t even want to think what the overload

would have been, or the impact of that, if we

were still using the old lines,” – Paul Richards,

construction projects manager for APS, in The

Arizona Republic, 9/25/06

Page 7: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

7

Project Profile: Densely Populated or Underbuilt Area

Project Overview: • Customer: Allegheny Power

• Project: Bedington Nipetown

• Location: West Virginia

• Year Installed: 2008

• Length: • Conductor length: 6 miles (9.7 km)

• Line length: 2 miles (3.2 km)

• Voltage: 138 kV line

Solution: 3M ACCR 1033-T13 Curlew (525 mm2)

Results:

• Increased transmission capacity using only existing

towers

• Sagged neatly with an adjacent 954 kcmil (490 mm²)

ACSR conductor on the same structure

• Minimized impact on under-built lines and allowed them

to remain in service during installation

“By using the 3M ACCR, the money and time saved was

invaluable on this fast-paced project. The design and

ordering process was a simple task because of 3M’s

sales and technical staff which demonstrates a service

culture of which 3M should be proud.” - Richard Hoch –

Engineer for Allegheny Power.

Page 8: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

8

Project Profile: Reliability

Project Overview:

• Customer: Silicon Valley Power

• Project: Center Loop Reconductor

• Location: Santa Clara, California

• Year Installed: 2008

• Length: • Conductor length: 23 miles, (37 km)

• Line length: 4 miles (6.4 km)

• Voltage: 60 kV

Solution: 3M ACCR 715-T13 Stilt (365 mm2)

Results:

• Provided a highly reliable solution to sensitive high-tech

customers

• Increased capacity using existing towers and maintained

existing right of way

• Matched existing sag and tension without adding additional

stress to existing towers

• Minimized disturbance to neighborhood and high-tech

industrial customers, including re-energizing the line at the

end of work each day for sensitive server farms and

electronic wafer manufacturers

“We needed a way to significantly increase

transmission capacity without the extra cost of

making major structural changes. 3M ACCR fit

our needs exactly and at quite a savings over

other alternatives.” - Kevin Keating, manager

of engineering for Silicon Valley Power

Page 9: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

9

Project Profile: Reliability

“The Timberline-Harmony line is an important

part of the grid between Denver and

Cheyenne, and we chose 3M ACCR as a way

to safeguard against overloading when

demand is high.” – Mike Dahl, Division

Manager Electric Operations, Platte River

Power Authority

Project Overview:

• Customer: Platte River Power Authority (PRPA)

• Project: Timberline-Harmony

• Location: Fort Collins, Colorado

• Year Installed: 2007

• Length: • Conductor length: 15 miles (24 km)

• Line length: 5 miles (8 km)

• Voltage: 230 kV

Solution: 3M ACCR 954-T13 Cardinal (490 mm2)

Results:

• Increased transmission capacity to meet the N-1 reliability

requirements

• 3M ACCR performed as required in heavy loads and

emergency conditions during 2008 tornado

• Used only the existing, relatively new towers

• Eliminated the need for permitting and other requirements

which would have been necessary for new towers

• Preserved the sightline

• Avoided impacting nearby bike path and railroad

Page 10: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

10

Project Profile: New Construction

“This has been an eagerly anticipated event that opens

the door to a much greater level of new economic

development. We’re very pleased to be the first tribal

power company to apply this technological advance in

electricity transmission.” - William Cyr, general

manager of Aha Macav Power Services.

Project Overview: • Customer: Aha Macav Power Services & Western Area

Power Administration (WAPA)

• Project: Firehouse – No Name Reliability Interconnect

• Location: Needles, CA

• Year Installed: 2008

• Length: • Conductor length: 15 miles (24 km)

• Line length: 5 miles (8 km)

• Voltage: 69 kV line

Solution: 3M ACCR 300-T16 Ostrich (150 mm2)

Results:

• Increased transmission capacity to meet growing demand,

which caused reliability issues in nearby community

• Provided operational reliability in severe desert conditions

and peak periods

• Installed double circuit with towers same height as previous

single circuit

• Met environmental permitting restrictions

Page 11: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

11

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: Western Area Power Administration (WAPA)

• Project: Topock-Davis

• Location: Near Bullhead City, Arizona

• Year Installed: 2007

• Length: • Conductor length: 60 miles (97 km)

• Line length: 20 miles (32 km)

• Voltage: 230 kV line

Solution: 3M ACCR 795-T16 Drake (418 mm2)

Results:

• Increased capacity on the line, as well as overall path

rating

• Used the existing structures

• Minimized environmental impact

• Cost savings from significantly reduced permitting and

environmental study requirements

“You can put the 3M ACCR on the same structures

as the existing conductor, which mitigates the overall

cost, and gets a large increase in capability” – Tony

Montoya – assistant regional manager for the federal

Western Area Power Administration, as quoted in The

Arizona Republic, September 25, 2006

Page 12: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

12

Project Profile: Large Ampacity Upgrade, Changing Clearances

Project Overview:

• Customer: Pacific Gas & Electric (PG&E)

• Project: Northern Receiving Station (NRS) to Scott

• Location: Santa Clara, CA

• Year Installed: 2005

• Length: • Conductor length: 0.7 miles (1 km)

• Line length: 0.25 miles (0.40 km)

• Voltage: 115 kV

Solution: 3M ACCR 477-T16 Hawk (238 mm2)

Results:

• Gained necessary capacity

• Maintained all clearances at higher capacity with existing

structures

• Increased clearance requirements in substation with

confined space.

• Avoided the need to replace 2 towers

Page 13: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

13

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: Alabama Power

• Project: Miller Substation

• Location: Birmingham, AL

• Year Installed: 2008

• Length: • Conductor length: 9 miles (14.5 km)

• Line length: 3 miles (4.8 km)

• Voltage: 230 kV

Solution: 3M ACCR 1033-T13 Curlew (525 mm2)

Results:

• Achieved capacity increase for future load growth

• Maintained all clearances by reconductoring on existing

structures

Page 14: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

14

Project Overview

• Customer: Hawaii Electric Company (HECO)

• Project: Pole 810 to Pole 818, Kahuku

• Location: Hawaii

• Year Installed: 2002

• Length: • Conductor length: 1 mile (1.6 km)

• Line length: 0.32 miles (0.5 km)

• Voltage: 46 kV line

Solution: 3M ACCR 477-T16 Hawk (238 mm2)

Results:

• Used same tension on existing towers as old conductor

• Eliminated need for intersets

• Continuously operating for several years beyond the

expected life of steel or polymer core conductors in salt

water environment

Project Profile: Harsh Environment

Page 15: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

15

Project Profile: Harsh Environment

Project Overview:

• Customer: Western Area Power Administration

(WAPA)

• Project: Jamestown to Fargo

• Location: Fargo, North Dakota

• Year Installed: 2002

• Length: • Conductor length: 2.5 miles (4 km)

• Line length: 0.8 miles (1.3 km)

• Voltagte: 230 kV line

Solution: 3M ACCR 795 T-16 Drake (418 mm2)

Results:

• Operated over several years with at least 2 heavy

ice loading events with no failures or measurable

degradation

• Operated through extreme cold and hot ambient

conditions and high winds

Page 16: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

16

Project Profile: Reliability

Project Overview:

• Customer: Alabama Power

• Project: Bynum to Anniston

• Location: Anniston, Alabama

• Year Installed: 2008

• Length: • Conductor length: 28 miles (45 km)

• Line length: 9 miles (14.5 km)

• Voltage: 230 kV

Solution: 3M ACCR 1033-T13 Curlew (525 mm2)

Results:

• Upgraded to meet contingency requirements

• Increased transmission capacity to serve summer

peak loads

• Eliminated need to replace existing transmission

structures and install 8 additional structures

• Reduced time required to fit available outage window

“The use of the 3M ACCR Conductor for this project

allowed us to avoid the replacement of 22 transmission

structures and the installation of eight additional

structures. This will significantly reduce our construction

time frame and allow the line to be taken out of service

for this project without impacting the reliability of our

grid.” Andy Wallace, Transmission line manager for

Alabama Power.

Page 17: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

17

Project Profile: Environmentally Sensitive Area

Project Overview:

• Customer: Companhia de Transmissao de Energia

Eletrica Paulista (CTEEP)

• Project: Jup-Tri Paraná River crossing

• Location: Border of São Paulo and Mato Grosso do

Sul States, Brazil

• Year Installed: 2009

• Length: • Conductor length: 12 miles (19 km)

• Line length: 2 miles (3.2 km);

• Voltage: 138 kV

Solution: 3M ACCR 300-T16 Ostrich (150 mm²)

Results: • Increased capacity by 220%

• Completed the river crossing using only existing

towers, and avoided major construction in

environmentally sensitive area

• Accommodated required span lengths

• Provided operational reliability in high winds and

ambient temperature

• Installed conductor in 6 days

“The 3M ACCR unique features were essential for us to

choose 3M as the supplier for this transmission line. We

needed a product that could accomplish the TL needs,

while being reliable and cost effective.” says CTEEP

engineering manager Caetano Cezario Neto.

Page 18: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

18

Project Profile: Densely Populated or Underbuilt Area

Project Overview:

• Customer: CPFL Piratininga

• Project: Ramal Duratex

• Location: Jundiaí-SP, Brasil

• Year Installed: 2009

• Length: • Conductor length: 12 miles (19 km)

• Line length: 2 circuit miles (3 km)

• Voltage: 88 kV

Solution: 3M ACCR 336-T16 Linnet (171 mm²)

Results:

• Increased capacity by 50%

• Avoided need for new towers in densely populated

urban area

• Left residences along narrow right-of-way

undisturbed during and after installation

“We studied several options and decided that 3M ACCR provides

the most reliable, cost-effective solution for delivering more power

through a dense neighborhood without creating numerous logistical

problems. We were impressed by its high performance in other

applications where new tower construction was undesirable. We

were also pleased that the installation process went smoothly and

everything is working as designed”. Paulo Ricardo Bombassaro,

engineering and planning manager for CPFL Energia.

Page 19: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

19

Project Profile: Large Ampacity Upgrade and Underbuilt Area

Project Overview:

• Customer: TATA Power

• Project: Borivali to Malad and Salsette to Saki

• Location: Mumbai, India

• Year Installed: 2009

• Length: • Conductor length: 120 miles (193 km)

• Line length: 10 miles (16 km)

• Voltage: 110 kV

Solution: 3M ACCR 300 T-16 Ostrich (150 mm²)

Results:

• Increased capacity from 900 amps to 2,000 amps just

2 years after last upgrade

• Resolved sag issue affecting hutments built under the

power lines

• Completed installation without disturbing residences

Page 20: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

20

Project Profile: Reliability

Project Overview:

• Customer: Silicon Valley Power

• Project: Palm Sub Project

• Location: Santa Clara, California

• Year Installed: 2009

• Length: • Conductor length: 17.6 miles (28 km)

• Line length: 3 miles (4.8 km)

• Voltage: 60 kV

Solution: 3M ACCR 715 T-13 Stilt (365mm2)

Results:

• Increased ampacity by 84% for growing substation loads

• Used only existing towers and right of way for existing line

• Matched tower heights with existing line for 2 new sections

• Re-energized existing portion of line every evening to

maintain reliable service

• Worked around railroad crossings and highways to install

• Delivered a reliable solution for sensitive high-tech

customers

“Using the cutting-edge aluminum matrix conductor mini-

mized disturbance for our customers while accommodating

the growing demand for power capacity in the area. Employ-

ing the latest technology also means less maintenance and

more reliability and we have plenty of capacity for rapid

response to customers’ increases in load requirements over

the next 15 to 20 years.” - John Roukema, Director of SVP.

Page 21: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

21

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: Chitaenergo

• Project: Kharonorskaya Hydro station to Turga (Line 64 – 65)

• Location: Siberia, Russia

• Year Installed: 2008

• Length: • Conductor length: 7.3 miles (11.0 km)

• Line length: 1.3 miles ( 1.7 km)

• Voltage: 110 kV

Solution: 3M ACCR 477-T13 Flicker (238 mm²)

Results:

• Increased ampacity by 100% to service railroad

• Reused existing towers without affecting under-built

facilities

• Provided a reliable solution in extreme ambient

temperatures and strong winds

“No problems that required any repair were recorded on this

section of power line during three years of operation of the

conductor . That allows to speak about the high quality of the

product and good economical affect of this project.“ – Dmitry

Popkov, Line Department Manager of Chitaenergo

Page 22: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

22

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: MOESK

• Project: Ochakovo-Odintsovo

• Location: Moscow, Russia

• Year Installed: 2008

• Length: • Conductor length: 51.1 miles (83 km)

• Line length: 8.26 miles (13.2 km);

• Voltage: 115 kV

Solution: 3M ACCR 477-T16 Hawk (238 mm²)

Results:

• Increased ampacity 98% by replacing ACSR 240/32

with 3M ACCR 477-T16 Hawk (238 mm²)

• Saved time

• Reused existing towers

• Provided a reliable solution for area with extreme

temperatures and heavy ice and wind loads

Page 23: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

23

Project Profile: Long-span Water Crossing

Project Overview:

• Customer: CPFL Paulista

• Project: Iacanga Substation

• Location: Sao Paulo, Brazil

• Year Installed: 2010

• Length: • Conductor length: 3.8 miles (6.1 km)

• Line length: 0.62 miles (1 km)

• Voltage: 138 kV

Solution: 3M ACCR 336-T16 Linnet (171 mm²)

Results:

• Eliminated need for tower on island submerged during

flooding of the Tietê River

• Avoided the delay of waiting until mid-year for river to

possibly subside

• Improved control over the overall project costs

• Lowered construction risks and environmental impacts

• Maintained same ampacity as ACSR Hawk 477 kcmil

(238 mm²) which is installed on the rest of the line

• Standard maintenance (no need for boats)

“Building the foundation and tower on submerged land

would have posed engineering difficulties; waiting until

mid-year for the river possibly to subside would have

caused unreasonable delay. Using 3M ACCR was a far

more desirable alternative - less costly, and safer for the

construction team.” - Paulo Ricardo Bombassaro,

engineering and planning manager for CPFL Energia.

Page 24: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

24

Project Profile: Validation at 400 kV

Project Overview: • Customer: Réseau de Transport d’Electricité (RTE)

• Project: Avoine – Distré

• Location: France

• Year Installed: 2010

• Length: • Conductor length: 9.3 miles (15 km)

• Line length: 0.75 miles (1.2 km)

• Voltage: 400 kV

Solution: 3M ACCR 1033 TW T-28

Results:

• Provided ampacity increase as a pilot on thermally limited, 400 kV line

• Installed in close quarters near Distré substation

• Passed intensive customer testing, including corona, strength, short circuit, resistance and thermal-mechanical testing, for use on extra-high voltage applications

Page 25: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

Project Profile: Permitting Environmentally Sensitive

Project Overview:

• Customer: Grays Harbor Public Utility District

• Project: Chehalis River Estuary Crossing

• Location: Aberdeen, Washington

• Year Installed: 2010

• Length: • Conductor length: 2.9 miles (4.6 km)

• Line length: 0.95 miles (1.5 km)

• Voltage: 115 & 69 kV

Solution: 3M ACCR 300 T-16

Results: • Avoided permitting and other potential delays by using

existing right-of-way and towers

• Avoided tower construction on the banks of the Chehalis River in an environmentally sensitive area

• Increased clearances by 44 ft. enabling GHPUD to raise the fiber optic line over the river to meet Army Corps of Engineers clearance requirements

• Increased capacity

• Upgraded 3 circuits on same crossing without

enlarging towers

“It is a significant advantage to be able to upgrade three circuits on

the same crossing, together with the under-built fiber optics, without

having to enlarge the towers. This allows us to avoid the permitting

and other potential delays that we are likely to have faced with a

construction project along the river” – Phil Penttila, System

engineering supervisor for Grays Harbor PUD.

Page 26: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

Project Profile: Densely Populated Area

Project Overview:

• Customer: Manila Electric Company (MERALCO)

• Project: Novalishe-Kaybiga Line

• Location: Manila, Philippines

• Year Installed: 2010

• Length: • Conductor length: 7.22 miles (11.55 km)

• Line length: 2.1 miles (3.4 km)

• Voltage: 115 kV

Solution: 3M ACCR 795 T-16 (418 mm2)

Results: • Avoided right-of-way issues

• Allowed significant savings and faster line construction

• Eliminated need for new wood poles compared to original plan using bundled 795 ACSR

• Increased line capacity to meet growing demand

• Minimized disturbance in highly crowded major thoroughfare

Page 27: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

Project Profile: Load Growth at 380 kV from Renewables

Project Overview: • Customer: Amprion GmbH (TSO of RWE)

• Project: BL 4307, Hannekenfähr - Gersteinwerk

• Location: Lingen, Germany

• Year Installed: 2009

• Length: • Conductor length: 5.2 miles (8.4 km)

• Line length: 2.6 miles (4.2 km)

• Voltage: 400 kV line

Solution: 3M ACCR 470 kcmil (238 mm2)

Results: • Operating successfully since installation on 380 kV line

• Increased ampacity to cover the expected load growth due to renewable energy expansion

27 © 3M 2010. All Rights Reserved.

ACCR

Page 28: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

Project Profile: Load Growth from Renewables

Project Overview: • Customer: E.ON Netz GmbH

• Project: Ostermoor - Marne

• Location: Brunsbüttel, Germany

• Year Installed: 2009

• Length: • Conductor length: 1.70 miles (2.70 km)

• Line length: 0.6 miles (0.9 km)

• Voltage: 110 kV line

Solution: 3M ACCR 470 kcmil (238 mm2)

Results:

• Increased capacity to support load growth created by renewable energy (on-shore wind farms)

• Preserved clearance on underbuilt 20 kV line owned by other utility

28 28 © 3M 2010. All Rights Reserved.

ACCR

Page 29: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

29

Project Profile: Ampacity Upgrade

Project Overview: • Customer: EDP Bandeirante

• Project: Ramal Cesar de Sousa

• Location: Mogi das Cruzes, Brazil

• Year Installed: 2010

• Length: • Conductor length: 21.7 miles (32.5 km)

• Line length: 3.1 miles (4.9 km)

• Voltage: 88 kV

Solution: 3M ACCR 267-T16

Results: • Avoided lengthy permitting delays and logistical

problems involved in expanding right of way

• Minimized environmental impact in an environmentally protected area

• Saved costs by not needing to acquire new right of way

“ We originally considered a conventional ACSR upgrade, but

the problems posed by construction in the protected area were

significant. The innovative 3M ACCR solution saves us a lot of

time and expense, allowing us to improve service about one

year sooner on a line that is already operating at full capacity”.

Vitor Luiz G. Gardiman, Bandeirante Energia’s executive

operations manager for high tension.

Page 30: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

Project Profile: Wetlands and Environmentally Sensitive Area

Project Overview:

• Customer: CPFL Piratininga

• Project: Henry Borden Jabaquara 1-2 and 3-4

• Location: Cubatão, São Paulo, Brazil

• Year Installed: 2010

• Length: • Conductor length: 50 miles (80 km)

• Line length: 7.5 miles (12 km)

• Voltage: 138 kV

Solution: 3M ACCR 780-T10

Results:

• Installed conductor with the same mechanical

characteristics as the old conductor

• Avoided environmental impacts of building a new

line through a marshy flood plain

• Reduced installation time to upgrade ampacity

• Performed the upgrade while keeping one circuit live

• Minimized crew time in places with challenging

access or critical areas

“We would have required two sets of foundations in that

difficult terrain, taking an estimated 10 months to complete.

The ACCR stringing needed only 4 months, with no

Construction time”. – Paulo Ricardo Bombassaro

Engineering Director of CPFL Piratininga

Page 31: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

31

Project Profile: Environmentally Protected Area

Project Overview:

• Customer: Georgia Power

• Project: Kraft-McIntosh

• Location: Savannah, GA

• Year Installed: 2011

• Length: • Conductor length: 106.2 miles (161.3 km)

• Line length: 34.3 miles (53.8 km)

• Voltage: 230 kV

Solution: 3M ACCR 1622 TW-T13 (823mm2)

Results: • Doubled capacity of lines while maintaining clearance

• Used existing towers with few modifications

• Maintained existing right of way (additional right-of-way was not available)

• Minimized impact on wet land

• Installed quickly within the outage window (Only one circuit could be out at a time - 10 weeks in the spring and 10 weeks in the fall)

• Saved several million dollars

Page 32: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

32

Project Profile: New Clearance Limits

Project Overview:

• Customer: National Grid

• Project: A127/B128

• Location: Massachusetts

• Year Installed: 2011

• Length: • Conductor length: 400 miles (640 km)

• Line length: 67 miles (107 km)

• Voltage: 115 kV

Solution: 3M ACCR 477-T16 Hawk (238mm2)

Results: • Replaced vintage 1920’s copper conductor

• Increased ampacity by approximately 20%

• Eliminated potential clearance violations

• Minimized tower reinforcement and replacement

• Reduced construction outage duration

• Minimized environmental and abutter impact

Page 33: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

33

Project Profile: Dense Population

Project Overview:

• Customer: AES Eletropaulo

• Project: Bandeirantes - Itaim

• Location: Sao Paulo, Brazil

• Year Installed: 2011

• Length: • Conductor length: 6.88 miles (11 km)

• Line length: 1.00 miles (1.6 km)

• Voltage: 138 kV

Solution: 3M ACCR 795-T13 TW

Results: • Increased capacity by more than 100%

• Used existing towers and right of way in a fast-growing, densely populated area

• Provided operational reliability in a tropical region with high humidity and extreme summer heat

• Installed without disrupting highway traffic or disturbing the adjacent river bed

Page 34: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

34

Project Profile: Cost Savings

Project Overview:

• Customer: Guadalupe Valley Electric Co-op

• Project: Schertz – Parkway T-361

• Location: San Antonio, TX

• Year Installed: 2011

• Length: • Conductor length: 9.10 miles (14.63 km)

• Line length: 3.00 miles (4.73 km)

• Voltage: 138 kV

Solution: 3M ACCR 680-T19

Results: • Increased ampacity by more than 60%

• Installed without the need to replace existing towers or add new towers

• Afforded additional capacity at a substantial savings

“3M ACCR conductor was chosen after an extensive review of the transmission load issues,

and the economics regarding replacement and addition of steel transmission structures. The

higher ampacity conductor afforded GVEC the additional capacity needed to meet the

planning requirement at a substantial savings to the GVEC membership.” - Rene Hernandez,

system engineer for GVEC.

Page 35: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

35

Project Profile: Long-span Water Crossing

Project Overview:

• Customer: EDP Escelsa

• Project: Rio Doce Crossing

• Location: Linhares, Espírito Santo, Brazil

• Year installed: 2011

• Length: • Conductor length: 3.6 miles (5.8 km)

• Line length: 0.574 miles (918 meters)

• Voltage: 138 kV double circuit

Solution: 3M ACCR 131-T58 (66.8 mm²)

Results:

• Eliminated need to replace towers on Doce River

border

• Improved clearance by 8.4 meters (27.5ft.)

• Avoided possible clearance issues during the rainy

season

• Lowered the overall project cost

• Reduced construction risks and environmental impacts

“The use of 3M ACCR conductor helped us to improve

our clearance before the rainy season, when the water

level in the river goes very high.” Luiz Tadeu Murad –

EDP Escelsa´s Transmission Line Projects and

Construction Engineer.

Page 36: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

Project Profile: Reliability

Project Overview • Customer: Irkutsk Energo

• Projects: Cimlyanskaya-Irkutsk HPP

Cimlyanskaya-Kirovskaya

• Location: Irkutsk, Russia

• Year Installed: 2010

• Length: • Conductor length: 36.0 miles (57.94 km)

• Line length: 6.21 miles (10.0 km)

• Voltage: 110 kv

Solution: 3M ACCR 427-T13 (215 mm2)

3M ACCR 636-T16 (320 mm2)

Results • Saved time and money

• Avoided having to acquire additional right-of-way in urban area

• Increased ampacity to 1240 – 1600 amps, providing reliable power during contingencies

36

Page 37: ACCR Case Studies Presentation 1-22-13 (1)

37

Project Profile: Reliability

Project Overview: • Customer: Vologdaenergo (VSEP)

• Project: Centralnaya 1,2

• Location: Vologda

• Year installed: 2011

• Length: • Conductor length: 10.8 miles (17.38 km)

• Line length: 1.74 conductor miles (3 km)

• Voltage: 110 kV double circuit

Solution: 3M ACCR 300-T16 (150 mm2)

Results: • Increased capacity by 50% on existing towers

• Improved area reliability while reducing imports from neighboring regions

© 3M 2011. All Rights Reserved. Electric Markets Division

ACCR

“A five-year investment program that began in 2011 will

include additional infrastructure upgrades, of which ACCR

will be an important component,” Anatoly Pinizhaninov,

chief engineer.

Page 38: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

38

Project Profile: Long River Crossing

Project Overview:

• Customer: BC Hydro

• Project: Fraser River Crossing

• Location: British Columbia, Canada

• Year Installed: 2012

• Length: • Conductor length: 2.7 (4.35 km)

• Line length: .87 miles (1.40 km)

• Voltage: 230 kV

Solution: 3M ACCR 588-T73 (283 mm2)

Results: • Successfully installed conductor 4,600 ft across

river .

• Installed 3M ACCR without having to replace tower which had been damaged by erosion to the foundations at the river’s edge

• Installed in 7 days, so line could be re-energized as quickly as possible

Page 39: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

39

Project Profile: Ampacity Upgrade

Project Overview:

• Customer: Henan Ping Mine Company

• Project: Yueshang Line

• Location: Pingdingshan, China

• Year Installed: 2011

• Length: • Conductor length: 1.92 miles (3.2 km)

• Line length: . circuit miles ( km)

• Voltage: 35 kV

Solution: 3M ACCR 267-T16

Results:

• Saved upgrade time using existing towers

• Doubled capacity

• Provided reliable power for mine company

Page 40: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

40

Project Profile: Challenging Timeline

Project Overview:

• Customer: Shenzhen Power Utility

• Project: Liyue Line

• Location: Shenzhen, Guangdong Province, China

• Year Installed: 2012

• Length: • Conductor length: 16.67 miles (26.83 km)

• Line length: 2.8 circuit miles (4.5 km)

• Voltage: 220 kV

Solution: 3M ACCR 477-T16 (238 mm2)

Results: • Saved upgrade time

• Increased capacity by almost 200% using existing towers

• Provided reliable power for highway and railway crossing

Page 41: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

41

Project Profile: Clearance Requirements

Project Overview:

• Customer: Central Maine Power

• Project: Penobscot River Crossing

• Location:. Bucksport, ME

• Year Installed: 2011

• Length: • Conductor length: 1.48 miles (2.38 km)

• Line length: 0.48 miles (.77 km) circuit length

• Voltage: 115 kV

Solution: 3M ACCR 788-T26 (400mm2)

Results: • Increased clearances for the river to meet Army

Corp of Engineers requirements

• Minimized environmental impact

Page 42: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

42

Project Profile: Dense Population & Underbuilds

Project Overview: • Customer: Georgia Power

• Project: Grady to Moreland

• Location: Atlanta, Georgia

• Year Installed: 2012

• Length: • Conductor length: 11.80 miles (18.99 km)

• Line length: 3.82 miles (6.15 km)

• Voltage: 115 kV

Solution: 3M ACCR 636-T16 (323 mm2)

Results: • Increased ampacity by 58%

• Required minimal structure work

• Avoided significant real estate acquisition costs

Page 43: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

43

Project Profile: Load Growth From Renewables

Project Overview:

• Customer: 50 Hertz

• Project: Pilot – UW Güstrow

• Location: Güstrow, Germany

• Length: • Conductor length: 0.30 miles (0.48 km)

• Line length: 0.09 miles (0.14 km)

• Voltage: 110 kV

Solution: 3M ACCR 1033-T13

Results:

• Proved ease of installation

• Installed and operating without any problems and fully in-line with expectations

• Energized since June 2011

• Replaced a slightly larger ACSR, twin bundle (right circuit in upper picture) with a single Curlew ACCR (left circuit in upper picture)

1 or 2 Photos of installation

Page 44: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

44

Project Profile: Ampacity Upgrade

Project Overview:

• Customer: TransnetBW

• Project: Daxlanden-Eichstetten Pilot

• Location: Baden-Baden, Germany

• Length: • Conductor length: 0.40 miles (0.64 km)

• Line length: 0.35 miles (0.56 km)

• Voltage: 220 kV

Solution: 3M ACCR 715-T13

Results: • Proved ease of installation

• Installed and operating without any problems and fully in line with expectations

• Energized since November 2011

• Replaced a twin bundle of ACSR 240/40

Page 45: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

45

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: PEPCO

• Project: Dickerson-Quince Orchard &

Dickerson-Pleasantview

• Location: Maryland/Suburban D.C.

• Year Installed: 2011

• Length: • Conductor length: 108.2 miles (173.8 Km)

• Circuit length: 18.0 miles (28.9 Km)

• Voltage: 230 kV

Solution: 3M ACCR 1590 T-11 &

3M ACCR 1033 T-13

Results: • Increased ampacity by approximately 84%

• Minimized environmental impacts and permitting issues by reconductoring on existing towers

• Saved time – timing was an issue

Page 46: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

46

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: PSE&G (Public Service Enterprise Group)

• Project: Branchburg to Readington

• Location: Branchburg, New Jersey

• Year Installed: 2010

• Length: • Conductor length: 14.93 miles (23.89 km)

• Line length: 4.98 miles (7.96 km);

• Voltage: 230 kV

Solution: 3M ACCR 1590-T11 (807 mm2)

Results: • Increased ampacity

• Used existing towers

Page 47: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

47

Project Profile: Large Ampacity Upgrade

Project Overview • Customer: Perm Energo

• Project: Perm - Tets-6

• Location: Perm, Ural region, Russia

• Year Installed: 2010

• Length: • Conductor length: 32.53 miles (52.35 km)

• Line length: 5.16 miles (8.3 km)

• Voltage: 110 kV

Solution: 3M ACCR 300-T16 - Ostrich

Results: • Increased ampacity from 450 A to 700 A to

serve an expanded combined cycle power plant

• Used exiting rights of way to avoid logistical and permission issues in a crowded urban area

“In cooperation with IDGC of the Ural, we have found the best power output option, which is cheaper and more effective by its implementation at the same time. It was very vital for us to timely receive lines with enhanced capacity, so network companies successfully managed this challenge and performed their obligations at a high-quality level and right on time”,

Andrey Vagner, First Deputy General Director of IES

Page 48: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

48

Project Profile: Densely Populated or Underbuilt Area

Project Overview • Customer: MOESK

• Project: Cheremushki - Yujhnaya

• Location: Moscow, Russia

• Year Installed: 2011

• Length: • Conductor length: 13.4 miles (21.6 km)

• Line length: 2.05 miles ( 3.3 km)

• Voltage: 110 kV

Solution: 3M ACCR 477-T16 Hawk (238 mm2)

Results:

• Increased ampacity from 450A up to 1000A

• Used exiting towers and existing right of way to avoid logistical and permitting issues in urban area

• Avoided disrupting multilane highways and railroad tracks

• Installed in one month

Page 49: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

49

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: PEPCO

• Project: Palmers Corner to Burches Hill

• Location: Clinton, MD (near Washington, D.C.)

• Year Installed: 2012

• Length: • Conductor length: 80.34 miles (129.29 km)

• Line length: 6.50 miles (10.46 km)

• Voltage: 230 kV

Solution: 3M ACCR 1590-T11 (807 mm2)

Results: • Increased ampacity by over 80%

• Minimized environmental impacts and permitting issues by reconductoring on existing towers

• Saved time

Page 50: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

50

Project Profile: Large Ampacity Upgrade

Project Overview:

• Customer: Meralco

• Project: Zapote-Kamagong-Legazpi

• Location: Philippines

• Year Installed: 2012

• Length: • Conductor length: 32.40 miles (52.14 km)

• Line length: 10.50 miles (16.90 km)

• Voltage: 115 kV

Solution: 3M ACCR 795-T16 (403 mm2)

Results: • Used existing structures

• Avoided right-of-way issues in an urban area

• Allowed significant cost savings and faster line construction

• Installed at night so heavily loaded line could be re-energized during the day

Page 51: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

51

Project Profile: Environmentally Sensitive Area

Project Overview:

• Customer: CPFL Piratininga

• Project: Port of Santos new transmission line

• Location: Santos, Sao Paulo, Brazil

• Year Installed: 2012

• Length: • Conductor length: 1.4 miles (2.25 km)

• Line length: 0.23 miles (0.38 km)

• Voltage: 138 kV

Solution: 3M ACCR 267-T16 (135 mm2)

Results: • Minimized environmental impact in mangrove area

by enabling use of smaller foundations and shorter towers

• Reduced cost compared to conventional solution

Page 52: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

52

Project Profile: New Construction in an Environmentally Sensitive

Area and River Crossing

Project Overview:

• Customer: CTT (Cross Texas Transmission)

• Project: Red River Crossing

• Location: Texas

• Year Installed: 2012

• Length: • Conductor length: 8.14 miles (13.10 km)

• Line length: .74 miles (1.19 km)

• Voltage: 345 kV

Solution: 3M ACCR 1622-T13 TW (823 mm2)

Results: • Kept tower height low enough to avoid FAA compliance

issues

• Avoided new towers and larger foundations in the floodplain, because longer spans could be used

• Avoided permitting issues

• Part of CREZ (Competitive Renewable Energy Zone) projects to enable renewable energy development in Texas

Page 53: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

53

Project Profile: Challenging Timeline

Project Overview:

• Customer: Yinchuan Power Utility

• Project: Yinchuan Substation Part 1 & 2

• Location: Yinchuan, Ningxia Province, China

• Year Installed: 2012

• Length: • Conductor length: .81 miles (.1.3 km)

• Line length: .27 circuit miles (.43km)

• Voltage: 220 kV

Solution: 3M ACCR 795-T13 and 591-T13

Results: • Doubled capacity within existing substation frame

• Installed in 9 days

Page 54: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

54

Project Profile: Large Ampacity Increase

Project Overview:

• Customer: City of Palo Alto

• Project: Park Blvd. – Encina

• Location: Palo Alto, CA

• Year Installed: 2012

• Length: • Conductor length: 5.7 miles (9.17 km)

• Line length: 1.78 miles (2.86 km)

• Voltage: 60 kV

Solution: 3M ACCR 636-T10 (323 mm2)

Results: • Increased ampacity by 80% on line in a highly

developed urban area

• Matched the existing sags and tensions

• Maintained clearance from underbuilt line

• Enabled the use of existing towers along narrow right of ways and city streets

“With 3M ACCR we were able to avoid replacing all of the

structures along the route of our sub-transmission reconductoring

project. 3M’s technical staff made the procurement easy and

error free,” Jim Bujtor, Sr. Electric Engineer, CPAU.

Page 55: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

55

Current Installations Name Reason for Installation Year

Xcel Energy Minneapolis/St. Paul Riverside Installation validation 2001

HECo Oahu Waialua-Kahuku Oahu Corrosive environment 2002

Western Fargo Jamestown to Fargo Heavy ice/wind loads 2002

BPA Washington State Pasco High temp operation 2004

Western Phoenix Liberty Substation Installation validation 2004

SRP Phoenix Santan Generating Plant High current operation 2004

PG&E Santa ClaraNorthern Receiving

Station to ScottHigh temp operation 2005

SDG&E San Diego EPRI test EPRI test 2005

Xcel Energy Minneapolis/St. Paul Blue Lake to Black Dog

Environmentally sensitive

area

River crossing

2005

APS Phoenix Phoenix Metro TrunklineDense population and

underbuilds2006

Western AZ/CA border Topock to Davis High growth 2007

Shanghai Power Shanghai YangGao to XinZhou Cost and time savings 2007

Platte River Fort Collins Timberline to Harmony Reliability 2007

Aha Macav Needles Firehouse to No Name Reliability 2008

Allegheny Power West Virginia Bedington to NipetownUnderbuilt facilities

Cost and time savings2008

British Columbia Transmission Company

(BC Hydro)

Sansum and Montague

CrossingsRiver crossing 2008

Dominion Virginia Power West Virginia Loudon to Brambleton Underbuilt facilities 2008

Alabama Power Alabama Miller SubstationUnderbuilt facilities

Load growth2008

3M ACCR Commercial Installations

Page 56: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

56

Current Installations Name Reason for Installation Year

Silicon Valley City of Santa Clara Center Loop

Environmental and

aesthetics

Reliability

2008

Chongqing Grid Co. Chongqing Shuinian to ShuangshanLoad growth

Time savings2008

MOESK Moscow Ochakovo-Odintsovo Load growth 2008

OAO ChitaEnergo Chita Line 64-65 Load growth 2008

Alabama Power Bynum to Anniston Cost and time savings 2008

Silicon Valley City of Santa Clara Palm Sub Environmental and

aesthetics

2009

CTEEP Sao Paulo Jup-Val Cost, time and

environmental impact

2009

Tata Power Mumbai Salsette to Saki Load growth 2009

Tata Power Mumbai Borivali to Malad Load growth 2009

CPFL Varzea Paulista Ramal Duratex Load growth

Cost and time savings

2009

RWE Service GmbH Europe Lab Test Line Test 2009

Chongqing Grid Co. China Lishuwan Substation Link to substation 2009

Xcel Energy St. Paul 3M Center LineLoad growth

Cost savings2009

Chongqing Grid Co. China

Qinan substation, Yuntai

substation, Youngchuan

substation, Songlin

substation

Substations 2009

Yunnan Dai Electric China Jianchuan Substation Substations 2009

E.ON Netz GmbH Germany Ostermoor-Marne Pilot line 2009

Amprion GmbH GermanyHanekenfähr-

GersteinwerkPilot line 2009

City of Palo Alto Palo AltoHoover Pavilion 60 kV

Relocation Project

New clearance issue

Maximum amps2009

3M ACCR Commercial Installations

Page 57: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

57

Current Installations Name Reason for Installation Year

Grand Bahamas Power/Barkley

TechnologiesGrand Bahamas

Maximum amps

Corrosive environment

Heavy winds

2009

Silicon Valley Power City of Santa Clara Kenneth Project Relationship 2009

RTE France Avoines-Distré Pilot line 2010

CPFL Iacanga, SPIacanga Substation Tietê

River Crossing

Tight timeline

Environmental impacts

Risk of construction

problems

2010

American Electric Power CompanySporn-Muskingum River

Relocation Project

Maximum amps

Reduce number of towers2010

Henan Zhengzhou Power Utility Henan Province Helu Line Maximum amps. 2010

EDP BandeiranteMogi das Cruzes,

BrazilCesar de Souza

Environmental impacts

Permitting

Maximum amps

2010

Gray's Harbor PUD1 Washington State Chehalis River Crossing Environmental impacts 2010

Hubei Huangshi Power Utility Hubei Daye LineTime savings

Reliability2010

CPFL Brazil Henry Borden Jabaquara Environmental impacts

Cost and time savings2010

Meralco Philipines Kaybiga-Novalishe Maximum amps 2010

Eletropaulo São Paulo Bandeirantes - ItaimDense population and

cost2010

Irkutsk Energo IrkutskIrkutsk Hydro to

KirovskayaCost savings 2010

Sinkiang Dushanzi Petrochemical Corp. Xing Jiang Du Shan Zhi (Xing Jiang) 2010

PSE&G New Jersey Branchberg-Readington Maximum amps 2010

3M ACCR Commercial Installations

Page 58: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

58

Current Installations Name Reason for Installation Year

National Grid Massachusettes Section 1 Cost savings 2010

Shanghai Power Utility Shanghai Sanlin Line Maximum amps. 2010

Irkutsk Energo IrkutskCimlyans-Irkutsk HPP

Part 1 and 2

Cost savings

Permitting Issues2010

Irkutsk Energo Irkutsk

Cimlyans - Irkutsk

Kirovskaya Circuit 1 and

2

Densely populated area 2010

PepCo Washington D.C.Dickerson-Quince

OrchardMaximum amps 2011

EDP Escelsa Brazil Rio Doce Crossing River Crossing 2011

Alabama Power AlabamaMontgomery -

Montgomery SubstationMaximum amps. 2011

Georgia Power GeorgiaBlandford-Little

OgeecheeOther 2011

Georgia Power GeorgiaKraft-McIntosh (part 1 of

2 - black)

Maximum amps.

Cost savings2011

Henan Ping Mining Co. Henan Yueshang ProjectMaximum amps., Delivery

time2011

Guangdong Shenzen Power Utility* Guang Liyue LineMaximum amps.,

Challenging timeline2011

Guadalupe Valley Elec. Co-op North America Schertz - Parkway T-361 Total project cost 2011

National Grid Massachusettes Section 2 Maximum amps 2011

PepCo Washington D.C. Dickerson-Pleasant View Clearance requirements 2011

Volgdaselenergoproekt Vologda, Russia Centralnaya 1,2 Maximum amps 2011

3M ACCR Commercial Installations

Page 59: ACCR Case Studies Presentation 1-22-13 (1)

3M™ ACCR

59

Current Installations Name Reason for Installation Year

Georgia Power Georgia Grady-MorelandDense Population,

Underbuild2012

Central Maine Power Co USA Penobscot River Xing Heavy ice 2011

BC Hydro Canada2L22 230 kV Fraser River

Crossing

Long River Crossing

Critical line issues2011

Meralco Philipines Zapote Paco Malibay Maximum amps 2012

EnBW GermanyDaxlanden-Eichstetten

PilotMaximum amps. 2011

50 Hertz GermanyGuestrow 50 Hertz Pilot

UWPilot line 2011

Yinchuan Power Utility ChinaYinshuan Substation Pt.

2Short Timelines 2012

Yinchuan Power Utility ChinaYinshuan Substation Pt.

1Short Timelines 2012

CTT - Cross Texas Transmission USA Red River Crossing

Environmentally sensitive

area

River crossing

2012

PEPCO USA Washington D.C.Palmers Corner - Burches

Hill2012

CPFL Brazil Santos Port Crossing

Environmentally sensitive

area

River crossing New

clearance limits

2012

Meralco Philippines Zapote Paco Malibay Maximum amps 2012

Perm Russia TETS 1,2 Cost savings 2010

City of Palo Alto USA Park Blvd. Sub - Encina

Dense Population,

Underbuilds

Maximum Amps

2012

3M ACCR Commercial Installations