con 2001 cve 4070 construction methods/engineering changes & extra work prof. ralph v. locurcio,...

35
CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Upload: stephen-campbell

Post on 29-Jan-2016

228 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

CON 2001 CVE 4070

Construction Methods/EngineeringChanges & Extra WorkProf. Ralph V. Locurcio, PE

Page 2: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE
Page 3: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Change order defined…

A written agreement to modify, add to or otherwise alter the work, timing or payment set forth in the original contract documents, for an agreed upon sum or compensation, which is signed by both parties to the original agreement.

Page 4: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Reasons for changes… Change of purpose or need… Changes to methods or manner of work... Correct errors or omissions… Differing site conditions… Value engineering… Contractor suggestions… Almost any other reason not envisioned when

the original contract was written.

Page 5: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Timing of changes…

41 2 3 5

Advertising Date

Bids Opened

Award Date

Sign Contract

Changes byAddenda to

Contract DocsNo Changes

Changes byChange Order

Construction Begins

Page 6: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Types of change orders…

Oral change orders Written and/or directed change orders Bilateral change orders Unilateral change orders Constructive change orders

Page 7: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Oral change order… An oral directive to accomplish work that is

not part of the original scope of work. May be issued by the owner’s rep or other

party representing the owner. May be precluded by the contract, but will

be upheld in court if the contractor performs work that is accepted.

Very dangerous because terms may not be clear, conditions may change, memories may differ as to what was agreed.

Page 8: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Written or directed change… A formal document directing a change

in scope or method. Generally bilateral, but not essential. Becomes part of the contract. Issued before work is accomplished. Parties agree on specific scope and

associated costs. Culminated by “notice to proceed”. Signed by parties authorized by the

owner and builder.

Page 9: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Unilateral change… Used in emergency situations or when

time does not permit a fully processed bilateral change.

May be issued over builder’s protest. May be backed by law in government

contracts. Intended to expedite a necessary

change to the contract. Must be replaced by a written bi-

lateral change

Page 10: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Bilateral change…

Both parties agree to the scope and terms of the agreement.

The normal or desired form of change.

Page 11: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Constructive change…

An “informal” act that authorizes or directs a modification to the contract.

May be act of commission or omission. Must be claimed in writing by the

contractor within a specified time (usually 10 days).

These are a major source of disputes.

Page 12: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Situations for constructive change…

Engineer’s interpretation of work. Improper inspection or rejection. Impossibility or impracticability of

performance. Unclear/conflicting contract documents. Owner fails to decide in timely manner. Unclear standards of work.

Page 13: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Change order process… Identify of need/reason for change

May be initiated by owner or contractor Initiator prepares detailed scope Change approved by owner Submit to designer of record for approval PM makes detailed cost estimate CM makes detailed estimate Negotiate final cost (PM & CM) Owner agrees & signs change document Notice to proceed issued to contractor

Page 14: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Change order process…

YES

Owner or EngineerInitiates Need for

Change

Owner’s Representative ReviewsDraft Change & Submits to PM

PM Reviews & Sends to Engineer of Record for

Recommendation

ChangeRecommended

Contractor Initiates Need for Change

Owner or EngineerPrep Draft Change Order

Prep Draft Change Order

Engineer of Record Reviews Makes Recommendation to

PM & Owner

NO

PM Prepares Change Docs

PM Requests Price Proposal

Disapprove & Return to

Contractor

Contractor PreparesCost Estimate

Owner’s RepresenatativeNegotiates Final Price

Engineer Prepares

Owner’s Estimate

Owner Signs

Change

Owner’s RepresenatativeIssues NTP to Contractor

Page 15: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Change order request…

YES

Owner or EngineerInitiates Need for Change

Owner’s Representative ReviewsDraft Change & Submits to PM

PM Reviews & Sends to Engineer of Record for

Recommendation

ChangeRecommended

Contractor Initiates Need for Change

Owner or EngineerPrep Draft Change Order

Owner or EngineerPrep Draft Change Order

Engineer of Record Reviews Makes Recommendation to

PM & Owner

NO

Disapprove & Return to Contractor

Proceed to Approval

Page 16: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Change order approval…

PM Prepares Change Docs

PM Requests Price Proposal

Contractor PreparesCost Estimate

Owner’s RepresenatativeNegotiates Final Price

Engineer PreparesOwner’s Estimate

Owner Signs

Change

Owner’s RepresenatativeIssues NTP to Contractor

Begin Approval Process

Page 17: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Change order cost estimate(s)…

Study the plans Organize your estimate Determine critical items & dimensions Determine materials & methods Determine quantities & labor Calculate the cost of each item Add taxes + overhead & profit Negotiate with the contractor

Page 18: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Making a detailed estimate

Take-off (count) quantities from plans Determine cost of materials in units Determine cost of labor in units Calculate cost of materials + labor Add sales taxes on materials (6%) Add labor taxes on labor cost (~25%) Add Overhead & Profit (~10%)

Note: obtain costs from RS Means or similar data

Page 19: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Foundation excavation-1…

Page 20: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Foundation-2…

Excav

Page 21: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Foundations… Concrete…

volume of concrete in CF cost of concrete in $$$/CF cost of labor in $$4/CF

Excavation volume of excavation in CF cost of excavation labor in $$$/CF

cost of equipment in $$$/CF or $$$/HR Foundation Cost = sum(conc + excav + labor)

Page 22: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Masonry walls…

W1

W2

W3/W6

W4

W5

W7

W8

W9

12”CMU

8” CMU

Insul

Brick

Page 23: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Walls… Walls…

length of walls in LF height of walls in LF area of walls in SF cost of wall material in $$$/SF cost of wall labor in $$$/SF cost = material + labor

Repeat for different materials Add all components for total cost of walls

Page 24: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Floor slab…

FS-1

FS-2

Page 25: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Floor Slab… Floor Slab

length of floor-1 in LF width of floor-1 in LF depth of floor-1 in LF volume of concrete in CF cost of concrete in $$$/CF cost of labor in $$$/CF repeat for floor-2 Floor = slab-1 + slab-2

Page 26: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Cost of Change Order

Cost of foundations + cost of walls + cost of floor slabs + other costs

Sum cost of all materials Sum cost of all labor Add sales taxes on materials (6%) Add labor taxes on labor cost (~25%) Add totals Add Overhead & Profit (~10%) Final estimate of change order

Page 27: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Impact costs…

Unforeseen costs that impact the progress of work as a result of the change, but are not calculated, or agreed to, at the time that the change is made.

Usually expressed as a claim for additional work at the end of a contract.

Some contracts may preclude these, but courts may honor them if actual costs or burden can be proven.

Page 28: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Format for Change Order

Page 29: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

HW #7

Page 30: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

HW #7

Page 31: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

HW #7

Page 32: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

HW #7

Page 33: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

HW #7

Page 34: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Almost the last slide…

Change Order Estimate Due Nov 10

Page 35: CON 2001 CVE 4070 Construction Methods/Engineering Changes & Extra Work Prof. Ralph V. Locurcio, PE

Questions…