4. project planning & scheduling pm0002 sem-3

Upload: mohammed-irfan

Post on 30-May-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    1/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    PROJECT PLANNING & SCHEDULING -PM0002

    MBA SEMESTER 3

    ASSIGNMENT (SET 1)

    Q1. Distinguish between value engineering &value analysis. Briefly explain the techniques used in value management?

    Ans: Value engineering: (VE) is a systematic method

    to improve the "value" of goods or products and services by using an examination of function. Value, as

    defined, is the ratio of function to cost . Value can

    therefore be increased by either improving the function

    or reducing the cost . It is a primary tenet of value

    engineering that basic functions be preserved and not be reduced as a consequence of pursuing value

    improvements.

    VE follows a structured thought process that is

    based exclusively on "function", i.e. what something

    "does" not what it is. For example a screw driver that isbeing used to stir a can of paint has a "function" of

    mixing the contents of paint can and not the original

    connotation of securing a screw into a screw-hole. In

    value engineering "functions" are always described in a

    LEARNING CENTRE JEDDAH Page 1 of 18MBA III Semester Assignment

    http://en.wikipedia.org/wiki/Costhttp://en.wikipedia.org/wiki/Costhttp://en.wikipedia.org/wiki/Costhttp://en.wikipedia.org/wiki/Cost
  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    2/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    two word abridgment of an active verb and measurable

    noun (what is being done - the verb - and what it is

    being done to - the noun) and to do so in the most non-

    prescriptive way possible. In the screw driver and can of paint example, the most basic function would be "blend

    liquid" which is less prescriptive than "stir paint" which

    can be seen to limit the action (by stirring) and to limit

    the application (only considers paint.) This is the basis

    of what value engineering refers to as "function

    analysis".

    Value analysis is an approach to improving the value of

    a product or process by understanding its constituent

    components and their associated costs. It then seeks to

    find improvements to the components by either reducing their cost or increasing the value of the

    functions.

    How Does It Work?

    To understand value analysis it is necessary to

    understand some key concepts:Value: the ratio between a function for customer

    satisfaction and the cost of that function.

    LEARNING CENTRE JEDDAH Page 2 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    3/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    Function: the effect produced by a product or by

    one of its elements, in order to satisfy customer

    needs.

    Value analysis: methodology to increase thevalue of an object the object to be analyzed could

    be an existing or a new product or process, and it is

    usually accomplished by a team following a work

    plan.

    Need: something that is necessary or desired by

    the customer.

    Value Management uses a unique combination of

    concepts and methods to create sustainable value for

    both organizations and their stakeholders.

    Some tools and techniques are specific to Value

    Management and others are generic tools that many

    organizations and individuals use. Detailed below is a

    summary of some of the main tools and techniques.

    Value = Function or objective / cost i.e. getting what you require/ for what you will pay

    Tool Description Benefits

    LEARNING CENTRE JEDDAH Page 3 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    4/18

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    5/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    journey (possible

    excursion). Moves

    delegated away from a

    problem tosomewhere where

    creativity flourishes.

    The return journey

    often releases such

    creativity and ideas

    that would not

    normally be evident

    used as a precursor to

    brainstorming or other

    idea generation tells.

    Function

    Analysis

    System

    Technique

    (fast)

    Identification of

    functions (at the heart

    of Value Management)

    of products, processes, projects or

    services. Focused on

    client needs and

    wants.

    Determines what

    functions are delivered

    i.e. what they do or

    must do, not what they are (avoiding solution

    mode). The FAST

    diagram works by

    asking how the

    functions (primary and

    secondary) relate to

    each other by ask How

    and Why questions o

    check the logic works.

    LEARNING CENTRE JEDDAH Page 5 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    6/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    Later costs are added

    to functions to assist in

    indentifying any VM

    mismatches or areas of over engineering

    Objective

    s

    Hierarchy

    Diagrammatic process

    for indentifying

    objectives in a

    hierarchical manner.

    Often used in

    conjunction with

    functions.

    Assists in focusing

    input where the key

    objectives are as the

    diagram is constructed

    is descending order.

    Issues

    Generati

    ons and

    Analysis

    A way of eliciting

    many issues

    connected with a

    problem or

    opportunity. Team

    members write down

    their issues on post-it

    notes and they are

    displayed on the wall

    under appropriate

    categories or

    groupings .e.g.

    Voting of the top 10

    important issues

    follows. Actions to

    address issued then

    explored.

    LEARNING CENTRE JEDDAH Page 6 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    7/18

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    8/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    superfluous items in

    the process for

    corrections.

    Risk

    Analysis

    A structured approach

    to indentify risks that

    could affect project,

    product, process or

    service success. Risks

    are identified,

    evaluated (in terms of

    cost, time, other

    impact) and robust

    action planning

    applied.

    Often used in parallel

    with Value

    Management as there

    are genuine links. Assists decision making

    or option selections.

    Stake

    holder

    Analysis

    Indentifies those key

    stakeholders (group of

    individuals) with an

    influence or interest in

    project, product,

    process or service.

    Can assist in focusingattention where the

    priorities are required

    i.e. satisfaction of key

    stakeholder interests.

    SWOT Analysis

    Indentifies strengths,weakness,

    opportunities and

    threats. A tool used in

    many organization to

    Assists inunderstanding

    strengths, weaknesses,

    opportunities and

    threats that can impact

    LEARNING CENTRE JEDDAH Page 8 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    9/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    assist in focusing

    activities where

    required and minimize

    those items that canimpact negatively.

    on an organization ,

    individual, product or

    process

    Value

    Analysis

    Structured team based

    approach to

    indentifying functional

    requirements of

    projects, products,

    processes or services.

    Optimization and

    maximization or value

    to the client or

    customer. Optimum

    balance between

    function and cost

    without detriment to

    quality 5Ws and

    H

    A technique for

    exploring problems

    which provokes further

    depth of questioning

    about the dimensions

    framing the problems

    or opportunity

    Who- e.g. is

    responsible?

    Why e.g. is the end

    date important?

    What e.g. what would

    happen if the scheme

    were delayed?

    When e.g. must the

    work start?

    Where e.g. might the

    problem occur?

    LEARNING CENTRE JEDDAH Page 9 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    10/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    How e.g. might we do

    this seemingly

    impossible thing?

    SCAMPER

    Used as checklist todevelop ideas by

    applying separate

    verbs to chosen ideas

    singly or together with

    others. E.g. combine,amend, modify, put to

    other use, expand,

    reverse /reduce.

    This could help with

    moving an idea from a

    creative thought to a

    more practical use,

    expand on the concept

    behind ideas, find

    different ways of

    expressing the idea,

    provoked new ideas,

    etc.

    Value Management is a structured team based

    approach to identify functional requirements of projects/contracts to achieve Optimum Function for

    Minimum Cost

    Q2. What is meant by project viability? How do

    you assess financial viability of a project?

    Project viability

    The rationale for the project is set out in the business

    case which will be expressed in terms of a set of

    LEARNING CENTRE JEDDAH Page 10 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    11/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    benefits which contribute towards strategic goal(s). The

    project framework and planning should be written to

    ensure that achievement of those benefits is

    maximized.

    Many things can affect project viability

    1. Cost overruns. If the project is based on a rate of

    return on capital invested, then an increase in

    project costs can eliminate this

    2. Time overruns. Some projects have to be delivered

    within a certain time frame to deliver benefits.

    Extending time may completely eliminate the

    benefits.

    3. Changes to specifications and scope. As projects

    progress changes to the plan or even the scope will

    inevitably be requested. These need to be carefully

    assessed against the continued ability to deliver the

    benefits

    4. Quality problems. It may become clear during the

    project life cycle that the original quality

    expectations cannot be met. This can have an

    impact on the acceptability and hence the usability

    LEARNING CENTRE JEDDAH Page 11 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    12/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    of the project's outputs by the end user. Changes to

    quality must be assessed against the benefits.

    5. Change in the business environment. Sometimes

    organisations have to take a different strategic

    path, making the need for the project obsolete.

    There is little point carrying on committing

    resources to a project for which there is no longer a

    need.

    Assessing Financial Viability of the Project

    Certain tools help us assess the financial viability of any

    project where investment is contemplated. We will

    discuss some tools in brief.Tools that determine the adequacy of the surplus:

    RETURN ON INVESTMENT (ROI)

    As we know, a project collects funds from two sources

    for long-term investment.

    The amount collected is used to create assets and

    operation, which generates surplus for the enterprise.

    Surplus is required to be distributed to the contributors

    of the funds. Interest is the compensation given to

    LEARNING CENTRE JEDDAH Page 12 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    13/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    contributors of borrowed capital, and net profit and

    depreciation are given to contributors of own capital.

    Why should one add depreciation here? Though

    depreciation reduces profit, it is a non-cash provisionmade to recover the original investment. Thus, the cash

    profit of the enterprise is increased to the extent of

    depreciation.

    Acceptance Rule

    For the investment to be financially viable, the RoI

    should be greater than the cost of investment.

    DEBT SERVICE COVERAGE RATIO (DSCR)

    Running an enterprise with financial support from

    banks/financial institutions requires their loans to be

    repaid with interest. Therefore, an entrepreneur must

    generate surplus, adequate to meet repayment

    obligations

    Acceptance Rule

    A project is considered financially viable if the

    cumulative DSCR during repayment period is at least

    2:1

    BREAK-EVEN POINT (BEP)

    This is another important tool. The break-even point is

    the level of activity where the total contribution is equal

    LEARNING CENTRE JEDDAH Page 13 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    14/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    to the total fixed cost. Contribution is the excess of

    sales over variable cost,

    DEBT-EQUITY RATIO

    This ratio indicates the extent to which the promotersfunds are leveraged to procure loans. The formula of

    DER is:

    Contribution = Sales Variable Cost

    A higher debt equity ratio indicates more risk due to a

    higher fixed cost of interest. The BEP of such enterprises

    will go up.

    Q3. Explain work breakdown structure of aconstruction activity with example.

    Ans: A work breakdown structure (WBS) in project

    management and systems engineering , is a tool used to

    LEARNING CENTRE JEDDAH Page 14 of 18MBA III Semester Assignment

    http://en.wikipedia.org/wiki/Project_managementhttp://en.wikipedia.org/wiki/Project_managementhttp://en.wikipedia.org/wiki/Systems_engineeringhttp://en.wikipedia.org/wiki/Project_managementhttp://en.wikipedia.org/wiki/Project_managementhttp://en.wikipedia.org/wiki/Systems_engineering
  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    15/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    define and group a project 's discrete work elements (or

    tasks ) in a way that helps organize and define the total

    work scope of the project

    A work breakdown structure element may be a product ,

    data , a service , or any combination. A WBS also

    provides the necessary framework for detailed cost

    estimating and control along with providing guidance for

    schedule development and control. Additionally the WBS

    is a dynamic tool and can be revised and updated asneeded by the project manager .

    The Work Breakdown Structure is a tree structure , which

    shows a subdivision of effort required to achieve an

    objective; for example a program , project , and contract .

    In a project or contract, the WBS is developed by

    starting with

    the end objective and

    successively subdividing it into manageable

    components

    in terms of size, duration, and responsibility (e.g.,

    systems, subsystems, components, tasks, subtasks,

    and work packages)

    LEARNING CENTRE JEDDAH Page 15 of 18MBA III Semester Assignment

    http://en.wikipedia.org/wiki/Projecthttp://en.wikipedia.org/wiki/Task_(project_management)http://en.wikipedia.org/wiki/Product_(business)http://en.wikipedia.org/wiki/Datahttp://en.wikipedia.org/wiki/Service_(economics)http://en.wikipedia.org/wiki/Project_managerhttp://en.wikipedia.org/wiki/Tree_structurehttp://en.wikipedia.org/wiki/Program_managementhttp://en.wikipedia.org/wiki/Projecthttp://en.wikipedia.org/wiki/Contracthttp://en.wikipedia.org/wiki/Projecthttp://en.wikipedia.org/wiki/Task_(project_management)http://en.wikipedia.org/wiki/Product_(business)http://en.wikipedia.org/wiki/Datahttp://en.wikipedia.org/wiki/Service_(economics)http://en.wikipedia.org/wiki/Project_managerhttp://en.wikipedia.org/wiki/Tree_structurehttp://en.wikipedia.org/wiki/Program_managementhttp://en.wikipedia.org/wiki/Projecthttp://en.wikipedia.org/wiki/Contract
  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    16/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    which include all steps necessary to achieve the

    objective

    W ork is effort performed by people to transform or create

    products, to solve identified problems or to satisfy specific

    needs. Just as the Implementing Agency hierarchically

    structures the people who perform work, so the work

    breakdown structure hierarchically structures the products/

    deliverables to be produced.

    In order to use the work breakdown structure as a

    framework for structuring the technical objectives of a

    project in addition to its use as a management tool for cost

    and schedule control- it is important that the work

    breakdown structure be productoriented. Its elements

    should represent identifiable work products whether they

    are goods, equipment, software, data, infrastructure

    elements or service products.

    LEARNING CENTRE JEDDAH Page 16 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    17/18

    Sikkim Manipal University ProjectPlanning & Scheduling PM0002

    Sample WBS of Construction:

    LEARNING CENTRE JEDDAH Page 17 of 18MBA III Semester Assignment

  • 8/9/2019 4. Project Planning & Scheduling PM0002 Sem-3

    18/18