the formwork to the millau viaduct - the forming of the bridge piers

104
The Formwork to The Millau Viaduct ice Ireland Engineers Ireland Nov 2007

Upload: dothu

Post on 05-Jan-2017

277 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Formwork to The Millau Viaduct

ice Ireland

Engineers Ireland

Nov 2007

Page 2: The Formwork to the Millau Viaduct - the forming of the bridge piers

Tonight’s Menu

� Introduction

� Background

� The Deck

� The Pier Bases

� The Piers

� The system used for climbing

� Shape and the challenges in forming it

� The philosophy behind the formwork engineering

� On the Way Up

� The completed Piers

� The Toll Plaza Canopy

� Conclusion

� What did we get for the money

Page 3: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Framework of the Presentation

� Background to the bridge

� Why it was built

� Where it is

� Who provided initial design

� How it came to look the way it does

� When it started and was finished

� What it is made of

Page 4: The Formwork to the Millau Viaduct - the forming of the bridge piers

Where

� A75 Motorway link from Clermont Ferrand to Berziers

Page 5: The Formwork to the Millau Viaduct - the forming of the bridge piers

Satellite Photo of the Trace

Page 6: The Formwork to the Millau Viaduct - the forming of the bridge piers

Why

� That stretch is missing link in motorway route from

Paris to Barcelona

� Before viaduct traffic drove down into the valley and

through the town of Millau

� August regularly saw delays of 5 hrs+ in Millau, which

gridlocked an entire town

Page 7: The Formwork to the Millau Viaduct - the forming of the bridge piers

Millau

Page 8: The Formwork to the Millau Viaduct - the forming of the bridge piers

Background to Design

� Originally designed by Michel Virlogeux whose concept was taken up by

Sir Norman Foster’s practise

� Pont de Normandie

� Wishbone Pylon and Cable Stay

� Briefly the longest cable stay span in the world

Page 9: The Formwork to the Millau Viaduct - the forming of the bridge piers

Design

� The slender design of the Virlogeux/Foster Viaduct was chosen but had a contrasting pier design to the Pont De Normandie

� The wide based Wishbone of the Normandie Piers had become a very slender “Y” shape for Millau

� High Level Wind Loads in Valley created a weak point in the wishbone

� One of the Millau piers is 4 times higher than the Normandie piers

Page 10: The Formwork to the Millau Viaduct - the forming of the bridge piers

The “Open Hands” Pier Design

� The Single main stem with transition to “Open Hands”

deck support gave best accommodation of wind loads

in the upper levels of the Tarn Valley.

� The Main Stem is hollow with internal cross slabs.

� The point of bifurcation is solid

� The twin piers are hollow

� Designed for 200km/h winds at deck level

Page 11: The Formwork to the Millau Viaduct - the forming of the bridge piers

Why was this design chosen

� Slender lines had least impact on environment of the valley

� Visually Stunning

� Had potential to make a striking architectural statement

� Kept traffic right out of Millau

� In March 2001 Eiffage TP won the contract to construct with a 75 year concession to operate (which can be removed if proves too profitable!)

� Deck was curved to a 20km radius to avoid sensation of “dreaming” or “flying”, and to allow sight of all pylons

Page 12: The Formwork to the Millau Viaduct - the forming of the bridge piers

Don’t trip out at the wheel

Page 13: The Formwork to the Millau Viaduct - the forming of the bridge piers

Framework…..

� The Deck

� Vital Statistics

� What that means for the piers

� Why it is curved

� How it was moved

Page 14: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Deck

� Is a trapezoidal Box Girder design

� If made from reinforced concrete it would be 7m deep and weigh c. 200,000 tonnes

� By making it in steel, the deck can reduce in depth to 4m, and in weight to 36,000 tonnes

� However, the reduction in dead weight on to the pier heads meantthat the deck would need stressing tendons down to the bifurcation point for stability.

� This adds 6,000 tonnes load per pier

� The dead weight of the single pier section is sufficient for stability

Page 15: The Formwork to the Millau Viaduct - the forming of the bridge piers

More Vital Statistics

� Carries 10,000 tonnes of tarmac on main carriageways and another

4,000 tones on hard shoulders

� Each pylon anchoring the cable stays is steel and weighs 700

tonnes

� Each Main Cable can take tensile load equivalent to 25 Jumbo Jets

at full thrust

� Steel of the cable stays adds 1500 tonnes to the overall weight

Page 16: The Formwork to the Millau Viaduct - the forming of the bridge piers

Deck Movement

� Hydraulic “Lift and move” Rams - Enerpac

Page 17: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Movement of the Deck

Page 18: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Enerpac Rams

Page 19: The Formwork to the Millau Viaduct - the forming of the bridge piers

Let’s now start at the Bottom

� In order to get from abutment to abutment, 14km of

road were constructed including a temporary bridge

over the Tarn.

� The Pier Bases

� Concentrate on Pier No.2 (P2) as this is the tallest

� Soil is principally Limestone and riddled with caves and

fissures containing bacteria used in the making of the

region’s main export……..

Page 20: The Formwork to the Millau Viaduct - the forming of the bridge piers

Roquefort Cheese

Page 21: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Foundations

� Each pier is founded on a plate or base, and four posts

or piles

� The piles are each 5m diameter and extend down to a

max depth of 14m

� On top is the base itself, which for P2 is 6m deep

� The Initial Launch pour for the pier is conventionally

shuttered

Page 22: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Base Plate

� As a solid concrete entity, base was too

big to tie shutters conventionally so each

base shutter was supported with PERI SB

Brace Frames anchored into purposely

laid rc base

� The piers together required 10,000

tonnes of reinforcement steel

� The bases required 13, 450 tonnes of

rebar

� The piles required 1,200 tonnes of rebar

� The piles alone used 6,000m3 of concrete

Page 23: The Formwork to the Millau Viaduct - the forming of the bridge piers

Pouring the Launch Pour

Page 24: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Piers

Page 25: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Piers

� Slender pier designed as “running, tapered octagon”

� Seven no. piers in total, similar shape from deck down,

but differing heights

Page 26: The Formwork to the Millau Viaduct - the forming of the bridge piers

Pier Heights

Page 27: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Pier Elevations

� Each Pier continually tapers in both planes from base to top

� In general, each pier is identical from the road deck down

� For a distance of 90m from the deck, a twin pier is used

� 90m below deck is a transition point where twin pier becomes a single pier

� Pier no.2 is benchmark at 245m high

� All others are “cut from below”

� MUST FIND A WAY TO CLIMB FORMWORK 90m

Page 28: The Formwork to the Millau Viaduct - the forming of the bridge piers

How To Construct the Pier

� It was decided to pour the pier in 4m lifts using a climbing form system

� Ideally it would go something like this

Page 29: The Formwork to the Millau Viaduct - the forming of the bridge piers

So how do we climb? - We asked an Expert

� An automatic rail climbing system (ACS)

� Formwork Shutter and Work platforms are integral

� Hydraulic Rams push shutter and carriage up the rail

� Rail runs through shoes fixed to concrete

� Rams lift rail up when carriage is fixed in position

Page 30: The Formwork to the Millau Viaduct - the forming of the bridge piers

Basic System Used Worldwide

Weichsel Bridge Warsaw

Petronas TowersAndromeda Tower

Page 31: The Formwork to the Millau Viaduct - the forming of the bridge piers

Mega Bridge Bangkok

Page 32: The Formwork to the Millau Viaduct - the forming of the bridge piers

Sharq Building Kuwait

Page 33: The Formwork to the Millau Viaduct - the forming of the bridge piers

And Many More…………

North Danube Bridge, Hungary Turning Torso, Malmo

Page 34: The Formwork to the Millau Viaduct - the forming of the bridge piers

And at Millau

Page 35: The Formwork to the Millau Viaduct - the forming of the bridge piers

Section Through a Complete External Climbing Unit

Struts punch against

wall

Lattice with

suspended formwork

elements

Self climbing system

ACS with hydraulic ram

(caterpillar)

Rail

Climbing Shoe

Pouring Platform

Finishing Platform

Page 36: The Formwork to the Millau Viaduct - the forming of the bridge piers

One Complete Lift of the Shutter and Carriage

Page 37: The Formwork to the Millau Viaduct - the forming of the bridge piers

How the Rail is Lifted

Page 38: The Formwork to the Millau Viaduct - the forming of the bridge piers

Section Through a Complete External Climbing Unit

Struts punch against

wall

Lattice with

suspended formwork

elements

Self climbing system

ACS with hydraulic ram

(caterpillar)

Rail

Climbing Shoe

Pouring Platform

Finishing Platform

Page 39: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Anchors

Page 40: The Formwork to the Millau Viaduct - the forming of the bridge piers

Advantages of the ACS System

� Self Climbing – Can climb without crane

� Carries the shutters on retracting carriage so all shutter

work can be done “on board”

� Carries follow up platform for “finishing off” tasks

� Can operate in 180km/h winds

� Acts as windshield for rebar fixing and internal work

� Allows all shutter modifications

Page 41: The Formwork to the Millau Viaduct - the forming of the bridge piers

ACS

� ACS is a self contained system that allows pure

repetition of procedure with each climb, simplifying

high rise concrete construction, and offering

tremendous speed of turn round.

Page 42: The Formwork to the Millau Viaduct - the forming of the bridge piers

Advantages of 4m lift heights

� Straightforward shutter maintenance on deck

� Easier control of concrete pours

� Highly accurate plumbing of shutters

� Greater adherence to performance tolerances

� Optimum positioning of ties

� One level in pour means less hole plugging

� Allows 3 day pour cycle.

� Allows maximum repetition of procedure – actually very logical

Page 43: The Formwork to the Millau Viaduct - the forming of the bridge piers

Strict Formwork tolerances

� All edges are sharp and straight

� No horizontal board lines within the 4m

pour

� Minimum no. of Ties and regular tie

pattern and level

� Regular and unobtrusive anchor pattern

� 0.5mm tolerance on vertical panel joints

� Max allowed 5mm deflection over 2m

length of shutter face plate

� Trapezoidal inverse beading delineates

pours

Page 44: The Formwork to the Millau Viaduct - the forming of the bridge piers

The concrete and the shutter

� 60N/mm strength

� Generated face pressure on shutter of 100kN/m2

� Reduce ties by tying over top of pour

� Consequently use steel faced and backed shutter

Waler for Tie positions

Page 45: The Formwork to the Millau Viaduct - the forming of the bridge piers

Pier Profile

� RunningTaper design means pier footprint changes dramatically

� P2 starts at 27m x 18m and tapers to 14.4m x 16.13m in single section

� Twin section tapers from 14.4m x 16.13m to 11m x 15.5m

� Need formwork system that can accommodate that change in layout

� With a pier involving over 60 pours, each one is different!!!!!,

� Each subsequent pour is 4m further off the ground

Page 46: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Changing Face of the Formwork

Page 47: The Formwork to the Millau Viaduct - the forming of the bridge piers

In Conclusion, the challenge is………

� To take a system based on repetition and use it on a

job with NO REPETITION in the climb whatsoever.

Page 48: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Shutter - How do we cope with changing Geometry ?

� Adaptaptability –

� Identify areas that remain Constant

Page 49: The Formwork to the Millau Viaduct - the forming of the bridge piers

Viaduc de Millau

� Description of the formwork solution

� External Formwork

Basic element

Basic element

Box out

Compensation

elements

Page 50: The Formwork to the Millau Viaduct - the forming of the bridge piers

External Shutter Adaptation

Adaptation to the

geometry

Telescopic Waler

Sliding Corner

Page 51: The Formwork to the Millau Viaduct - the forming of the bridge piers

Telescopic Waler

Telescopic steel waler in

compensation area

Rear of Steel Shutter

Page 52: The Formwork to the Millau Viaduct - the forming of the bridge piers

Shutter rises and closes (exaggerated)

Page 53: The Formwork to the Millau Viaduct - the forming of the bridge piers

Corner Closes (exaggerated)

Page 54: The Formwork to the Millau Viaduct - the forming of the bridge piers

Sliding Corner

Page 55: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Corner Pieces

Articulated corner connectionCorner connection in

compensation area

Page 56: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Platforms need to Adapt Also

Telescopic area

Removables

Page 57: The Formwork to the Millau Viaduct - the forming of the bridge piers

Internal Platforms

Telescopic area

Page 58: The Formwork to the Millau Viaduct - the forming of the bridge piers

Internal Climbing System

� Every 8 lifts a concrete cross slab is cast internally

� Prevents continued use of rail climbing system

� Use conventional crane handled “jump” form system

� PERI SKS

Page 59: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Internal Climbing System

� The issues of adaption remain, but here the crane is used

to lift units up and occasionally out.

Page 60: The Formwork to the Millau Viaduct - the forming of the bridge piers

Major Internal Adaptions

� Can crane entire units out for modification

Page 61: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Twin Pier Section

Page 62: The Formwork to the Millau Viaduct - the forming of the bridge piers

Twin Pier Platforms

� Externals

Page 63: The Formwork to the Millau Viaduct - the forming of the bridge piers

Twin Pier Sections

� Internal

Page 64: The Formwork to the Millau Viaduct - the forming of the bridge piers

Don‘t Forget Your Packed Lunch !!!

Page 65: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Finishes

Page 66: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Concrete Finish on the less exposed faces

Page 67: The Formwork to the Millau Viaduct - the forming of the bridge piers

What was Used

� 3 complete sets of formwork and climbing kit for single pier structures (External)

� 3 sets for above (Internal)

� 3 complete sets for twin pier structures (External)

� 3 Sets for above (Internal)

� 1 complete set for the transition area from single to twin pier (Internal and External)

� Kit moved from pier to pier as programme needed

� 6.5km2 of formwork face

� 196 ACS Frames

� 96 SKS Frames (Internal)

� 12 special frames

Page 68: The Formwork to the Millau Viaduct - the forming of the bridge piers

Design Demands

� For those of you who like paperwork………

� 800 Formwork Drawings

� 100 Assembly Plans

� 200 Method Statements

Page 69: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 70: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 71: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 72: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 73: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 74: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 75: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 76: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 77: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 78: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 79: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 80: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 81: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 82: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 83: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 84: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 85: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 86: The Formwork to the Millau Viaduct - the forming of the bridge piers
Page 87: The Formwork to the Millau Viaduct - the forming of the bridge piers

9th December 2003

Page 88: The Formwork to the Millau Viaduct - the forming of the bridge piers

The world’s tallest piers are all completed

Page 89: The Formwork to the Millau Viaduct - the forming of the bridge piers

Not to be outdone……

� PERI’s celebrations were a little more modest………

Page 90: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Finish on the Exposed Faces

Page 91: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Peerless Piers

Page 92: The Formwork to the Millau Viaduct - the forming of the bridge piers

Millau My - What a Bridge !.....

Page 93: The Formwork to the Millau Viaduct - the forming of the bridge piers

A perspective on the height……..

� The Royal Gorge Bridge, Colorado

Page 94: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Millau Toll Plaza

Page 95: The Formwork to the Millau Viaduct - the forming of the bridge piers

The “Segment Factory”

� Segments or Elements cast inside factory shutter

� Since segments were to be joined in final construction the neighbouring segment was cast above.

� Used Ceracem instead of Reinforced concrete

Page 96: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Queen Bee and her Offspring

Page 97: The Formwork to the Millau Viaduct - the forming of the bridge piers

Pre-Cast Elements

Page 98: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Finished Article

� A 98m x 28m Concrete Canopy

� Bolted and tensioned Segments

� Locates on 4 pairs of “trees”

� 4km from viaduct

� Stunning Gateway to an inspiring structure

Page 99: The Formwork to the Millau Viaduct - the forming of the bridge piers

The Millau Viaduct

� 2.46km Long on a 20km radius

� The longest multiple cable stay bridge in the world

� The Tallest bridge piers in the world (244.96m)

� One third taller than the previous tallest

� Tip of the Pylon is 343m high

Page 100: The Formwork to the Millau Viaduct - the forming of the bridge piers

Timeline

� 16th October 2001

� Construction Starts

� November 2002

� P2 reaches 100m height

� 26th February 2003

� Deck launch begins

� 28th May 2003

� P2 clears 180m to surpass Kochertal Viaduct and become world’s tallest pier

� November 2003

� Completion of the piers

� 26th March 2004

� Southern deck reaches P3

� 4th April 2004

� North Deck reaches P2

� 28th May

� The Decks meet

Page 101: The Formwork to the Millau Viaduct - the forming of the bridge piers

16th December 2004

Page 102: The Formwork to the Millau Viaduct - the forming of the bridge piers

Its Open at Night, Too

Page 103: The Formwork to the Millau Viaduct - the forming of the bridge piers

So what do you get for your 400m Euros

� 700,000 visitors in first 9 months

� In summer now gets up to 50,000 vehicles per day

� Of Course, you could always have …………….

Page 104: The Formwork to the Millau Viaduct - the forming of the bridge piers

A Regional Icon A Global Structure