cve 1000 construction engineering the project delivery system prof. ralph v. locurcio, pe
TRANSCRIPT
CVE 1000
Construction EngineeringThe Project Delivery SystemProf. Ralph V. Locurcio, PE
Why we are “civil” engineers…
The definition of “civil” of or relating to citizens as individuals; a condition of social order; adherence to social systems and
consideration for others
Why we are “civil” engineers…
The definition of engineers Engineering is the application of science
to the needs of humanity. This is accomplished through knowledge, mathematics, and practical experience applied to the design of useful objects or processes.
Why we are “civil” engineers!!
We build “civility” into daily life Water & Sanitary systems - keep us healthy Housing – keeps us warm & safe Transportation systems – help us travel Factories – build the stuff we need & want Office buildings – give us a place to work Schools – a place to prepare our children Energy systems – keep it all running
Recent memorable examples
Reconstruction of the World Trade Center
Reconstruction of New Orleans after hurricane Katrina
Class Problem… The time is 2000BC in Egypt The pharaoh has appointed you PM to
construct his burial pyramid He wants to know…
What tasks are necessary? What is the sequencing of tasks? How long will it take? How many people will you need? What will it cost?
Pyramid Construction…
Time2 4 6 8 10 12 14 16
General Design
Planning Preparation Construct Core
Trim Exterior
Demobilize
Interior Design Room Const Interior Finishes
Bury Pharoah
Structure
Site Selection
Master Plan
Open Quarry Cut Blocks Cut Trim
Workforce
Train Train Train
Build Camp
DemobCamp
FinalInsp
Design Process
Construction Process
Programming Process
Project Delivery Process…
Need for a projectIs recognized
Owner appointsProject Manager
Project Manager develops project
program: scope & cost parameters
Project is entered into an annual
capital program
Designer prepares concept design & preliminary cost
estimate
Designer completes plans &
specifications
Owner orders bid documents
Project Manager advertises for
construction bids
Contractors assemble team,
prepare & submit bid
Bids reviewed by owner
(with designer)
Builder’s credentials &
bonding approved
Owner approves program
Project Manager advertises for
designer
Owner hires designer
Owner authorizes final
design
Owner selectsbuilder
Notice to Proceed
Constructionbegins
Resident Engineeroversees
construction
Project phase(s)completed
All work completed final inspection
made
Progresspayment
Final paymentOwner accepts
facility
Programming Process…
Owner approves program
Need for project is
recognized
Owner appoints project
manager
PM develops scope & cost parameters
Project entered into
annual program
Project funding
provided
To Design Process
Design Process…
Owner hires
designer
PM advertises for
design
Designer prepares concept &
cost
PM develops scope & cost parameters
Designer prepares plans &
speifications
Project funding provided
To Construction
Process
Owner orders const
docs
Designer prepares
const cost estimate
Owner authorizes
final
Construction Process-1…
Owner selects builder
PM advertises for builder
Bids opened, reviewed
(w/designer)
Builder’s credentials
checked
Awardmade
Notice To
ProceedConstruction
Begins
Const contract signed
Builders assemble
teams & prep bids
4
1 2
3
5
Construction Process-2…
Progress payments
made
Resident Engineer appointed
Project phase(s)
completed
Work accepted
All project phases
completed
Owner accepts & occupies
ProjectCompleted
Final payment
made
Builder & subcontractors
mobilize
Finalinspection
Project Organization…Owner
Quality Control
Superintendent Project Engineer
Project Engineer
Contractor
Project Manager, Construction Manager
and/orContracting Officer
Subcontractor
Subcontractor
Subcontractor
Subcontractor
Subcontractor
Design Manager
ProjectArchitect
StructuralEngineer
CivilEngineer
MechEngineer
ElectricalEngineer
A
B
C
Quality Assure
OfficeEngineer
TechnicalInspectors
A/E Const Staff
Resident Engineer
UsingAgency
Project Organization-designOwner
ProjectArchitect
StructuralEngineer
CivilEngineer
MechanicalEngineer
Design Manager
Corporate Management
Project Manager, Construction Manager
and/orContracting Officer
ConstructionContract
UsingAgency
ElectricalEngineer
Design Staff Design Staff Design Staff Design Staff Design Staff
Consultant A Consultant B Consultant C
Project Organization-const mgt…
Owner
Quality Assurance
OfficeEngineer
TechnicalInspectors
A/E Const Staff
ResidentEngineer
Corporate Management
Corporate staff
Field site
FoundationElectrical
Mechanical
Shop DrawingsRFI controlMaterialsSamples
SchedulesPayments
RFI responsesClarification of drawings
Monitor compliance
Monitor QC processPrepare QA reports
Monitor corrective actionsDocument QA/QC
Project Manager, Construction Manager
and/orContracting Officer
ConstructionContract
Responsibility
Project Organization-const opnsOwner
Quality Control
Superintendent Project Engineer
Project Engineer
Contractor
Corporate Management
Corporate staff
Field site
Interpret Drawings & SpecsShop Drawings
RFI controlMaterialsSamples
Construction operationsCoordination of trades
SchedulesPayments
Safety-OSHAChanges
RFI responsesClarification of drawings
Monitor compliance
Monitor QC processPrepare QC reportsMake inspections
Take corrective actionDocument QC checks
Construction Managerand/or
Contracting Officer
ConstructionContract
Subcontractor A Subcontractor B Subcontractor C Subcontractor D Subcontractor E
Sub-contracts
Project Organization…Owner
Quality Control
Superintendent Project Engineer
Project Engineer
Contractor
Project Manager, Construction Manager
and/orContracting Officer
Subcontractor
Subcontractor
Subcontractor
Subcontractor
Subcontractor
Design Manager
ProjectArchitect
StructuralEngineer
CivilEngineer
MechEngineer
ElectricalEngineer
A
B
C
Quality Assure
OfficeEngineer
TechnicalInspectors
A/E Const Staff
Resident Engineer
UsingAgency
Participants & Responsibilities…
The Owner The Designer The Builder The Project Manager (PM) The Construction Manager (CM)
Class exercise: define responsibilities
The Owner… Pays for the project Accepts the project on completion Sets criteria for design Sets cost parameters Establishes time line for completion Determines contract type Hires the designer & builder Appoints the construction manager Makes decisions when needed
The Designer… Oversees planning & advises owner Evaluates siting options Develops concept design Prepares contract plans Prepares contract specifications Prepares cost estimates Prepares bid package Assists in selection of builder Assists during construction
The Builder or Contractor… Prepares and submits bid documents Organizes project team Hires & pays subcontractors Obtains permits and licenses Mobilizes contract work force on NTP Builds IAW plans & specifications Controls quality & cost Manages construction site & safety Turns over completed project on time
The Project Manager (PM) Represents the Owner in all matters Serves as technical assistant to owner Controls project budget, schedule, quality & timing Makes recommendations on budget, schedule,
changes, & quality changes Makes recommendations on payments Recommends acceptance of project
Construction Manager (CM)… Represents the contractor in all matters Oversees construction operations Monitors schedule & costs Provides interface with client operations Follows all contract provisions Makes recommendations on changes or claims Submits progress payments Responsible for quality control Ensures all work is completed
Construction Scheduling…
Common methods:1. Bar Charts2. Velocity Charts3. Line-of-Balance Charts 4. Network Diagrams: CPM/PERT
Bar Chart Schedule…
Task Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9
Excavate xxxxxFoundation xxx xxxxx
Slab xxxxxStructure xxxxxxx
Roof xxxxxx Walls xxxxxxxxxxDoors xxxx
Windows xx xx xx xxInterior Walls xxxxxxxxx
Ceilings xxxxxxxxPaint xxxxx
Floor Tile xxxxxxPlumbing xxx xxx xxxx
Mechanical xxx xxxx xxxElectrical xxx xxxx xxxFurniture xxxxx
Punch List xxClose out xxxx
Simple Bar Chart Schedule
Velocity Chart…or S-curve
Excav Found Slab Struct Walls Roof Partitions Ceilings Paint CleanSchedule 100 225 275 575 975 1275 1725 1850 1950 2000Cum Hrs 88 218 268 568 768 993 1493 1493 1493 1493Plan Hrs 100 125 50 300 400 300 450 125 100 50Act Hrs 88 130 50 300 200 225 500
Simple Velocity Chart
0
500
1000
1500
2000
2500
Excav
Found
Slab
Struct
Wall
sRoo
f
Partiti
ons
Ceilin
gsPain
t
Clean
Schedule
Cum Hours
Plan Hours
Act Hours
Line-of-Balance Chart
Characteristics of methods… Bar Charts
Simple & easy to read Based on contractor field experience Do not show interdependencies Do not show critical path
S-Curves Good for showing progress Do not show interdependencies Do not show critical path
Line-of-Balance Show interdependencies May show progress Do not show critical path
CPM/PERT Chart…
Management of Quality…
Definition of Quality Control Definition of Quality Assurance Designer’s responsibility Contractor’s responsibility
Total QualityManagement
Savings from quality
Quality Control Process… Must have a Quality Control Plan… an inspection"
system” Special considerations:
Timing of inspections; preclude delays Protection of work in place Most work is irreversible; i.e.. concrete, foundations Logistical sequencing Follow plans & specifications; changes not authorized Report and correct errors & deviations from spec;
documents Three phased inspections system
Preparatory inspection Pre-inspection Final inspection
QC Staff must be qualified, trained & dedicated
Inspection & Testing Manual… Detailed inspection procedures:
Preparatory inspection: work flow, submittals, methods Initial inspection: workmanship & components Follow-up: results of work, tests, appearance
Acceptance/rejection criteria Testing requirements & frequency Responsibilities for testing Approval of outside labs & testing agencies Timing of inspections & work Reports required, frequency & format Documentation of test results
Inspection Process (text p304)…Inspecton
Work & Materials
Visual Or
Lab Test
Lab TestVisual Test
Compare w Plans & Specifications
Samples to lab
Lab Results
Conform? Test OK?Yes
No
Issue Non-Comp
Defective Mat Report
No Payment till corrected
Follow-upRecord in log
Reinspect When Corrected
No
Issue Non-Comp
Defective Mat Report
No Payment till corrected
Follow-upRecord in log
Resample When Corrected
Make FinalInspection
Work AcceptedPayment Authorized
Submittal Process…Inspecton
Work & Materials
Visual Or
Lab Test
Lab TestVisual Test
Compare w Plans & Specifications
Samples to lab
Lab Results
Conform? Test OK?Yes
No
Issue Non-Comp
Defective Mat Report
No Payment till corrected
Follow-upRecord in log
Reinspect When Corrected
No
Issue Non-Comp
Defective Mat Report
No Payment till corrected
Follow-upRecord in log
Resample When Corrected
Make FinalInspection
Work AcceptedPayment Authorized
Shop Drawing?
AE Review
Civil Engineering Jobs…
Design – specific discipline Construction Facilities Engineering Project Management Construction Management Public agency Private firm