risk analysis in capital budgeting decisions

Upload: tanweer-anwer

Post on 07-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    1/26

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    2/26

    7/1/20117/1/2011 22

    Common Techniques used forCommon Techniques used for

    Investment EvaluationInvestment Evaluation Discounted Cash Flow TechniquesDiscounted Cash Flow Techniques

    -- Net present valueNet present value

    -- Internal Rate of ReturnInternal Rate of Return-- Profitability IndexProfitability Index

    NonNon--Discounted Cash Flow TechniquesDiscounted Cash Flow Techniques

    -- Payback PeriodPayback Period

    -- Accounting Rate of ReturnAccounting Rate of Return

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    3/26

    7/1/20117/1/2011 33

    Nature of RiskNature of Risk

    Risk exists because of the inability of theRisk exists because of the inability of the

    decisiondecision--maker to make perfect forecasts.maker to make perfect forecasts.

    An investment is not risky if we can specify aAn investment is not risky if we can specify aunique sequence of cash flows for it.unique sequence of cash flows for it.

    However there are always uncertainties aboutHowever there are always uncertainties about

    cash flows which render risk to the capitalcash flows which render risk to the capital

    investment proposals with regard to theirinvestment proposals with regard to their

    acceptance.acceptance.

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    4/26

    7/1/20117/1/2011 44

    Concept of ProbabilityConcept of Probability

    The concept of probability is fundamental toThe concept of probability is fundamental to

    the use of risk analysis techniques.the use of risk analysis techniques.

    The probability estimate based on a very largeThe probability estimate based on a very largenumber of observations is known as annumber of observations is known as an

    objective probability.objective probability.

    The probability estimates that are dependentThe probability estimates that are dependent

    on the state of belief of a person are calledon the state of belief of a person are called

    subjective probabilities.subjective probabilities.

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    5/26

    7/1/20117/1/2011 55

    Statistical Techniques for RiskStatistical Techniques for Risk

    AnalysisAnalysis Expected Net Present Value (ENPV) = TheExpected Net Present Value (ENPV) = The

    expected net present values can be found outexpected net present values can be found out

    by multiplying the monetary values of theby multiplying the monetary values of thepossible events (cash flows) by theirpossible events (cash flows) by their

    probabilities.probabilities.

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    6/26

    7/1/20117/1/2011 66

    ENPV for a Single PeriodENPV for a Single Period

    Calculate theCalculate the

    ENCF for eachENCF for each

    project and findproject and find

    out which projectout which projectis preferable if theis preferable if the

    initial outlay is Rs.initial outlay is Rs.

    6500?6500?

    EventEvent Project AProject A Project BProject B

    CFCF ProbProb CFCF probprob

    MM 45004500 0.20.2 1400014000 0.150.15

    NN 52005200 0.10.1 1200012000 0.100.10

    OO 67006700 0.40.4 70007000 0.500.50

    PP 71007100 0.10.1 50005000 0.100.10

    QQ 84008400 0.20.2 30003000 0.150.15

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    7/26

    7/1/20117/1/2011 Bindu NairBindu Nair -- IMMIMM 77

    Solution.Solution.

    EventsEvents Project AProject A Project BProject B

    MM CFCF ProbProb Exp.Exp.

    ValueValue

    CFCF ProbProb Exp.Exp.

    ValueValue

    NN 45004500 0.20.2 900900 1400014000 0.150.15 21002100

    OO 52005200 0.10.1 520520 1200012000 0.100.10 12001200

    PP 67006700 0.40.4 26802680 70007000 0.500.50 35003500

    QQ 71007100 0.10.1 710710 50005000 0.100.10 500500

    84008400 0.20.2 16801680 30003000 0.150.15 450450

    ENCFENCF 64906490 77507750

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    8/26

    7/1/20117/1/2011 88

    Expected NPV Multiple PeriodExpected NPV Multiple Period

    A company hasA company hasdetermined thedetermined thefollowingfollowing

    probabilities forprobabilities for

    net cash flowsnet cash flowsfor three yearsfor three yearsgenerated by agenerated by a

    project:project:

    Calculate theCalculate the

    ENPV at 12%ENPV at 12%discount rate ifdiscount rate ifthe expectedthe expectedcash outflow iscash outflow is6000?6000?

    Year1Year1 Year2Year2 Year3Year3

    CFCF ProbProb CFCF ProbProb CFCF ProbProb

    11001100 0.10.1 11001100 0.20.2 11001100 0.40.4

    24002400 0.30.3 24002400 0.30.3 24002400 0.10.1

    32003200 0.20.2 32003200 0.40.4 32003200 0.30.3

    45004500 0.40.4 45004500 0.10.1 45004500 0.20.2

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    9/26

    7/1/20117/1/2011 99

    Standard DeviationStandard Deviation the absolutethe absolute

    measure of riskmeasure of risk Variance of NCF = (NCFVariance of NCF = (NCF11 ENCF)ENCF)

    22 * Prob* Prob11 ++

    (NCF(NCF22 ENCF)ENCF)22 * Prob* Prob22 + (NCF+ (NCFnn ENCF)ENCF)

    22 **

    ProbProbnn

    Standard Deviation = Root of variance.Standard Deviation = Root of variance.

    Coefficient of variation : it is the relativeCoefficient of variation : it is the relative

    measure of risk.measure of risk.

    CV = Standard Deviation / Expected Net CashCV = Standard Deviation / Expected Net Cash

    Flow.Flow.

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    10/26

    7/1/20117/1/2011 1010

    Question???Question???

    Calculate theCalculate the

    Variance, StandardVariance, Standard

    Deviation andDeviation and

    Coefficient ofCoefficient ofVariationVariation

    EventEvent Project AProject A Project BProject B

    CFCF ProbProb CFCF probprob

    MM 45004500 0.20.2 1400014000 0.150.15

    NN 52005200 0.10.1 1200012000 0.100.10

    OO 67006700 0.40.4 70007000 0.500.50

    PP 71007100 0.10.1 50005000 0.100.10

    QQ 84008400 0.20.2 30003000 0.150.15

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    11/26

    7/1/20117/1/2011 1111

    Conventional Techniques of RiskConventional Techniques of Risk

    AnalysisAnalysis

    RiskRisk--adjusted discount rateadjusted discount rate

    Certainty EquivalentCertainty Equivalent

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    12/26

    7/1/20117/1/2011 1212

    RiskRisk--adjusted Discount rateadjusted Discount rate

    RiskRisk--adjusted discount rate method uses aadjusted discount rate method uses a

    higher discount rate for more risky cash flowshigher discount rate for more risky cash flows

    and lesser discount rate for less risky cashand lesser discount rate for less risky cash

    flows.flows.

    RiskRisk--adjusted discount rate = Riskadjusted discount rate = Risk--free rate +free rate +

    Premium for the riskPremium for the risk

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    13/26

    7/1/20117/1/2011 1313

    Question???Question???

    An investment in a project will cost Rs.An investment in a project will cost Rs.

    100000 initially and it is expected to generate100000 initially and it is expected to generate

    cash flows in years one through four of Rs.cash flows in years one through four of Rs.

    25000, 50000, 35000,and 20000. What is the25000, 50000, 35000,and 20000. What is the

    projects NPV, assuming a 10% riskprojects NPV, assuming a 10% risk--free rate.free rate.

    Also compute the riskAlso compute the risk--adjusted NPV if theadjusted NPV if the

    discount rate is 15%.discount rate is 15%.

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    14/26

    7/1/20117/1/2011 1414

    Solution.Solution.

    RiskRisk--free NPV = + 3970free NPV = + 3970

    RiskRisk adjusted NPV =adjusted NPV = -- 59805980

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    15/26

    7/1/20117/1/2011 1515

    Certainty EquivalentCertainty Equivalent

    Certainty Equivalent approach computes theCertainty Equivalent approach computes theNPV of the project by converting the riskyNPV of the project by converting the riskycash flows into equivalent riskcash flows into equivalent risk--free cash flowsfree cash flows

    and discount them with riskand discount them with risk free rate.free rate. The certainty equivalent coefficient can beThe certainty equivalent coefficient can be

    calculated as :calculated as : Certain net cash flow/Risky netCertain net cash flow/Risky net

    cash flow.cash flow. The certainty equivalent coefficient is always aThe certainty equivalent coefficient is always a

    value between 0 and 1.value between 0 and 1.

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    16/26

    7/1/20117/1/2011 1616

    Question????Question????

    Riskless Enterprises is a fastRiskless Enterprises is a fastgrowing company that follows agrowing company that follows a

    rather conservative approach to itsrather conservative approach to its

    capital expenditure plans due tocapital expenditure plans due to

    the inherent risks involved. Thethe inherent risks involved. The

    firm normally does not takefirm normally does not take

    capital expenditure that last morecapital expenditure that last more

    than 5 years and follows a policythan 5 years and follows a policy

    of converting the risky cash flowsof converting the risky cash flows

    to their certainty equivalents byto their certainty equivalents by

    assigning certainty equivalentassigning certainty equivalent

    factors of 0.9, 0.8, 0.7, 0.6 and 0.5factors of 0.9, 0.8, 0.7, 0.6 and 0.5for the cash flows of Year 1 tofor the cash flows of Year 1 to

    Year 5, respectively.Year 5, respectively.

    The cost of capital is 15% whileThe cost of capital is 15% while

    riskrisk--free return is 6%free return is 6%

    YearYear ProjectProject

    AA

    Project BProject B

    00 --250250 --250250

    11 6060 100100

    22 7070 120120

    33 8080 100100

    44 120120 2020

    55 120120 4040

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    17/26

    7/1/20117/1/2011 1717

    Question contd..Question contd..

    Which project should be undertaken based onWhich project should be undertaken based on

    NPV rule?NPV rule?

    Which project should be undertaken if C.E.Which project should be undertaken if C.E.approach is followed?approach is followed?

    Which project would you recommend ifWhich project would you recommend if

    (a) Shareholders are dominant(a) Shareholders are dominant (b) Debt holders are dominant.(b) Debt holders are dominant.

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    18/26

    7/1/20117/1/2011 1818

    Practice Question???Practice Question???

    Delta corp. is considering anDelta corp. is considering aninvestment in one of the twoinvestment in one of the twomutually exclusive proposals;mutually exclusive proposals;Project A involves an initialProject A involves an initialoutlay of Rs. 1,70,000 and Projectoutlay of Rs. 1,70,000 and ProjectB Rs. 1,50,000. The C.EB Rs. 1,50,000. The C.EApproach is employed inApproach is employed inevaluating the risk associated withevaluating the risk associated withthe investments. The current yieldthe investments. The current yieldon the treasury bills is 5% . Theon the treasury bills is 5% . Theexpected values of cash inflowsexpected values of cash inflowswith their C.Es are follows:with their C.Es are follows:

    Which Project should beWhich Project should beaccepted?accepted?

    Which project is riskier? HowWhich project is riskier? Howdo you know?do you know?

    YrsYrs Project AProject A Project BProject B

    CashCash

    FlowFlow

    C.EC.E CashCash

    FlowFlow

    C.EC.E

    11 9090 0.80.8 9090 0.90.9

    22 100100 0.70.7 9090 0.80.8

    33 110110 0.50.5 100100 0.60.6

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    19/26

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    20/26

    7/1/20117/1/2011 2020

    Scenario AnalysisScenario Analysis

    Scenario Analysis measures the change inScenario Analysis measures the change in

    NPV of the project under different scenariosNPV of the project under different scenarios

    changing several variables at a time because ofchanging several variables at a time because of

    interrelationship of variables amongstinterrelationship of variables amongst

    themselvesthemselves

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    21/26

    7/1/20117/1/2011 2121

    Decision Tree AnalysisDecision Tree Analysis

    A decision tree is a powerful tool of analyzingA decision tree is a powerful tool of analyzing

    sequential decisions. It breaks up complexsequential decisions. It breaks up complex

    decisions into smaller decisions and calculatedecisions into smaller decisions and calculate

    the NPV backwards to arrive at the mostthe NPV backwards to arrive at the most

    pragmatic decision based on maximization ofpragmatic decision based on maximization of

    NPV.NPV.

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    22/26

    7/1/20117/1/2011 2222

    Question???Question???

    ABC computers is considering an optionABC computers is considering an option

    to develop two models; Model A andto develop two models; Model A and

    Model B of Laptops. Both the modelsModel B of Laptops. Both the models

    are expected to be hot sellers for theare expected to be hot sellers for the

    next two years.next two years.

    The capital expenditure involved inThe capital expenditure involved in

    Model A is 225 cr. while Model B costsModel A is 225 cr. while Model B costs

    Rs. 250 cr.Rs. 250 cr.

    Since Model A is an improvised versionSince Model A is an improvised version

    of the existing laptop it offers a certainof the existing laptop it offers a certain

    Cash Flow of Rs. 140 cr. and Rs. 180 cr.Cash Flow of Rs. 140 cr. and Rs. 180 cr.

    for the next two years.for the next two years.

    However in case of Model B ABC isHowever in case of Model B ABC is

    not very sure of its Cash Flows.not very sure of its Cash Flows. It expects a cash inflow of Rs. 150 cr inIt expects a cash inflow of Rs. 150 cr in

    the first year with 70% probability andthe first year with 70% probability and

    under exceptional circumstances it mayunder exceptional circumstances it may

    yield a cash flow of Rs. 180 cr.yield a cash flow of Rs. 180 cr.

    The cash flows in the second year areThe cash flows in the second year are

    dependent upon the outcome of thedependent upon the outcome of the

    first year. If the firm gets normal cashfirst year. If the firm gets normal cash

    inflow of 150 cr in the first year theinflow of 150 cr in the first year the

    chances are 30% that it would repeatchances are 30% that it would repeat

    the cash flows, 40% chances that itthe cash flows, 40% chances that it

    might improve to 180 cr. And 30%might improve to 180 cr. And 30%

    chances that it might do exceptionallychances that it might do exceptionally

    well and it may increase to 220 cr.well and it may increase to 220 cr.

    If the firm does exceptionally well inIf the firm does exceptionally well in

    the first year then ,chances are itthe first year then ,chances are it

    would have cash flows of eitherwould have cash flows of either

    220cr, 230 cr, or 250 cr, with220cr, 230 cr, or 250 cr, with

    probabilities of 50%, 30% and 20%probabilities of 50%, 30% and 20%

    respectively.respectively.

    Examine both proposals andExamine both proposals and

    recommend the best one to ABCrecommend the best one to ABC

    assuming a cost of capital of 12%assuming a cost of capital of 12%

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    23/26

    7/1/20117/1/2011 2323

    Solution.Solution.

    Model AModel A Cash InflowCash Inflow Present value@Present value@12%12%

    Ist YearIst Year 140.00140.00 125.00125.00

    IInd YearIInd Year 180.00180.00 143.49143.49

    Total Present Values of InflowsTotal Present Values of Inflows 268.49268.49

    Less Initial InvestmentLess Initial Investment 225.00225.00

    NPVNPV 43.4943.49

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    24/26

    7/1/20117/1/2011 2424

    Model BModel B

    Year 1Year 1 Year 2Year 2

    ProbabilityProbability Cash FlowCash Flow ProbabilityProbability Cash FlowCash Flow

    0.70.7 150150 0.30.30.40.4

    0.30.3

    150150180180

    220220

    0.30.3 180180 0.50.5

    0.30.3

    0.20.2

    220220

    230230

    250250

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    25/26

    7/1/20117/1/2011 2525

    Model B contd.Model B contd.

    Present Value of Year 2 cash flows at the end of year 1Present Value of Year 2 cash flows at the end of year 1

    ENCF = 0.3*150 + 0.4*180 + 0.3*220 = 183.ENCF = 0.3*150 + 0.4*180 + 0.3*220 = 183.

    Present Value of ENCF @ 12% = 183*0.893 = 163.41Present Value of ENCF @ 12% = 183*0.893 = 163.41

    ENCF = 0.5*220 + 0.3*230 + 0.2*250 = 229ENCF = 0.5*220 + 0.3*230 + 0.2*250 = 229 Present Value of ENCF @ 12% = 229*0.893 = 204.46Present Value of ENCF @ 12% = 229*0.893 = 204.46

  • 8/6/2019 Risk Analysis in Capital Budgeting Decisions

    26/26

    7/1/20117/1/2011 2626

    Model BModel B

    Value of Cash FlowValue of Cash Flow YY ZZ

    Cash Flow of Yr.1Cash Flow of Yr.1 150.00150.00 180.00180.00

    PV of Cash Flow of YearPV of Cash Flow of Year22

    163.39163.39 204.46204.46

    Total Cash Flow at YearTotal Cash Flow at Year

    11

    313.39313.39 384.46384.46

    Expected Cash Flow AtExpected Cash Flow AtPoint XPoint X

    313.39 * 0.7 + 384.46*0.3 = 334.71313.39 * 0.7 + 384.46*0.3 = 334.71PV of 334.71 = 298.85PV of 334.71 = 298.85

    ENPV = 298.85ENPV = 298.85 250 = 48.85250 = 48.85