risk in capital budgeting
DESCRIPTION
TRANSCRIPT
Which one you go for??
Nokia E-71 Nokia 6030 Nokia 3310
Presented By
Noman
Anil
Fahad
Adil
RISK IN CAPITAL BUDGETING AND TIME VALUE OF
MONEY
Investors Main Strategies
Simple & Compound Interest
Simple Interest: Interest continues to accrue over a period of time at a given rate.
SI = P(r)(n)
Compounding of interest:compensation for the investor not actually receiving interest periodically.
A = P (1+ r)n
Future & Present value
Future Value: Value that money will acquire in future, if compounded at a given rate of return.
FV = PV (1+r)n
Present Value:
Value of money that is expected in future, today.
PV = FV/ (1+r)n
What is Capital Budgeting?
Capital budgeting is used to determine the requirements of the long-term investments of a company. Examples of long-term investments are those required for replacement of equipments and machinery.
Purpose…
Planning for Capital Assets
Approaches
NPV:If we consider a series of cash flows, and compute present values of all the
cash flows at a particular discounting rate, and then sum up the present values, the result is called net present value.
NPV = CF0 – (CF1/(1+r)1 +CF2/(1+r)2+ .....+CFn/(1+r)n)
IRR: The word internal or implicit is only to state that on the face of it, the rate was not explicit.
IRR is the rate where NPV = 0
NPV = 0 = CF0 – (CF1/(1+r)1 +CF2/(1+r)2+ .....+CFn/(1+r)n)
Or; CF0 = (CF1/(1+r)1 +CF2/(1+r)2+ .....+CFn/(1+r)n)
Approaches
Profitability Index: A ratio of whether and how much an investment will result in a profit. It is
calculated by taking the NPV of expected future cash flows from an investment and dividing by the investment's original cost. A ratio above one indicates that the investment will be profitable, while a ratio below one means that it will not.
PI=PV of future cash flows/ Initial Investment
Payback Period: The length of time it takes to recover the cost of an investment. It is
calculated as shown here:
PB= Cost of Project/ Annual Cash Inflows
Relevant Risks in Capital Budgeting
Stand-alone risk
Corporate risk
Market (or beta) risk
Stand-Alone Risk
The project’s risk if it were the firm’s only asset and there were no shareholders.
Ignores both firm and shareholder diversification.
Measured by the or CV of NPV, IRR, or MIRR.
Corporate Risk
Reflects the project’s effect on corporate earnings stability.
Considers firm’s other assets (diversification within firm).
Depends on:project’s , andits correlation with returns on firm’s other assets.
Measured by the project’s corporate beta.
Market Risk
Reflects the project’s effect on a well-diversified stock portfolio.
Takes account of stockholders’ other assets.
Depends on project’s and correlation with the stock market.
Measured by the project’s market beta.
Risk Analysis in Capital Budgeting
Scenario Analysis Simulation AnalysisDecision Tree Analysis
Scenario Analysis
Examines several possible situations, usually worst case, most likely case, and best case.
Provides a range of possible outcomes.
Examples
Scenario Probability NPV(000)
Worst 0.25 $ 15 Base 0.50 82 Best 0.25 148
E(NPV) = $ 82
(NPV) = 47
CV(NPV) = (NPV)/E(NPV) = 0.57
Since CV = 0.57 > 0.4, this project has high risk.
Simulation Analysis
• A computerized version of scenario analysis which uses continuous probability distributions.
• Computer selects values for each variable based on given probability distributions.
Example
• NPV and IRR are calculated.
• Process is repeated many times (1,000 or more).
• End result: Probability distribution of NPV and IRR based on sample of simulated values.
• Also gives NPV, CVNPV, probability of NPV > 0.
Noman Usman
Anil Saleem
Fahad Ali
Adil Rahman