project monitoring and controlling

40
Monitoring and Controlling Your Project Tom Milner, PMP

Upload: tom-milner-pmp-pmi-acp

Post on 19-Jan-2015

4.133 views

Category:

Documents


2 download

DESCRIPTION

Presented 11/12/2010

TRANSCRIPT

Page 1: Project Monitoring And Controlling

Monitoring and ControllingYour Project

Tom Milner, PMP

Page 2: Project Monitoring And Controlling

2

Objectives

At the end of this session you will be able to

� Monitor and Control Changes in your Project

� Evaluate the Impact of Proposed Changes (scope, schedule, and cost)

� Control the Flow of Changes in your Project

� Stop Worrying and BE IN CONTROL

� Earn Your Pay as a Project Manager

Page 3: Project Monitoring And Controlling

3

Road Map

� Plan A

Project goes As Planned

� Plan B

Changes from the Peanut Gallery

� Plan C

Risk Happens

Page 4: Project Monitoring And Controlling

4

Project Goes As Planned

� Plan

� Do

� Check

� Act

Page 5: Project Monitoring And Controlling

5

Process Groups

� Initiating

� Planning

� Executing

� Monitoring & Controlling

� Closing

Extracted from A Guide to The Project Management Body of Knowledge (PMBOK® Guide) - Fourth Edition,

©2008 Project Management Institute

Page 6: Project Monitoring And Controlling

6

Process Groups

Extracted from A Guide to The Project Management Body of Knowledge (PMBOK® Guide) - Fourth Edition,

©2008 Project Management Institute

Page 7: Project Monitoring And Controlling

7

Process Groups

Extracted from A Guide to The Project Management Body of Knowledge (PMBOK® Guide) - Fourth Edition,

©2008 Project Management Institute

Page 8: Project Monitoring And Controlling

8

Initiating

Project Charter

� Issued by sponsor

� Authorizes existence of a project

� Gives project manager the authority to

– Apply organizational resources

– Conduct project activities

� Like a contract

Page 9: Project Monitoring And Controlling

9

Planning

Project Management Plan

� Defines how a project is:

– Executed

– Monitored and Controlled

� May include other plans and documents

– Scope / Requirements

– Schedule Baseline / Milestones

– Budget / Cost Performance Baseline

Page 10: Project Monitoring And Controlling

10

Executing

� Direct and manage project execution

Page 11: Project Monitoring And Controlling

11

Monitoring & Controlling

� Monitor and Control Project Work

� Perform Integrated Change Management

Page 12: Project Monitoring And Controlling

12

Road Map

� Plan A

Project goes As Planned

� Plan B

Changes from the Peanut Gallery

� Plan C

Risk Happens

Page 13: Project Monitoring And Controlling

13

Project Goes As Planned

� Plan

� Do

� Check

� Act

Page 14: Project Monitoring And Controlling

14

Project Goes As Planned

� Plan – Set the Baseline

� Do – Execute Project Activities

� Check – Compare actual vs. planned project

performance

� Act – Take corrective action

Page 15: Project Monitoring And Controlling

15

Project Goes as Planned

� Plan – Set the Baseline

� Do – Execute Project Activities

Page 16: Project Monitoring And Controlling

16

Project Goes as Planned

� Plan

� Do

� Check – Compare actual vs. planned project

performance

– Tollgate Review

– Earned Value Analysis

Page 17: Project Monitoring And Controlling

17

Tollgate Review

LaunchTestDevelop-

mentDesignAnalysisConcept

CloseImproveAnalyzeMeasureDesign

Page 18: Project Monitoring And Controlling

18

Earned Value Analysis

� CV=EV-AC

� SV=EV-PV

EV: Earned Value – As of today, the estimated value of the work actually accomplished

PV: Planned Value – As of today, the estimated value of the work planned to be done

AC: Actual Cost – As of today, the actual cost incurred for the work accomplished

� CPI=EV/AC

� SPI=EV/PV

Extracted from A Guide to The Project Management Body of Knowledge (PMBOK® Guide) - Fourth Edition,

©2008 Project Management Institute

Page 19: Project Monitoring And Controlling

19

Project Goes As Planned

� Plan

� Do

� Check

� Act – Take corrective action

– Within tolerances, no formal change request

– Outside tolerances, Project Manager enters a Change Request

Page 20: Project Monitoring And Controlling

20

Project Goes as Planned

Take corrective action

� Tolerances

How far off before you fix it

– 3 days late

– 10% over budget

� Measure each major deliverable

Or whole project?

Page 21: Project Monitoring And Controlling

21

Project Goes as Planned

� Measure each major deliverable

Or whole project?

Page 22: Project Monitoring And Controlling

22

Project Goes As Planned

� Plan

� Do

� Check

� Act

Page 23: Project Monitoring And Controlling

23

Road Map

� Plan A

Project goes As Planned

� Plan B

Changes from the Peanut Gallery

� Plan C

Risk Happens

Page 24: Project Monitoring And Controlling

24

Changes from the Peanut Gallery

� Integrated Change Management

� Change Request Form

� Change Control Board

� Manage Baselines

Only Approved Changes are Implemented

Page 25: Project Monitoring And Controlling

25

Changes from the Peanut Gallery

� Change Happens in all projects

� Change Requests Come from Stakeholders:

– Project Manager

– Sponsor

– Team Members

– Customer

– Regulators

– Peanut Gallery

Only Approved Changes are Implemented

Page 26: Project Monitoring And Controlling

26

Change Control Board

� Meets to review change requests

� Approves or rejects change requests

� Roles are clearly defined and agreed upon

by appropriate stakeholders

� All board decisions are documented and

communicated to stakeholders

for information and follow-up actions

Only Approved Changes are Implemented

Page 27: Project Monitoring And Controlling

27

Manage Baselines

� Approved changes are documented and

added to the project plan

� Manage baselines to include these changes

– Scope baseline

– Schedule baseline

– Cost baseline

Page 28: Project Monitoring And Controlling

28

Changes from the Peanut Gallery

� Integrated Change Management

� Change Request Form

� Change Control Board

� Manage Baselines

Only Approved Changes are Implemented

This Protects the Project Manager

Page 29: Project Monitoring And Controlling

29

Road Map

� Plan A

Project goes As Planned

� Plan B

Changes from the Peanut Gallery

� Plan C

Risk Happens

Page 30: Project Monitoring And Controlling

30

Risk Happens

� Change requests can result from risks

� An uncertain event or condition that, if it

occurs, has a positive or negative effect on a

project’s objectives

Page 31: Project Monitoring And Controlling

31

Risk Happens

Risk Management

� Plan Risk Management

� Identify Risks

� Perform Qualitative Risk Analysis

� Perform Quantitative Risk Analysis

� Plan Risk Responses

� Monitoring and Control Risks

Extracted from A Guide to The Project Management Body of Knowledge (PMBOK® Guide) - Fourth Edition,

©2008 Project Management Institute

Page 32: Project Monitoring And Controlling

32

Risk Happens

Strategies to Manage Risk� Avoid� Transfer� Mitigate� Exploit� Share� Enhance� Acceptance

Extracted from A Guide to The Project Management Body of Knowledge (PMBOK® Guide) - Fourth Edition,

©2008 Project Management Institute

Page 33: Project Monitoring And Controlling

33

Risk Happens

� Risk mitigation may require action

� Project Manager submits a change request

� Change Control Board reviews request

� Approved or Rejected

� Communicate to Stakeholders

� Adjust Baselines

Page 34: Project Monitoring And Controlling

34

Risk Happens

� Change requests can result from risks

� An uncertain event or condition that, if it

occurs, has a positive or negative effect on a

project’s objectives

Page 35: Project Monitoring And Controlling

35

Road Map

� Plan A

Project goes As Planned

� Plan B

Changes from the Peanut Gallery

� Plan C

Risk Happens

Page 36: Project Monitoring And Controlling

36

Project Goes As Planned

� Plan

� Do

� Check

� Act

Page 37: Project Monitoring And Controlling

37

Changes from the Peanut Gallery

� Integrated Change Management

� Change Request Form

� Change Control Board

� Manage Baselines

Only Approved Changes are Implemented

� This Protects the Project Manager

Page 38: Project Monitoring And Controlling

38

Risk Happens

� Change requests can result from risks

� An uncertain event or condition that, if it

occurs, has a positive or negative effect on a

project’s objectives

Page 39: Project Monitoring And Controlling

39

Objectives

At the end of this session you will be able to

� Monitor and Control Changes in your Project

� Evaluate the Impact of Proposed Changes (scope, schedule, and cost)

� Control the Flow of Changes in your Project

� Stop Worrying and BE IN CONTROL

� Earn Your Pay as a Project Manager

Page 40: Project Monitoring And Controlling

Monitoring and ControllingYour Project

Tom Milner, PMP

[email protected]

Any Questions?