improved return on investment through increased production, enhanced recovery… · 2018-02-12 ·...
TRANSCRIPT
Improved return on investment through increased production, enhanced recovery, and reduced cost
1
Per Bloch Helmers, OneSubsea Subsea Expo 2018, Aberdeen
HOW ENABLING SUBSEA BOOSTINGTECHNOLOGY AND A NOVEL BUSINESSMODEL UNLOCK INCREASED RECOVERYFROM A REMOTE DEEPWATER FIELD
2
1. Introduction to Dalmatian2. Development strategy3. Project overview4. Enabling technologies5. Business case6. Conclusions
Agenda
3
Acknowledgements:
Mike Clarke, Murphy Exploration and ProductionArill Smaaland Hagland, OneSubsea
Desoto Canyon Field Development Gulf of Mexico, 260 km southeast
of New Orleans Two-well tie back Marginal developments, challenging in
current climate (2016); daisy-chained phased development most economic
Depletion drive, limited aquifer support
The Dalmatian Field
4
Host: Chevron Petronius Platform• 550-m water depth• Limitations on pull tube and deck space
but available power
Phase 1: 35-km PIP oil well tieback and 38-km gas well tie back• 1,770-m water depth• Common 14 tube umbilical
Phase 2: 18-km extension to Phase 1• 1,980-m water depth
The Dalmatian Field
5
DC4 #1DC48 #1
Subsea Pump• Lowers wellhead
pressure• Increases near-term
production• Captures additional
reserves
Petronius(Chevron)
DC134 #2
DC134 #1(future)
DC91(future)
Studies undertaken to look at IOR• Water injection• Artificial lift
Lowest reservoir risk and higher confidence in enhanced production via subsea boosting
Integrated modeling• GAP and OLGA* dynamic multiphase flow
simulator
Sanctioned on existing two well production• Future well opportunities and improved
economics with boosted production
EPCIC contract• Onus on contractor to manage
interface risk• Functional specification• Fit-for-purpose design
Development strategy
6
Scope of supply (hardware):
Foundation Flowbase with interface arrangements Retrievable pump module Flowline jumpers Combined power and control umbilical Topside and subsea control system Topside power system Barrier fluid hydraulic power unit Tools and spares
Project overview
7
Scope of services:
Transportation Site-receive testing Installation of subsea equipment
and umbilical Support during installation of topside
equipment Support during pre-commissioning,
commissioning, and startup Training
Project overview
8
Mature and well-proven pump technology• Significant operating experience (>3mill hours)• Over 100 pump units• More than 200 MW of installed power
High-boost pump design• Result of joint industry partnership (JIP)
from 2007• Full-scale unit built and tested• Field proven on many projects
Dalmatian pump design• Heavily leveraged by JIP pump• Major reductions in risk, engineering, and lead
time• High-volume motor design key enabler
Enabling technologies
9
High-voltage motor design• 35-km step-out without subsea transformers
or high-voltage connectors
Based on the standard motor design• Voltage rating increased • No change in insulation design
Full-scale qualification program• Test program completed in June 2016
Game changer for marginal long-step-out tiebacks• Reduces hardware scope and complexity
Enabling technologies
10
Subsea Integration Alliance• Integrated schedule• Designed for installation• Interface management
Alternative business models Fit-for-purpose solution leveraging
previous experience
Committing to the Business Case
11
Thank you
12