pumping system design seminar - home - ohio water ... mullen itt columbus, oh-5-13-10.pdf ·...
TRANSCRIPT
Water & Wastewater
Pumping System Design Seminar
Hydraulic Variations for Both PC and Centrifugal Grinder Pumps Utilized in Pressure Sewer Systems
Dana Mullen, Market Manager Pressure Sewer Systems5-13-10 COLUMBUS, OHIO
5-13-10 2
Water & Wastewater
A Pressure Sewer is . . . A sanitary sewer system that utilizes a network of grinder pumps to
transport wastewater through small diameter pipes to a collection and treatment system.
A grinder pump is a submersible pump designed to reduce wastewater particulate to a slurry through the use of a grinding mechanism.
Grinder Pumps in Pressure Sewers Page 2
Figure 1.1 -- Typical lakefront pressure sewer system
Service Connection Lateral
Road Pressure Sewer Collection System
5-13-10 3
Water & Wastewater
Pressure Sewer System
5-13-10 4
Water & Wastewater
How big is it?
Systems can be as small as a single station pumping into an existing gravity sewer line
Systems can be as large as thousands of stations tied together with a piping network stretching for miles before discharging toa collection point
Grinder Pumps in Pressure Sewers Page 3
5-13-10 5
Water & Wastewater
Gravity sewers require big equipment, major excavation
Grinder Pumps in Pressure Sewers Page 4
5-13-10 6
Water & Wastewater
Pressure Sewers do not rely on limitations of gravity
• Wastewater is pumped through small diameter pipes following the contour of the land, set in shallow trenches just below the frost line
• Lift stations are minimized or eliminated in virtually every installation
• Wastewater treatment plants for these systems are less costly to build since the system is closed to infiltration and solid sizes are minimized.
Grinder Pumps in Pressure Sewers Page 5
5-13-10 7
Water & Wastewater
Infrastructure development costs are lower•Major excavation is eliminated•Labor and material costs can be
dramatically reduced•Environmental disruption and restoration
are minimized•Time to complete construction is reduced
1 ¼” – 4” 8” – 24”
Pressure Gravity
Grinder Pumps in Pressure Sewers Page 6
5-13-10 8
Water & Wastewater
Overcoming obstacles
•Directional boring can eliminate the need for trenches and install pipe under rivers and roadways
•Site restoration costs are minimized
Grinder Pumps in Pressure Sewers Page 7
5-13-10 9
Water & Wastewater
Pressure Sewers provide…
An economical solution to geo-technically challenging environmental conditions where gravity sewers may be impractical if not impossible.
Examples include:
- Rocky soil
- Hilly terrain
- Shallow bedrock
- High water tables
- Long flat terrain
- Slow growth areas
- Existing structures
and roads
- Shallow bedrock
Grinder Pumps in Pressure Sewers Page 8
5-13-10 10
Water & Wastewater
Pressure Sewers are economical
Prepackaged systems lower up front costs by allowing developers to add grinder pump stations as new homes are built
Allows developers to build in areas that are inaccessible to gravity sewers
Minimizes the need for manholes and lift stations, making more lots marketable for sale
Lower cost per lot in low density development areas
Grinder Pumps in Pressure Sewers Page 9
5-13-10 11
Water & Wastewater
Pressure Sewers:A Proven Technology
First used in the early 1970’s
Provide daily service to millions of users worldwide
Have demonstrated excellent performance, high reliability and low Operating and Maintenance costs
Grinder Pumps in Pressure Sewers Page 10
5-13-10 12
Water & Wastewater
A compatible solution
Pressure sewer systems are compatible with other types of collection systems
Pressure sewer systems can be integrated into existing collection systems
Multiple systems can be blended into site specific designs to provide a complete solution to wastewater challenges
Grinder Pumps in Pressure Sewers Page 11
5-13-10 13
Water & Wastewater
Grinder Pumps in Pressure Sewers Page 13
Typical residential installation
5-13-10 14
Water & Wastewater
Typical residential Grinder Pump site components•A pressure sewer collection line is laid along the edge of the roadway, following the contour of the land
•The pressure sewer collection line delivers the wastewater to a central treatment system, manhole, or force main
•Wastewater may be transported several thousand feet to a discharge point at a higher elevation
Grinder Pumps in Pressure Sewers Page 14
5-13-10 15
Water & Wastewater
Station operating sequence
If the pump does not operate when signaled by the level sensor the sewage level continues to rise, activating a high water alarm
The high water alarm is normally an audible and/or visual alarm and may be a remotely monitored signal
Pump “Off”
Pump “On”
Pump “Alarm”
Alarm Light
Grinder Pumps in Pressure Sewers Page 21
5-13-10 16
Water & Wastewater
•A grinder pump station is located in the yard or basement of each home
•Wastewater flows into the station from the building’s sewer line (typically 4”)
•The basin contains a grinder pump, level sensors, valves and discharge piping
Typical residential installation
Grinder Pumps in Pressure Sewers Page 12
5-13-10 17
Water & Wastewater
Centrifugal & PC Grinder Pump Cutters
A submersible pump designed to reduce wastewater particulate to a slurry through the use of a grinding mechanism
Typical Types– Progressing Cavity (1 - 2 HP) – Centrifugal (2 - 15 HP)
Discharge Size - 1-1/4” to 3”
Grinder Pumps in Pressure Sewers Page 16
5-13-10 18
Water & Wastewater
Pump Hydraulics
Typical residential performance curves
A – CentrifugalB – Progressing Cavity
A
B
Grinder Pumps in Pressure Sewers Page 17
5-13-10 19
Water & Wastewater
Hydraulic Variations for Both PC & Centrifugal
5-13-10 20
Water & Wastewater
2-STAGE HIGH HEAD CENTRIFUGAL
5-13-10 21
Water & Wastewater
RESIDENTIAL & LIGHT COMMERICAL GRINDER PUMP PACKAGE STATION
24” Diameter 30” Diameter
5-13-10 22
Water & Wastewater
PRESSURE BELL OR FLOAT TREE
5-13-10 23
Water & Wastewater
Basin Design Considerations
Grinder Pumps in Pressure Sewers Page 18
5-13-10 24
Water & Wastewater
5-13-10 25
Water & Wastewater
PRESSURE SEWER DESIGN IDEOLOGY
PROBABILITY METHOD
RATIONAL METHOD
5-13-10 26
Water & Wastewater
PROBABILITY / CONSTANT FLOW
PROBABILITY (PM) Method3 KEY DETERMINATES:
“Maximum number of pumps theoretically expected to be running at any time.”
Constant Flow Rate of each Pump Running
A Consistent Inflow Pattern, (i.e., 200 gpd/edu)
EPA Manual 625/1-91/024
5-13-10 27
Water & Wastewater
PROBABILITY (PM) METHOD
0.732.66165515312-344
0.642.48154514279-311
0.562.31143513246-278
0.482.13132512213-245
1.152.98121411180-212
0.972.71110410147-179
0.82.449949114-146
0.642.17884881-113
1.73.14773751-80
1.282.69663631-50
0.912.24553519-30
1.572.66442 1/2410-18
2.332.9233234-9
3.253.04221 1/222-3
1.772111 1/411
Friction Loss/100ft.FPSGPMPipe SizePumps runningEDU'S
Quick Design Reference
5-13-10 28
Water & Wastewater
RATIONAL METHOD “A design flow corresponding to the
number of homes served by the pressure sewer” (EPA Manual 625/1-91/024)
“The rational method can be logically applied when either centrifugal pumps or progressive cavity pumps are used”
5-13-10 29
Water & Wastewater
Rational Method Baseline FormulaQ = AN+B
Q = Predicted flow derived from input data below
A = Coefficient that adjusts based on ave. daily flow {EPA national average is 67 GPCD or 200GPD / EDU} { Assigned value is typically 0.5 }
N = Number of Equivalent Domestic Units or Lots
B = Minimum flow one pump will produce with maximum static head and no friction loss
Alternative EDU’S x GPD x 2.5{pf} = GPM1440
5-13-10 30
Water & Wastewater
Total EDU’S x gal/day/house x peak factor
Hour’s flow/day x 60 min.
92 x 400 x 2.5
24 x 60
Q = 64 GPM LPS Design flow
20
4 GRINDER PUMPS running simultaneously to satisfy design flow requirements
5-13-10 31
Water & Wastewater
DESIGNING AN LPS SYSTEMWHAT ARE WE TRYING TO ACHIEVE?
Assure that each beginning mainline will be flushed at least once daily
Assure that all hydraulic grade conditions are met with the correct pump type- Centrifugal or PC
Assure that minimum velocity requirements set by EPA are achieved
Size the LPS system with the appropriate pipe size and type.
Achieve design flow requirements
5-13-10 32
Water & Wastewater
PIPE DIAMETER PIPE TYPE GPM REQ. 2-FPS
1.25 ” DR-11 9
1.5 ” DR-11 11.50
2 ” DR-11 18
3 ” DR-11 40
4 ” DR-11 65
6 ” DR-11 140
5-13-10 33
Water & Wastewater
TP
LPS SYSTEM DESIGN92 EDU’S connected to PSS92 X 400(2.5) = 64 GPM
1440
5-13-10 34
Water & Wastewater
LPS Design Steps1. IDENTIFY TOTAL HOMES CONNECTED TO THE LPS
SYSTEM = 92
2. ESTABLISH DESIGN FLOW =
3. 92 EDU’S * 400 GPD * PF{2.5}1440 = 64 GPM
4. Q = AN + B66 = .5 *92 + 20
5. IDENTIFY THE LOWEST ELEVATION IN THE SYSTEM VS. THE HIGHEST STATIC ELEVATION INCLUDING THE TE Static = 15 FEET
6. IDENTIFY LONGEST PUMPING DISTANCE FROM TE IS LOTS # 79 & 26
7. 4 PUMPS WILL OPERATE SIMULANTEOUSLY LOTS # 40, 79, 15, 26
5-13-10 35
Water & Wastewater
HYDRAULIC VARIATIONS PC & CENTRIFUGAL
5-13-10 36
Water & Wastewater
CENTRIFUGAL HYDRAULIC ANALYSIS
5-13-10 37
Water & Wastewater
PC HYDRAULIC ANALYSIS
5-13-10 38
Water & Wastewater
CENTRIFUGAL PUMPS –VERTICAL OR HORIZONTAL DISCHARGE
5-13-10 39
Water & Wastewater
PC GRINDER PUMPSE-1
5-13-10 40
Water & Wastewater
BARNES
5-13-10 41
Water & Wastewater
MYERS-HYDROMATIC & DELTA ENVIRONMENTAL
5-13-10 42
Water & Wastewater
ZOELLER
5-13-10 43
Water & Wastewater
FLYGT
5-13-10 44
Water & Wastewater
PSS APPLICATIONS UTILIZE BOTH
CENTRIFUGAL
&
PROGRESSIVE CAVITY
WHAT DO YOU CHOOSE AND WHY?
5-13-10 45
Water & Wastewater
QUESTIONS / COMMENTS / SUGGESTIONS?
5-13-10 46
Water & Wastewater
In conclusion…
5-13-10 47
Water & Wastewater
THANK YOU TODAY
Dana Mullen, Market ManagerPSS Pre-engineered Package
Pump stations