environmental and social impact assessment of the...
TRANSCRIPT
ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT OF THE UPPER MARIKINA DAM GREATER METRO MANILA AREA FLOOD MANAGEMENT PROJECT REQUEST FOT PUBLIC SCOPING 14 July 2017
for the
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Bonifacio Drive Port Area 652 Zone 068, Manila, 1018 Metro Manila and THE WORLD BANK
Prepared by DOHWA ENGINEERING CO., LTD. Project Consultant for the Feasibility Study and Preparation of Detailed Engineering Design of the Proposed Upper Marikina Dam and CHACHI CIVIL ENGINEERING SERVICES ESIA Subcontractor
REQUEST FOR PUBLIC SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
TABLE OF CONTENTS |xi
Table of Contents
ABBREVIATIONS AND ACRONYMS ......................................................................................................... xiii REPORT TITLE, AUTHORS AND DISCLAIMER .......................................................................................... xiv PROJECT SUMMARY ...............................................................................................................................xv CHECKLIST OF DOCUMENTS ................................................................................................................. xvii PROOF OF CONDUCT OF IEC ............................................................................................................... xviii RESULT OF THE PERCEPTION SURVEY ................................................................................................... xix PROJECT DESCRIPTION FOR SCOPING .................................................................................................. xxii 1. INTRODUCTION .................................................................................................................................. 1
1.1 Project Background and Rationale ............................................................................................. 1
1.2 ESIA Objectives ........................................................................................................................... 2
2. BASIC PROJECT INFORMATION ........................................................................................................... 3 1.3 Project Information .................................................................................................................... 3
1.4 Proponent Profile ....................................................................................................................... 3
3. PROJECT DESCRIPTION ....................................................................................................................... 5 1.5 Project Location and Area .......................................................................................................... 5
1.5.1 Project Location ............................................................................................................... 5
1.5.2 Area of Influence (AoI)..................................................................................................... 6
1.6 Impact Areas .............................................................................................................................. 7
1.6.1 Direct Impact Area (DIA) .................................................................................................. 7
1.6.2 Indirect Impact Area (IIA) .............................................................................................. 10
1.7 Regional Impact Zone (RIZ) ....................................................................................................... 11
1.8 Project Components List .......................................................................................................... 13
LIST OF FIGURES
Figure 0-1 Artist’s rendering of the Upper Marikina Dam ....................................................................... 1 Figure 0-1 Project Location, Proposed Upper Marikina Dam .................................................................. 6 Figure 0-2 General Layout of Flood Controls dowsnstream of UMD ....................................................... 8 Figure 0-3. UMD Catchment Area ........................................................................................................... 9 Figure 0-4 UMD Location Alternatives.................................................................................................. 10 Figure 0-5 River Basins, Lake Basin, and Drainage Basins in the Greater Metro Manila Area ............... 12 Figure 0-6. The Yokohama Dam - a similar structure to UMD ............................................................... 13 Figure 0-7 Typical Dam Sections ............................................................................................................ 14
LIST OF TABLES
Table 0.1 List of barangays in the catchment area of UMD ................................................................... 10 Table 0.2 Features of River Basins, Drainage Basins and the Laguna Lake Basin ................................... 11
REQUEST FOR PUBLIC SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
TABLE OF CONTENTS |xii
LIST OF PHOTOS
Photo 0.1 Montalban Gorge .................................................................................................................... 7 Photo 0.2 Visualization of UMD through the Montalban Gorge ............................................................. 7
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
ABBREVIATIONS AND ACRONYMS |xiii
ABBREVIATIONS AND ACRONYMS
DAO DENR Administrative Order
DED Detailed Engineering Design
DENR Department of Environment and Natural Resources
DFAT Department of Foreign Affairs and Trade
DIA Direct Impact Area
DPWH The Department of Public Works and Highways
ECC Environmental Compliance Certificate
EGF Environmental Guarantee Fund
EIA Environmental Impact Assessment
EIARC Environmental Impact Assessment Review Committee
EIS Environmental Impact Statement
EMB Environmental Management Bureau
EMP Environmental Management Plan
ESIA Environmental and Social Impact Assessment
ESMP Environmental and Social Management Plan
FS Feasibility Study
GDP Gross Domestic Product
GPS Global Positioning System
IEC Information Education Campaign
IIA Indirect Impact Area
IP Indigenous People
IPDP Indigenous People Development Plan
IRR Implementing Rules and Regulations
ISF Informal Settler Families
IUCN International Union for Conservation of Nature
JICA Japan International Cooperation Agency
LGU Local Government Unit
MCM Million Cubic Meter
MGB Mines and Geoscience Bureau
MOA Memorandum of Agreement
NGO Non-Government Organization
NTP Notice to Proceed
NWRB National Water Resources Board
PAGASA Philippine Atmospheric Geophysical and Astronomical Services Administration
PAPs Project Affected Persons/People
PAWB Protected Area and Wildlife Bureau
PD Presidential Decree
PDS Project Description for Scoping
PEISS Philippine Environmental Impact Statement System
PHIVOLCS Philippine Institute of Volcanology and Seismology
PH-PTF Philippines Programmatic Trust Fund
RAP Resettlement Action Plan
RIZ Regional Impact Zone
RPM Revised Procedural Manual
SDF Social Development Framework
SDP Social Development Plan
SVAP Stream Visual Assessment Protocol
TSP Total Suspended Particle
UMD Upper Marikina Dam
UMRBPL Upper Marikina River Basin Protected Landscape
WB World Bank
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
TITLE | AUTHORS | DISCLAMER |xiv
REPORT TITLE, AUTHORS AND DISCLAIMER
Title REQUEST FOR PUBLIC SCOPING
Environmental and Social Impact Assessment of the Upper Marikina Dam Greater Metro Manila Area Flood Management Project
Beneficiary:
Department of Public Works and Highways Government of the Philippines
Consultants: DOHWA Engineering Co., Ltd.
ESIA Subcontractor: CHACHI Civil Engineering Services
Source of Project Funding: The World Bank
Study Team Members
Louernie F. de Sales, Ph.D. Welesito M. Rombaua, MA Julius F.B. Giron, RCE Joseph P. Lalo, MA Milben A. Bragais, MS Engr. Charlon Gonzales, MS Lorenzo Antonio Lim, RChE Maria Connie Alvior, RChE Chijun Kim, CE
Environmental Specialist and Team Leader Socio-Economic Analyst / Economist Water Quality Specialist/Water Resources Engineer Anthropologist Terrestrial Ecologist (Flora and Fauna) Air Quality Specialist/Climate Change Specialist Pollution Management Officer, EIA Specialist Environmental Specialist Waste Management Specialist
Document Revision Table
Version Number
Date of Issue Author(s) Brief Description of Change(s)
1 11 July 2017 Louernie F. de Sales, PhD and Team
2 20 July 2017 Louernie F. de Sales, PhD and Team
Changing the Document Title from Project Description for Scoping to Request for Public Scoping based o Section 7of the DENR Administrative Order 2017-015.
Disclaimer
The content of this report constitutes technical assistance provided solely for the project purpose and its terms of reference and is the sole responsibility of CHACHI Civil Engineering Services. The views expressed herein cannot be taken to be the opinion of the Department of Public Works and Highways (DPWH) or the World Bank (WB).
The authors welcome further discussion of issues raised in this report.
This report, and other project reports, should not be distributed without the written authorization of DPWH.
REQUEST FOR PUBLIC SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT SUMMARY |xv
PROJECT SUMMARY
Project Title: Environmental and Social Impact Assessment of the Upper Marikina Dam Greater Metro Manila Area Flood Management Project
Overall Project Goal:
Recurrent flooding has the greatest negative impact on the poorest populations who generally live in higher-risk flood prone areas. It restricts people’s ability to exit from poverty and inhibits growth. It causes damage to houses and property and impedes movement and traffic out of the flooded area thereby affecting productive capacities. Designing and investing in structural and non-structural flood management activities would reduce the vulnerability of the population to future flood events.
The Flood Management Master Plan for the Greater Metro Manila Area was prepared by the Government of the Philippines through the Department of Public Works and Highways (DPWH), with technical and financial assistance of the World Bank. Among the main large-scale priority interventions that were identified in the said master plan is the construction of a high dam in the upper Marikina river catchment area to reduce the peak flows entering the city during typhoon and other extreme rainfall events. At the end of rainy season, the dam will store water which will be released during dry season for supplementing raw water for water supply to Metro Manila and vicinity areas.
Overview and Scope: The Philippine Programmatic Trust Fund (PH-PTF) Grant and associated government funds finance the preparation of feasibility and design studies for a high dam in the upper Marikina River catchment area. For the World Bank, OP 4.01, Environmental Assessment, is triggered since the studies are expected to lead to investments expected to have positive but also potentially adverse environmental and social impacts if not managed adequately. On the side of the Philippine Government, the project proponent or DPWH must secure an Environmental Compliance Certificate (ECC) from EMB-DENR prior to implementing the dam construction. The Project Impact Areas includes the Greater Metro Manila Area and the barangays along the Marikina River in the municipalities of San Mateo, Tanay, Antipolo, and Rodrigues in Rizal Province.
The Environmental and Social Consultant is to undertake the Environmental and Social Impact Assessment (ESIA) in line with WB’s environmental and social safeguards and their policy objectives and following the Philippine Environmental Impact Statement System or Presidential Decree (PD) 1586, the DENR Department Administrative Order DAO No. 2003-30 or the Implementing Rules and Regulations of PD 1586, and all applicable laws, guidelines and regulations.
Other safeguard policies of the WB that triggered by the project are the following:
1) Natural Habitats OP/BP 4.04 2) Forests OP/BP 4.36 3) Physical Cultural Resources OP/BP 4.11 4) Indigenous Peoples OP/BP 4.10 5) Involuntary Resettlement OP/BP 4.12 6) Safety of Dams OP/BP 4.37 It is expected that the ESIA shall address the above policy concerns in an ESIA level of details. A Resettlement Policy Framework Plan and Indigenous People Framework Plan will be integrated into the ESIA Report.
The environment and social impact assessments for the Upper Marikina Dam will carefully assess the environment and social impacts including impacts from ancillary facilities as well as cumulative impacts, and lay out detailed plans for mitigation in the Environmental and Social Management Plan (ESMP), and develop a monitoring and reporting program. The ESMP will be properly costed to ensure that the costs get adequately incorporated into the overall investment proposals. The various options in terms of sites, alignments, and
REQUEST FOR PUBLIC SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT SUMMARY |xvi
resettlement/re-housing will also be analyzed as part of the ESIAs. A Grievance Redress Mechanism will be developed and will be detailed in the ESMP and be presented to the communities during public consultations.
The ESIA will identify natural habitats and other ecologically sensitive areas that may be affected by the investments when implemented. The project will not design activities that would significantly convert or degrade critical natural habitats. If the ESIA indicates that a project would significantly convert or degrade non-critical natural habitats, or affect physical cultural resources, the project would include acceptable mitigation measures to be implemented when the investments are financed. Such mitigation measures could include, as appropriate, minimizing habitat loss (e.g. strategic habitat retention and post-development restoration) and establishing and maintaining an ecologically similar protected area, as well as avoidance or preservation of physical cultural resources. The ESIA will confirm the project impacts on forests and forest-dependent communities, particularly in and around the proposed dam site. As needed, the ESMP will include measures to address impacts on forests, forest health, and forest-dependent communities.
Since the project will entail the design of a high dam as one of its investments, the OP on Safety of Dams is triggered. The policy requires that experienced and competent professionals design and supervise construction, and that the borrower adopts and implements dam safety measures throughout the project cycle.
REQUEST FOR PUBLIC SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT SUMMARY |xxii
PROJECT DESCRIPTION FOR SCOPING
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
INTRODUCTION | 1
1. INTRODUCTION
1.1 Project Background and Rationale
Typhoons and related flooding are regular events in the Philippines, with an average of 20 typhoons affecting the country per year. There seems to be a trend towards more numerous and more devastating floods in recent years, especially caused by human activities such as deforestation and rapid urbanization, and possibly by climate change. Metro Manila and the adjacent areas of Laguna de Bay and part of Bulacan Province, hereafter called the Greater Metro Manila Area, have not been spared during the past years. Considering that the Greater Metro Manila Area contributes about 35 percent to the economy of the Philippines and is home to around 17 million people, recurrent flooding has a negative impact on millions of people’s lives and the economy. This is worsening over time with rapid urbanization and land availability issues, requiring especially informal settler families (ISF) to live in danger zones. On September 26, 2009, one of the most severe tropical storms in history, Ondoy (internationally named Ketsana), affected the Greater Metro Manila Area. It caused substantial damage and losses, equivalent to 2.7 percent of Gross Domestic Product (GDP).
The adverse impacts on the productive sectors were largely due to damaged or lost inventories, raw materials, and crops. In addition, business operations were interrupted by access problems, power and water shortages, damaged machinery, and absent employees, which contributed to an overall reduction in production capacity. The Master Plan identified that a dam in the upper Marikina River catchment area would be the best structure to reduce the river flows to Metro Manila during major typhoon activity. Grants from the Philippines Programmatic Trust Fund (PH-PTF), which is being administered by the World Bank on behalf of Australia’s Department of Foreign Affairs and Trade (DFAT), and Japan Policy and Human Resources Development (PHRD) shall finance the development of feasibility study and the detailed engineering design of priority infrastructure.
Figure 1-1 Artist’s rendering of the Upper Marikina Dam
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
INTRODUCTION | 2
The proposed UMD project objective is to improve flood management and urban resilience in the Greater Metro Manila Area. Based on mathematical models linked to flood hazard maps and a detailed assessment of a long list of options, the Master Plan proposes a program of priority infrastructure to safely manage major flood events in the Greater Metro Manila Area. Among the key priority interventions that have been identified are: (i) a high dam in the upper Marikina River catchment area to reduce the peak flows entering the city during typhoon events; (ii) flood protection works in the Marikina River; (iii) land raising of certain sections of the flood plain of Laguna de Bay to protect the population against high water levels in the lake; and (iv) further development of a comprehensive flood forecasting system and monitoring and early warning system for the Greater Metro Manila Area, with maximum participation of local communities. The Upper Marikina Dam construction shall be the subject of this ESIA.
The feasibility study and preparation of detailed engineering design of the Proposed Upper Marikina Dam Greater Metro Manila Area Flood Management Project are being undertaken by a group of consultants led by DOHWA Engineering Co., Ltd. (DOHWA). CHACHI Civil Engineering Services is commissioned as a subcontractor to provide consultancy services to undertake the Environmental and Social Impact Assessment (ESIA) of Upper Marikina Dam Project.
1.2 ESIA Objectives
In general, the objective of the consultancy services for this ESIA is to prepare the environmental impact assessment documents and gather all endorsements from various stakeholders required in securing the ECC for the Upper Marikina Dam project. The specific objectives are as follows:
1) Present the legal, administrative and policy framework for the ESIA so that it is consistent with
WB environmental and social safeguard policies and operating procedures and compliant with
all applicable government rules and regulations;
2) Prepare the Environmental Impact Statement (EIS) in accordance with the governing legal,
administrative and policy framework particularly the Philippine Environmental Impact
Statement System or Republic Act No. 9275, DENR Department Administrative Order DAO No.
2003-30 or the Implementing Rules and Regulations of Presidential Decree No. 1586,
Establishing the Philippine Environmental Impact Statement System) and its Revised
Procedural Manual of 2007 or MC 2007-002, the newly issued DAO No. 2017-015 or the
Guidelines on Public Participation under the Philippine Environmental Impact Statement
System (PEISS), WB’s applicable social and safeguard policies, and all applicable laws, rules,
policies, guidelines and/or regulations;
3) Carry out the ESIA in close coordination with the feasibility and detailed design consultants of
the Proposed Upper Marikina Dam Greater Metro Manila Area Flood Management Project led
by DOHWA;
4) Prepare the ESIA document in coordination and consultation with WB project representatives
and the ESSD of DPWH; and
5) Participate in public hearings and EIA review meetings required by EMB.
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
BASIC PROJECT INFORMATION |3
2. BASIC PROJECT INFORMATION
1.3 Project Information
Project Name: UPPER MARIKINA DAM GREATER METRO MANILA AREA FLOOD MANAGEMENT PROJECT
Project Location: The Upper Marikina Dam shall be located at Brgy. San Rafael, Municipality of Rodriguez, in the Province of Rizal located directly east of Metro Manila. The dam was proposed to be constructed at about four (4) km upstream from the existing Wawa Dam in Montalban Gorge.
Project Classification & Type:
Classification: Infrastructure Type: Dams
Project Size: 1) Dam Height: 70 meters 2) Catchment Area: 971.4 square kilometers (for confirmation) 3) Crest of Dam: EL.110m 4) Length of Dam: 263m 5) Storage for flood control: 67MCM 6) Sediment: 7.5MCM 7) Storage for water supply: 8.9MCM 8) Water Storage Capacity: 83.8 million cubic meters 9) River Catchment Area: 259 square kilometers 10) Spillway: Spillway with Gate + Spillway with Non-gate
Project Benefits: 1) To reduce flooding occurrences and therefore avoidance of social and economic losses due to flood damages on personal properties, commerce and businesses, and productive capacities
2) To reduce flood damages to infrastructure and social support services 3) Provide water supply to Metro Manila 4) Labor and employment benefits during project construction and operation and
maintenance. 5) Improve living conditions of Project Affected Persons (PAPs) through
resettlement program with livelihood assistance.
Project Cost: Construction Cost = PHP 8,632, 961,990
1.4 Proponent Profile
Proponent: Main Office:
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS Bonifacio Drive Port Area 652 Zone 068, Manila, 1018 Metro Manila Contact Person: PATRICK B. GATAN, CESO III Project Director, DPWH, FCMC-UPMO
Project Consultant: Feasibility Study Detailed Design Bidding Document
DOHWA ENGINEERING CO., LTD. UPPER MARIKINA DAM - PMO DPWH 2nd Rizal District Engineering Office Westbank Road, Manggahan Floodway Rosario, Pasig City Contact Person: Kim, Myong-Nim
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
BASIC PROJECT INFORMATION |4
Team Leader
Subcontractor: ESIA and ECC acquisition
CHACHI CIVIL ENGINEERING SERVICES Project Office: Lot 7 West Los Angeles Street, California Village Novaliches, Quezon City 1116 Metro Manila Philippines Telefax. No. (632) 282 4242 Email: [email protected] Contact Person: Louernie F. de Sales, Ph.D. Team Leader and Environmental Specialist Telefax. No. (632) 417 8888 Email: [email protected]
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|5
3. PROJECT DESCRIPTION
1.5 Project Location and Area
1.5.1 Project Location
The proposed Upper Marikina Dam shall be in San Rafael, Rodriguez, Rizal in the northern section of the Pasig-Marikina River Basin. The eastern side is mountainous and forms part of the Southern Sierra Madre Mountain Range in Luzon Island. The Marikina River forms a gorge in the most upstream reach and a valley with hilly to gentle topography in the upstream to midstream reaches. The topography becomes rather gentle to flat land to the westward direction along the lower reach of the Marikina River as well as along the Pasig River.
The catchment area of the Pasig-Marikina River Basin is 641 sq.km., broken down into 103, 89 and 538 square kilometers of drainage areas for Pasig River, San Juan River, and Marikina River, respectively. Marikina River used to be an important transport route during the Spanish colonial era until the Philippines' national highway system became more established. The resulting lack of river boat traffic and the deforestation of the upland areas in what is now the Upper Marikina River Basin Protected Landscape contributed to the river's siltation reducing further its transportation importance.
In Brgy. Wawa in Rodriguez, the Marikina River is dammed by Wawa Dam, a structure built during the early 1900s to provide water for Manila. From Rodriguez, the river flows through San Mateo then to its namesake city of Marikina. In Pasig City, the river meets the gates of the Manggahan Floodway, a controlled waterway used to prevent flooding in Manila during heavy rains by diverting most of the water from Marikina towards Laguna de bay instead of Pasig River. Located 6.75 km downstream is the confluence of Marikina and Pasig Rivers.
The river's depth ranges from 3–21 m and spans from 70–120 m. It has a total area of nearly 75.2 hectares and is 27 kilometers long. The riverbank has an elevation of eight (8) m above sea level at the boundary of San Mateo and Marikina. This slowly goes down at an elevation of four (4) m nearly before the Malanday and Santo Niño boundary. There is an unconfirmed claim that its lowest elevation is along Calumpang which is two (2) m above sea level.
The Marikina River has a number of tributaries in the form of creeks and rivers, and at least one former river-section in Marikina's Barangay Tumana from which its flow has been diverted. These tributaries drain four municipalities (Baras, Rodriguez, San Mateo, and Tanay) and one city (Antipolo) in the Province of Rizal, and three cities in the Philippines' National Capital Region (Pasig, Marikina, San Juan). The biggest of these tributaries are upstream in the more mountainous areas of Rodriguez. This includes the Tayabasan and Montalban Rivers, the Boso Boso River, and the Wawa River, which meets the Marikina River just upstream of Wawa Dam. Further downstream from the dam, but still in the town of Rodriguez are the Puray River (which flows near Avilon Zoo), and the Manga River.
Up till this point the river follows an East-West direction until San Jose, Rodriguez, where it takes a sharp North-South turn towards the Municipality of San Mateo, where the Ampid River forms the boundary between Barangays Maly and Ampid. At this point across the River in Quezon City, Calamiong Creek drains Barangay Bagong Silang. Further downstream the Nangka River and its own tributary in the Sapang Labo Creek mark the Boundary between San Mateo and Marikina (Figure 3-1).
Attachment 1 shows the project location in a larger scale in a NAMRIA procured topographic map.
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|6
Figure 3-1 Project Location, Proposed Upper Marikina Dam
1.5.2 Area of Influence (AoI)
The project’s area of influence, which is the area likely to be affected by the project, including all its ancillary aspects includes:
1) The entire catchment area of the Upper Marikina River Basin which is the upper area of the drainage basin of the Marikina River. The area is 26,125.64 hectares covering the upper reaches of the Marikina watershed in the Province of Rizal, flowing through the Antipolo, Baras, Rodriguez, San Mateo, and Tanay. In Rodriguez, the river is dammed by Wawa Dam, a structure built during the early 1900s to provide water for Manila. It is also surrounded by significant bodies of water such as the Boso-Boso River, Sapa Bute-Bute, Tayabasan River, Montalban River and the Wawa Dam.
2) the UMD site and immediate surroundings, i.e. the site of the dam and ancillary infrastructure: construction site, workers' settlements, access roads, areas required for construction material borrow, etc.;
3) in terms of flood control benefits, the project’s area of influence includes the Greater Metro Manila Area.
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|7
Photo 3.1 Montalban Gorge
Photo 3.2 Visualization of UMD through the Montalban Gorge
Figure 3-2 shows the general layout of the entire flood control program downstream of the proposed dam. The coverage area for the Upper Marikina Dam is shown in Figure 3-3, UMD catchment area. The positions of the three alternatives sites are shown in Figure 3-4.
1.6 Impact Areas
1.6.1 Direct Impact Area (DIA)
Based on Annex 2-2 of MC 2007-002 or the Revised Procedural Manual (RPM) for DAO 03-30, the Direct
Impact Area (DIA) is initially delimited during the Pre-EIA Study Stage as the area where all project
facilities are proposed to be constructed/situated and where all operations are proposed to be
undertaken. For most projects, the DIA is equivalent to the total area applied for an ECC. The Revised
Procedural Manual includes buffer zones into the limits of the DIA where a particular environmental
equality is also affected.
For the UMD, these areas are the locations of the dam, reservoir, access roads, and facilities including
storage and disposal sites of borrow materials and wastes, also referred to as ancillary facilities. DIA is
initially delimited in terms of impact on natural habitats as affected by the inundation of the area; and
on the need for involuntary resettlement resulting from the acquisition of the project site and right-of-
way (ROW). If the zone of impact on natural habitats is considered, the DIA may also include the
downstream area of the Upper Marikina River where the freshwater ecology may also be directly
affected by the change in water flow due to the dam.
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|8
Figure 3-2 General Layout of Flood Controls dowsnstream of UMD
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|9
Figure 3-3. UMD Catchment Area
This UMD catchment area spans eleven (11) barangays in three (3) municipalities and one city in the province of Rizal (Table 3.1). The province is located east of Manila and accessible via Ortigas Avenue, Marcos or Smiling Highways.
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|10
Table 3.1 List of barangays in the catchment area of UMD
Municipality/City Barangays in Catchment Area
Rodriguez Puray, San Rafael1, Burgoz, Geronimo
San Mateo Pintong Bukawe
Antipolo City San Juan, Calawis, Bagong Nayon, Inarawan, San Jose
Tanay Cayumbay
Within the DIA are the locations of the dam, reservoir, access roads, and facilities including storage and
disposal sites of borrow materials and wastes, also referred to as ancillary facilities. Figure 3-4 shows
the alternative locations of the dam in a topographic map from NAMRIA.
Figure 3-4 UMD Location Alternatives
1.6.2 Indirect Impact Area (IIA)
Annex 2 of the RPM states that IIA during the pre-EIA Study can only be assumed or qualitatively estimated but may be guided by secondary data and information from key interviews of reliable local authorities. IIA is clearly delineated only after the EIA Study is done, and is more accurately established during post-ECC monitoring. The socio-cultural IIA shall be based on the area of influence of the biophysical IIA. For the biophysical environment, the IIA may be the area from the outer boundary of the mixing or buffer zone to the point or area where the baseline environmental quality is calculated or monitored to be met.
1 San Rafael is the location of the dam site.
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|11
For the UMD, the areas outside the reservoir where the biophysical environment is affected is IIA. IIA will be initially delineated according to impacts on the natural habitat including the affected terrestrial and freshwater ecosystem; where displacement of people, including IP concerns may be triggered.
In terms of the environmental impact to the natural ecosystem, except those areas tagged above as DIA the entire catchment area of the Upper Marikina River is set as the IIA. The indirect impact areas as a result of the need for involuntary resettlement due to the dam project and downstream flood control structures will potentially be the barangays along the Marikina River in the municipalities of San Mateo and Rodriguez in Rizal Province.
1.7 Regional Impact Zone (RIZ)
Areas that may be positively benefited by the project due to reduction in flood damages are considered within the RIZ. RIZ pertains more to the general area where the impact of the project would be felt, such as the entire municipality, province or region. This project is an important component of the flood control master plan covering the Greater Metro Manila Area and adjoining municipalities of surrounding provinces. The RIZ can be visualized using Figure 3-5 which shows all river, drainage and lake basins in the zone. The area covers the Laguna Lake Basin, four river basins and three drainage basins, such as:
1) Pasig-Marikina River Basin 2) Manila Core Area Drainage Basin 3) Malabon-Tullahan River Basin 4) Malabon-Navotas Drainage Basin 5) Meycauayan River Basin 6) Laguna Lake (including the inflow rivers to Laguna Lake) 7) South Parañaque-Las Piñas River Basin 8) Parañaque-Las Piñas Drainage Basin
The catchment area, river length, and pertinent features of these basins relative to their contributions to flooding in the RIZ are summarized in Table 3.2.
Table 3.2 Features of River Basins, Drainage Basins and the Laguna Lake Basin
River Basin Catchment Area (km2)
River Length (km) Remarks
1) Pasig-Marikina RB 641 52.2 (Pasig River: 17.1, Marikina River up to
Wawa: 35.1)
Pasig River: 103km2 including San Juan River (89km2)
Marikina River: 538km2.
2) Manila Core Area DB 73 Drainage area with/without direct pumps to Manila Bay.
3) Malabon-Tullahan RB 70 26
4) Malabon-Navotas DB 20 Drainage area with/without pumps to Manila Bay except that in Malabon-Tullahan River Basin.
5) Meycauayan RB 171 52 (Including Marilao River)
6) Laguna Lake (including the inflow rivers into Laguna Lake)
3,281 40 (Maximum length of the lake of south-
north stretch)
Lake area: about 900km2
Shore line: about 285 km Inflow rivers: about 100
7) South Parañaque-Las Piñas River Basin
101 13 Including Zapote River Basin (47km2).
8) Parañaque-Las Piñas DB 15 Pump drainage area and/or direct drainage area to Manila Bay.
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|12
River Basin Catchment Area (km2)
River Length (km) Remarks
Total Area 4,373
Discussions on project benefits will be included in the ESIA to highlight the importance of the project to the RIZ and how these benefits will outweigh the negative environmental and social impacts and the residual impacts that are unavoidable despite instituting mitigating measures. Inputs from the project economist working under the feasibility study into the ESIA will be required for this task. The RIZ will cover the Greater Metro Manila Area and its surrounding areas.
Figure 3-5 River Basins, Lake Basin, and Drainage Basins in the Greater Metro Manila Area
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|13
1.8 Project Components List
The Master Plan proposes a 70-m high gravity concrete dam with large orifice openings as one of the large programs of priority infrastructures to safely control and manage major flood events in Metro Manila. The gross storage capacity of the proposed dam is around 80 million m3/s which would be sufficient to reduce the peak river flow during a 100-year event from about 3,600 to 900 m3/s. The master plan cites the Yokohama Dam in Japan as a closely similar structure (Figure 3-6). Although the primary purpose of the proposed dam would be flood management, the Master Plan identified that there are opportunities to utilize some of the reservoir water for much needed water supply purposes for Metro Manila as well.
Figure 3-6. The Yokohama Dam - a similar structure to UMD
Typical cross sections of the dam are shown in (Figure 3-7). The dam components are still in the planning stage and their locations are still being determined. The components will likely include the following:
a. Reservoir, intake and dam b. Magazine area c. Contractor's and engineers’ office d. Fuel dump area e. Quarry areas f. Contractor's laydown area g. Contractor's camp h. Batching plant i. Access Road
The flood management master plan has an estimated cost of PhP352 billion (USD7.86 billion) for its implementation within 23 years. Aside from investments in large program of priority infrastructures, the master plan also presents proposals for non-structural measures as flood forecasting, early warning systems, and community-based flood risks management. It also has recommendations to improve the institutional structure to deal with flood with flood management in an integrated manner. The other main large-scale priority interventions that have been identified in the said master plan are as follows:
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION|14
(a) provision of flood protection works in the Marikina River, upstream of the proposed Phase IV and V of the Pasig-Marikina River Channel Improvement Project (PMRCIP).
(b) land raising or another similar development along the western shore of Laguna de Bay to protect the population against high water levels in the lake (as the designed solution will most likely involve, land raising, as also proposed in the master plan, this is referred to in the rest of the text, although there is still a possibility that a more preferred option is selected at the feasibility stage); and
(c) participation of local communities.
Figure 3-7 Typical Dam Sections
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION |14
2.6 Project Phases, Key Environmental Aspects, Wastes, Issues, Built-in Measures
The PH-PTF Grant and associated government funds currently finances the preparation of feasibility and design studies for a high dam (or other flood management structure) in the upper Marikina River catchment area. The government finances the social and environmental impact assessments including the social surveys that will target the communities that are affected by the potential projects that may need to be resettled, related to this intervention as well as intervention for which the technical studies will be funded from the PHRD Grant.
Upon completion of the feasibility study and prior to the preparation of the detailed design of the preferred option, the results will be submitted first to NEDA for deliberation/evaluation and subsequent approval that will become the basis of the project design stage.
The project is still under the Feasibility Study stage and project phasing is yet to be established while the project components are yet to be identified. These components will become available in time for the three-level scoping process.
Key environmental aspects likely to be affected are shown below together with the potential impacts of the project during construction and operations phases
PROJECT PHASE / ENVIRONMENTAL
ASPECT
ENVIRONMENTAL COMPONENT LIKELY
TO BE AFFECTED POTENTIAL IMPACT
CONSTRUCTION STAGE A. Land Land Use 1) Inconsistency with land use
2) Encroachment in ECAsGeology / Geomorphology
- Change in surface landform/ topography/terrain/slope
KEY ENVIRONMENTAL COMPONENTS LIKELY TO BE AFFECTEDkk
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION |15
PROJECT PHASE / ENVIRONMENTAL
ASPECT
ENVIRONMENTAL COMPONENT LIKELY
TO BE AFFECTED POTENTIAL IMPACT
Pedology 1) Inducement of subsidence, liquefaction, landslides,
mud / debris flow2) Soil erosion / Loss of topsoil/overburden3) Change in soil quality/fertility
Terrestrial Ecology 1) Removal of vegetation (including reforestation treesplanted under the NGP)
2) Loss of important local species3) Loss of habitat for wildlife species4) Hindrance to wildlife access
B. Water Hydrology 1) Change in drainage morphology2) Change in stream/ water depth due accrued sediments
on the riverbed3) Occurrence or aggravation of flooding in nearby areas4) Depletion/ Competition in water resource use
Freshwater Ecology 1) Alteration of natural flow and threat to existence ofspecies
Water Quality Water quality degradation through:
a) Sediments from open areas reaching the waterwaysb) Solid and liquid wastes from construction area and
workers’ campsc) Run-off from excavated materials reaching the
waterwaysd) Waste from equipment and vehicles repairs
C. Air Ambient Air Quality 1) Ambient air quality impacts due to fugitive dust fromground clearing operations, structure erection andfrom vehicles plying access roads
2) Effects of Vibrations:a) Dust from blasting activities, access road
construction, and hauling waste rock to wasterock disposal areas
b) Emission of standard pollutants from vehiclesand heavy equipment operation
Ambient Noise Quality Increase in ambient noise level during construction D. People 1) Displacement of settlers
2) Displacement of Property/ Conflict in Land Ownership3) Right of Way Conflict4) Increased in-migration that may result in:5) Proliferation of informal settlers6) Competition in the delivery of basic services7) Lifestyle change:8) For IPs who have their own cultural norms and practices9) For rural residents in terms of
a) increased traffic; increased videoke, drinking places; possibly increasedprostitution; urbanization
b) More tourists are expected to come in the sacred stone (Istampang Bato)that possibly increased solid waste, which can be harmful to the aestheticsof the place
10) Threats to Public Health/Safety:a) Increased accidents (traffic and construction related)
PROJECT DESCRIPTION FOR SCOPING Environmental and Social Impact Assessment
Upper Marikina Dam Greater Metro Manila Area Flood Management Project
PROJECT DESCRIPTION |16
PROJECT PHASE / ENVIRONMENTAL
ASPECT
ENVIRONMENTAL COMPONENT LIKELY
TO BE AFFECTED POTENTIAL IMPACT
b) Increased incidences of petty crime and disorderly conductc) Proliferation of alcohol, drugs, prostitution, gambling
11) Increased employment opportunities12) Increased small-business, retail, trading, service and transportation business
opportunities
DURING OPERATIONS A. Land Geology /
Geomorphology Scouring of downstream of spillway
Pedology Soil erosion / Loss of topsoil/overburden Terrestrial Ecology 1) The loss of terrestrial wildlife to drowning during
reservoir filling2) Reduced river flow can impede essential biophysical
functions and modify flow patterns and floodingcharacteristics along river stretch. This will lower thewater levels along this stretch and there will be slightchanges in species composition towards moredroughts tolerating plant species along the River.
E. Water Hydrology 1) Sedimentation behind the dam2) Change in drainage morphology3) Reduction in volumetric flow4) Change in stream/water depth5) Depletion of water6) resources/competition in water use7) Occurrence or aggravation of flooding in nearby areas
Freshwater Ecology 1) Disruption of fisheries due to changes in flow, blockingof fish migration, and
2) changes in water qualityWater Quality 1) Decrease in dissolved oxygen levels in water due to
thermal stratification2) Degradation of water quality in the reservoir
C. Air Air Noise
1) Contribution to climate change due to greenhouse gasemissions
2) Noise GenerationD. People 1) Displacement of settlers during flood events at lower reservoir/ Dam Break
2) Right of Way Conflict3) Threat to Public Health/Safety4) Flood control5) Increased LGU revenue from
a) ER 1-94b) Payment of annual taxes and permits
6) Complaints of effects and impacts of the project on various aspects of people’slives
7) Constraints on health facilities, school facilities and employment opportunitiesin the area
2.7 Project Cost and Duration
Construction Cost = PhP 8,632, 961,990
PROCESS TECHNOLOGY AND ALTERNATIVES
To determine the optimal scale of dams and other appurtenances, a hydraulic, hydrological
analysis will be performed using rainfall data, and streamflow data from the station which is
located around the project areas.
Table 3. Hydrological Analysis Process
Item Major issues Application
Rainfall
analysis
&
Estimation
of
Flood
Basin-wide
mean
&
areal rainfall
• Estimate basin-wide mean rainfall
using the Thiessen network • Estimate areal rainfall using ARF
(Areal Reduction Factor)
• Used to determine the
optimal scale of structures
• Used to assess a hydrological
stability
• Used to assess flood control
capacity
• Used to determine reservoir
operation level
• Used to identify impacts on
the upper/lower river
Probable
Rainfall
• Derive annual maximum series of
duration rainfall data • Estimate probable rainfall by
frequency (i.e. return period)
Flood
• Estimate flood using the SUH
(synthetic unit hydrograph)
method • Test & correct estimated flood
using historical large-flood data
The consultant will develop a detailed historical climate and water resources database for
the Upper Marikina Catchment Area. Organize the data in electronic form in order to allow
future data entry/updating, and a fast way of retrieving it for various purposes using easy
data retrieval methods;
The consultant will review the mathematical model prepared under the Metro Flood
Management Master Plan and the one prepared by JICA for the review of proposals under
the Pasig-Marikina river Channel Improvement Project if available. The model should have
a capacity to stimulate the design flood event in the Marikina River and be able to propose
different interventions, techniques, and operation rules to minimize the flood discharges in
the Pasig-Marikina River system by optimizing the retention or diversion of flood waters in
the Upper Marikina Catchment Area;
(4) Selection of the preferred flood management structure in the upper Pasig-Marikina
watershed.
The consultant will review other possible flood management infrastructure options and select
the most efficient and structurally stable flood management structure as the preferred option
for development.
The Consultant will analyze & evaluate structure stability, constructability, economic
feasibility and layout plans for major structures at the alternative sites to determine optimal
dam type and location The main processes of dam design are as follows.
Figure 8. Process of Dam design
Table 4. Comparison among different dam types
Item Concrete Dam Zone & Core Dam Concrete Face Rockfill
Dam
Schematic
diagram
Dam height
• No specific limitation
in dam height
• No specific limitation
in dam height
• In general, 100m or
lower recommended
(to prevent problems
with the settlement of
body)
Availability of
construction
materials
• Applicable to cases
where it’s easy to
procure aggregates.
• Applicable to cases
where all kinds of
materials are
available
• Applicable to cases
where it’s difficult to
procure soil materials
Meteorologica
l conditions
• No specific limitation
in meteorological
conditions
• Limited in core
constructability
• No specific limitation
in meteorological
conditions
Topographical
constraints
• No specific limitation
in topographical
conditions
• No specific limitation
in topographical
conditions
• Not recommendable
in cases where both
banks are sharply
sloped, which may
accompany
differential settlement
Geological
conditions
• Mainly applicable to
rock mass foundation
• Mainly applicable to
sand & gravel
foundation or rock
mass foundation
• Mainly applicable to
rock mass foundation
Earthquake • Relatively safe for
earthquakes
• Relatively vulnerable
to earthquakes
• Relatively safe for
earthquakes
(5) Preparation of feasibility study that determines possible options and settles on preferred
option through economic evaluation including social and environmental impact assessment
The consultant will prepare the preliminary engineering designs for possible structures and
facilities. If selected, special attention should be paid in optimizing the height of the dam
and the reservoir volume to have maximum benefits to the design of the spillway gates to
allow several discharge operation patterns that may change over time due to climate change
or other factors, and to the fact that the proposed dam site is near an active fault.
Figure 9. Preliminary Design of Marikina Dam.
The Consultant will determine the optimal capacity of a spillway which is hydraulically safe
enough to resist against design flood discharge, and optimal energy dissipator type.
Table 5. Comparison among different spillway types
Item Description
Open
channel
types
Overflow
• Allow overflow by lowering the
elevation of dam crest
• Shape the longitudinal profile of a
spillway into the lower part of nappe
where the sharp-edged weir is fully
overflowed
Ogee
• Overflow → Chute way → Lower
river
• Mainly applicable to an open-
channel-type chute spillway
•
Side
channel
• Parallel between the centerlines of
overflow weir and side channel
• Applicable to cases where it’s
difficult to sufficiently secure
spillway length
•
Tunnel
channel
types Tunnel
• Install a tunnel to drain out flood
discharge
• Lower the sectional area of stream
flow to smaller than 75% of that of
pipes to keep the inside of an
outflow pipe in open-channel state
Siphon
• Applicable to cases where flood
scale is small and installation space
is limited
• Design reservoir level so that it may
automatically lie within a specific
range
•
Shaft
• Morning-glory-shaped shaft
spillway into which water is
overflowed
• Inlet section: Morning-glory-shaped
• Applied in line with an auxiliary or
emergency spillway
•
Free overfall
spillway
•
• Induce the free overfall of stream
flow from a weir
• Construct a saddle dam in a lower
river to make an artificial reservoir
and thereby provide against erosion
where stream flow falls down
The Consultant will determine the optimal method of river diversion works in terms of
constructability, stability and economic feasibility considering the following issues:
Table 6. Optimization of river diversion
Item Full-scale coffering Partial coffering Step-by-step coffering
Schemati
c
Drawing
• • •
Features
• The diversion tunnel
can be used as water
inlet and discharge
facility
• Increase of construction
period and cost
• Not able to use the
cofferdam crests as
construction roads
• Reduction of
construction period and
cost
• The cofferdam crests
can be used as
construction roads
• Reduction of
construction period
and cost,