research on the prediction model of blasting vibration ... - mdpi

12
Citation: Guo, J.; Zhang, C.; Xie, S.; Liu, Y. Research on the Prediction Model of Blasting Vibration Velocity in the Dahuangshan Mine. Appl. Sci. 2022, 12, 5849. https://doi.org/ 10.3390/app12125849 Academic Editor: Ricardo Castedo Received: 10 May 2022 Accepted: 6 June 2022 Published: 8 June 2022 Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affil- iations. Copyright: © 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https:// creativecommons.org/licenses/by/ 4.0/). applied sciences Article Research on the Prediction Model of Blasting Vibration Velocity in the Dahuangshan Mine Jiang Guo 1 , Chen Zhang 1, *, Shoudong Xie 2 and Yi Liu 2 1 School of Resources and Safety Engineering, Central South University, Changsha 410083, China; [email protected] 2 Hongda Blasting Engineering Group Co., Ltd., Guangzhou 510623, China; [email protected] (S.X.); [email protected] (Y.L.) * Correspondence: [email protected] Abstract: In order to improve the prediction accuracy of blast vibration velocity, the model for predicting the peak particle velocity of blast vibration using the XGBoost (Extreme Gradient Boosting) method is improved, and the EWT–XGBoost model is established to predict the peak particle velocity of blast vibration by combining it with the EWT (Empirical Wavelet Transform) method. Calculate the relative error and root mean square error between the predicted value and measured value of each test sample, and compare the prediction performance of the EWT–XGBoost model with the original model. There is a large elevation difference between each vibration measurement location of high and steep slopes, but high and steep slopes are extremely dangerous, which is not conducive to the layout of blasting vibration monitoring equipment. The vibration velocity prediction model adopts the numerical simulation method, selects the center position of the small platform as the measurement point of the peak particle velocity, and studies the variation law of the blasting vibration velocity of the high and steep slopes under the action of top blasting. The research results show that the EWT–XGBoost model has a higher accuracy than the original model in the prediction of blasting vibration velocity; the simultaneous detonation method on adjacent high and steep slopes cannot meet the relevant requirements of safety regulations, and the delayed detonation method can effectively reduce the blasting vibration of high and steep slopes. The shock absorption effect of the elevation difference within 45 m is obvious. Keywords: elevation difference; blasting vibration velocity; EWT; XGBoost; prediction model 1. Introduction Blasting plays a key role in open-pit mining [1], especially in construction stone mines, which account for a large share of open-pit mining. Although blasting is widely used for rock crushing in open pit mines, the impact of blasting vibration cannot be ignored [2]. Sometimes, it is even necessary to use mechanical crushing to eliminate the negative impact of blasting vibration, so the prediction of blasting vibration velocity is particularly critical. The blasting vibration velocity prediction mainly refers to predicting the PPV (peak particle velocity). Blasting workers in open-pit mines often use blasting vibration monitoring results to optimize blasting parameters. In this way, blasting workers can reduce the impact of structures below the steep slope by controlling the PPV. In engineering blasting, people pay more and more attention to avoid serious acci- dents through conducting blasting vibration prediction in advance, which can help reduce damage to structures and improve personnel safety [35]. Many scholars have conducted extensive and in-depth research on blasting vibration prediction, and their research meth- ods include empirical formulas, machine learning, and numerical simulations. The ground vibration level is described by empirical formulas mainly considering rock characteristics, distance, maximum single-shot charge, and other blasting conditions [68]. Appl. Sci. 2022, 12, 5849. https://doi.org/10.3390/app12125849 https://www.mdpi.com/journal/applsci

Upload: khangminh22

Post on 27-Apr-2023

0 views

Category:

Documents


0 download

TRANSCRIPT

Citation: Guo, J.; Zhang, C.; Xie, S.;

Liu, Y. Research on the Prediction

Model of Blasting Vibration Velocity

in the Dahuangshan Mine. Appl. Sci.

2022, 12, 5849. https://doi.org/

10.3390/app12125849

Academic Editor: Ricardo Castedo

Received: 10 May 2022

Accepted: 6 June 2022

Published: 8 June 2022

Publisher’s Note: MDPI stays neutral

with regard to jurisdictional claims in

published maps and institutional affil-

iations.

Copyright: © 2022 by the authors.

Licensee MDPI, Basel, Switzerland.

This article is an open access article

distributed under the terms and

conditions of the Creative Commons

Attribution (CC BY) license (https://

creativecommons.org/licenses/by/

4.0/).

applied sciences

Article

Research on the Prediction Model of Blasting Vibration Velocityin the Dahuangshan MineJiang Guo 1 , Chen Zhang 1,*, Shoudong Xie 2 and Yi Liu 2

1 School of Resources and Safety Engineering, Central South University, Changsha 410083, China;[email protected]

2 Hongda Blasting Engineering Group Co., Ltd., Guangzhou 510623, China; [email protected] (S.X.);[email protected] (Y.L.)

* Correspondence: [email protected]

Abstract: In order to improve the prediction accuracy of blast vibration velocity, the model forpredicting the peak particle velocity of blast vibration using the XGBoost (Extreme Gradient Boosting)method is improved, and the EWT–XGBoost model is established to predict the peak particle velocityof blast vibration by combining it with the EWT (Empirical Wavelet Transform) method. Calculatethe relative error and root mean square error between the predicted value and measured value ofeach test sample, and compare the prediction performance of the EWT–XGBoost model with theoriginal model. There is a large elevation difference between each vibration measurement location ofhigh and steep slopes, but high and steep slopes are extremely dangerous, which is not conduciveto the layout of blasting vibration monitoring equipment. The vibration velocity prediction modeladopts the numerical simulation method, selects the center position of the small platform as themeasurement point of the peak particle velocity, and studies the variation law of the blasting vibrationvelocity of the high and steep slopes under the action of top blasting. The research results showthat the EWT–XGBoost model has a higher accuracy than the original model in the prediction ofblasting vibration velocity; the simultaneous detonation method on adjacent high and steep slopescannot meet the relevant requirements of safety regulations, and the delayed detonation method caneffectively reduce the blasting vibration of high and steep slopes. The shock absorption effect of theelevation difference within 45 m is obvious.

Keywords: elevation difference; blasting vibration velocity; EWT; XGBoost; prediction model

1. Introduction

Blasting plays a key role in open-pit mining [1], especially in construction stone mines,which account for a large share of open-pit mining. Although blasting is widely used forrock crushing in open pit mines, the impact of blasting vibration cannot be ignored [2].Sometimes, it is even necessary to use mechanical crushing to eliminate the negative impactof blasting vibration, so the prediction of blasting vibration velocity is particularly critical.The blasting vibration velocity prediction mainly refers to predicting the PPV (peak particlevelocity). Blasting workers in open-pit mines often use blasting vibration monitoring resultsto optimize blasting parameters. In this way, blasting workers can reduce the impact ofstructures below the steep slope by controlling the PPV.

In engineering blasting, people pay more and more attention to avoid serious acci-dents through conducting blasting vibration prediction in advance, which can help reducedamage to structures and improve personnel safety [3–5]. Many scholars have conductedextensive and in-depth research on blasting vibration prediction, and their research meth-ods include empirical formulas, machine learning, and numerical simulations.

The ground vibration level is described by empirical formulas mainly considering rockcharacteristics, distance, maximum single-shot charge, and other blasting conditions [6–8].

Appl. Sci. 2022, 12, 5849. https://doi.org/10.3390/app12125849 https://www.mdpi.com/journal/applsci

Appl. Sci. 2022, 12, 5849 2 of 12

The improved formula of the traditional Sadovskii formula is well applied. Lin et al. [9]used the dimensionless analysis method to improve the nonlinear regression predictionmodel of the blasting vibration propagation law. After the improvement, the model canreflect the elevation effect. According to the measured data, the prediction accuracy of theimproved model is improved by 13.55% compared with that of the original model.

Machine learning methods have been introduced into the field of blasting vibrationprediction, and many scholars have conducted in-depth research on it. Yue et al. [10]established a least squares support vector machine model to predict the blasting vibrationeffect of open pit mines and optimized the regularization parameters and kernel functionwidth coefficients through a particle swarm optimization algorithm, so that the model has ahigher generalization ability and prediction accuracy. Sun et al. [11] considered eight factors,including blast center distance, elevation difference, propagation medium conditions,maximum single-stage charge, total charge, differential time, detonation direction, andthe shock absorption effect of the excavated chamber, and established the PSO–LSSVMmodel to predict the blasting vibration of underground gas storage caverns. YAN et al. [12]used the GEO–ELM model to predict the PPV and frequency of the ground vibration when,caused by blasting demolition, the building collapses. The model has a higher predictionaccuracy after combining it with the gray wolf algorithm. The random forest algorithm iswidely used in the blasting vibration problem, and the improved method for its algorithmhas been proven to have a higher accuracy [13,14].

The low cost of the numerical simulation method can provide a certain referencefor blasting vibration safety evaluation and the optimization of blasting parameters. Laket al. [15] compared Green′s function solution, the experimental results, and the numericalsimulations for the PPV results of rock blasting, and the results show that the three arehighly consistent. Aiming at the problem of the demolition of adjacent buildings by benchblasting construction, Lei et al. [16] took a bench blasting project as the background andstudied the blasting vibration propagation law with a maximum single-shot charge of3.8 kg and a blast hole diameter of 38 mm under the combined action of horizontal distanceand elevation.

The blasting vibration velocity is affected by many aspects in the open-pit mine [17–19],which affects the accuracy of the blasting vibration velocity prediction. Compared with themachine learning method, the empirical formula has great disadvantages considering thenumber of factors and the consumption of resources and time. In this paper, the improvedmachine learning algorithm XGBoost and the finite element numerical simulation methodare used to establish the blasting vibration velocity prediction model of the Dahuangshantuff rock mine. This paper focuses on the prediction of blasting vibration velocity.

2. Materials and Methods2.1. Engineering Overview

The Dahuangshan Tuff Building Stone Mine is an open-pit mine. The mining area islocated in the hilly area in the north of Cezi Island and belongs to Taoyaomen Community,Cengang Street, Dinghai District, Zhoushan City, Zhejiang Province. The location of themine area is shown in Figure 1. The rock formations in the mining area are mainly tuffand hard rocks with a compact structure. The mining process includes DTH drilling,medium and deep hole blasting, mechanical secondary crushing, loader shovel loading,and truck transportation, and the mining process is discharged to the designated location.The minimum mining elevation is +6 m.

2.2. Blasting Vibration Monitoring

The blasting vibration monitoring uses the T-4850 sensor to collect blasting signals.The Figure 2 shows the layout of the monitoring points during blasting on the 141 platform.The blasting adopts a digital electronic detonator detonation network, a total of 77 holes, atotal of 195 detonators, and 18 m in the hole. The digital electronic detonator and the 10

Appl. Sci. 2022, 12, 5849 3 of 12

m digital electronic detonator are used to process the priming charge. The interval delaybetween the rows is set to 130 ms, and the interval delay between the holes is set to 50 ms.

Appl. Sci. 2022, 12, x FOR PEER REVIEW 3 of 12

Figure 1. Geographical location of the mining area.

2.2. Blasting Vibration Monitoring

The blasting vibration monitoring uses the T-4850 sensor to collect blasting signals.

The Figure 2 shows the layout of the monitoring points during blasting on the 141 plat-

form. The blasting adopts a digital electronic detonator detonation network, a total of 77

holes, a total of 195 detonators, and 18 m in the hole. The digital electronic detonator and

the 10 m digital electronic detonator are used to process the priming charge. The interval

delay between the rows is set to 130 ms, and the interval delay between the holes is set to

50 ms.

(a)

Figure 1. Geographical location of the mining area.

Appl. Sci. 2022, 12, x FOR PEER REVIEW 3 of 12

Figure 1. Geographical location of the mining area.

2.2. Blasting Vibration Monitoring

The blasting vibration monitoring uses the T-4850 sensor to collect blasting signals.

The Figure 2 shows the layout of the monitoring points during blasting on the 141 plat-

form. The blasting adopts a digital electronic detonator detonation network, a total of 77

holes, a total of 195 detonators, and 18 m in the hole. The digital electronic detonator and

the 10 m digital electronic detonator are used to process the priming charge. The interval

delay between the rows is set to 130 ms, and the interval delay between the holes is set to

50 ms.

(a)

Appl. Sci. 2022, 12, x FOR PEER REVIEW 4 of 12

(b) (c)

Figure 2. Blasting Vibration Monitoring: (a) Measuring point layout (141 Blasting area); (b) Moni-

toring instrument at the measuring point; (c) The site of the blasthole layout.

2.3. Theory of the EWT Method

The empirical wavelet transform method was proposed by Gilles [20] in 2013. It in-

tegrates the EMD algorithm [21] and the wavelet transform method [22–24], so it has the

characteristics of both methods. The EMD algorithm has data-driven adaptivity, a high

signal-to-noise ratio, a good time-frequency focus, and advantages in terms of analyzing

nonlinear and non-stationary signal sequences, and the original signal can be decomposed

into each intrinsic mode function by the EMD algorithm. The equation is as follows:

𝑓(𝑡) =∑ 𝑓𝑘(𝑡)𝑁

𝑘=0 (1)

The algorithm process of the empirical wavelet transform method is as follows:

firstly, the Fourier transform is performed on the original input signal, the empirical scale

function and empirical wavelet are defined by the following formula, and, finally, the

wavelet filter is constructed to decompose the signal to obtain each mode function.

𝑛(𝜔) =

1 𝑖𝑓|𝜔| ≤ (1 − 𝛾)𝜔𝑛

cos [π

2β(

1

2γωn(|ω| − (1 − γ)ωn))]

𝑖𝑓(1 − 𝛾)𝜔𝑛 ≤ |𝜔| ≤ (1 + 𝛾)𝜔𝑛0 𝑜𝑡ℎ𝑒𝑟𝑤𝑖𝑠𝑒

(2)

𝑛(𝜔) =

1 𝑖𝑓(1 + 𝛾)𝜔𝑛 ≤ |𝜔| ≤ (1 − 𝛾)𝜔𝑛+1

cos [π

2β(

1

2γωn+1(|ω| − (1 − γ)ωn+1))]

𝑖𝑓(1 − 𝛾)𝜔𝑛+1 ≤ |𝜔| ≤ (1 + 𝛾)𝜔𝑛+1

sin [π

2β (

1

2γωn(|ω| − (1 − γ)ωn))]

𝑖𝑓(1 − 𝛾)𝜔𝑛 ≤ |𝜔| ≤ (1 + 𝛾)𝜔𝑛0 𝑜𝑡ℎ𝑒𝑟𝑤𝑖𝑠𝑒

(3)

2.4. Theory of the XGBoost Method

The XGBoost method is an ensemble learning method based on decision trees. It was

proposed by Chen Tianqi et al. [25] in 2016. Each decision tree learns the residual between

the target value and the sum of the predicted values of all previous trees. The XGBoost

model fuses multiple tree models and adds the prediction results of many trees to obtain

the final prediction result. The basic principles are as follows:

Figure 2. Blasting Vibration Monitoring: (a) Measuring point layout (141 Blasting area); (b) Monitor-ing instrument at the measuring point; (c) The site of the blasthole layout.

Appl. Sci. 2022, 12, 5849 4 of 12

2.3. Theory of the EWT Method

The empirical wavelet transform method was proposed by Gilles [20] in 2013. Itintegrates the EMD algorithm [21] and the wavelet transform method [22–24], so it has thecharacteristics of both methods. The EMD algorithm has data-driven adaptivity, a highsignal-to-noise ratio, a good time-frequency focus, and advantages in terms of analyzingnonlinear and non-stationary signal sequences, and the original signal can be decomposedinto each intrinsic mode function by the EMD algorithm. The equation is as follows:

f (t) = ∑Nk=0 fk(t) (1)

The algorithm process of the empirical wavelet transform method is as follows: firstly,the Fourier transform is performed on the original input signal, the empirical scale functionand empirical wavelet are defined by the following formula, and, finally, the wavelet filteris constructed to decompose the signal to obtain each mode function.

φn(ω) =

1 i f |ω| ≤ (1− γ)ωn

cos[

π2 β(

12γωn

(|ω| − (1− γ)ωn))]

i f (1− γ)ωn ≤ |ω| ≤ (1 + γ)ωn0 otherwise

(2)

ψn(ω) =

1 i f (1 + γ)ωn ≤ |ω| ≤ (1− γ)ωn+1

cos[

π2 β(

12γωn+1

(|ω| − (1− γ)ωn+1))]

i f (1− γ)ωn+1 ≤ |ω| ≤ (1 + γ)ωn+1

sin[

π2 β(

12γωn

(|ω| − (1− γ)ωn))]

i f (1− γ)ωn ≤ |ω| ≤ (1 + γ)ωn0 otherwise

(3)

2.4. Theory of the XGBoost Method

The XGBoost method is an ensemble learning method based on decision trees. It wasproposed by Chen Tianqi et al. [25] in 2016. Each decision tree learns the residual betweenthe target value and the sum of the predicted values of all previous trees. The XGBoostmodel fuses multiple tree models and adds the prediction results of many trees to obtainthe final prediction result. The basic principles are as follows:

yi = Φ(xi) = ∑Kk=1 fk(xi) ( fk ∈ F) (4)

F =

f (x) = ωq(x)

(q : Rm → T, ω ∈ RT

)(5)

In the formula, yi represents the predicted value of the XGBoost model, which issuperimposed by multiple decision trees fk(xi) in the series; K represents the number ofdecision trees; F represents the decision tree function space; q(X) represents that the sampleX is mapped to the leaf nodes of the tree; ωq(x) represents the weight of the leaf nodes;Rm represents the m-dimensional real vector; T represents the number of leaf nodes of thedecision tree; and RT represents the T-dimensional real vector.

The XGBoost method improves the calculation accuracy by adding a regular term tothe loss objective function and by performing a second-order Taylor expansion. The lossobjective function is composed of an error term l and a regular term Ω. The formula isas follows:

L(∅) = ∑i l(yi, yi) + ∑k Ω( fk) (6)

Ω( f ) = γT +12

λω2 (7)

Appl. Sci. 2022, 12, 5849 5 of 12

In the formula, l(yi, yi) represents the error between the predicted value and the actualvalue; Ω( fk) represents the regular term, which is used to constrain the number of leafnodes T and the leaf weight ω of the decision tree; γ represents the L2 square of the Tmodulus coefficient; and λ denotes the L2 squared modulus coefficient of ω.

For regression problems, the accuracy evaluation index of the model is often measuredby the RMSE (root-mean-square error). The formula is as follows:

RMSE =

√√√√Σni=1

(Xpred,i − Xmea,i

)2

n(8)

In the formula, Xpred,i represents the predicted value, Xmea,i represents the measuredvalue, and n represents the number of samples.

3. Model3.1. EWT–XGBoost Model

The process of using the EWT–XGBoost model to achieve PPV prediction is shown inFigure 3. The original data of the blasting vibration are denoised by EWT, and the obtaineddata are divided into the training set and the test set. The cross-validation method canobtain the parameters that optimize the generalization performance of the model. Thecommon hyperparameters of the XGBoost model are the learning rate, the minimum leafweight, the number and depth of the tree, etc. It divides the dataset into multiple subsets,among which a subset is used as the validation set, and the average error is calculatedfor multiple trainings to improve the generalization performance of the model. Becausethe amount of blasting vibration data collected this time is small, the leave-one-out cross-validation method is used to make the number of samples equal to the divided number oftraining subsets.

Appl. Sci. 2022, 12, x FOR PEER REVIEW 6 of 12

Data Set

Train Set Validation Set

Test Set

Define inputs and outputs

LOO-CV

XGBoost Model

Forecast Result

Raw Data

EWT Noise reduction

Figure 3. EWT–XGBoost prediction model flowchart.

When predicting blasting vibration velocity, the amount of explosives (Q), blasting

center distance (R), and elevation difference (H) are input as features, and the output is

the blasting peak particle velocity (PPV). Both the training data samples and test data

samples are derived from the blasting vibration data of the Dahuangshan mine project

from July 8 to July 20; the original data samples are shown in Table 1:

Table 1. Raw sample data.

No. Q (Kg) R (m) H (m) PPV (cm/s)

1 9072 466 81 0.335

2 9518 389 81 0.343

3 9942 486 96 0.339

4 9975 38 30 8.390

5 9975 201 45 0.193

6 9975 70 75 3.710

7 9975 129 90 0.350

8 5745 671 121 0.043

9 5745 683 121 0.051

10 10,077 80 -15 6.730

11 10,077 152 30 0.210

12 10,077 522 45 0.783

13 10,077 678 90 0.192

14 7401 47 15 5.830

15 7401 140 15 1.774

16 7401 273 15 0.416

17 7401 432 30 0.143

Figure 3. EWT–XGBoost prediction model flowchart.

Appl. Sci. 2022, 12, 5849 6 of 12

When predicting blasting vibration velocity, the amount of explosives (Q), blastingcenter distance (R), and elevation difference (H) are input as features, and the output is theblasting peak particle velocity (PPV). Both the training data samples and test data samplesare derived from the blasting vibration data of the Dahuangshan mine project from July 8to July 20; the original data samples are shown in Table 1:

Table 1. Raw sample data.

No. Q (Kg) R (m) H (m) PPV (cm/s)

1 9072 466 81 0.3352 9518 389 81 0.3433 9942 486 96 0.3394 9975 38 30 8.3905 9975 201 45 0.1936 9975 70 75 3.7107 9975 129 90 0.3508 5745 671 121 0.0439 5745 683 121 0.05110 10,077 80 −15 6.73011 10,077 152 30 0.21012 10,077 522 45 0.78313 10,077 678 90 0.19214 7401 47 15 5.83015 7401 140 15 1.77416 7401 273 15 0.41617 7401 432 30 0.14318 7401 654 51 0.15219 9545 55 15 2.28320 9545 161 15 0.71721 9545 286 15 0.52422 9545 677 51 1.01223 8041 484 96 0.28724 9812 523 81 0.79825 8041 461 90 0.14926 9812 209 75 3.10827 8041 592 75 0.11628 9812 304 60 3.97929 8041 588 45 0.19830 9812 381 30 0.94831 8041 601 30 0.32332 9812 52 15 9.026

By performing empirical wavelet decomposition on the collected blasting vibrationsignals, each mra component can be obtained, as shown in Figure 4. The blasting signal canbe found by removing the noise, and the maximum value among them can be selected asthe new particle peak particle velocity data sample, as input to the EWT–XGBoost blastingvibration velocity prediction model.

3.2. High Steep Slopes Model

Simulation of the blasting on adjacent high and steep slopes is carried out, and theparameters of the model include the slope parameters and blasting parameters. The slopeparameters include the foot of the slope (+6 m), the step height (15 m), eight steps, the footof the step (75), the safety platform (5 m), the cleaning platform (8 m), and three safetyplatforms with one cleaning platform at the intervals (safety platform at the +111 m, +96 m,+81 m, +51 m, +36 m, +21 m mining levels; cleaning platform at the +66 m mining level).The blasting parameters include the borehole diameter (110 mm), the depth of the borehole(16.5 m), the length of the stemming (4 m), the length of the charge (12.5 m), the chargediameter (90 mm), the hole space (the column distance is 6.2 m; the row distance is 3.3 m),

Appl. Sci. 2022, 12, 5849 7 of 12

the minimum burden (3 m), and the subdrilling (1.5 m). The schematic diagram of the siteand the corresponding model are shown in Figure 5.

Appl. Sci. 2022, 12, x FOR PEER REVIEW 7 of 12

18 7401 654 51 0.152

19 9545 55 15 2.283

20 9545 161 15 0.717

21 9545 286 15 0.524

22 9545 677 51 1.012

23 8041 484 96 0.287

24 9812 523 81 0.798

25 8041 461 90 0.149

26 9812 209 75 3.108

27 8041 592 75 0.116

28 9812 304 60 3.979

29 8041 588 45 0.198

30 9812 381 30 0.948

31 8041 601 30 0.323

32 9812 52 15 9.026

By performing empirical wavelet decomposition on the collected blasting vibration

signals, each mra component can be obtained, as shown in Figure 4. The blasting signal

can be found by removing the noise, and the maximum value among them can be selected

as the new particle peak particle velocity data sample, as input to the EWT–XGBoost blast-

ing vibration velocity prediction model.

Figure 4. Blasting vibration signal EWT and spectrogram.

3.2. High Steep Slopes Model

Simulation of the blasting on adjacent high and steep slopes is carried out, and the

parameters of the model include the slope parameters and blasting parameters. The slope

parameters include the foot of the slope (+6 m), the step height (15 m), eight steps, the foot

of the step (75°), the safety platform (5 m), the cleaning platform (8 m), and three safety

platforms with one cleaning platform at the intervals (safety platform at the +111 m, +96

m, +81 m, +51 m, +36 m, +21 m mining levels; cleaning platform at the +66 m mining level).

The blasting parameters include the borehole diameter (110 mm), the depth of the bore-

hole (16.5 m), the length of the stemming (4 m), the length of the charge (12.5 m), the

charge diameter (90 mm), the hole space (the column distance is 6.2 m; the row distance

is 3.3 m), the minimum burden (3 m), and the subdrilling (1.5 m). The schematic diagram

of the site and the corresponding model are shown in Figure 5.

Figure 4. Blasting vibration signal EWT and spectrogram.

Appl. Sci. 2022, 12, x FOR PEER REVIEW 8 of 12

(a)

(b)

Figure 5. Schematic diagram of the scene and the corresponding model: (a) Site map of the slope;

(b) Schematic diagram of the model.

Among the various material ontological models provided by LS-DYNA, the ontolog-

ical models that are often used to describe the rock material are the RHT model, the HJC

model, etc. In this paper, the HJC ontological model is used to describe the tuff material,

and the relevant parameters of the tuff are derived from reference [26], as shown in Table

2.

Table 2. HJC model parameters of the tuff material.

ρ

/(g·cm-3)

G

/(MPa) A B C N

fc/

(MPa)

1.8 6543 0.55 1.77 0.0097 0.77 50

T/(MPa) ε0/(s−1) εf,min Smax Pc/(MPa) Uc PL/(MPa)

3.3 1 × 10−6 0.01 17 17 0.00253 2500

UL D1 D2 K1/(MPa) K2/(MPa) K3/(MPa) fs

0.38 0.04 1 3100 6000 8400 0.035

ρ: mass density, G: shear modulus, A: normalized cohesive strength, B: normalized pressure hard-

ening, C: strain rate coefficient, N: pressure hardening exponent, fc: quasi-static uniaxial compressive

strength, T: maximum tensile hydrostatic pressure, ε0: quasi-static threshold strain rate, εf,min:

amount of plastic strain before fracture, Smax: normalized maximum strength, Pc: crushing pressure,

Uc: crushing volumetric strain, PL: locking pressure, UL: locking volumetric strain, D1: damage con-

stant , D2: damage constant, K1: pressure constant, K2: pressure constant, K3: pressure constant, fs:

failure type.

The air domain is used for the contact between the solid and fluid media. The fluid-

solid coupling algorithm is used to couple the fluid parts, such as the air and explosives,

Figure 5. Schematic diagram of the scene and the corresponding model: (a) Site map of the slope;(b) Schematic diagram of the model.

Appl. Sci. 2022, 12, 5849 8 of 12

Among the various material ontological models provided by LS-DYNA, the ontologi-cal models that are often used to describe the rock material are the RHT model, the HJCmodel, etc. In this paper, the HJC ontological model is used to describe the tuff material,and the relevant parameters of the tuff are derived from reference [26], as shown in Table 2.

Table 2. HJC model parameters of the tuff material.

ρ/(g·cm−3) G/(MPa) A B C N f c/(MPa)

1.8 6543 0.55 1.77 0.0097 0.77 50

T/(MPa) ε0/(s−1) εf,min Smax Pc/(MPa) Uc PL/(MPa)

3.3 1 × 10−6 0.01 17 17 0.00253 2500

UL D1 D2 K1/(MPa) K2/(MPa) K3/(MPa) fs

0.38 0.04 1 3100 6000 8400 0.035ρ: mass density, G: shear modulus, A: normalized cohesive strength, B: normalized pressure hardening, C: strainrate coefficient, N: pressure hardening exponent, f c: quasi-static uniaxial compressive strength, T: maximumtensile hydrostatic pressure, ε0: quasi-static threshold strain rate, εf,min: amount of plastic strain before fracture,Smax: normalized maximum strength, Pc: crushing pressure, Uc: crushing volumetric strain, PL: locking pressure,UL: locking volumetric strain, D1: damage constant, D2: damage constant, K1: pressure constant, K2: pressureconstant, K3: pressure constant, fs: failure type.

The air domain is used for the contact between the solid and fluid media. The fluid-solid coupling algorithm is used to couple the fluid parts, such as the air and explosives,with the solid rock part. The keyword MAT_NULL is used to add air materials. The stateequation formula is:

P = C0 + C1µ + C2µ2 + C3µ3 +(

C4 + C5µ + C6µ2)

E (9)

In the formula, E is the specific energy, which refers to the energy per unit volume;C0~C6 are constants; and µ is the specific volume. The air-related parameters are shownin Table 3.

Table 3. Air parameters.

C0 C1 C2 C3 C4 C5 C6 E/(MPa)

0 0 0 0 0.4 0.4 0 0.25

The explosive material is defined by the keyword “MAT_HIGH_EXPLOSIVE_BURN”.The JWL equation of state is used to represent the pressure and volume changes duringthe explosion. The No. 2 rock emulsion explosive is used in the field. Its parameters arederived from reference [27], as shown in Table 4:

Table 4. Parameters of the No. 2 rock emulsion explosive.

ρ/(kg/m3) D/(m/s) G/(MPa) A/(GPa) B/(Gpa) R1 R2 ω E/(MPa)

1100 3600 3500 214.4 0.182 4.2 0.9 0.15 4 192

Set the top and slope faces as free boundaries and the rest as transmission boundarieswith fixed displacement directions.

4. Result and Discussion4.1. Analysis of the Learning Results

Import the test samples into the trained EWT–XGBoost blasting vibration velocityprediction model for prediction. The comparison of the test samples and prediction resultsis shown in Table 5:

Appl. Sci. 2022, 12, 5849 9 of 12

Table 5. Test sample data and comparison of forecast results.

No. Q(Kg) R(m) H(m)XGBoost Model EWT–XGBoost Model

MeasuredValue

PredictedValue

MeasuredValue

PredictedValue

1 9975 38 30 8.390 8.231 3.882 3.8772 5745 683 121 0.051 0.057 0.013 0.0123 7401 47 15 5.830 5.800 1.566 1.5634 9545 55 15 2.283 2.369 0.941 0.9465 9812 523 81 0.798 0.806 0.063 0.064

It can be seen from the Figure 6 that the maximum relative error of the prediction resultof the blasting vibration velocity of the EWT–XGBoost model is 7.69%, which is less thanthe maximum relative error of the XGBoost model (11.8%). The average relative error ofthe prediction results of the EWT–XGBoost model can be obtained by statistical calculationof the relative error, which yields 2.03%, which is less than the average relative error of theprediction results of the XGBoost model (4.49%). Formula 8 is used to calculate the rootmean square error of the two models. According to the calculation, it can be concluded thatthe root mean square error of the prediction result of the EWT–XGBoost model is 0.0035,which is smaller than the root mean square error of the prediction result of the XGBoostmodel, which is 0.0836. Therefore, in terms of predicting the blasting vibration velocity TheEWT–XGBoost model is better than the XGBoost model.

Appl. Sci. 2022, 12, x FOR PEER REVIEW 10 of 12

Figure 6. Relative results histogram of the prediction results.

4.2. Predictive Analysis of Nodal Vibration Velocity

By building a numerical model of high and steep slopes and comparing and analyz-

ing the variation of blasting vibration velocity at the center positions of different plat-

forms, the following rules are found: the Figure 7 shows the blasting vibration velocity

changes at the center positions of the platforms 51, 66, 81, 96, and 111 within the initial 10

ms, when the blastholes are detonated at the same time. The vibration velocity of the 111

platform exceeds the safe vibration velocity specified in the blasting safety regulations

[28]. From the 96 platform to the 111 platform, the blasting vibration velocity decays rap-

idly. The vibration velocity of the 51, 66, and 81 platforms does not change significantly,

and the peak particle velocity is less than 1cm/s.

Figure 7. 10 ms blasting vibration velocity diagram of the 51–111 platform.

The 111 platform is close to the explosion source and is greatly affected by the shock

wave, so the response fluctuates violently in the vibration velocity. With the increase in

the explosion center distance, the vibration parameters change gradually. According to

this, the safety monitoring of the 111 platform should be strengthened, and active protec-

tion should be carried out.

The Figure 8 is a line chart of the peak blasting vibration velocity of each platform

height with different delay times. Compared with simultaneous blasting, delayed blasting

has a significant impact on the peak particle velocity of the 66–111 platform. The difference

in elevation is 45 m. The peak blasting vibration of the delay times of 130 ms and 80 ms is

Figure 6. Relative results histogram of the prediction results.

4.2. Predictive Analysis of Nodal Vibration Velocity

By building a numerical model of high and steep slopes and comparing and analyzingthe variation of blasting vibration velocity at the center positions of different platforms, thefollowing rules are found: the Figure 7 shows the blasting vibration velocity changes atthe center positions of the platforms 51, 66, 81, 96, and 111 within the initial 10 ms, whenthe blastholes are detonated at the same time. The vibration velocity of the 111 platformexceeds the safe vibration velocity specified in the blasting safety regulations [28]. Fromthe 96 platform to the 111 platform, the blasting vibration velocity decays rapidly. Thevibration velocity of the 51, 66, and 81 platforms does not change significantly, and thepeak particle velocity is less than 1 cm/s.

The 111 platform is close to the explosion source and is greatly affected by the shockwave, so the response fluctuates violently in the vibration velocity. With the increase in theexplosion center distance, the vibration parameters change gradually. According to this,the safety monitoring of the 111 platform should be strengthened, and active protectionshould be carried out.

Appl. Sci. 2022, 12, 5849 10 of 12

Appl. Sci. 2022, 12, x FOR PEER REVIEW 10 of 12

Figure 6. Relative results histogram of the prediction results.

4.2. Predictive Analysis of Nodal Vibration Velocity

By building a numerical model of high and steep slopes and comparing and analyz-

ing the variation of blasting vibration velocity at the center positions of different plat-

forms, the following rules are found: the Figure 7 shows the blasting vibration velocity

changes at the center positions of the platforms 51, 66, 81, 96, and 111 within the initial 10

ms, when the blastholes are detonated at the same time. The vibration velocity of the 111

platform exceeds the safe vibration velocity specified in the blasting safety regulations

[28]. From the 96 platform to the 111 platform, the blasting vibration velocity decays rap-

idly. The vibration velocity of the 51, 66, and 81 platforms does not change significantly,

and the peak particle velocity is less than 1cm/s.

Figure 7. 10 ms blasting vibration velocity diagram of the 51–111 platform.

The 111 platform is close to the explosion source and is greatly affected by the shock

wave, so the response fluctuates violently in the vibration velocity. With the increase in

the explosion center distance, the vibration parameters change gradually. According to

this, the safety monitoring of the 111 platform should be strengthened, and active protec-

tion should be carried out.

The Figure 8 is a line chart of the peak blasting vibration velocity of each platform

height with different delay times. Compared with simultaneous blasting, delayed blasting

has a significant impact on the peak particle velocity of the 66–111 platform. The difference

in elevation is 45 m. The peak blasting vibration of the delay times of 130 ms and 80 ms is

Figure 7. 10 ms blasting vibration velocity diagram of the 51–111 platform.

The Figure 8 is a line chart of the peak blasting vibration velocity of each platformheight with different delay times. Compared with simultaneous blasting, delayed blastinghas a significant impact on the peak particle velocity of the 66–111 platform. The differencein elevation is 45 m. The peak blasting vibration of the delay times of 130 ms and 80 ms isnot significantly reduced, and, among them, the peak particle velocity of the 111 platformhas the largest decrease. The peak particle velocity of the 80 ms delayed detonation isreduced by 17% compared to the 130 ms delayed detonation on the 111 platform. The51 platform is located in the middle, and its peak particle velocity has been significantlystrengthened. The blasting vibration velocity below the 51 platform has an amplificationeffect, and the peak particle velocity has slightly rebounded.

Appl. Sci. 2022, 12, x FOR PEER REVIEW 11 of 12

not significantly reduced, and, among them, the peak particle velocity of the 111 platform

has the largest decrease. The peak particle velocity of the 80 ms delayed detonation is

reduced by 17% compared to the 130 ms delayed detonation on the 111 platform. The 51

platform is located in the middle, and its peak particle velocity has been significantly

strengthened. The blasting vibration velocity below the 51 platform has an amplification

effect, and the peak particle velocity has slightly rebounded.

Figure 8. Line graph of the peak particle velocity of the 6–111 platform.

5. Conclusions

In this study, a machine learning model and a numerical simulation model were de-

veloped to predict blast vibration velocity at the Dahuangshan mine. A machine learning

model for blast vibration prediction considering elevation difference was established, and

the mean relative error and root mean square error were calculated by training the original

blast vibration monitoring data and predicting the test sample data. It was found that the

EWT–XGBoost model reduces the average relative error by 2.46% and the root mean

square error by 0.0801 compared with the XGBoost model, so the improved XGBoost

method can be applied to the analysis of blasting events in open-pit mines. In terms of

PPV prediction, the EWT–XGBoost model can achieve a higher prediction accuracy com-

pared with that of the original model. A numerical model for predicting the vibration

velocity of high and steep slope blasting is established, and the simulation results show

that the vibration velocity of platform 111 exceeds the safety regulations when the simul-

taneous detonation method is used compared with when the hole-by-hole method is used.

The peak particle velocity of blasting at the top of the mountain decreases sharply when

using the deferred detonation method, and the deferred blasting can have a good vibra-

tion damping effect on the high and steep slope. The vibration damping effect is especially

obvious within a 45 m difference in elevation. The high and steep slopes are dangerous,

so we did not place the sensors. This is an oversight in our work, and we will improve it

in future studies.

Author Contributions: J.G. and S.X. provided the experimental ideas and carried out the experi-

ment; Y.L. directed and assisted the experiment; C.Z. wrote the paper; J.G. reviewed the paper. All

authors have read and agreed to the published version of the manuscript.

Funding: This research was funded by the Central South University School-Enterprise Joint Project

“Research on rapid evaluation technology of open-pit blasting effect in plateau mines”

(2021xqlh065) and by the Central South University-Hongda Blasting Engineering Group Postgrad-

uate Joint Training Base (2020pyjd91).

Conflicts of Interest: The authors declare no conflict of interest.

Figure 8. Line graph of the peak particle velocity of the 6–111 platform.

5. Conclusions

In this study, a machine learning model and a numerical simulation model weredeveloped to predict blast vibration velocity at the Dahuangshan mine. A machine learningmodel for blast vibration prediction considering elevation difference was established, andthe mean relative error and root mean square error were calculated by training the originalblast vibration monitoring data and predicting the test sample data. It was found that theEWT–XGBoost model reduces the average relative error by 2.46% and the root mean squareerror by 0.0801 compared with the XGBoost model, so the improved XGBoost method canbe applied to the analysis of blasting events in open-pit mines. In terms of PPV prediction,the EWT–XGBoost model can achieve a higher prediction accuracy compared with thatof the original model. A numerical model for predicting the vibration velocity of highand steep slope blasting is established, and the simulation results show that the vibrationvelocity of platform 111 exceeds the safety regulations when the simultaneous detonation

Appl. Sci. 2022, 12, 5849 11 of 12

method is used compared with when the hole-by-hole method is used. The peak particlevelocity of blasting at the top of the mountain decreases sharply when using the deferreddetonation method, and the deferred blasting can have a good vibration damping effect onthe high and steep slope. The vibration damping effect is especially obvious within a 45 mdifference in elevation. The high and steep slopes are dangerous, so we did not place thesensors. This is an oversight in our work, and we will improve it in future studies.

Author Contributions: J.G. and S.X. provided the experimental ideas and carried out the experiment;Y.L. directed and assisted the experiment; C.Z. wrote the paper; J.G. reviewed the paper. All authorshave read and agreed to the published version of the manuscript.

Funding: This research was funded by the Central South University School-Enterprise Joint Project“Research on rapid evaluation technology of open-pit blasting effect in plateau mines” (2021xqlh065)and by the Central South University-Hongda Blasting Engineering Group Postgraduate Joint TrainingBase (2020pyjd91).

Conflicts of Interest: The authors declare no conflict of interest.

References1. Nikkhah, A.; Vakylabad, A.B.; Hassanzadeh, A.; Niedoba, T.; Surowiak, A. An Evaluation on the Impact of Ore Fragmented by

Blasting on Mining Performance. Minerals 2022, 12, 258. [CrossRef]2. Gharehgheshlagh, H.H.; Alipour, A. Ground vibration due to blasting in dam and hydropower projects. Rud.-Geol.-Naft. Zb. 2020,

35, 59–66.3. Feher, J.; Cambal, J.; Pandula, B.; Kondela, J.; Sofranko, M.; Mudarri, T.; Buchla, I. Research of the technical seismicity due to

blasting works in quarries and their impact on the environment and population. Appl. Sci. 2021, 11, 2118. [CrossRef]4. Jiang, N.; Zhang, Y.; Zhou, C.; Wu, T.; Zhu, B. Influence of Blasting Vibration of MLEMC Shaft Foundation Pit on Adjacent

High-Rise Frame Structure: A Case Study. Energies 2020, 13, 5140. [CrossRef]5. Ma, Y.; Liu, C.; Wang, P.; Zhu, J.; Zhou, X. Blast Vibration Control in A Hydropower Station for the Safety of Adjacent Structure.

Appl. Sci. 2020, 10, 6195. [CrossRef]6. Lutovac, S.; Medenica, D.; Glušcevic, B.; Tokalic, R.; Beljic, C. Some Models for Determination of Parameters of the Soil Oscillation

Law during Blasting Operations. Energies 2016, 9, 617. [CrossRef]7. Mesec, J.; Strelec, S.; Tezak, D. Ground vibrations level characterization through the geological strength index (GSI). Rud.-Geol.-Naft.

Zb. 2017, 32, 1–6. [CrossRef]8. Yin, Z.Q.; Hu, Z.X.; Wei, Z.D.; Zhao, G.M.; Ma, H.F.; Zhuo, Z.; Feng, R.M. Assessment of Blasting-Induced Ground Vibration in an

Open-Pit Mine under Different Rock Properties. Adv. Civ. Eng. 2018, 2018, 4603687. [CrossRef]9. LIN, H. Blasting vibration propagation law and control technology of high slope. Eng. Blasting 2020, 26, 69–74.10. Yue, Z.; Wu, Y.; Wei, Z.; Wang, G.; Wang, Y.; Li, X.; Zhou, Y. Prediction of blasting vibration effect in open-pit mine based on

PSO-LSSVM model. Eng. Blasting 2020, 26, 1–8.11. Sun, M.; Wu, L.; Yuan, Q.; Zhou, Y.; Ma, C. Blasting vibration prediction of underground gas storage caverns based on PSO-LSSVM

algorithm. Blasting 2017, 34, 145–150.12. Yan, Y.; Hou, X.; Cao, S.; Li, R.; Zhou, W. Forecasting the Collapse-Induced Ground Vibration Using a GWO-ELM Model. Buildings

2022, 12, 121. [CrossRef]13. Yu, Z.; Shi, X.; Zhou, J.; Chen, X.; Qiu, X. Effective Assessment of Blast-Induced Ground Vibration Using an Optimized Random

Forest Model Based on a Harris Hawks Optimization Algorithm. Appl. Sci. 2020, 10, 1403. [CrossRef]14. Zhang, H.; Zhou, J.; Jahed Armaghani, D.; Tahir, M.M.; Pham, B.T.; Huynh, V.V. A Combination of Feature Selection and Random

Forest Techniques to Solve a Problem Related to Blast-Induced Ground Vibration. Appl. Sci. 2020, 10, 869. [CrossRef]15. Lak, M.; Marji, M.F.; Bafghi, A.Y.; Abdollahipour, A. Analytical and numerical modeling of rock blasting operations using a

two-dimensional elasto-dynamic Green’s function. Int. J. Rock Mech. Min. Sci. 2019, 114, 208–217. [CrossRef]16. Lei, Z.; Gao, Z.; Zhuo, Y.; He, X.; Yuan, Y.; He, L. Research on vibration propagation law and dynamic response characteristics of

bench blasting. Blasting 2019, 36, 137–145.17. Choi, Y.-H.; Lee, S.S. Predictive Modelling for Blasting-Induced Vibrations from Open-Pit Excavations. Appl. Sci. 2021, 11, 7487.

[CrossRef]18. Gonen, A. Investigation of Fault Effect on Blast-Induced Vibration. Appl. Sci. 2022, 12, 2278. [CrossRef]19. Yan, B.; Liu, M.; Meng, Q.; Li, Y.; Deng, S.; Liu, T. Study on the Vibration Variation of Rock Slope Based on Numerical Simulation

and Fitting Analysis. Appl. Sci. 2022, 12, 4208. [CrossRef]20. Gilles, J. Empirical wavelet transform. IEEE Trans. Signal Processing 2013, 61, 3999–4010. [CrossRef]21. Huang, N.E.; Shen, Z.; Long, S.R.; Wu, M.C.; Shih, H.H.; Zheng, Q.; Yen, N.-C.; Tung, C.C.; Liu, H.H. The empirical mode

decomposition and the Hilbert spectrum for nonlinear and non-stationary time series analysis. Proc. R. Soc. London. Ser. A Math.Phys. Eng. Sci. 1998, 454, 903–995. [CrossRef]

Appl. Sci. 2022, 12, 5849 12 of 12

22. Daubechies, I. Ten Lectures on Wavelets; SIAM: Philadelphia, PA, USA, 1992.23. Jaffard, S.; Meyer, Y.; Ryan, R.D. Wavelets: Tools for Science and Technology; SIAM: Philadelphia, PA, USA, 2001.24. Meyer, Y. Wavelets, Vibrations and Scalings; American Mathematical Soc.: Providence, RI, USA, 1998.25. Chen, T.; Guestrin, C. Xgboost: A scalable tree boosting system. In Proceedings of the 22nd Acm Sigkdd International Conference

on Knowledge Discovery and Data Mining, San Francisco, CA, USA, 13 August 2016; pp. 785–794.26. Qin, F.; Xiang-zhen, K.; Hao, W.; Zi-Ming, G. Determination of Holmquist-Johnson-Cook consitiutive model parameters of rock.

Eng. Mech. 2014, 31, 197–204.27. Feng, M.; Wenhua, Z.; Dongqing, L. Application of water-couple charge blasting in tunnel excavation. Chin. J. Undergr. Space Eng.

2012, 8, 1008–1013.28. Safety Regulations for Blasting: GB 6722-2014; China Standards Press: Beijing, China, 2015.