accr case studies 6-9-10

26
3M™ Aluminum Conductor Composite Reinforced (ACCR) More Amps, More Confidence for your most challenging applications 3M ACCR Case Studies 6/10

Upload: raulitoroque

Post on 18-Dec-2015

32 views

Category:

Documents


1 download

DESCRIPTION

accr

TRANSCRIPT

  • 3M Aluminum Conductor Composite Reinforced (ACCR)

    More Amps, More Confidence

    for your most challenging applications

    3M ACCR Case Studies

    6/10

  • 23M ACCR

    Project Profile: Large Ampacity Upgrades

    Project Overview: Customer: Shanghai Electric Power Company Ltd Project: YangGao to XinZhou (Yangxing line) Location: Shanghai, China Length & Voltage: 60 Conductor Miles (96.6 km); 10 circuit

    miles(16.1 km); 220 kV

    Solution: 3M ACCR 795 kcmil (418 mm2)

    Results: Doubled capacity to meet growing demand in the World

    Expo area of Central Shanghai Eliminated need for new towers Provided fast, cost-effective option for delivering additional

    energy in a time-sensitive project Installed in 18 days Based on the October 14 line energizing, 3M ACCR

    works well. After passing a real projects running test, we believe 3Ms ACCR will have a brilliant future in field application and will help us enhance the city transmission network. Mr. Pan, Shanghai Power Yanggao Project designer.

  • 33M ACCR

    Project Profile: Long-span Water Crossing

    Project Overview: Customer: BC Hydro/BCTC Project: Vancouver Island Transmission Reinforcement

    (VITR) Location: Vancouver Island Length & Voltage: 6 conductor miles (9.7 km), 2 circuit

    miles (3.2 km); 230 kV

    Solution: 3M ACCR 788 kcmil (400 mm2)

    Results: Avoided major construction including extensive use of

    helicopters, barges, and road construction by using existing towers

    Upgraded with minimal disturbance to environmentally sensitive waterway and provincial park

    Preserved the existing sightline Successfully installed conductor across 5,800 ft (1.5

    km), single-span with no additional towers and no tower in the waterway

  • 43M ACCR

    Project Overview: Customer: Xcel Energy Project: Black Dog to Blue Lake Location: Minneapolis, MN Length & Voltage: 30 conductor miles (48.3 km), 10 circuit

    miles (16 km), 115 kV line

    Solution: 3M ACCR 795 kcmil (418 mm2)

    Project Profile: Challenging Timelines

    Without 3M ACCR we would have had to replace existing towers to accommodate larger sized conventional conductors. Use of the new conductor allowed us to boost capacity on the line while avoiding major construction in an area with sensitive wetlands. Doug Jaeger, transmission vice president for Xcel Energy

    Results: Boosted capacity on the line for peaking plant upgrade

    coming on-line Used only existing towers, Avoided major construction in National Wildlife Refuge,

    sensitive wetlands area Solved difficult installation challenges on site, and used single

    pull across protected area Provided fast, cost-effective option for delivering energy by

    saving months of permitting

  • 53M ACCR

    Project Profile: Challenging Timeline

    Project Overview: Customer: Chongqing Electric Power Corporation Project: Shuinian to Shuangshan (Shuishuang line) Location: Chongqing, China Length & Voltage: 24 conductor miles (38.6 km), 4

    circuit miles (6.4 km), 220 kV line

    Solution: 3M ACCR 680 kcmil (346 mm2)

    Results: More than doubled transmission capacity using only

    existing towers Provided operational reliability in a sub-tropical region

    with high humidity and extreme summer heat Completed in 2 weeks, just one month before the start

    of the OlympicsThis is one of the hottest cities of China, with monsoonal weather, and we required a conductor that could be relied upon to carry more current under those conditions, and could be installed quickly and reliably within the existing infrastructure. Installation required only two weeks. Wang Xinkuan, chief design engineer for Chongqing Electric Power Corporation

  • 63M ACCR

    Project Profile: Densely Populated or Underbuilt Area

    Project Overview: Customer: Arizona Public Service Project: Phoenix Metro Trunkline Upgrade Location: Phoenix, AZ Length & Voltage: 16 conductor miles (25.8 km) 5.5 circuit miles

    (8.9 km); 230 kV

    Solution: 3M ACCR 1272 kcmil (642 mm2)

    Results: Provided capacity to serve the fast-growing, congested area,

    including airport, and downtown sports stadium Used existing medium-duty structures without any tower

    modifications Avoided siting, acquiring rights-of-way, and environmental

    permitting Minimized installation time (3 weeks) Minimized disruption to neighborhoods and facilities near the line

    I dont even want to think what the overload would have been, or the impact of that, if we were still using the old lines, Paul Richards, construction projects manager for APS, in The Arizona Republic, 9/25/06

  • 73M ACCR

    Project Profile: Densely Populated or Underbuilt Area

    Project Overview: Customer: Allegheny Power Project: Bedington Nipetown Location: West Virginia Length & Voltage: 6 conductor miles (9.7 km), 2

    circuit miles (3.2 km); 138 kV line

    Solution: 3M ACCR 1033 kcmil (525 mm2)

    Results: Increased transmission capacity using only existing

    towers Sagged neatly with an adjacent 954 ACSR

    conductor on the same structure Minimized impact on under-built lines and allowed

    them to remain in service during installationBy using the 3M ACCR, the money and time saved was invaluable on this fast-paced project. The design and ordering process was a simple task because of 3Ms sales and technical staff which demonstrates a service culture of which 3M should be proud. - Richard Hoch Engineer for Allegheny Power.

  • 83M ACCR

    Project Profile: Reliability

    Project Overview: Customer: Silicon Valley Power Project: Center Loop Reconductor Location: Santa Clara, California Length & Voltage: 23 conductor miles, (37 km), 4 circuit

    miles (6.4 km); 60 kV

    Solution: 3M ACCR 715 kcmil (365 mm2)

    Results: Provided a highly reliable solution Increased capacity using existing towers and maintained

    existing right of way Matched existing sag and tension without adding additional

    stress to existing towers Minimized disturbance to neighborhood and high-tech

    industrial customers, including re-energizing the line at the end of work each day for sensitive server farms and electronic wafer manufacturers

    We needed a way to significantly increase transmission capacity without the extra cost of making major structural changes. 3M ACCR fit our needs exactly and at quite a savings over other alternatives. - Kevin Keating, manager of engineering for Silicon Valley Power

  • 93M ACCR

    Project Profile: N-1 Reliability

    The Timberline-Harmony line is an important part of the grid between Denver and Cheyenne, and we chose 3M ACCR as a way to safeguard against overloading when demand is high. Mike Dahl, Division Manager Electric Operations, Platte River Power Authority

    Project Overview: Customer: Platte River Power Authority (PRPA) Project: Timberline-Harmony Location: Fort Collins, Colorado Length & Voltage: 15 conductor miles (24 km), 5 circuit

    miles (8 km); 230 kV

    Solution: 3M ACCR 954 kcmil (490 mm2)

    Results: Increased transmission capacity to meet the N-1

    reliability requirements 3M ACCR performed as required in heavy loads and

    emergency conditions during 2008 tornado Used only the existing, relatively new towers Eliminated the need for permitting and other

    requirements which would have been necessary for new towers

    Preserved the sightline Avoided impacting nearby bike path and railroad

  • 10

    3M ACCR

    Project Profile: New Construction

    This has been an eagerly anticipated event that opens the door to a much greater level of new economic development. Were very pleased to be the first tribal power company to apply this technological advance in electricity transmission. - William Cyr, general manager of Aha Macav Power Services.

    Project Overview: Customer: Aha Macav Power Services & Western Area

    Power Administration (WAPA) Project: Firehouse No Name Reliability Interconnect Location: Needles, CA Length & Voltage: 15 conductor miles (24 km), 5 circuit

    miles (8 km); 69 kV line

    Solution: 3M ACCR 300 kcmil (150 mm2)

    Results: Increased transmission capacity to meet growing

    demand, which caused reliability issues in nearby community

    Provided operational reliability in severe desert conditions and peak periods

    Installed double circuit with towers same height as previous single circuit

    Met environmental permitting restrictions

  • 11

    3M ACCR

    Project Profile: Large Ampacity Upgrade

    Project Overview: Customer: Western Area Power Administration (WAPA) Project: Topock-Davis Location: Near Bullhead City, Arizona Length & Voltage: 60 conductor miles (97 km), 20 circuit

    miles (32 km); 230 kV line

    Solution: 3M ACCR 795 kcmil (418 mm2)

    Results: Increased capacity on the line, as well as overall path

    rating Used the existing structures Minimized environmental impact Cost savings from significantly reduced permitting and

    environmental study requirements

    You can put the 3M ACCR on the same structures as the existing conductor, which mitigates the overall cost, and gets a large increase in capability Tony Montoya assistant regional manager for the federal Western Area Power Administration, as quoted in The Arizona Republic, September 25, 2006

  • 12

    3M ACCR

    Project Profile: Thermal Upgrade With Changing Clearance Requirements

    Project Overview: Customer: Pacific Gas & Electric (PG&E) Project: Northern Receiving Station (NRS) to Scott Location: Santa Clara, CA Length & Voltage: 0.7 conductor miles (1 km), .25 circuit

    miles (0.40 km); 115 kV

    Solution: 3M ACCR 477 kcmil (238 mm2)

    Results: Gained necessary capacity Maintained all clearances at higher capacity with existing

    structures Avoided the need to replace 2 towers

  • 13

    3M ACCR

    Project Profile: Ampacity Upgrade

    Project Overview: Customer: Alabama Power Project: Miller Substation Location: Birmingham, AL Length & Voltage: 9 conductor miles (14.5 km), 3

    circuit miles (4.8 km), 230 kV

    Solution: 3M ACCR 1033 kcmil (525 mm2)

    Results: Achieved capacity increase for future load growth Maintained all clearances by reconductoring on existing

    structures

  • 14

    3M ACCR

    Project Overview Customer: Hawaii Electric Company (HECO) Project: Pole 810 to Pole 818, Kahuku Location: Hawaii Length & Voltage: 1 conductor mile (1.6 km), .32 circuit

    miles (.5 km); 46 kV line

    Solution: 3M ACCR 477 kcmil (238 mm2)

    Results: Used same tension on existing towers as old conductor Eliminated need for intersets Continuously operating for several years beyond the

    expected life of steel or polymer core conductors in this corrosive environment

    Project Profile: Harsh Environment

  • 15

    3M ACCR

    Project Profile: Harsh Environment

    Project Overview: Customer: Western Area Power Administration

    (WAPA) Project: Jamestown to Fargo Location: Fargo, North Dakota Length & Voltage: 2.5 conductor miles (4 km), .8

    circuit miles (1.3 km); 230 kV line

    Solution: 3M ACCR 795 kcmil (418 mm2)

    Results: Operated during at least 2 heavy ice loading events

    over several years with no failures or measurable degradation

    Operated through extreme cold and hot ambient conditions and high winds

  • 16

    3M ACCR

    Project Profile: Reliability

    Project Overview: Customer: Alabama Power Project: Bynum to Anniston Location: Anniston, Alabama Length & Voltage: 28 conductor miles (45 km), 9

    circuit miles (14.5 km); 230 kV

    Solution: 3M ACCR 1033 (525 mm2)

    Results: Line was upgraded to meet contingency

    requirements Increased transmission capacity to serve

    summer peak loads Eliminated need to replace existing transmission

    structures and install 8 additional structures Reduced time required to fit available outage

    window

    The use of the 3M ACCR Conductor for this project allowed us to avoid the replacement of 22 transmission structures and the installation of eight additional structures. This will significantly reduce our construction time frame and allow the line to be taken out of service for this project without impacting the reliability of our grid. Andy Wallace, Transmission line manager for Alabama Power.

  • 17

    3M ACCR

    Project Profile: Environmentally Sensitive Area

    Project Overview: Customer: Companhia de Transmissao de Energia

    Eletrica Paulista (CTEEP) Project: Jup-Tri Paran River crossing Location: Border of So Paulo and Mato Grosso do

    Sul States, Brazil Length & Voltage: 12 conductor miles (19 km), 2

    circuit miles (3.2 km); double circuit 138 kV

    Solution: 3M ACCR 300 kcmil (150 mm)

    Results: Increased capacity by 220% Completed the river crossing using only existing

    towers, and avoided major construction in environmentally sensitive area

    Accommodated required span lengths Provided operational reliability in high winds and

    ambient temperature Conductor Installation finished in 6 days

    The 3M ACCR unique features were essential for us to choose 3M as the supplier for this transmission line. We needed a product that could accomplish the TL needs, while being reliable and cost effective. says CTEEP engineering manager Caetano Cezario Neto.

  • 18

    3M ACCR

    Project Profile: Dense Population and Underbuilt Facilities

    Project Overview: Customer: CPFL Energia Project: Ramal Duratex Location: Jundia-SP, Brasil Length & Voltage: 12 conductor miles (19 km)

    2 circuit miles (3 km), 88 kV

    Solution: 3M ACCR 336 kcmil (171 mm)

    Results: Capacity was increased by 50% Avoided need for new towers in densely

    populated urban area Left residences along narrow right-of-way

    undisturbed during and after installation We studied several options and decided that 3M ACCR provides the most reliable, cost-effective solution for delivering more power through a dense neighborhood without creating numerous logistical problems.

    We were impressed by its high-performance results in other applications where new tower construction was undesirable. We were also pleased that our transmission line installation process went very

    smoothly and everything is working as designed. Paulo Ricardo Bombassaro, engineering and planning manager for CPFL Energia.

  • 19

    3M ACCR

    Project Profile: Underbuilt & Capacity Increase

    Project Overview: Customer: TATA Power Project: Borivali to Malad Location: Mumbai, India Length & Voltage: 120 conductor miles (193 km), 10

    circuit miles (16 km), 110 kV double circuit, twin bundled

    Solution: 3M ACCR 300 T-16 kcmil

    Results: Capacity was increased from 900 amps to 2,000

    amps just 2 years after last upgrade Resolved sag issue affecting hutments built under the

    power lines Completed installation without disturbing residences

  • 20

    3M ACCR

    Project Profile: Reliability

    Project Overview: Customer: Silicon Valley Power Project: Palm Sub Project Location: Santa Clara, California Length & Voltage: 17.6 conductor miles (28 km), 3

    circuit miles (4.8 km), 60 kV

    Solution: 3M ACCR 715 (365mm2)

    Results: Increased ampacity by 84% for growing substation loads Used only existing towers and right of way for existing

    line Matched tower heights with existing line for 2 new

    sections Re-energized existing portion of line every evening to

    maintain reliable service Worked around railroad crossings and highways to install Delivered a reliable solution for sensitive high-tech

    customers

    Using the cutting-edge aluminum matrix conductor minimized disturbance for our customers while accommodating the growing demand for power capacity in the area. Employing the latest technology also means less maintenance and more reliability and we have plenty of capacity for rapid response to customers increases in load requirements over the next 15 to 20 years. - John Roukema, Director of SVP.

  • 21

    3M ACCR

    Project Profile: Capacity Increase

    Project Overview: Customer: Chita Project: Line 64-65 Location: Siberia, Russia Length & Voltage: 7.3 conductor miles

    (11.3km), 1.3 circuit miles ( 1.8km) ; 110 kV

    Solution: 3M ACCR 477-T13 (Flicker)

    Results: Increased ampacity by 243% Reused existing towers without affecting under-

    built facilities Provided a reliable solution in extreme ambient

    temperatures

  • 22

    3M ACCR

    Project Profile: Ampacity Upgrade

    Project Overview: Customer: MOESK Project: Ochakovo-Odintsovo Location: Moscow, Russia Line Length: 60 conductor miles (97 km), 10 circuit

    miles (16.1 km); 115 kV

    Solution: 3M ACCR 477-T16 (Hawk)

    Results: Increased ampacity 98% by replacing ACSR 240/32

    with 3M ACCR 477-T16 Saved time Reused existing towers Provided a reliable solution for area with extreme

    temperatures and heavy ice and wind loads

  • 23

    3M ACCR

    Project Profile: River Crossing

    Project Overview: Customer: CPFL Paulista Project: Iacanga Substation Location: Sao Paulo, Brazil Length & Voltage: 3.8 conductor miles (6.1 km),

    .062 circuit miles (1 km); 138 kV double circuit

    Solution: 3M ACCR Type 336 kcmil

    Results: Eliminated need for tower on island submerged

    during flooding of the Tiet River Avoided the delay of waiting until mid-year for river

    to possibly subside Better control over the overall project costs Lower construction risks and environmental impacts Standard maintenance (no need for boats) Ampacity equivalent to ACSR Hawk 477 kcmil

    installed on the rest of the line

    Building the foundation and tower on submerged land would have posed engineering difficulties; waiting until mid-year for the river possibly to subside would have caused unreasonable delay. Using 3M ACCR was a far more desirable alternative - less costly, and safer for the construction team. - Paulo Ricardo Bombassaro, engineering and planning manager for CPFL Energia.

  • 24

    3M ACCR

    Current Installations Name Reason for Installation YearXcel Energy Minneapolis/St. Paul MN Installation validation 2001HECo Oahu HI Waialua-Kahuku Oahu Corrosive environment 2002Western Fargo ND Jamestown to Fargo Heavy ice/wind loads 2002BPA Washington State WA Pasco High temp operation 2004Western Phoenix AZ Liberty Substation Installation validation 2004SRP Phoenix AZ Santan Generating Plant High current operation 2004

    PG&E Santa Clara CA Northern Receiving Station to Scott High temp operation 2005

    SDG&E San Diego CA EPRI test EPRI test 2005

    Xcel Energy Minneapolis/St. Paul MN Blue Lake to Black DogEnvironmentally sensitive areaRiver crossing

    2005

    APS Phoenix AZ Phoenix Metro Trunkline Dense population and underbuilds 2006

    Western AZ/CA border Topock to Davis High growth 2007Shanghai Power Shanghai, China YangGao to XinZhou Cost and time savings 2007Platte River Fort Collins CO Timberline to Harmony Reliability 2007Aha Macav Needles CA Firehouse to No Name Reliability 2008

    Allegheny Power West Virginia Bedington to Nipetown Underbuilt facilitiesCost and time savings 2008

    British Columbia Transmission Company (BC Hydro) Canada

    Sansum and Montague Crossings River crossing 2008

    Dominion Virginia Power West Virginia VA Loudon to Brambleton Underbuilt facilities 2008

    3M ACCR Commercial Installations

  • 25

    3M ACCR

    *Installation scheduled or underway

    Current Installations Name Reason for Installation Year

    Alabama Power Alabama AL Miller Substation Underbuilt facilitiesLoad growth 2008

    Silicon Valley City of Santa Clara CA Center LoopEnvironmental and aestheticsReliability

    2008

    Chongqing Chongqing, China Shuinian to Shuangshan Load growthTime savings 2008

    Silicon Valley City of Santa Clara CA Palm SubEnvironmental and aestheticsReliability

    2009

    CTEEP Sao Paulo, Brazil Jup-ValCost, time and environmental impact savings

    2009

    Confidential Europe Load growth 2008TATA Power India Salsette to Saki Load growth 2009TATA Power India Borivali to Malad Load growth 2009OAO Chita Energo Chita, Russia Line 64-Line 65 Load growth 2008

    Alabama Power AL Bynum to Anniston Cost and time savings 2008

    Confidential Southeastern U.S. Maximum amps 2009

    Confidential Southeastern U.S. Delivery timeMax amps 2009

    Confidential Southeastern U.S. New clearance issue 2009

    CPFL Varzea Paulista, Brazil Ramal to DuratexLoad growthCost and time savingsSocial impacts

    2009

    Confidential China Link to substation 2009

    3M ACCR Commercial Installations

  • 26

    3M ACCR

    Current Installations Name Reason for Installation Year

    Xcel Energy St. Paul MN 3M Center Line Load growthCost savings 2009

    Confidential China Substations 2009Confidential China Substations 2009E.ON Netz GmbH* Germany Ostermoor-Marne Pilot line 2009Confidential* Europe Pilot line 2010

    Amprion GmbH Germany Hanekenfhr-Gersteinwerk Pilot line 2009

    Confidential* Eastern U.S. New clearance issue 2009

    Confidential* Western U.S. New clearance issueMaximum amps 2009

    Confidential CarribeanMaximum ampsCorrosive environmentHeavy winds

    2009

    CPFL* Varzea Paulista, BrazilIacanga Substation Tiet River Crossing

    Tight timelineEnvironmental impactsRisk of construction problems

    2010

    Confidential Midwest U.S. Maximum ampsReduce number of towers 2010

    Confidential* Europe Pilot line 2010Confidential* China 2010

    Confidential* BrazilEnvironmental impactsPermittingMaximize amps

    2010

    Confidential* Western U.S. 2010

    * Installation scheduled or underway

    3M ACCR Commercial Installations

    3M ACCRCase StudiesProject Profile: Large Ampacity UpgradesProject Profile: Long-span Water CrossingProject Profile: Challenging TimelinesProject Profile: Challenging TimelineProject Profile: Densely Populated or Underbuilt AreaProject Profile: Densely Populated or Underbuilt AreaProject Profile: ReliabilityProject Profile: N-1 ReliabilityProject Profile: New ConstructionProject Profile: Large Ampacity Upgrade Project Profile: Thermal Upgrade With Changing Clearance RequirementsProject Profile: Ampacity UpgradeProject Profile: Harsh EnvironmentProject Profile: Harsh EnvironmentProject Profile: ReliabilityProject Profile: Environmentally Sensitive AreaProject Profile: Dense Population and Underbuilt FacilitiesProject Profile: Underbuilt & Capacity IncreaseProject Profile: ReliabilityProject Profile: Capacity IncreaseNmero do slide 22Project Profile: River CrossingNmero do slide 24Nmero do slide 25Nmero do slide 26