erection guide - new inside page - mabani steel mabani steel llc erection guide is intended to be an...
TRANSCRIPT
ERC/EG-2014-Rev00 1-Jan-2014
1
ERC/EG-2014-Rev00 1-Jan-2014
2
MABANI AIM
Mabani Steel LLC produces high quality, Pre-Engineered Metal Buildings. For your new building to yield optimum integrity and durability, proper assembly & Erection is required. This Erection Guide provides general assembly instructions.
The Mabani Steel LLC Erection Guide is intended to be an aid to your Pre-Engineered Erection Drawings, which dictate specifi c building parts and construction details. Mabani Steel LLC assumes that only an experienced, knowledgeable erector with trained crews and proper equipment will perform the assembly & erection.
The methods & procedures suggested by this Erection Guide are fundamental in nature and present good, safe erection practices. They can, and should, be modifi ed when necessary to adapt to special conditions or circumstances. Before beginning, familiarize with the building details and sequence of erection. Some buildings need complex sequence of erection; those must be processed & assessed by specialist before execution.
All anchor bolts in the concrete pedestals must be casted in compliance with the Mabani Steel LLC’s Anchor bolt Setting Plan Drawing marked “Issued for Construction”. This must be done by the assigned civil work contractor and should be checked by Mabani steel LLC’s Erection specialist prior to move in or start of erection. The responsibility and accuracy of placement of all anchor bolts rests to the Customer and his assigned civil contractor.
Prior to starting the erection, all the anchor bolts cast must be thoroughly double checked for the following such as: location, dimensions, orientation, projection/level, center to center distance and the squareness of the structure.
Check again all anchor bolts threads must be free from any concrete or rusting.
Ensure all anchor bolts levelling nuts were fi xed according to the required level and projection.
Any discrepancies found must be reported immediately and require action must be taken by the assigned civil contractor to immediately rectify.
Mabani Aim
Anchor Bolt Position Cross Checking
Initial Requirements Prior to Start Erection Activity
Required Basic Erection Equipment & Tools
Safe Unloading & Effective Storing Procedure
Segregation, Preparation & Assembling
Basic Erection Execution Sequence
Bolt Tightening & Inspection Procedure
Under Column Grouting Details
Touch up Paint
Correct & Incorrect Ways
PPA / Sheeting Work Procedure
Insulation
Gutter & Down Spout Pipes
Fasteners at a Glance
Water Leak Test Method Statement
Container Unloading Procedure
Important Notes
Accreditation
02
02
03
03
04
04
05
11
12
12
12
15
16
18
19
19
20
22
23
CONTENTS PAGE
ANCHOR BOLT POSITION CROSS CHECKING
ERC/EG-2014-Rev00 1-Jan-2014
3
INITIAL REQUIREMENTS PRIOR TO START ERECTION ACTIVITY
Prior to commencement of the steel erection, Mabani will visit / check the actual condition, readiness of the site and double check the following listed below:
UNLOADING EQUIPMENT: Fork Lift, Tele Handler or Mobile Crane
LIFTING EQUIPMENT: Mobile Crane, Tower Crane
ACCESS EQUIPMENT: Man Lift, Scissor Lift, and Mobile Crane/Tele Handler with Man Basket
POWER TOOLS: Screw Gun, Drilling Machine, Nibbler, Reciprocating Cutter etc.
[ NEED: plan showing 5 M clear around perimeter of building2 access ramp & compacted ground ]
The 5 meter wide clear, levelled/compacted and unobstructed passage area around the building is required to facilitate access of our erection equipment and for the installation of scaffolding.
Backfi lled and compacted ground area inside the building is require to facilitate the access in manoeuvring of the equipment during the erection.
Access ramp is also required to facilitate movement in and out of the equipment in the building.
The site area should be checked for overhead electrical lines and should be free from any other overhead utilities.
Prior to moving in and starting the erection, handing over from the civil contractor must be received /secured that full area is ready move in and erection. If the concrete fl oor will be completed prior to start erection it will be advantage.
243524372438243924342433243224312430242924282427242624252424242324232422242124202419241824172416241524142413 243556789101112131415161718192021222324252627284 293031
ANCHOR BOLT
CRITICAL DIMENSION
2439
MEASURE ALL CRITICAL DIMENSIONSCD1, CD2, CD3 ARE SAMPLE CRITICAL DIMENSIONS
CD1 CD2 CD3
STEE
L LI
NE
STEE
L LI
NE
STEE
L LI
NE
STEE
L LI
NE
GR
ID L
INE
GR
ID L
INE
ANCHOR BOLT
ANCHOR BOLT
STEEL TAPEANCHOR BOLT PROJECTION 'D' SHOULD BE SAME AS THAT IN ERECTION DRAWING
D
[ Check individual anchor bolts for size, projection &distance from other bolts in the group ]
[ Check critical distance, span, bay spacing & diagonal distance from anchor bolt group to group ]
REQUIRED BASIC ERECTION EQUIPMENT & TOOLS
RA
MP
RA
MP
SW STEEL LINE
PEDESTALS
EW STEEL LINE
MAN LIFT MOVEMENT
LOAD ALLMOVEMENT
MOBILE CRANEMOVEMENT
MAN LIFTMOVEMENT
MAN LIFT MOVEMENT
5m CLEAR ANDCOMPACTED ALL AROUND
LEVELLED AND COMPACTED FLOOR
NOTE : Mabani will not be liable for any damage to concrete slab.
ERC/EG-2014-Rev00 1-Jan-2014
4
[ Inclined storage to allow water run off ]
[ Refer part mark drawing to segregate the materials near respective grids ]
SAFE UNLOADING & EFFECTIVE STORING PROCEDURE
SEGREGATION, PREPARATION & ASSEMBLING
G/L G/L G/L G/L G/L G/L G/L
G/L
G/L6 FASTNERS AND LOOSE CLIPS
5 PANEL BUNDLE
4 SECONDARY MEMBERS BUNDLE (EAVE STRUTS, GIRTS, PURLINS ETC.,)
3 ENDWALL RAFTER
2 ENDWALL COLUMN
1 MAIN FRAME MEMBERS
6
6
5
4
5
44
3
3
4
2
1
1
2
S/L ITEM
STORAGE AND PROTECTIONFOR PANEL SHEETING SLOPE FOR DRAINAGE
WOODEN SPACERS
WOODEN SPACERS
1.5 M MAXIMUM
SPACING
SLOPE FOR DRAINAGE
1.5M MAXIMUMSPACING
STORAGE AND PROTECTIONFOR STEEL MEMBERS
NOTE: SANDWICH PANELSTACKING MAXIMUM OF2 BUNDLES ONLY
TEMPORARY PACKING
WOODEN SPACERS
ERC/EG-2014-Rev00 1-Jan-2014
5
[ Lift the column with suffi cient guy wire rope ]
[ Tightened the nut over supplied washerafter plumbing the column ]
BASIC ERECTION EXECUTION SEQUENCE
Each of our buildings are customer specifi c, different in specifi cations; shape, size and weight etc, hence erection sequence for each buildings differ. Here we have illustrated erection sequence for a simple box building with clear span up to 30 M & height within 10 M. For different building systems the fundament erection procedure is followed with detailed sequencing system referring to particular building size & weight.
GROUND RULE: Erection always starts on a braced bay.
SNUG TIGHTED ANCHOR BOLT
COLUMN IN ERECTED CONDITION
FINISHED FLOOR
[ Similarly erect other columns ]
RF COLUMN
TEMPORARY CABLE BRACE STAY
GROUP ANCHOR BOLT
2
A
3
C
TEMP STAY(Typ.)
ERECTION MARKS:
WHEN STEEL MEMBERSHAVE CRITICALORIENTATIONREQUIREMENTS AND WHERE IT IS POSSIBLE TO FIT THOSE MEMBERSINCORRECTLY AN ERECTION MARKCAN BE FOUND ON THE MEMBER. THIS ERECTIONMARK IS A SMALL ROUND PLATE WELDED BUTINDICATED IN THE ERECTION DRAWINGS BY THIS SYMBOL.
ERECTION MARK
PLATE AT THE MARKED END.
BEAMS WITH ERECTION MARKS SHOULD BEERECTED WITH THE WELDED
RF COLUMN
CRANE HOOK
GUIDE ROPE
2
A
TEMPORARYSTAY
NYLON BELTHEAVY DUTY
ANCHOR BOLT
NUTWASHER
FINISHED FLOOR ADJUSTABLE
NUT
[ Position the column on levelling nut ]
[ Tie all the temporary bracings before releasing the crane load ]
RF COLUMN
TEMPORARYSTAY
ANCHORBOLT
BASE PLATE
A
2
ERC/EG-2014-Rev00 1-Jan-2014
6
[ Install the side wall girts ]
RF COLUMN
WALL GIRT
TEMPORARY CABLEBRACE STAY
CONNECTION BOLT
WALL GIRT IN ERECTED CONDITION
WALL GIRTCONNECTEDTO COLUMN
GIRT
GIRT CLIP
2
3
A
RF COLUMN
WALL GIRT
TEMPORARY CABLE BRACE STAY
GROUPANCHOR BOLT2
A
3
C
[ Repeat the steps on opposite side wall ]
ERC/EG-2014-Rev00 1-Jan-2014
7
ERECTED COLUMN
CRANE HOOK
GIRT INSTALLED
SPREADER BAR
RAFTER
COLUMN
2
3
A
C
TEMPORARY CABLE BRACINGSTAYGUIDE ROPE
GUIDE ROPE
FLANGE
BRACE
RAFTER
BOLT
FLANGEBRACE
RAFTERASSEMBLY
[ Lift & erect the rafter assembly, ensure to tie enough guy wire ropes & tag lines ]
SUPPORT
RIDGE SPLICE PLATE
BOLT
FLANGE BRACE
FLANGEBRACE
RAFTER
BOLT
STEEL ROPE FORTEMPORARY STAY
GUIDE ROPE
GUIDE ROPE
[ Position & rig the rafter assemblies ]
SUPPORT
RIDGE SPLICE PLATE
BOLT
[ Assemble the rafters, don’t forget to install the fl ange braces & tighten the splice joints ]
RAFTER
CONN. BOLT
RAFTER
SUPPORT
RIDGE SPLICE PLATE
BOLTNUT & WASHER
AFTER BOLT CONNECTION ON ONE SIDE
SUPPORT
ERC/EG-2014-Rev00 1-Jan-2014
8
[ Similarly lift & erect the other rafter assembly of the 1st braced bay ]
[ Fill the purlins in between ]
TEMPORARYCABLE BRACINGSTAY
TEMPORARYCABLE BRACING STAY
TEMPORARYCABLE BRACINGSTAY
ROOF PURLIN
NOTE: FLANGE BRACES TO BEFIX AFTER INSTALLING PURLINSBAY BY BAY
2
3
A
C
FLANGE BRACEINSTALLED / FIXED
CRANE HOOK
SPREADER BAR
RAFTER ASSEMBLY
TEMPORARY CABLE BRACINGSTAY
TEMPORARY CABLE BRACINGSTAY
2
3
A
C
FLANGEBRACE
GUIDEROPE
TEMPORARY CABLE BRACINGSTAY
ERC/EG-2014-Rev00 1-Jan-2014
9
[ Install all the roof & wall bracings and align the bay ]
GROUND RULE: Proceed to next bay only after aligning the 1st Braced bay
BRACED BAY
BRACED BAY
2C
3
4
5
6
7
8
9
ATEMPORARY
CABLE BRACINGSTAY
TEMPORARYCABLE BRACING
STAY
TEMPORARYCABLE BRACINGSTAY
NOTE: TEMPORARY CABLE SHOULDNOT BE REMOVED ON BOTH ENDWALLSUNTIL ROOF SHEETING WORKS COMPLETED.
FLAT WASHER
NUT
HILLSIDE WASHER RAFTEREYE BOLT
SLOT IN WEB TO INSERT
HILLSIDE WASHERAND EYEBOLT
BRACE GRIP
CABLE
[ Details of installing hill side washer for cable bracings or rod bracings ]
TEMPORARYCABLE BRACING
STAY
TEMPORARYCABLE BRACING STAY
ROOF PURLIN
ROOF BRACING
WALLBRACING2
3
A
C
TEMPORARYCABLE BRACING
STAY
[ Similarly erect the other frames on grids ]
ERC/EG-2014-Rev00 1-Jan-2014
10
BAY DIMENSION
(CEN. TO CEN. OF COLUMN OR RAFTER WEB)
SMALL ANGLE
PROJECTION
SMALL ANGLE
PROJECTION
NOTE : PROJECTION OF HILLSIDE WASHER SHOULD COME ON THE SMALL ANGLE SIDE
LARGE ANGLE
LARGE ANGLE
HILL SIDE WASHER
HILL SIDE WASHER
PROJECTION
PROJECTION
G/LG/L
CENTER LINE OF CABLE
FINISHED FLOORSTEEL LINE
RIGID FRAME
COLUMNPORTALCOLUMN
NOTE:TEMPORARY STAYS NOT SHOWN
PORTAL BEAM BRINGING TO PORTALCOLUMN WITH CRANE HOIST
DOUBLEANGLE BRACING
SPACER
GUSSET PLATE
CONNECTION DETAILS OF ANGLE BRACING
[ Details of installing hill side washer for cable bracings or rod bracings ]
[ Details of installing portal bracing ] [ Details of installing angle bracings ]
[ Details showing purlin overlap, fl ange brace & lapping bolts ] [ Details of installing strut purlin with stabilizers ]
400 400
675
RAFTER
FLANGE BRACEGUSSET
LAP BOLTLAP BOLTFLANGE BRACECONN. BOLT
FLANGEBRACE
PURLIN
CONN. BOLT
RAFTER
PURLINCLIP
VIEW - 'A'IF IT IS REQUIRED BYDESIGN. CHECK ERECTION DRAWINGISSUED FOR CONSTRUCTION.
'A'
CONN.BOLT
NOTE: FLANGE BRACE MAYBE PRESENT ON BOTH SIDE
1500(MAX) 1500(MAX) STABILIZER
SDSFASTENER
ERC/EG-2014-Rev00 1-Jan-2014
11
[ Position of nuts before & after turn off the nut method ]
BOLT TIGHTENING & INSPECTION PROCEDURE
TIGHTENING:Ensure all connection bolts have been installed as per issued for construction drawings; verify the sized mentioned in the erection drawings.
All the bolts should be brought to Snug tight position before tensioning. (Position the bolts to snug tight by manual operation using an ordinary spud wrench. A full effort of an erector using an ordinary spud wrench would bring the bolt to a snug tight position. No wrench extension or long wrenches should be used to bring the bolt to a snug tight position in order to avoid tensioning. A 300 mm long spud wrench is normally used)
Once the snug tight position is achieved, the outer face of the nut shall be match-marked with the help of a permanent marker pen.
After marking further tightening / tensioning shall be proceed until the desire nut rotation meets requirement shown in Table 8.2 (Tightening shall be carried out Manually by extending the spud wrench length or increasing the number of erectors to two; electric impact wrench can also be used, but ensure to avoid over tensioning)
INSPECTION:
Inspection of bolts shall be visual
check of match marks before and
aft er bolt tightening. Th e bolted
connection shall be accepted when
match marks have reached the
required rotation as stated in table 8.2
Th e QC Inspector shall keep records of inspection of connections, 10% of bolts shall be inspected at random
connections, out of which 90% must pass for successful inspection.
13
13
Table 8.2. Nut Rotation from Snug-Tight Condition for Turn-of-Nut Pretensioning a,b
Disposition of Outer Face Bolted Parts
Bolt Length c
Not more than 4db
More than 4dbbut not more than 8db
More than 8dbbut not more than 12db
Both facesnormal tobolt axis
1/3 turn
1/2 turn
2/3 turn
Nut rotation is relative to bolt regardless of the element ( nut or bolt) being turned. For required nut rotations of 1/2 turn and less,the tolerance is plus or minus 30 degrees, for required nut rotations of 2/3 turn and more, the tolerance is plus or minus 45 degrees.
Applicable only to joints in which all material within the grip is steel.
When the bolt length exceeds 12 db, the required nut rotation shall be determined by actual testing in a suitable tension calibrator
Beveled washer not used.
1/2 turn
2/3 turn
2/3 turn
5/6 turn
5/6 turn
1 turn
One face normal tobolt axis, other slopednot more than 1;20 d
Both faces slopednot more than 1;20
from normal to bolt axis d
ERC/EG-2014-Rev00 1-Jan-2014
12
UNDER COLUMN GROUTING DETAILS
Th e purpose of providing a grout pocket above fi nish
fl oor is to allow for the correction of uneven pedestal
heights.
Mabani Steel LLC details almost all buildings allowing
for a 50mm grout under the column base plates
measured upwards from fi nished fl oor level. It is
important to understand that provision must be made
for this grout at the time of setting anchor bolts by
ensuring that the projection of the anchor bolts is as
per the latest “Issued For Construction” anchor bolts
drawings. Failure to do this will aff ect building eave
height, interior vertical clearances, sidewall and end
wall door framed openings and may limit the erector’s
ability to level the building correctly.
Th e Civil Contractor is responsible for providing and
setting the non-shrink grout immediately aft er the
erector has declared that the erection of the PEBSS of a
building or area of a building (in the case of large foot
print buildings) is complete.
Th e Civil Contractor should ensure that the grout is in
full bearing against the underside of the column base
plate and no air pockets remain around the anchor bolts.
In buildings with mezzanines it is extremely important
that the grout is set prior to casting of the mezzanine
slab. Failure to set the grout in a timely manner i.e.
before the mezzanine slab is cast or before the use of
overhead cranes (if present) may result in deformation
to the base plates and columns, necessitating expensive
rework or replacement.
RIGID FRAME COLUMN
50MM NON-SHRINKABLE GROUT
(BY OTHERS)
ANCHOR BOLTSTRAIGHT TYPE
(TYP)CONCRETEPEDESTAL BY OTHERS
BASE PLATE
TOUCH UP PAINT
CORRECT & INCORRECT WAYS
Touch up paint during & aft er erection is always a part of erection method statement. As scratched developed during
erection / mechanical damages must be addressed immediately by proper surface preparation & application of
proper coating to avoid corrosion.
GROUND RULE: it’s wiser to address the touch up paint at ground than at height.
[ Correct & Incorrect installing desk panels ]
CO
NC
RE
TETH
ICK
NE
SS
150
JOIST
DECKING PANEL
EDGE ANGLE
CORRECT WAY INCORRECT WAY
CO
NC
RE
TETH
ICK
NE
SS
150
JOIST
DECKINGPANEL
EDGE ANGLE
ERC/EG-2014-Rev00 1-Jan-2014
13
[ Correct & Incorrect way of panel lapping ]
[ Correct way of lifting single skin & sandwich panels ]
START OFPANEL END OF
PANEL
SYPHONBREAK
SYPHONBREAK
BEAD MASTIC @ SIDELAP NORMALLYNOT REQUIRED WHEN A SYPHON BREAK ISPRESENT IN THE PANEL
INCORRECT WAYCORRECT WAY
NOTE:
CRANE HOOK
SPREADER BAR
TEMPORARYPACKING
CORRECT WAYFOR SINGLE SKIN PANEL
CRANE HOOK
SPREADER BAR
WOOD PALLETSUPPORT
WOOD PALLETSUPPORT
CORRECT WAYFOR SANDWICH PANEL
TEMPORARY PACKING
WOODEN PALLET SUPPORT
ERC/EG-2014-Rev00 1-Jan-2014
14
[ Collateral hangings loads from purlins, correct method ]
[ Collateral hangings loads from rafters, correct method ]
[ Correct & Incorrect way for the erection: beams, rafters & columns ]
DO NOT HANG COLLATERAL LOADS FROM BOTTOM FLANGE OF PURLINS. ATTACH COLLATERAL LOADS TO THE WEB OF PURLIN. ALTERNATIVELYCOLLATERAL LOADS CAN BE HUNG BY A BRIDGING ANGLE (BY OTHERS) ATTACHED TO THE BOTTOM FLANGE OF TWO ADJECENT PURLINS.
CO
LLAT
ER
AL
LOA
D
ROOF PURLIN
CORRECT WAY
ATTACH THE LOAD TOBRIDGING ANGLE
ROOF PURLIN
CO
LLAT
ER
AL
LOA
D
DO NOT ATTACH THE LOADTO FLANGE OF PURLIN
INCORRECT WAY
CO
LLAT
ER
AL
LOA
D
CO
LLAT
ER
AL
LOA
D
DO NOT HANG COLLATERAL LOADS FROM ONE SIDE OF BEAM FLANGE. ATTACH COLLATERAL LOADS TO THE BOTH SIDES OF BEAM BOTTOM FLANGE
CO
LLAT
ER
AL
LOA
D
CO
LLAT
ER
AL
LOA
D
CORRECT WAY INCORRECT WAY
NOTE:STIFFENER IS NOT ALLOWED TO BE CUT
FLANGE/WEB IS NOT ALLOWED
TO PUNCTURE ANY HOLES
CORRECT WAY INCORRECT WAY
ERC/EG-2014-Rev00 1-Jan-2014
15
PPA / SHEETING WORK PROCEDURE
GROUND RULE: Sealant is must to avoid any water leakages in future.
1
2
3
A
B
C
FIRST PANEL @ EAVE
SHEET PROJECTIONFROM STEEL LINE
GABLE ANGLE
EAVE STRUTSTEEL LINE
STRING LINE
ROOF PANEL
TEMPORARYCABLE BRACING
STAY
TEMPORARYCABLE BRACING
STAY
BEADMASTIC
FASTENERLOCATION
150ROOFPURLIN
ROOF PANEL
PANELFASTENER
ROOFPURLIN
ROOF PANEL
NOTE: TEMPORARY CABLE SHOULDNOT BE REMOVED ON BOTH ENDWALLSUNTIL ROOF SHEETING WORKS COMPLETED.
TOP OF RAFTERMASTIC
BEADPURLIN
150
200 LAP
SCREW 50FIXING
SECTION-P
PQ
TOP OF RAFTER
PURLIN
SCREW FIXING
SECTION-Q
STITCH SCREWS
STITCH SCREWSDS 4.8x20@ 500 O.C
'B'(TYP.)
'A'(TYP.)
NOTE: REFER THE ERECTION DRAWINGS FORTHE DIMENSIONS 'A' & 'B'
PURLIN @ PANEL LAP
INTERMEDIATE PURLIN
ROOF PANEL
ROOF PANEL
DETAIL 'A' DETAIL 'B'
[ Single skin panels laying, sealant & lapping details ]
[ Single skin panel lapping, sealant & fastening details ]
ERC/EG-2014-Rev00 1-Jan-2014
16
INSULATION
[ Sandwich panels lapping, sealant & fastening details ]
[ Laying Insulations on roof ]
A
SECTION - A
CB
CB
CB
CB
C
ROOF PURLIN @ PANEL LAP
SANDWICH PANEL
SANDWICH PANEL
SANDWICH PANEL
SANDWICH PANEL FASTENER (TYP.)
SHEETING ANGLE
SHEETING ANGLE
ROOF PURLIN
NOTE:SHEETING ANGLE IS REQUIRETO BE INSTALLED BEFORE LAYINGTHE SANDWICH PANEL AND TO FIX WITHDOUBLE LINE SCREW AS SHOWN SECTION 'A'
NOTE:REFER THE ERECTION DRAWINGSFOR THE DIMENSIONS 'B' & 'C'
BEAD MASTIC
CORRECT
TOO LOOSE
TOO TIGHT
[Correct screw tightening]
GIRT
1
2
3
A
B
C
EAVESTRUT
DOUBLEFACETAPE
RIDGE PURLIN
INSULATIONROLL
DOUBLE FACE TAPE
FIBERGLASS
INSULATION
200 - 250
FIBERGLASSINSULATION
NOTE: FOLLOW SAME PROCEDUREON GRIDLINE A & B, AS SHOWN INGRID B & C
GABLEANGLE
INSULATIONROLL
DOUBLE
TEMPORARYCABLE BRACE STAY
FACETAPE
ERC/EG-2014-Rev00 1-Jan-2014
17
1
2
3
A
B
C
SHEETINGPANELS
RIDGE CAPPANEL
SECONDINSULATIONRUN
TEMPORARYCABLE BRACE STAY
STEP 1 :- PULL TABS TOGETHER & STAPLE
FULL LENGTH AS SHOWN IN FIGURE
STEP 2 :- FOLD TABS OVER & STAPLE
STAPLES AS SHOWN IN FIGURE
INSULATION SIDE LAP
PREVIOUSSTAPLES
NEWSTAPLES
D.1
THRU FOLDED TABS BETWEEN PREVIOUS
AT APPROX. 150mm ON CENTERS ALONG
[ Laying ridge cap panel on roof ]
[ Laying Insulations on wall & Lapping details ]
EDGE ANGLE@ E.W
INSULATIONFACING(FOLDED)
WALL PANEL(FIRST RUN)
INSULATION(SECOND RUN)
UNFOLDEDEND
DET.C
[Temporary timber / wooden supportfor side girts alignment]
2
3
C
TEMPORARY
TIMBER
SUPPORTS
DETAIL-C
INSULATIONFACING
INSULATIONFACING
(FOLDED)
DOUBLEFACETAPE
ERC/EG-2014-Rev00 1-Jan-2014
18
[ Assembly of DSP & details ]
[ Gutter & DSP details ]
GUTTER & DOWN SPOUT PIPES
SLIT AT FOUR CORNERS OF THE DOWNSPOUT UP TO 30mm AS SHOWN ABOVE.
LINE CUTS
LINE CUTS
SHEAR SNIP
DOWNSPOUT
25 to 30 mm SLIT DOWNSPOUT
BENT END
UNBENT END
DOWNSPOUTSHOE
UNBENT END
BENT END
40 M
M (A
PP
RO
X.)
40 M
M (A
PP
RO
X.)
25 TO 30 MM BEND INWARD(TYP.)
BENT
INWARD
SLIGHTLY
VIEW AT BENT END
VIEW AT CUT SECTION
SLIGHTLY BEND INWARD ALL FOUR SIDES OF THE SLITTED END AT AN APPROPRIATE ANGLE JUST ENOUGH FOR THE DOWNSPOUT TO SLIDE INTO ANOTHER DOWNSPOUT OR DOWNSPOUT SHOE AS SHOWN IN FIGURE 3.
INSERT THE DOWNSPOUT INTO THE DOWNSPOUT AND/OR DOWNSPOUT SHOE.
POP RIVET (TYP.)
23
1
DOWNSPOUT
DOWNSPOUTSTRAP
POP RIVET(TYP.)
DOWNSPOUTSTRAP
POP RIVET
GUTTER & DOWN SPOUT PIPES
NOTE: DOWNSPOUT STRAP IS FOLDED AT SITE TO THE REQUIRED SHAPE
ERC/EG-2014-Rev00 1-Jan-2014
19
GUTTER & DOWN SPOUT PIPESFASTENERS AT A GLANCE
FIN-NECK BOLT STOVE BOLT POP RIVET GROMMET SELF DRILLING SCREWDECKING SCREW EXPANSION BOLT CONNECTION BOLT
[ Different kind of fasteners ]
WATER LEAK TEST METHOD STATEMENT
WATER LEAK TEST PROCEDURES:
Site Requirements for “water leak test”:
Manpower to conduct the leak test on site – 2 Erectors on roof to apply and 2 ground crew to check / observe underneath.
Water tank with the hose pipe (1 ½ “inch diameter) ready with enough length.
Key plan of the building, where the water leak test will be carried out.
Site preparation prior to conduct water leak test:
Prepare the roof area of the building for leak test. Double check all the possible roof penetration must be fully sealed off properly.
Mobilize the manpower and the water tank, ensure above requirements fully complied and checked prior to any water test.
Water Leak Test Application:
Safely access the 2 Erectors at the top of roof, who will conduct the application of water test. Water pressure must be normal and run through the lower rib of the roof panels.
Start the leak test on the fi rst bay at roof ridge (ridge panel) and let the water free fl ow through the roof panel, skylights, roof penetration, curved panel or to the gutter.
The ground crew will check underneath the roof, any water coming it will be marked on the ground fl oor. The applications will do until last bay of the building.
Any leaks must be repaired immediately and make the re-test until all marked points is cleared. Upon completion, the KEY PLAN will be marked / signed by all parties.
ERC/EG-2014-Rev00 1-Jan-2014
20
CONTAINER UNLOADING PROCEDURE
PROVIDE 2 OR 3MM THICK METAL STRIPS TO FORM `DISCHARGE TRACK' OF THE `TRACK' INSIDE THE CONTAINER AS SHOWN IN THE INSET DRAWING. MAKE SURE THAT THE LEVEL OF THE DISCHARGE TRACK IS THE SAME LEVEL AS THAT OF THE INSIDE TRACK. ONCE THE LEVEL OF INSIDE AND DISCHARGE TRACK IS ALIGNED, FIX THE DISCHARGE TRACK TO THE WOODEN TIES USING NAILS.
THE DISCHARGE TRACK IS CRITICAL.IT IS NECESSARY TO EVENLY SUPPORT THE WEIGHT OF
THE SPACING OF THE WOODEN - TIES SUPPORTING
THE SKID. THE TIES SHOULD BE LEVEL ANDWITH NO GAP BETWEEN THE TIES.
MAKE SURE THAT THE CONTAINER LIES ONSUITABLE LEVEL GROUND BEFORE OPENING.A MINIMUM OF 12 METERS MUST BE UNOBSTRUCTEDIN FRONT OF THE CONTAINER DOORS.
3
GROUND LINESKID INSIDETRACK
DISCHARGE TRACK
CONTAINER
DISCHARGE TRACK-`A'
INSIDE TRACK
WOODEN TIE
DISCHARGETRACK-`A'
TRACK-`B'DISCHARGE
TRACKINSIDE
TIEWOODEN
SKID
VIEW- A' '
' 'A
CONTAINER
CONTAINER IS ON THE BED OF THE TO UNLOAD THE CONTENTS WHILE THE ON FLAT GROUND. DO NOT ATTEMPTTHE CONTAINER MUST BE DISCHARGED
TRUCK. DO NOT TILT OR DRAG THECONTAINER.
1
2
ERC/EG-2014-Rev00 1-Jan-2014
21
GREASE THE DISCHARGE TRACK (AS SHOWN).SECURELY CONNECT ONE END OF A CABLE (OR CHAIN)TO SKID FRAME AND THE OTHER ENDTO DISCHARGE VEHICLE.
INSIDETRACKS
NAILS
AFTER REMOVING THE CONTENTSFROM THE CONTAINER, REMOVE THE INSIDE TRACKS FROM THE CONTAINER BYPULLING OUT THE NAILS.WHEN THE INSIDE TRACK HAS BEENREMOVED FROM THE CONTAINER THE CONTAINER IS READY TO BERETURNED TO THE TERMINAL.
6
PULL THE SKID FROM THE CONTAINER USING AN EVEN PULL SPEED. SAFETY SHOULD ALWAYS BE OBSERVED. DO NOT JERK THE SKID BY ACCELERATING DISCHARGE VEHICLE; CABLES (OR CHAINS) SHOULD ALWAYS BE TIGHT DURING ENTIRE DISCHARGE PULL. (SEE GENERAL NOTE 6)5
CONTAINER SKID
MEMBERSP.E.B.
CABLE
Unloading Vehicle
PULLDIRECTION
4
For outside UAE and other GCC countries the procedures shown are only a guidefor unloading the contents from the skid - packed "DRY" containers.
Safety should be observed at all times. MABANI STEEL is not responsible forany accident or damage resulting from carelessness on the part ofthe Contractor / Sub-Contractor or Customer.
To Unload the cargo Piece-By-Piece.To Unload the container components while the container is on a truck. OR
Under no circumstances should attempts be made either :A
B
Careful consideration of these guidelines and proper planning at theunloading point will result in a safe & damage- free unloading of the cargo.
The unloading vehicle must be capable of pulling20 Tons weight on the Greased Track.
The materials required to unload the containeraccording to this procedure, which are not includedin the scope of MABANI STEEL: Nails, Wooden Ties,Cables / Chains & Grease.
GENERAL NOTES
ERC/EG-2014-Rev00 1-Jan-2014
22
IMPORTANT NOTES
If Mabani Steel LLC is not being used to erect the buildings, Mabani Steel LLC accepts no responsibility for erection quality, defects or collapse due to negligence or improper erection procedure.
Mabani Steel LLC’s policy of continuous product improvement may necessitate change in materials, design specifi cations and procedures without notice.
FIRST AND FOREMOST! Rent a Forklift / Tele Handler / Mobile Crane, etc. or make necessary arrangements in advance to have your supplied building unloaded upon arrival !
Buyer /End User Responsibilities
It is the responsibility of the BUYER/END USER to obtain appropriate approvals and secure necessary permits from City, County, State, or Authorities as required, and to advise/release Mabani Steel LLC upon receiving such.
The BUYER/END USER is responsible for setting of anchor bolts in accordance with Mabani Steel LLC “Issued For Construction” drawings only. Use only fi nal “Issued For Construction” drawings. (Section 7 AISC Code of Standard Practice, 9th Edition).
A Mabani Steel LLC - Erection Specialist may be available to check the correct setting of anchor bolts.
Normal erection operations include the corrections of minor misfi ts by moderate amounts of reaming, chipping, welding or cutting, and the drawing of elements into line through the use of drift pins. Errors which cannot be corrected
by the foregoing means or which require major changes in member confi guration are to be reported immediately to Mabani Steel LLC by the BUYER/END USE CUSTOMER, to enable whoever is responsible either to correct the error or the approve the most effi cient and economic method of correction to be used by others. (Section 7 AISC Code of Standard Practice, 9th Edition).
All bracing shown and provided by Mabani Steel LLC for the building is required and shall be installed by the erector as a permanent part of the structure.
Any claims or shortages by buyer must be made to Mabani Steel LLC within seven (7) working days after delivery, or such claims shall be considered waived by the customer and disallowed.
Mabani Steel LLC has a commitment to manufacture quality buildings that can be safely erected. However, the safety commitment and job site practices of the erector are beyond the control of Mabani Steel LLC. It is strongly recommended that safe working conditions and accident prevention practices be the top priority of any job site. Local, State, and Federal safety and health standards should always be followed to help ensure workers safety. Make certain all employees know the safest and most productive way of erecting a building. All employees should know emergency procedures. Daily meetings highlighting safety procedures are also recommended. The use of hard hats, rubber sole shoes for roof work, proper equipment for handling material, and safety nets where applicable, are recommended.
ERC/EG-2014-Rev00 1-Jan-2014
23
esStee l Bu i ld ings and St r uctureS
A C C R E D I T A T I O N
ERECTION GUIDEPrepared By
General Manager - Steel Buildings Erection Services
AHMED HUSSAIN
Reviewed ByManagement Representative
NARGES FATTAH NIA
Approved ByPresident
TIMOTHY J LEFEBVRE
p