Pierre Delebecque – Stephane Jezequel 2014-04-10 1 IBL - LAPP Cooling lines LAPP team Jacky Ballansat, Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque, Sabine Elles, Nicolas Massol, Thibaut Rambure, Theodore Todorov, Tamer Yildizkaya 1.Design and production status and schedule 2.Installation

Upload: jadzia

Post on 22-Feb-2016

53 views

Category:

Documents


0 download

DESCRIPTION

IBL - LAPP Cooling lines . Design and production status and schedule Installation. LAPP team Jacky Ballansat , Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque , Sabine Elles, Nicolas Massol , Thibaut Rambure, Theodore Todorov , Tamer Yildizkaya. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-101

IBL - LAPPCooling lines

LAPP team Jacky Ballansat, Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque, Sabine Elles,

Nicolas Massol, Thibaut Rambure, Theodore Todorov, Tamer Yildizkaya

1. Design and production status and schedule 2. Installation

Page 2: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-102

Design and production status

Page 3: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-103

Stainless steel cooling lines production Design and production status

14 A side lines 95% ready (last adjustments on the template (delivered W16), final bending in the Splitter box region and ends lengh adjustments to be done)

14 C side lines to be bent (W16)

Page 4: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-104

28 elements tested / 26 validated (all at room temperature 150 bars He and 3 at cold) – 10 % failed

IsolatorsDesign and production status

Page 5: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-105

Design almost finished (delay due to changes asked after the review / isolations) Delivery of the final models planned W17 Temporary plastic model will be produced for adjustments and welding phases

(W16)

Splitter boxes A and C sidesDesign and production status

Page 6: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-106

2 tables A and C sides to be delivered and mounted W16-W17 Inlet/outlet connexion (metalic version) delivered W18 – Plastic version should be

available W16-W17 for adjustments

Welding stands

Design and production status

Page 7: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-107

2 toolings A and C sides to be delivered and mounted W16-W17

Transportation toolings

Design and production status

Page 8: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-108

All the fittings have a cap protection Before any assembly and tightening the cone and the sphere is cleaned with alcool and

a visual inspection is done The more critical part is the sphere, located on a dismountable part (outside) Hundreds mounting/dismounting have been performed without any issue (LAPP and

SR1) All the fitting passed the leak tests with signals less that 10-8 mbar.l.s-1 @ 20 bars He

(spec is 10-5 mbar.l.s-1 @1 bar) When we first try to damage the fitting for the repair test the leak level was too low (10-7

mbar.l.s-1) so the technician had to scratch the surfaces once again.

1- Protection of the fittings an reability

Fitting protection and repair scenarii

Page 9: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-109

First step In case of issue : the torque can be increased up to 6 N.m Second step : put some glue between the sphere and the cone. The samples passed the

leak tests before irradiation but not after : conditions of the irradiation to be clarified. Third possibility : using a special metalic piece used a a seal between the sphere and

the cone (C.F Eric)

2- Repair scenarii

Gluing tool

Fitting protection and repair scenarii

Page 10: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-1010

Installation

Page 11: IBL - LAPP Cooling lines

Pierre Delebecque – Stephane Jezequel2014-04-1011

Installation – Transportation and assembly

Need a time slot (half a day) to check the transportation and flexible line deployment