con 2001 & cve 4070 construction engineering risk management prof. ralph v. locurcio, pe
DESCRIPTION
What is risk??? An outcome different from what you expected or estimated… Or… different from what you bid!TRANSCRIPT
CON 2001 & CVE 4070
Construction EngineeringRisk ManagementProf. Ralph V. Locurcio, PE
Views of risk taking…
What is risk??? An outcome different from what you
expected or estimated…
Or… different from what you bid!
Sources of risk in construction… Construction operations are hazardous Labor capacity, capability, competence… Subsurface conditions; physical factors Contractual provisions; timing, LDs… Economic conditions; prices, labor… Political & public; new laws, opposition
Basic premise… All risks accrue to the owner unless
assigned by contract to another party
Assigning risk to another they must be (a)able to assess the risk fairly, (b)competent to do the task, and (c) result in a better solution
Risk allocation… at start
Owner
Designer Builder
Not yet involved
Risk allocation… traditional
Owner
Designer Builder
Risk allocation… design-build
Owner
Designer + Builder
Risk Management Tools Best Value procurements
Two stage bid process Contractor helps finalize design Incorporates VE
Risk Management Risk identification Analysis Response
Pareto Principle 80/20 rule…
States that 80% of the value comes from 20% of the activities.
Therefore, we need a method to focus on the 20% of the activities that have the most influence on the outcomes.
And… we should avoid the 80% of activities that produce little gain
Risk identification Identify areas of risk intensity
1. Buildability, logistics, health & safety2. Environmental, permits3. Cost environment
Develop risk registers1. Catalog all risk factors2. Assign responsibility to team
members
Risk analysis Use decision & simulation theory
Quantify maximum effect of each risk Identify probability of occurrence Determine economic impact of each Determine impact of combinations
Risk response Plan mitigation strategies
Specific action to be taken Avoidance, sharing, protection, etc. Accountable team member Account for inter-relationships Account for multiple risk scenarios
Risk Management Strategies Avoidance Transfer or Sharing Mitigation Insurance Recovery
Construction Risk Management Avoidance Retention
InsuranceEducation & Training
Exemption ClausesRisk sharing
Protection Clauses Retention Money
Liquidated DamagesRescind contract
Contingencies
Basic risk management-1… Build a Risk Allocation Matrix
Identify all potential risk of loss Assign to Owner, Contractor or Designer Quantify your potential loss Develop a risk management strategy
Basic risk management-2 Management strategies…
Avoid the potential loss Transfer the risk Share risk with another firm Mitigate the potential for loss Recover any unavoidable loss
• Claim• Insurance• Litigation
Basic risk management-3 Keys to allocation of risk…
Must be a reward for any risk assigned Asignee must be able to control risk Must produce “best” solution Must have financial capability Must follow terms assigned
Avoidance… Careful estimating & bidding Study the contract terms Study the owner’s style & record Study limits of insurance Prior planning for construction
Examine the plans, specs & conditions Examine the contract requirements Examine the site for unknowns & hazards Examine each process & plan your method
Transfer or sharing… Reduce source & size of risk
Use the contract terms General conditions Plans & specs
Negotiate new terms May not work with government
Change strategic approach Merger or joint venture with another firm Hire subcontractor for high risk work Purchase additional insurance
Mitigation… Good planning & communication
Quality control processes Use/acquire the right skills
Use/acquire the right equipment Use your experience wisely
Act promptly if the unexpected occurs
Insurance… Covers unexpected situations
Situations beyond your control Your track record is important Cost is a factor Do not overuse
Recovery…if all else fails Read the contract Good record keeping… especially impacts Follow correct procedures Demonstrate mitigation efforts Make a convincing presentation Attempt settlement at lowest level Seek legal help
Cost recovery 101 Read the contract
Begin mitigation immediately to minimize loss Stay within contractor’s authority Determine risk allocation for each problem Comply with all notification requirements Request contract change when required Establish new activity code for all added work Track cost of new work Quantify delay to other work
Change Order Solution
Change Order Solution
Change Order Solution
Change Order Solution-1 Student: _________________________________________
HW#7 - Solution to Change Order
Item to change Units L W/H Quantity Price/unit Credit Charge Value Score
Add CMU walls - Wall B SF 5.66 8 45.28 $8.48 $383.97 5
Credit CMU wall (@ door F) SF 5.66 8 45.28 $4.24 $191.99 5
Credit CMU wall A SF 11.33 8 90.64 $4.24 $384.31 5
Add CMU walls - Wall D SF 11.33 8 90.64 $8.48 $768.63 5
Credit for windows EA 1.00 $310.00 $310.00 5
Add Interior stud walls SF 11.33 8 90.64 $4.06 $368.00 5
Credit Interior stud walls SF 5 8 40.00 $2.03 $81.20 5
Add precast lintels LF 0.00 $28.00 $0.00
Credit precast lintels LF 4.5 4.50 $28.00 $126.00 5
Add foundation-wall D LF 11.33 11.33 $12.54 $142.08 5
Change Order Solution-2Credit foundation - wall door F & wall B cancel LF 0.00 $12.54 $0.00
Add downpours - wall D EA 4 4.00 $88.00 $352.00 5
Credit downpours - wall A & door F wall EA 5 5.00 $88.00 $440.00 5
Add stucco - wall D SF 11.33 8 90.64 $4.93 $446.86 5
Credit stucco - wall door F & wall B cancel SF 0 0 0.00 $4.93 $0.00 5
Add roof SF 11.33 24.33 275.66 $6.25 $1,722.87 5
Add 4" floor slab SF 11.33 24.33 275.66 $3.42 $942.75 5
Add tile floor SF 0 0 0.00 $3.42 $0.00
Add carpet in FR SY 5.66 11.33 2.38 $13.55 $32.18 5
Add carpet in LR & MBR SY 11.33 24.33 10.21 $13.55 $138.34 5
Subtotal charges $5,297.68 5
Subtotal credits $1,533.50 5
Subtotal job $3,764.18
Change Order Solution-3Labor @ 2x net materials $7,528.35 5
Add Extras @ 10% $752.84
Job Total $12,045.37 10
Your score 110
Percent score 100%
Test-3 Review 200 points Mix of questions… T/F, short answer Calculations for estimates Be prepared to “think”
Review-11. Ethics
a. Know the 3 basic sections of the Engineer’s Code of Ethics b. Know what is the sub-parts of each section c. Be able to apply each section to an ethics case study
2. Estimating & Change Orders
a. Know how to calculate a conceptual estimate b. Know how to calculate a detailed estimate for a change order c. Know how to use location, sizing & quantity factors d. Know how to adjust cost factors for timing & escalation to the mid-point of construction e. Be able to make recommendations based on your estimates
3. Negotiations
a. Negotiating styles b. Benefits of each style c. Results in long term or short term solution d. What method achieves the best solution
Review-23. Dispute resolution
a. What is a dispute b. Actions the owner should take in a dispute c. Actions the contractor should take in a dispute d. Methods to resolve a dispute
7. Payments to contractor
a. Know the basis for payments to a contractor b. Know how to calculate the payment c. Know the meaning of “retainage” and how to use it
8. Construction Contract Review
a. Know the major types of contracts: Fixed Price, Unit Price, Cost Plus and Incentive Fee b. Understand the pros & cons of each c. Understand the different risks associated with each of these contracts d. Know when to use: Fixed Price, Unit Price, Cost Plus and Cost Plus Incentive Fee contracts
Ethics HW handout Due: December 1st Read instructions carefully Cases on my web site
Questions?
Best Value ProcessUnderstand
Client Requirements
&Intent
BrainstormPossible Areas
forAdding Value
Find & IncludeExperts in Key Areas
DevelopOptions
WithPros & Cons
ID PreferredSolution &
Obtain NeededDesign Info
Present toExec Team
ForDecision
PreliminaryDesign
DetailedDesign
DevelopmentPlans
&Specs
Final ReviewBy
Exec Team
Final ApprovalBy
ClientConstruction
Contractor
Cost recovery 101 (a)… Detailed Work Breakdown Structure
(WBS) for estimating List & code each activity & duration Establish start & finish dates & labor hours List materials required & procurement lead Labor hours for shop drawings & submittals Have accounting code for each of above
Cost recovery 101 (b)… Develop change/claim spreadsheet
Use bid data as base line List all estimated activities & costs in a WBS Calculate “actual” duration & costs for WBS Establish % triggers to identify problems Notify owner’s rep immediately of problems
Cost recovery 101 (c)… Use data to analyze source of problem
Defective plans & specs Differing site conditions Interruption of work flow Unusual weather conditions Delay in receiving EI or submittal response Problems with labor Bad bid