precast concrete closed spandrel arch bridge system as viable alternative to conventional beam...

6
Precast Concrete Closed Spandrel Arch Bridge System As Viable Alternative to Conventional Beam Bridge System Chong Yong Ong 1, a , Kok Keong Choong 1,a , Geem Eng Tan 2, b , Tai Boon Ong 2,b 1 School of Civil Engineering, Universiti Sains Malaysia, Engineering Campus, 14300 Nibong Tebal, Seberang Perai Selatan, Pulau Pinang, MALAYSIA 2 Rivo Precast Sdn Bhd, Lot 5127, Batu 6, Jalan Kenangan Off Jalan Meru, 41050 Klang, Selangor Darul Ehsan, MALAYSIA a [email protected], b [email protected] Keywords: precast closed spandrel arch bridge system, corrugated arch section, conventional beam bridge system, crown beam. Abstract. A precast concrete closed spandrel arch bridge system developed for river crossing in Malaysia is presented. The 7.1m clear rise and 20.1m clear span overfilled arch bridge was proposed. Conventional beam bridge construction system has been ruled out due to the handling difficulty and cost factors. A structurally efficient precast arch section with corrugated shape was conceptualized, designed and developed. The economical viable solution adapted was a precast closed spandrel arch bridge system consisting of two connecting half-leaf panels with insitu crown beam. This system has been proven effective featuring simple precasting technique, handling process and practical jointing system at the crown. Comparisons between Precast closed spandrel arch bridge system and conventional beam bridge system is also highlighted. Introduction Bridges have been categorized as an important road structure which function as crossing over rivers or valleys. For the past centuries, arch bridges was fully used as transport network system to connect cities or countries. The most common arch bridge construction materials are stone, timber, iron and steel. Due to the unbelievable durability and appealing aesthetic, many of these arch bridges are still in service conditions. The development of reinforced concrete since late of 18 th century by Francois Hennebique has brought the innovation to current concrete structures [1]. One of the current trend is to prefabricate components which is cost effective and short in construction period. Enchanted by the great features of precasting techniques, it has been applied as a solution to bridge construction. Conventional Beam Bridge System Beam system has been extensively used in many countries covering from short to medium span from 5m to 50m. For a simple supported beam under point load as shown in Figure 1(a), as the span increases, the bending moment increases. This relationship can be illustrated in Figure 1(b). In cross section design using stress block concept, bending moment is directly proportional to the lever arm between resultant force of concrete in compression zone and steel in tension zone (Equation 1). Hence, it may result in bigger, thicker and bulky cross section as span increases. Figure 2 shows the different type of beam sections based on their respective span range. This system is basically suitable for lower rise bridge requirement projects. Applied Mechanics and Materials Vol. 802 (2015) pp 261-266 Submitted: 2015-04-29 © (2015) Trans Tech Publications, Switzerland Revised: 2015-05-20 doi:10.4028/www.scientific.net/AMM.802.261 Accepted: 2015-05-20 All rights reserved. No part of contents of this paper may be reproduced or transmitted in any form or by any means without the written permission of Trans Tech Publications, www.ttp.net. (ID: 175.137.187.239-13/10/15,15:45:05)

Upload: usm

Post on 10-Nov-2023

0 views

Category:

Documents


0 download

TRANSCRIPT

Precast Concrete Closed Spandrel Arch Bridge System As Viable

Alternative to Conventional Beam Bridge System

Chong Yong Ong1, a, Kok Keong Choong1,a, Geem Eng Tan2, b, Tai Boon Ong2,b 1School of Civil Engineering, Universiti Sains Malaysia, Engineering Campus, 14300 Nibong Tebal,

Seberang Perai Selatan, Pulau Pinang, MALAYSIA

2Rivo Precast Sdn Bhd, Lot 5127, Batu 6, Jalan Kenangan Off Jalan Meru, 41050 Klang, Selangor

Darul Ehsan, MALAYSIA

[email protected],

[email protected]

Keywords: precast closed spandrel arch bridge system, corrugated arch section, conventional beam bridge system, crown beam.

Abstract. A precast concrete closed spandrel arch bridge system developed for river crossing in

Malaysia is presented. The 7.1m clear rise and 20.1m clear span overfilled arch bridge was proposed.

Conventional beam bridge construction system has been ruled out due to the handling difficulty and

cost factors. A structurally efficient precast arch section with corrugated shape was conceptualized,

designed and developed. The economical viable solution adapted was a precast closed spandrel arch

bridge system consisting of two connecting half-leaf panels with insitu crown beam. This system has

been proven effective featuring simple precasting technique, handling process and practical jointing

system at the crown. Comparisons between Precast closed spandrel arch bridge system and

conventional beam bridge system is also highlighted.

Introduction

Bridges have been categorized as an important road structure which function as crossing over

rivers or valleys. For the past centuries, arch bridges was fully used as transport network system to

connect cities or countries. The most common arch bridge construction materials are stone, timber,

iron and steel. Due to the unbelievable durability and appealing aesthetic, many of these arch bridges

are still in service conditions.

The development of reinforced concrete since late of 18th

century by Francois Hennebique has

brought the innovation to current concrete structures [1]. One of the current trend is to prefabricate

components which is cost effective and short in construction period. Enchanted by the great features

of precasting techniques, it has been applied as a solution to bridge construction.

Conventional Beam Bridge System

Beam system has been extensively used in many countries covering from short to medium span

from 5m to 50m. For a simple supported beam under point load as shown in Figure 1(a), as the span

increases, the bending moment increases. This relationship can be illustrated in Figure 1(b). In cross

section design using stress block concept, bending moment is directly proportional to the lever arm

between resultant force of concrete in compression zone and steel in tension zone (Equation 1).

Hence, it may result in bigger, thicker and bulky cross section as span increases. Figure 2 shows the

different type of beam sections based on their respective span range. This system is basically suitable

for lower rise bridge requirement projects.

Applied Mechanics and Materials Vol. 802 (2015) pp 261-266 Submitted: 2015-04-29© (2015) Trans Tech Publications, Switzerland Revised: 2015-05-20doi:10.4028/www.scientific.net/AMM.802.261 Accepted: 2015-05-20

All rights reserved. No part of contents of this paper may be reproduced or transmitted in any form or by any means without the written permission of TransTech Publications, www.ttp.net. (ID: 175.137.187.239-13/10/15,15:45:05)

(a) (b)

Figure 1: Structural Behaviour of Beam Bridge Under Point load: (a) Free Body Diagram, (b)

Bending Moment Diagram

M = Fst x z (1)

Where, M = Bending Moment

Fst = Resultant force of tensile steel

Z = lever arm between resutant force of concrete

in compression zone and steel in tensile zone

Figure 2: Precast Beam Types and Span Ranges [2]

Description of Project

A bridge system was proposed for a development project in Malaysia. The exhibited design was

conventional beam bridge system with an R.C. U-drain as to protect the elevated foundation. Figure 3

describes the bridge elevation section for the exhibited design.

Figure 3: Bridge Elevation Section for Exhibited Design

P

0.5P 0.5P

L Moment=0.25PL

262 Modern Civil Engineering in Trend of the Sustainable InfrastructureDevelopment

Beam M4 was selected in this exhibited design. The weight for one piece of 20m span Beam M4 is

18.52 tons (per metre width). In terms of handling, lifting and installation process, contractor may

face difficulty and inconvenience. Besides, 100 tonage of crane is needed for the handling, lifting and

installation purposes. Greater self weight of bridge panel may cause heavier foundation design which

is not preferred most of the time.

Hence, Precast Concrete Closed Spandrel Arch Bridge System was developed and proposed to

provide viable solution to the above problems.

Precast Concrete Closed Spandrel Arch Bridge System

In theory of structure, arch bridge possess lower bending moment than beam due to the arch shape

(Figure 4). As such, thinner section in arch bridge system required compared to beam bridge system

for the same span. This will result in reducing load on pile and optimize the foundation design as well.

(a) (b)

Figure 4: Structural Behaviour of Circular Arch under Point Load; (a) Free Body Diagram,

(b) Bending Moment Diagram

Precast concrete closed spandrel arch bridge system consists of precast arch element, spandrel

wall, foundation, wingwall and backfilling components (Figure 5).

Figure 5: Components of Precast Concrete Closed Spandrel Arch Bridge System

Several proprietary precast concrete arch bridge systems [3], [4], [5] have been developed to

replace conventional masonry arch construction, but their spans have been limited to range of 6m to

25.6m due to logistic and lifting limitations. Notably, the system comprises of a series of precast arch

segments enclosed with two end spandrel units. The empty enclosure above the arches is then

overfilled in compacted layers with suitable granular materials. The stability of the arch structure is

achieved through soil-concrete interactions with side fills providing the lateral supports to withstand

the service loads. The commercially available arch systems are generally assembled from single-leaf,

double-leaf or triple-leaf precast segments as shown in Figure 6 with their respective proprietary

jointing systems.

(a)

(b)

(c)

Figure 6: Precast arch segment types:

(a) Single leaf; (b) Double leaf; (c) Triple leaf

P

H1

V1

H2

V2 L

h

Moment = 0.25PL-Hh

Applied Mechanics and Materials Vol. 802 263

The arches can be in circular, elliptical or parabolic profile to suit the structural and functional

requirements of the specific project. Those systems are distinguishable from many design and

construction details but with one common feature – the simple rectangular reinforced concrete section

adopted for the precast segments. Understandably the rectangular section is easy for mould

fabrication. It also simplifies the precasting process. However the section becomes heavy and bulky

for longer span arch with the increased thickness. Subsequent costs of handling, transporting and

installation are also affected with the increased weight of the precast segments resulting in the

necessity of heavier machineries and equipment.

The idea of using ribbed section in ‘Tee’ or ‘inverted-Tee’ shape was explored initially but the

material savings were found to be not substantial in this context due to the reasons of self-weight.

Efficient structural shapes with high flexural stiffness and minimal self-weight are often exhibited in

natural forms like palm tree or banana branches. Inspired by nature, an alike folded plate section in

corrugated form was conceptualized and developed (Figure 7). With the proposed section, the

self-weight is minimized by approximately 40% of equivalent solid rectangular section. Unlike the

ribbed section, the main advantage of this corrugated shape is the equal sectional moduli for top and

bottom fiber to resist bending moment with minimum materials. Although moulding is complicated at

first glance, repetitions will offset all once standardization is done as demonstrated in this pilot

project. The general arrangement of this project is represented in Figure 8. Patent has been granted for

this new innovation of corrugated arch segment [6].

(a) (b)

Figure 7: Dimension Details: (a) Arch Profile, (b) Section A-A

(a) (b)

Figure 8: General Arrangement: (a) Elevation, (b) Bridge Deck Section

Design and Development

With the aim of achieving a complete solution for a bridge taking full advantage of precast

technology and limitation, the following aspects have been taken into account in the

conceptualization and development of the closed spandrel arch bridge system : functionality and

aesthetics, arch profile development and foundation design, constructability in precast way -

transportation and arch panel, connection, casting, de-moulding and stacking, site installation and

on-site joint, backfilling process.

The new closed spandrel bridge is designed to withstand the loading as specified in BS 5400: Part

1 & 2 (1978) [7], [8], BD 31/01 [9] and BD 37/01 [10] for a design period of 120 years. Primary live

loads considered for the design of the bridge are as follows: (a) HA-UDL + HA-KEL and (b) HB-45

unit guided at the centerline of the deck. The dead load of the precast arch panel is resisted initially

by a three-pinned arch system. Once the crown is connected, the ring of the precast arch panel acts as

264 Modern Civil Engineering in Trend of the Sustainable InfrastructureDevelopment

a two-pinned arch system to resist loads. They are modelled accordingly in design and analysis for all

possible loading stages. Figure 9 shows the results of envelope sagging bending moment (298kNm/m

width), hogging bending moment (282 kNm/m width), axial force (856kN/m width) and shear force

(194kN/m width) from the PLAXIS analysis.

(a) (b) (c)

Figure 9: PLAXIS Envelope Results: (a) Bending Moment, (b) Axial Force and (c) Shear Force

Construction Method

Arch panels were prefabricated and cured for at least 28 days at factory. At the same time, the

keyway of the footing for the sitting of arch panels was levelled and checked for the critical

dimensions. Once it was done, installation works for arch panels started. First, the arch panel was

lifed from the ground and was pitched into horizontal position as shown in Figure 12(a) and 12(b).

Then, arch panels were hoisted from both sides and were self-propped at the mid span as shown in

Figure 12(c) and 12(d). The installation work was done in two days. Once after finishing the

installation, keyway was grout and crown beam would be cast later to connect both panels to form

rigid support at the mid span. The completed views of precast closed spandrel arch bridge system are

represented in Figure 13 and Figure 14.

(a) (b) (c) (d)

Figure 12: Installation Sequence: (a) Lifting from ground, (b) Pitching into position,

(b) Hoisting from both ends, (d) Self-prop at mid span

Figure 13: Installed Arch Panels Figure 14: Completed arch and spandrel

Material Comparisons

It is also important to compare the overall materials used for each system. From Table 1, it is

clearly shown that the total concrete used by beam bridge system is about 1.5 times than arch bridge

system which is 617 m3 and 394 m

3, rescpectively. However, for arch bridge system,a total of 1814m

3

backfill is used. It is not a critical issue which soil backfill materials can be easily found nearby the

Applied Mechanics and Materials Vol. 802 265

project site. In short, reducing usage of concrete materials for arch bridge system is able to bring the

sustainable solution to bridge construction.

Table 1: Overall Materials Comparison (Concrete Volume) For Conventional Beam Bridge

System and Precast Closed Spandrel Arch Bridge System

Bridge Structures Conventional Beam

Bridge System

Precast Closed Spandrel

Arch Bridge System

Foundation : Piles

Pile Cap

Strip Footing

84 pcs

93 m3

-

-

-

216 m3

Abutment 141 m3 -

Transition Slab 32 m3 -

Bridge Components : Panel

Concrete Deck

Soil Backfill

R.C Spandrel Wall

230 m3

(30 sets)

121 m3

-

-

142 m3

(20 sets)

-

1814 m3

36 m3

Concluding Remarks

Precast closed spandrel arch bridge system with corrugated section as viable alternative to

conventional beam bridge system has been described. A structurally efficient corrugated arch bridge

system offers higher stiffness, better aesthetic value and material save compared to beam bridge

system. With the development of precast concrete closed spandrel arch bridge system, it is able to

further explore in new applications such as military bunkers, utility vaults or aircraf shelters . Thus, it

is anticipated that this precast concrete arch bridge system will offer better solution to sustainable

bridge construction in the near future.

References

[1] D.G. Mcbeth, F. Hennebique and L.G. Mouchel, Francois Hennebique ( 1842-1921 ), Reinforced

Concrete Pioneer, Proceeding of the ICE – Civil Engineering, Volume 126, Issue 2, 1998, pp.

86-95

[2] G.E. Tan, T.B. Ong, C.Y. Ong and K.K Choong, Development and Standardisation of New

Precast Concrete Open Spandrel Arch Bridge System, 37th

International Association for Bridge

and Structural Engineering (IABSE) Symposium Madrid, 2014, Vol 102, pp. 799 - 806

[3] Product Brochure: Matiere Arch by ACPi Persys Engineering

[4] Product Brochure: Hume Bebo Arch 2002

[5] Product Brochure: Techspan Precast Concrete Arch System, The Reinforced Earth Company

[6] Malaysian Patent MY-142912-A. 2008. Corrugated Arch Elements for Culvert, Bridge, Crossing

or Shelter and a Construction Thereof.

[7] British Standards Institute. BS5400-1:1978: Steel, concrete and composite bridges. General

statement. London

[8] British Standards Institute. BS5400-2:1978: Steel, concrete and composite bridges. Specification

for loads. London

[9] Highways Agency (UK). BD31/01, Departmental Standards. The Design of Buried Concrete Box

and Portal Frame Structure. Department of Transport, Highway and Traffic, November 2001

[10] Highways Agency (UK). BD37/01, Departmental Standards. Loads for Highway Bridges,

Design Manual for Roads and Bridges. Department of Transport, Highway and Traffic, 2001

266 Modern Civil Engineering in Trend of the Sustainable InfrastructureDevelopment