  • CMS Electronics Week November 2002 1

    Electronics IssuesDrew Baden

    University of Maryland

    USCMS HCALUSCMS HCALUSCMS HCAL

  • CMS Electronics Week November 2002 2

    ShieldWall

    SBS

    HPD

    FE MODULE

    12 HTRs perReadout Crate,2 DCC

    FRONT-ENDRBXReadout Box (On detector)

    READ-OUT CrateTrigger Primitives

    Fibers at 1.6 Gb/s3 QIE-channels per fiber

    QIE

    QIE

    QIE

    QIE

    QIE

    QIE

    CC

    A

    GOL

    DCC

    TTC

    GOL

    CC

    A

    HTR

    HTR

    CALREGIONALTRIGGER

    32 bits@ 40 MHz

    16 bits@ 80 MHz

    CC

    A

    S-Link: 64 bits @ 25 MHz

    Rack CPU

    FE/DAQ ElectronicsFE/DAQ ElectronicsFE/DAQ Electronics

    CLK

    HTR

    DAQ

  • CMS Electronics Week November 2002 3

    Readout VME CrateReadout VME CrateReadout VME Crate“BIT3” board

    – Slow monitoring over VME– Commercial VME/PCI Interface to CPU

    FanOut board– Takes TTC stream in– Clone and Fanout timing signals

    HTR (HCAL Trigger and Readout) board– Spy output over VME– FE-Fiber input– TPG output (SLBs) to CRT– DAQ/TP Data output to DCC

    DCC (Data Concentrator Card) board– Input from HTRs– Spy output– Output to DAQ

    DCC

    VME CRATE

    20m Copper1.2 Gb/s

    DAQ

    Calorimeter Regional Trigger

    BIT3

    Fiber1.6 Gb/s

    FanOut

    HTR

    Front End Electronics

    HTR

    DCC

    HTR

    HTR

    ...

    TTC fiber

  • CMS Electronics Week November 2002 4

    HCAL RacksHCAL RacksHCAL Racks• HCAL will need 8 Racks

    • 2 crates/rack• ~200 HTR cards

    • ~3000 fibers and ~525 SLB with TPG cables• All I/O via front panels• Doors on front of rack required

    • Sufficient standoff to satisfy fiber curvature requirement• Keeps people from pulling out the fibers

    • Two 6U panels for cable/fiber support• Computer access in front of rack for fiber/TPG

    installation • Wireless in counting room?• Laptop/monitor/keyboard mounted somewhere close?

  • CMS Electronics Week November 2002 5

    TPG Cable IssuesTPG Cable IssuesTPG Cable Issues• Amphenol skew-clear cables work @ 20m ok

    • Skew spec ~125ps @ 20m running at 1.2Gbaud• Eye pattern will survive, BER = 10-15

    • Each cable carries 2 pair – need 2 cables per SLB connector• $100/cable + ~$150 for assembly/testing (custom connector molding)

    • Electrically these are very nice cables, but…• Formidable mechanical challenges – 6 of these beasts per HTR!

    • We are investigating quad cable, much thinner• Single cable, ~$180 for 20m• Would not require custom molding – much cheaper ~$30 for assembly• However…skew is almost x2 worse for 20m (230ps)• Amphenol spec says this will give 10-15 BER for 15m @ 1.6Gbaud

    • They were not clear about 1.2Gbaud – we will measure• If at all possible a 15m spec will:

    • Save money (~$100k)• Give breathing room on BER• Save 1 clock tick in L1 latency• Decrease mechanical risks on all boards

  • CMS Electronics Week November 2002 6

    VME Rack LayoutVME Rack LayoutVME Rack Layout• 56U Total rack height, 55 used

    (Note: Can recover 3U by using 1U exchangers)

    • Rack computer (3U)• Air circulation has to be front → back

    ala DAQ crate• Recirculation/Monitoring (4U)• Extra Heat Exchanger • 2 VME crate zones:

    • Cable support (6U) • Front panel only• Fibers and TPG cables are formidable

    • VME Crate (9U)• Air/Water heat exchanger (2U)• Fan Tray (2u)

    • Power Supply zone (6U)• Cheaper, robust, safe, D0/CDF• Air transport issue here• Will have to build wire harness• Put A/C circuit breakers here?

    • Return air guide (2U)Return Air Guide 2U

    SBS

    Air/Water Heat Exchanger 2U

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    DCC

    DCC

    TTC

    HTR

    9U

    Cable Strain Relief 6U

    Air/Water Heat Exchanger 2U

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    HTR

    DCC

    DCC

    TTC

    HTR

    9U

    Cable Strain Relief 6U

    Air/Water Heat Exchanger 2U

    Recirculation Fan & Rack Protection 4U

    Rack Computer (dual Intel/Linux) 3U

    Fan Tray 2U

    Fan Tray 2U

    Power Supply Zone 6U

  • CMS Electronics Week November 2002 7

    Power Consumption EstimatesPower Consumption EstimatesPower Consumption Estimates

    • VME crate ~ 1.2kW (2 crates/rack only)• HTR 70W/slot

    • 7A @ 5V = 35W• 11A @ 3.3V = 33W• Includes 6 SLBs, but many cards will have fewer• 13 or fewer HTR/crate = 910W

    • Fanout card ~20W/slot• .5A @ 5V = 2.5W• 4.5A @ 3.3v ~16W

    • DCC ~ 60W/double slot• 5A @ 5V = 25W• 10A @ 3.3V = 33W• S-Link64 current draw is a wild guess• 2 DCC/crate = 120W

    • Add power for rack computer, monitor and fans to get rack power• 1kW max

    • Total power dissipated by entire rack ~3.5kW• Note current CMS power consumption ~2kW/crate, >6kW/rack

  • CMS Electronics Week November 2002 8

    Production ScheduleProduction ScheduleProduction Schedule

    • Front-End• CCM Jun – Sep 03• FE cards Jul – Oct 03• RBX Aug 03 – May 04• HPD deliveries from now until Apr 04

    • HTR• Pre-production Jan 03, production Apr 03 – Sep 03

    • DCC• Motherboards nearly complete, logic cards by Aug 03

    • Awaiting final specs on S-Link64

    • Fanout Card• Complete soon after QPLL, Q2/03

  • CMS Electronics Week November 2002 9

    HCAL TriDAS Integration StatusHCAL HCAL TriDASTriDAS Integration StatusIntegration Status

    • First integration completed, summer 02• FE ⇒ HTR ⇒ DCC ⇒ SLINK ⇒ CPU

    • All links well established

    • No obvious clocking problems• Work needed on synch monitoring and reporting• Improvements expected using crystal for TI refclk

    • Will always have TTC/QPLL clock as backup…

    • HTR firmware fairly mature• Switch to Virtex2 all but complete• TPG and BCID ready but not tested

    • To commence when next HTR version delivered and Wisconsin TPG boards delivered (est Q1 2003 for testing to commence)

    • Will be main effort when next HTR version arrives Jan 2003

  • CMS Electronics Week November 2002 10

    HTR Production ScheduleHTR Production ScheduleHTR Production ScheduleO N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

    FirmwareBoard layoutFab/assembly 20 boards will be built but not assembled Pre-production HTR boardCheckoutBoard layout if neededFab/assembly if needed Production prototypeCheckoutProductionTestbeam ?Vertical Slice ?SLB Production

    2002 2003 2004 2005

    Issues:• Parts availability for HTR

    • Stratos LC’s, FPGAs, etc., so far so good – should make schedule ok• QPLL not needed for HTR since we have a Fanout card per crate

    • Firmware requirements• Will learn a lot in 2003…very far along now

  • CMS Electronics Week November 2002 11

    Integration Goals 2003Integration Goals 2003Integration Goals 2003• Continued development of HTR and DCC firmware

    • Commission TPG path• Firmware requirements/logic, LUTs, synchronization, SLB output…

    • Monitoring, error reporting, etc. • Preliminary US-based integration at FNAL Q1/03

    • Full system as in the previous testbeam• Except TPG which will be done initially at UMD, moved to FNAL if appropriate

    • Testbeam in the summer (to begin in spring)• Same goals as summer 02

    • Support calibration effort and continue commissioning the system• Operate a “vertical slice” for an extended period Q4/03

    • Fully pipelined, monitoring, TPG, DAQ, synchronization, clocking….

    • Develop software to support DAQ activities• Testbeam software improvements• Software for commissioning HTR needed

    • Allow us to verify fiber mapping, download LUTs, firmware version, etc.

    • By end of 2003 will have most of the HCAL TRIDas functionality

  • CMS Electronics Week November 2002 12

    Installation ScheduleInstallation ScheduleInstallation Schedule

    1st integration with L1

    Q3Q2Q1 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

    2003 2004 2005 2006

    Vert. Slice

    Testbeam

    Production

    RacksInstall in USC:

    Crates

    HCAL Alcove Tests (HB/E/O?)Integration

    HB in UXC

    HF in UXC

    HF mated

    No detector – rely on emulator for further commissioning/debugging

    Cable HB/F

    HE+ HE-

    Cable HECable HF

    TriDASIntegration

    HO in UXC

  • CMS Electronics Week November 2002 13

    Installation RequirementsInstallation RequirementsInstallation Requirements• Production cards will be available, all systems• Front-end emulator will be important

    • No other way to light up the fibers during installation• Design very close to actual front-end card (GOL, not TI)• Built by FNAL

    • Close interaction with UMD on board• UMD firmware

    • HCAL mapping nightmare will have to be implemented very carefully

    • Will need to be able to connect to rack CPU from inside shield wall as we plug the fibers in one at a time

    • Will need to have audio communication between operators inside shield wall and at VME racks

  • CMS Electronics Week November 2002 14

    HCAL InstallationHCAL InstallationHCAL Installation• We have a modest amount of stuff to be installed in USC:

    • 8 VME racks, 16 crates• ~3000 Fibers into front of HTR cards

    • Fibers laid by CERN personnel?• ~525 TPG cables from HTR’s to RCT

    • We will provide technician for installation• We will have 3 senior physicists at CERN:

    • Pawel de Barbaro, Laza Dragoslav, Dick Kellogg• Other personnel:

    • Post-doc(s), student(s), US-based physicist(s)…• In USC:

    • Need a place for someone to sit in front of HTRs when fibers are being plugged in

    • Access via HCAL Rack computer for VME access to cards• Wireless in counting house?• Mounted monitor/keyboard to interface with rack computer?• Both might be good…

    • Will there be cabinets, work benches, etc?

  • CMS Electronics Week November 2002 15

    Installation Manpower EstimatesInstallation Manpower EstimatesInstallation Manpower Estimates

    • Drawing on D∅ Level 2 experience for the current Tevatron Run 2a…

    • Each significant card requires on-site expertise:• Probably 1-2 postdoc-level (or above) and 1 engineer• Maybe the same engineer for both DCC and HTR…

    • HCAL will have an electronics setup at CERN• Total personnel estimate:

    • Front End 1• HTR 2• DCC 2• Miscellaneous (grad students, transients, etc.) maybe 4?

    • Very difficult to say with any accuracy

  • CMS Electronics Week November 2002 16

    HCAL ClockingHCAL ClockingHCAL Clocking• System Goals:

    • FE fiber physical layer synchronization locking• FPGA clock phase locked with LHC clock• Be able to achieve TPG alignment• Keep track of and handle BC0/EVN• Correct tagging of L1A bucket inside Level 1 pipeline

    • Known issues:• Random 4-5 clock latency within TI deserializer• Quality of TTC/QPLL clock jitter• Whether we can use crystals for TI refclk

    • Unknown issues:• Good point!

  • CMS Electronics Week November 2002 17

    FE ClockingFE ClockingFE Clocking

    • TTCex fiber input to CCM• Agilent Fiber receiver + TTCrx chip + QPLL

    • 40MHz clean clock converted to PECL• 40MHz clean PECL clock driven by 1-9 clock

    driver onto backplane to FE module

  • CMS Electronics Week November 2002 18

    FE LinkFE LinkFE Link• Issue:

    • FE uses GOL Tx and TI Serdes Rx (TLK2501)• TLK2501 requires

    • Refclk jitter < 40ps pkpk• Equivalent to 6.5kHz bandwidth on PLL

    • Frequency offset < ± 100ppm• Equivalent to ± 4kHz on fLHC

    • NB: commercial applications always use crystals• Solutions

    • Use crystal for Refclk, or…• QPLL jitter spec

  • CMS Electronics Week November 2002 19

    HTR SchematicHTR SchematicHTR Schematic

    P1

    to D

    CC

    P2

    LVDS

    to L

    evel

    1 C

    al T

    rigge

    r

    LVDS

    SLB

    SLB

    SLB

    SLB

    SLB

    SLB

    FPGAXilinxXC2V

    LCLC

    TITITI

    TI

    TI

    TITI TI

    LCLC

    FPGAXilinxXC2V

    LCLC

    TITITI

    TI

    TI

    TITI TI

    LCLC

    VMEFPGA

    Fibers

    No

    P3!

    8-way8-way

    88

  • CMS Electronics Week November 2002 20

    Clocking SchematicClocking SchematicClocking Schematic

    TTCrxTTC

    80 MHz LVPECL Crystal 1 to 8

    Fanout

    1 to 8 Fanout

    Single width VME

    BC080MHz40MHz

    SLB

    SLB

    SLB

    SLB

    SLB

    SLB

    TI(16)

    FPGA

    BC0 BC0

    40MHz 1 to 8 Fanout

    80MHz

    TTC mezzTTC TTC broadcast bus

    Cat 6/7 quad cable (allows LVDS/PECL)

    TTC FanoutBoard

    QPLL

    • Start with Fanout card• TTCrx Maryland mezzanine card or CERN TTCrm daughterboard• QPLL• Fanout on Cat6/7 quad twisted pair TTC, BC0, 40MHz, 80MHz

    • In HTR:• Send TTC signal to TTCrx mezzanine board, access to all TTC signals• Send 80MHz clean clock (cleaned by QPLL) to mux

    • Select 80MHz clean clock OR crystal to TI deserializers

    80 MHz

    40 MHz

  • CMS Electronics Week November 2002 21

    HCAL TRIDas Clock SchemeHCAL HCAL TRIDasTRIDas Clock SchemeClock Scheme

    TTCrx QPLL

    (‘CC’ means Clean Clock)

    Cat6/7 RJ45

    RJ45 TTCMezz

    TTC

    SLB

    Xilinx

    TTC broadcast, L1A, BCR, EVR, CLK40

    Fanout Card

    4 twisted pair…

    TTC BC0 CC40CC80

    HTR Board

    CC40

    CC80

    BC0

  • CMS Electronics Week November 2002 22

    Fanout – HTR schemeFanoutFanout –– HTR schemeHTR scheme

    HTR

    TTC fiber

    TTC LVDS

    CLK803.3V-PECL

    RX_BC0 LVDS

    Cat6Eor Cat7cable

    8 clksto TLKs

    DS90LV001

    Q1Q2Q3Q4Q5Q6Q7Q8

    MC100LVE3103.3V PECL

    CLK403.3V-PECL

    LVDSFanoutx 8

    PCK953LVPECL-to-LVTTLFanout(top layer)

    PCK953LVPECL-to-LVTTLFanout(top layer)

    8 clks to TLKs + TPs

    To 6SLBs

    Diff. to 2Xilinx+ termin.

    Diff. to 6 SLBsSingle-end to 2 xilinx

    TTCdaughter

    card

    ININ_b

    Brdcst,BrcstStr, L1A,BCntResto xilinxand SLBs

    CLK80 LVDS

    FanoutBoard

    Low-jitterFanout x 15

    O/E

    Brdcst,BrcstStr BC0

    Fanoutbuffer TTC

    TTC

    TTC

    FPGA

    Fanoutx 15

    Brdcst,BrcstStr,BCntRes,L1A

    CMOSLVDSor diffPECL

    ……..……..……..……..

    15 connectorson bottomlayer ?

    15 Cables &Connectorstbd

    ……..……..

    NB100LVEP221is LVDS compatible

    TTCrx

    (or daughter card)

    QPLL

    AN1568/D Fig 11Onsemi.com

    RJ45

    ~FifteenRJ45connectors

    PECLfanout

    e.g. DS90LV110

    ..

    ..2 TestPoints forCLK40andBC0

    CLK40 LVDS

    PECLfanout

    ..

    ..

    ..

    ..

    80.0789 MHz3.3V crystalDiff. PECL

    MC100LVEL37

    CKCKCK/2CK/2

    ..

    ..

    ..

    ..

    9U Front-panel space = 325 mm ; => space per connector ~ 21.5 mm

    Notes: SLBs require fanout of CLK40, BC0. FE-link possibly requires CLK80. PECL fanout was tested in TB2002. One Cat6E cable (low x-talk) replaces the 2 Cat5 cables used in TB2002. TTC and BC0 remain LVDS as in Weiming’s board.HTR needs Broadcast bus, BCntRes and L1A: from TTCrx if we get it to work, otherwise we have to fan them out.

    LVDS

    Tullio Grassi

  • CMS Electronics Week November 2002 23

    TTCrx Mezzanine cardTTCrxTTCrx Mezzanine cardMezzanine card

    • Very simple card:• 2 PMC connectors• TTCrx chip• TTC signal

    receiver and driver on motherboard

    • Used by HTR, DCC, and Fanoutcards

  • CMS Electronics Week November 2002 24

    TTC Distribution – Fanout CardTTC Distribution TTC Distribution –– FanoutFanout CardCard

    • Currently HCAL has 6 TTC partitions:• Each partition requires TTCvi and TTCex• Each HCAL VME crate will have a single TTCrx

    receiving data directly from TTCex in a single VME card (Fanout Card)

    • Fanout TTC signal to HTR mezzanine card with TTCrx chip

    • Use quad twisted pair CAT6/7 cable• TTC and BC0 fanout using LVDS• Also fanout of 40 and 80MHz clean clocks over LVPECL

    • Cost savings and simplification• TTC monitoring by Fanout card over VME

  • CMS Electronics Week November 2002 25

    TTC MonitoringTTC MonitoringTTC Monitoring

    • Chris Tully has built a very nice TTC monitoring board:

    • 6U VME form factor board• Needs only 5V power, so could be used as a standalone monitor

    with an appropriate battery

    • Hosts a TTCrm module• Front-panel LEDs displays:

    • TTC system activity• History of broadcasts• Event counter/bunch counter values

    • Useful for debugging and monitoring.

  • CMS Electronics Week November 2002 26

    TTC Display BoardTTC Display BoardTTC Display Board

  • CMS Electronics Week November 2002 27

    Random Latency IssueRandom Latency IssueRandom Latency Issue•Texas Instruments TLK2501 Serdes

    • Run with 80MHz frame clock – 20 bits/frame, 1.6GHz bit clock• 626ps bit time

    • Latency from data sheet:• “The serial-to-parallel data receive latency…fixed once the link is well

    established. However…variations due to… The minimum…is 76 bit times…the maximum is 107 bit times…”

    • Latency is 47.5 to 66.875 or 19.4ns – could cross a 40MHz bucket boundary!

    •How to fix? Two ways• SLB “knows” this latency – we will read it out after each reset• HCAL LED fast rise time

    • Can pulse during abort gap and align channels• Requires LED pulsing alignment

  • CMS Electronics Week November 2002 28

    TPG AlignmentTPG AlignmentTPG Alignment

    • TPG alignment performed in SLB• Necessary: All HTRs will send common BC0 to SLB’s

    within each of 16 VME crates• Calibration procedure to be performed for crate-crate

    alignment• Initial alignment with LEDs, laser, etc.• Final alignment with LHC first beam data

    • CMS should consider pushing for initial beam with only 1 bucket populated

    • This will ensure successful alignment

  • CMS Electronics Week November 2002 29

    DAQ AlignmentDAQ AlignmentDAQ Alignment

    • DAQ data must also be aligned• Must know L1A bucket for zero suppression• Solution: discussed in previous slide

    • Read from SLB• FE sending known ID after with fixed offset relative to

    BC0 during abort gap• Comparison of the two for error checking

    • DAQ check on BC0 in DCC for alignment• Will send BC0 and EVN with the data to DAQ

  • CMS Electronics Week November 2002 30

    MISC ErrorsMISC ErrorsMISC Errors• What happens if DCC finds mismatch in EVN?

    • DCC will then issue reset request to aTTS system• Details not yet defined but is fully programmable

    • Fiber Link/synchronization errors (GOL/TI)• Work out protocols to inform DCC

    • Reset requests to aTTS as well

    • FE Clock/GOL PLL link errors• If GOL loses synch, then transmitter will send out IDLE

    characters• IDLE characters are illegal in a pipelined system!

    • HTR will trap on IDLE as a signal that FE/GOL is having trouble