IBL CO 2 cooling Vacuum control system development status 30.05.2013. Lukasz Zwalinski Thomas Eisel. Overview. Presentation overview. P&ID status Control system architecture overview Logic/start up sequence and interlocks definitions Components purchasing progres Rack layout proposal - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: IBL CO 2  cooling Vacuum  control  system development status 30.05.2013

IBL CO2 coolingVacuum

control system development status

30.05.2013

Lukasz Zwalinski Thomas Eisel

Page 2: IBL CO 2  cooling Vacuum  control  system development status 30.05.2013

Presentation overview• P&ID status• Control system architecture overview• Logic/start up sequence and interlocks definitions• Components purchasing progres• Rack layout proposal• Still to do

Overview

Lukasz Zwalinski IBL 30th May 2013

Page 3: IBL CO 2  cooling Vacuum  control  system development status 30.05.2013

P&ID Completed Conforming with vacuum systems in ATLAS

Lukasz Zwalinski IBL 30th May 2013

Page 4: IBL CO 2  cooling Vacuum  control  system development status 30.05.2013

Control system architecture

CERN Technical Network

CERN GPN

OWS OWS OWS

EN/CV Terminal server

Detector Control System

DIP

Central Control Room

Critical data tunnel from PLC to DCS

IBL plant ALocal MODBUS TCP/IP

Pneumatic lines

FESTO

WAGO I/Os

Local Touch Screen

Premium CPU Premium CPU

IBL plant BLocal MODBUS TCP/IP

Pneumatic lines

FESTO

WAGO I/Os

Local Touch Screen

Vacuum PLC

M340M CPU

Lukasz Zwalinski IBL 30th May 2013

Page 5: IBL CO 2  cooling Vacuum  control  system development status 30.05.2013

Lukasz Zwalinski IBL 30th May 2013

• Logic/start up sequence and interlocks definitions is completed

Logic

Page 6: IBL CO 2  cooling Vacuum  control  system development status 30.05.2013

Lukasz Zwalinski IBL 30th May 2013

Components purchasing status

• Most of the PLC components comes from ATLAS spare• Additional PLC components already ordered• Vacuum gauges and their red-out system ordered and mostly delivered• Electro valves + manual valve ordered• PR conditioners for safety actions ordered• Diffusion pumps ordered• Primary pumps ordered and delivered• Thermal switches for diffusion pumps ordered and delivered

Page 7: IBL CO 2  cooling Vacuum  control  system development status 30.05.2013

Lukasz Zwalinski IBL 30th May 2013

Rack layout proposal

USXUSA Seen from Geneva side

Accumulator unit A&B CO2 unit B300 Chiller unit B400 CO2 unit A100 Chiller unit A200 Control rack A&BVacuum control

New rack!H1600 W800 D800

Control racks new position!Moved by 800mm

FESTO

FESTO

Cable tray

Compressed air blocks (supply modules and

electro pneumatic valves)

Side view

AB

Page 8: IBL CO 2  cooling Vacuum  control  system development status 30.05.2013

Lukasz Zwalinski IBL 30th May 2013

Still to do

• Write functional analysis• Complete electrical schematics• Choose 24V DC power supply• Define/buy pull signal and power cables (we are in contact with Sergey and

LHC vacuum group)• Do 3D CATIA design of control cabinet• Design local interconnection boxes in UX15• Find a help to assemble control rack