lecture 10 - monitoring and controlling project

20
LECTURE 10 Monitoring and Controlling Project

Upload: nen-tran-ngoc

Post on 09-Nov-2015

241 views

Category:

Documents


2 download

DESCRIPTION

Lecture 10 - Monitoring and Controlling Project

TRANSCRIPT

  • LECTURE 10

    Monitoring and Controlling Project

  • Introduction

    Control is the process of:

    comparing actual performance to the plan

    to determine the variances,

    evaluate possible alternatives, and

    take appropriate action.

    The ability to control a project is directly tied to the effectiveness of the project plan.

    Problems will always occur but they should be kept to a minimum.

    2

  • Good Cost And Control System

    PLANNINGWORK

    AUTHORIZATIONAND RELEASE

    DATACOLLECTION

    AND REPORTING

    COSTACCOUNTING

    CUSTOMER ANDMANAGEMENT

    REPORTING

    PHASE I PHASE II PHASE III PHASE IV PHASE V

    OPERATING CYCLECYCLE

    PLANNING

    Cost estimating Cost accounting Project cash flow Company cash flow Direct labor costing Overhead rate costing Others, such as incentives, penalties, and profit-sharing

    3

  • Explanation of Project Costs

    Project Indirect Costs

    Costs that cannot be associated with any particular work package or project activity.

    Supervision, administration, consultants, and interest

    Costs that vary (increase) with time.

    Reducing project time directly reduces indirect costs.

    Direct Costs

    Normal costs that can be assigned directly to a specific work package or project activity.

    Labor, materials, equipment, and subcontractors

    Crashing activities increases direct costs.

    4

  • Principles of Monitoring and Control

    Set up a formal process to control changes in the project.

    Dont micro-manage.

    Elevate problems to the lowest level of management that can make the decision and take action.

    Be consistent, calculating and reporting schedule progress, cost expenditures, and scope performance throughout the project life.

    If you have more than one project, be sure to handle significant, highly-visible projects first and more often, followed by average and then low priority projects.

    5

  • Establishing a Plan to Monitorand Control the Project

    Determining Information Needs

    Determining Data Collection Methods

    Determining Frequency of Data Collection

    Status Information

    Variances

    Reports

    Course of Action

    6

  • Determine Data Collection Methods

    Electronic

    Manual

    Onsite Inspection

    One-on-one Interviews

    Team Meetings

    7

  • Determine Frequency of Data Collection

    The reporting requirements of the customers

    Average duration of the project activities.

    Experience (known or unknown subject matter).

    8

  • Variances

    Impact on the project.

    Whether impact is a problem.

    Cause of variance, including reasons and people involved.

    Whether the cause of the variance will create variances elsewhere in the project.

    The management cost and control system (MCCS)

    9

  • Reports

    What the plan says should be happening.

    What is ACTUALLY happening (status).

    Variance between plan and status.

    10

  • Cost data collection and reporting flow chart

    Actuals

    Labor

    ACWP

    InventoryAccounts

    BCWP

    Computer

    BCWS

    Monthly TotalProgram Effort

    Weekly LaborReports

    MCCS Comparisonreports To All Mngt

    Variance Report

    11

  • Course of Action

    Implement the decision.

    Follow up to ensure that the action solves the problem.

    Take additional action if necessary to solve the problem.

    Document the decisions that make significant changes in the approved plans.

    Take preventative action to ensure that similar problems dont happen again.

    12

  • Variance Analyses

    13

  • Variables for Variance Analysis

    Budgeted Cost For Worked Scheduled (BCWS)

    The budgeted amount of cost for word scheduled to be accomplished plus the amount of level of effort or apportioned effort scheduled to be accomplished in a given time period.

    Budgeted Cost For Work Performed (BCWP)

    The budgeted amount of cost for completed word, plus budgeted for level of effort or apportioned effort activity completed within a given time period. This is sometimes referred to as an earned value.

    Actual Cost For Work Performed (ACWP)

    The amount reported as actually expended in completing the work accomplished within a given time period.

    Cost Variance = BCWP ACWP

    Schedule/Performance Variance = BCWP - BCWS14

  • Methods of Variances Analysis

    The cost variance (CV) compares deviations only from the budget and does not provide a measure of comparison between work scheduled and work accomplished.

    The scheduling variance (SV) provides a comparison between planned and actual performance but does not include costs.

    15

  • Cost Variance Calculation

    A NEGATIVE VARIANCE INDICATES A COST OVERRUN

    CV = BCWP - ACWP

    16

  • Schedule Variance Calculation

    SV = BCWP - BCWS

    A NEGATIVE VARIANCE INDICATESA BEHIND SCHEDULE CONDITION

    17

  • Variance Percents

    SCHEDULE VARIANCE % =(SVP)

    COST VARIANCE % =(CVP)

    SVBCWS X 100

    CVBCWP X 100

    18

  • Classroom Activity 10a

    Consider a potential problem that could occur in your current project.

    What recommendation would you make to solve it and to whom would you make it?

    What alternatives would you suggest if they dont accept your recommendation?

    19

  • 20

    Questions?