2 risk and uncertainity in capital budgeting
TRANSCRIPT
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
1/23
Capital Budgeting
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
2/23
Capital Budgeting Decisions
Capital investment refers to the investment in projectswhose results would be available only after a year. Theinvestments would be heavy and the return will beavailable only after some time.
Cases of capital budgeting decisions Replacements
Expansion
Diversification
R & D Miscellaneous (Pollution control as per legal requirements)
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
3/23
Concept of Capital Budgeting
Capital Budgeting refers to long-term planningfor proposed capital outlays and their financing.
It includes both raising of long-term funds aswell as their utilisation.
It is the decision making process by which thefirms evaluate the purchase of major fixed assets
It refers to the firms formal process for the
acquisition and investment of capital
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
4/23
Capital Expenditure Budget
It is a functional budget It provides guidance as to the amount of capital
that may be required for procurement of capital
assets during the period
The budget is prepared after taking into
consideration the available production
capacities, probable reallocation of existing
resources and possible improvements in the
production techniques
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
5/23
Need & Importance of Capital Budgeting
Large investments Long term commitment of funds
Irreversible nature
Long term effect on profitability Difficulties of investment decision
National importance
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
6/23
Capital Budgeting Process
Capital
Budgetin
g Process
1. Identification
of Investment
Proposal
2. Screen
Proposals
3. Evaluate
Proposals
4. Fix
Priorities
5. Final
approval
6.
Implementthe Proposal
7. Review
the
performance
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
7/23
Kinds of Capital Budgeting Decisions
Basic categories Those which increase revenue
Those which reduce cost
Other Categories Accept/Reject decisions
Mutually exclusive project decisions
Capital rationing decisions
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
8/23
Methods/Evaluation of Investment Proposals
Traditional methods Pay-Back Period/ Pay Out/ Pay Off Method
Improved Pay-Back Period Method
Post-pay Back Profitability method
Pay back Reciprocal method Post-pay Back Period method
Discounted Pay-Back Method
Rate of Return/Accounting Method
Average rate of Return Method
Return per unit of investment method
Return on average investment method
Average return on average investment method
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
9/23
Methods/Evaluation of Investment Proposals
Time-Adjusted/ Discounted Methods
Net Present Value Method- NPV
Internal Rate of Return Method- IRR Profitability Index Method-PI
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
10/23
RISK MANAGEMENT FUNCTION
Risk management
involves identifying a
firms risk exposures
and using insurance
products or selfinsurance to manage
those exposures.
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
11/23
RISK AND UNCERTAINTY IN CAPITAL BUDGETING
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
12/23
1. Risk Adjusted Discount Rate/ Method ofvarying discount rate- RAD
2. Certainty equivalent method-CE
3. Sensitivity technique
4. Probability Distribution technique-PD5. Standard deviation method-SD
6. Co efficient of variation method-COV/CV
7. Decision tree analysis
8. Simulation Analysis
RISK AND UNCERTAINTY IN CAPITAL BUDGETING
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
13/23
RAD is the simplest method of accounting for risk
in capital budgeting The cut-off rate or the discount factor will be
increased by a certain percentage on account of risk
The highly risky projects which have grater
variability in expected returns will be discounted at a
higher rate when compared to the projects which are less
risky and are expected to have lesser variability in
returns
The drawback of this method is that it is not
possible to determine the risk premium rateappropriately
Another drawback is that it is the future cash flow
which is uncertain and requires adjustment and not the
discount rate
Risk Adjusted Discount Rate/Method of Varying Discount Rate
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
14/23
CE is another simple method
This method aims to reduce expected cash flows bycertain amounts
It can be employed by multiplying the expected cash
flows by certainty equivalent co-efficient as to convert the
uncertain cash flows to certain cash flows
Certainty Equivalent Method-CE
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
15/23
Sensitivity Technique is applied where cash inflows
are very sensitive under different circumstances In such cases, more than one forecast of the future
cash inflows may be made
These inflows may be regarded as Optimistic, Most
Likely and pessimistic Further cash inflows may be discounted to find out
the net present values under these three different
situations
If the NPVs under the three situations differ widelyit implies that there is a great risk in the project and the
investors decision to accept or reject a project will
depend upon his risk bearing abilities
Sensitivity Technique
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
16/23
A probability is the relative frequency with which
an event may occur in the future When future estimates of cash inflows have
different probabilities the expected monetary values may
be computed by multiplying cash inflow with the
probability assigned The monetary values of the inflows may further be
discounted to find the present values
The project that gives higher net present value may
be accepted
Probability Distribution Technique
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
17/23
If two projects have the same cost and their net
present values are also the same, standard deviation ofthe expected cash inflows of the two projects may be
calculated to judge the comparative risk of the projects
The project having a higher standard deviation is
said to be more risky as compared to the other
Standard Deviation Method
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
18/23
Coefficient of variation is a relative measure of
dispersion. If the projects have the same cost butdifferent NPVs, relative measure i.e., Coefficient of
variation should be computed to judge the relative
position of risk involved. It can be calculated as
Coefficient of variation= (Standard Deviation/Mean)*100
Coefficient of Variation Method
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
19/23
In modern business there are complex investment
decisions which involve a sequence of decisions overtime Such subsequential decisions can be handled by
plotting decision trees
A decision tree is a graphic representation of the
relationship between a present decision and futureevents, future decisions and their consequences
The sequence of events is mapped out over time in a
format resembling branches of tree and hence the
analysis is known as decision tree analysis
Decision Tree Analysis
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
20/23
Identification of the problem
Finding out the alternatives Exhibiting the decision tree indicating the decision
points, chance events and other relevant data
Specification of probabilities and monetary values
for cash inflows Analysis of the alternative
Steps in Decision Tree Analysis
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
21/23
Simulation analysis is a technique to analyse risk in
capital budgeting decisions It is unique in the sense that it allows all the
variables to vary at the same time
It also finds out the impact of NPV
Random numbers are used for simulation
Simulation Analysis
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
22/23
1. Model the project. The model of the project shows
how the NPV is related to the parameters and theexogenous variables.
(Parameters are input variables specified by the decision
maker and held constant over all simulation runs.
Exogenous variables are input variables which are
stochastic in nature and outside the control of the
decision maker)
2. Specify the values of parameters and the probability
distributions of the exogenous variables
3. Select a value, at random, from the probabilitydistributions of each of the exogenous variables
4. Determine the net present value corresponding to the
randomly generated values of exogenous variables and
pre-specified parameter values
Procedure for Simulation Analysis
-
8/3/2019 2 Risk and Uncertainity in Capital Budgeting
23/23
5. Repeat steps (3) & (4) a number of times to get a large
number of simulated NPVs6. Plot the frequency distribution of the NPVS
(Problem Financial Management Prasanna Chandra
Pg.No 340)
Procedure for Simulation Analysis-contd