synchrophasor-based emergency generation dispatch...independent synchrophasor infrastructure • the...

20
ISO-NE PUBLIC 2018-06-26 | WASHINGTON, DC Xiaochuan Luo, Eugene Litvinov, Song Zhang BUSINESS ARCHITECTURE AND TECHNOLOGY FERC's 2018 Technical Conference Synchrophasor-based Emergency Generation Dispatch

Upload: others

Post on 19-Jan-2021

19 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

2 0 1 8 - 0 6 - 2 6 | W A S H I N G T O N , D C

Xiaochuan Luo, Eugene Litvinov, Song ZhangB U S I N E S S A R C H I T E C T U R E A N D T E C H N O L O G Y

FERC's 2018 Technical Conference

Synchrophasor-based Emergency Generation Dispatch

Page 2: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Outline

• Motivation – Typical EMS communication network – Loss of SCADA/EMS

• Overview of ISO-NE’s syncrhophasor infrastructure

• Synchrophasor-based emergency operation– Automatic Generation Control (AGC)– Emergency dispatch

• Prototype implementation

• Conclusions and future plans

2

Page 3: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Typical EMS Communication Network

3

Page 4: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC4

318 EMS events (October 2013 – April 2017) from 130 NERC Compliance RegistriesNERC report: Risks and Mitigations for Losing EMS Functions

Page 5: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Loss of SCADA/ICCP/EMS

• Low probability events, such as coordinated cyber or physical attack, EMP or natural hazards may cause complete failure of the SCADA/EMS system.

• Loss of monitoring and control capability– No SE, RTCA, SCED, AGC, etc.

• Staffing of key substations by LCCs, with a periodic update of meter reading and topology to the ISO

• ISO will determine the merit order dispatch manually for the expected change in load or tie schedule to maintain ACE– Manual DDP, if ED network is still available– Verbal manual dispatch by contacting the DE, if ED network is

unavailable

5

Page 6: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Synchrophasor Technology

• Synchrophasor:– Phasor (magnitude and angle)– Precise GPS time stamp – High sampling rates

• 30 to 120 samples per second

• PMU - Phasor Measurement Unit

6

Synchrohasor = Phasor + GPS + high sampling rate

Page 7: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

New England Synchrophasor System

7

ISO-NE PDC

DQMS

External Entity

ISO-NENetwork

• 44 stations• 86 PMUs• 429 Phasors

• NYISO• PJM• MISO

Phasor Point

OSL

State Estimation

APPMV

EIDSN

Page 8: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

New England Synchrophasor System (Cont.)

• Approved Operating Procedure 22 changes, effective December 2017, requiring TOs to install new PMUs at: – All new 345 kV substations– Point of Interconnection (POI) for all new and existing power

plants above 100 MVA– Other locations as designated by the ISO, mainly for IROL

and SOL monitoring

• OP 22 changes will double the existing number of PMUs in the next five years.

8

Page 9: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Independent Synchrophasor Infrastructure

• The synchrophasor infrastructure is independent from the SCADA/EMS system– Separate communication infrastructure with its own circuits,

routers, firewalls, encryption, etc.– Time aligned and synchronized with the GPS clock – MW flow and frequency of tie lines– MW and MVAr Outputs of large power plants at POI (100 MW

and above) – All 345 kV and some 115 kV line flows

• Ideal as a backup for emergency monitoring and control when there is a complete loss of SCADA/EMS

9

Page 10: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Synchrophasor-based Automatic Generation Control (AGC)

• Area Control Error (ACE) is an indicator of a BA to meet its obligation to continuously balance its generation and interchange schedule with its load 𝐴𝐴𝐴𝐴𝐴𝐴𝑝𝑝 = 𝑃𝑃𝑡𝑡𝑡𝑡𝑡𝑡𝑠𝑠𝑠𝑠𝑠𝑡𝑡𝑠𝑠𝑠𝑠𝑠𝑠𝑡𝑡 − 𝑃𝑃𝑡𝑡𝑡𝑡𝑡𝑡(𝑝𝑝) + 10𝐵𝐵(𝑓𝑓𝑎𝑎𝑎𝑎𝑡𝑡𝑎𝑎𝑠𝑠𝑠𝑠𝑠𝑡𝑡𝑠𝑠𝑠𝑠𝑠𝑠𝑡𝑡 − 𝑓𝑓𝑎𝑎𝑎𝑎𝑡𝑡𝑎𝑎 (𝑝𝑝))

𝑃𝑃𝑡𝑡𝑡𝑡𝑡𝑡𝑠𝑠𝑠𝑠𝑠𝑡𝑡𝑠𝑠𝑠𝑠𝑠𝑠𝑡𝑡 - Scheduled net interchange

𝑃𝑃𝑡𝑡𝑡𝑡𝑡𝑡(𝑝𝑝) - PMU measured actual net interchange

𝑓𝑓𝑎𝑎𝑎𝑎𝑡𝑡𝑎𝑎𝑠𝑠𝑠𝑠𝑠𝑡𝑡𝑠𝑠𝑠𝑠𝑠𝑠𝑡𝑡 - Scheduled system frequency (60 Hz)

𝑓𝑓𝑎𝑎𝑎𝑎𝑡𝑡𝑎𝑎 (𝑝𝑝) - PMU measured weight-averaged frequency

𝐵𝐵 - Frequency bias setting (MW/0.1 Hz)

• AGC: dead band, PI controller, low pass filter, AGC setpoints

10

Page 11: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Synchrophasor-based Emergency Generation Dispatch

min�𝑐𝑐𝑡𝑡∆𝑃𝑃𝑡𝑡

𝑠𝑠. 𝑡𝑡. �∆𝑃𝑃𝑡𝑡 = ∆𝐿𝐿 𝑇𝑇 − 𝐴𝐴𝐴𝐴𝐴𝐴𝑠𝑠𝑐𝑐𝑐𝑐𝑡𝑡𝑎𝑎𝑐𝑐𝑠𝑠

∆𝑃𝑃𝑡𝑡𝑅𝑅𝑡𝑡

≤ 𝑇𝑇

𝑃𝑃𝑚𝑚𝑡𝑡𝑐𝑐 ≤ 𝑃𝑃𝑡𝑡0 + ∆𝑃𝑃𝑡𝑡≤ 𝑃𝑃𝑚𝑚𝑎𝑎𝑚𝑚

𝑖𝑖 -- PMU monitored generators 𝑐𝑐𝑡𝑡 -- generator incremental cost ∆𝑃𝑃𝑡𝑡 -- generator delta dispatch amount𝑃𝑃𝑡𝑡0 -- generator output𝑇𝑇 -- dispatch look ahead time (5 minutes)𝑅𝑅𝑡𝑡 -- generation ramp rate ∆𝐿𝐿 -- short term forecasted load change 𝑃𝑃𝑚𝑚𝑡𝑡𝑐𝑐 𝑃𝑃𝑚𝑚𝑎𝑎𝑚𝑚 -- generator economic minimum and maximum operating limits

11

Page 12: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Synchrophasor-based Emergency Operation

12

Loss of SCADA/EMS;ED network is available

Loss of SCADA/EMS;ED network is unavailable

Synchrophasor-based Automatic Generation Control (AGC)

Yes (every 4 seconds) No

Synchrophasor-based Emergency Dispatch

Yes (every 5 or 10 minutes) ; only PMU monitored units

Yes (every 5 or 10 minutes) ; only PMU monitored units

Page 13: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Prototype - A Closed-Loop Simulation Platform

13

Page 14: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Test Case

14

4/22/2018, 16:00 hr. – 17:00 hr., about 900 MW increase

Page 15: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Test Case – w/o Emergency Dispatch

15

0 1000 2000 3000

time [s]

-400

-200

0

200A

CE

[MW

]

0 1000 2000 3000

time [s]

59.9

59.95

60

60.05

60.1

frequ

ency

[Hz]

0 1000 2000 3000

time [s]

-600

-400

-200

0

200

CP

S1

[%]

59.9 59.95 60 60.05 60.1

Frequence [Hz]

-2000

-1000

0

1000

2000

AC

E [M

W]

BAALL o w

Limit

BAALH i g h

Limit

Page 16: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Test Case – with Emergency Dispatch

16

0 1000 2000 3000

time [s]

-200

0

200

AC

E [M

W]

0 1000 2000 3000

time [s]

59.9

59.95

60

60.05

60.1

frequ

ency

[Hz]

0 1000 2000 3000

time [s]

100

120

140

160

180

200

CP

S1

[%]

59.9 59.95 60 60.05 60.1

Frequence [Hz]

-2000

-1000

0

1000

2000

AC

E [M

W]

BAALL o w

Limit

BAALH i g h

Limit

Page 17: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Test Case – Emergency Dispatch (DDP)

17

0 500 1000 1500 2000 2500 3000 3500

time [s]

-0.2

0

0.2

0.4

0.6

0.8

1

DD

P [p

.u.]

Unit 1

Unit 2

Unit 3

Unit 4

Unit 5

Unit 6

Page 18: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Test Case – Emergency Dispatch (MW outputs)

18

0 500 1000 1500 2000 2500 3000 3500

time [s]

0

50

100

150

200

250

300

350

Act

ive

pow

er o

utpu

t [M

W]

Unit 1

Unit 2

Unit 3

Unit 4

Unit 5

Unit 6

Page 19: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC

Conclusions and Future Plans

• Synchrophasor infrastructure is independent from the SCADA/EMS system

• Synchrophasor based AGC and emergency dispatch can be an ideal backup tool for monitoring and control when there is a complete loss of SCADA/EMS

• Once validated on the closed-loop simulation platform, the data source will be switched from simulation to real time PMU

• On-premises production implementation • Future cloud hosted environment

19

Eugene Litvinov, Song Zhang, Xiaochuan Luo, “Synchrophasor-based generation dispatch for emergency area balancing”, accepted for publication in 2018 IEEE PES General Meeting

Page 20: Synchrophasor-based Emergency Generation Dispatch...Independent Synchrophasor Infrastructure • The synchrophasor infrastructure is independent from the SCADA/EMS system – Separate

ISO-NE PUBLIC20