Colton Joint Unified School District Commitment to Equal Opportunity
Minutes March 3, 2014
The Measure G – Citizens’ Oversight Committee met on Monday, March 3, 2014 at 5:30 p.m. at the Board Room, 18829 Orange Street, Bloomington, CA 92316. Opening –Mr. Ayala called the meeting to order at 5:31p.m.
I. CALL TO ORDER – Roll Call – by Elsa Aguilar. Introductions were made.
Members Present (*absent) Ms. Elsa Aguilar – Chair Mr. Jorge Valdez * Mr. Forrest M. John III Mrs. Pamela Valdez Mrs. Laura Morales Mrs. Summer Zamora Jorrin Mrs. Amanda Salazar Staff Members Present Mr. Jaime R. Ayala Mr. Owen Chang Mrs. Joanne Medina Mrs. Katie Orloff
II. APPROVAL OF MINUTES
April 9, 2013 & August 5, 2013 meeting minutes were reviewed and approved, motion by Mrs. Morales, and second by Mrs. Salazar, and carried on a 6-1 vote (Mr. Valdez absent).
III. PUBLIC COMMENT Mrs. Aguilar opened for public comment. No public comment.
IV. OLD BUSINESS
None.
V. NEW BUSINESS New Member Orientation- Mr. Chang
Mrs. Aguilar discussed the position of vice-chair. Mr. Chang presented each member with a binder which included bylaws, agendas, minutes, the annual report, and the audit report. Mr. Chang reviewed the new member orientation powerpoint. Handouts were distributed. (Exhibit A). Additionally an overview of the team, prioritization (identification), master plan, and funding was discussed. Mr. Chang also discussed the upcoming Board Facility workshop scheduled for April 8.
COLTON JOINT UNIFIED SCHOOL DISTRICT Measure G COC - Minutes March 3, 2014 P a g e | 2
Mr. Ayala discussed property values and the real estate market. Funding is dependent on the economy. An analysis which was conducted a few months ago predicts it will be approximately three years until we can sell more bonds therefore the district is proceeding cautiously. Mr. Chang gave an overview of the completed projects within the last few years and discussed the current projects under construction. Mr. Chang also discussed future planned projects that are in the planning/design phase. Mr. Chang discussed the Colton High School (CHS) and Bloomington High School (BHS) multi-purpose buildings. BHS has been DSA approved and we are currently waiting on CHS which will be approved in April or May. The district will then have 4 years to begin construction. Two different architects were hired for the projects. Mr. Chang briefed the committee on the program outlook discussing the request for qualification (RFQ) process and also the Board of Education priority list. Mr. Chang spoke about the bond audit and the formation of a subcommittee. Mrs. Aguilar already met with the independent auditors last week on behalf of the CBOC. A subcommittee will need to be formed, preferably 3 members to review the audit results, and then provide an annual report to the Board of Education. Additionally there is a new education code for the bond oversight committee. Members will now be able to serve three consecutive terms instead of two. The amended bylaws will require Board approval.
VI. FINANCIAL REPORT Mr. Chang reviewed the consolidated budget status report (Exhibit B).
VII. MEMBER COMMENT
Mrs. Morales nominated Mrs. Zamora Jorrin for vice-chair. Mrs. Zamora Jorrin accepted.
VIII. NEXT MEETING – (Quarterly) Mrs. Medina will be in contact with the members for the next meeting date. Next
meeting will be scheduled in June. Bylaws will be added to the agenda for the next meeting.
IX. ADJOURNMENT
There being no further business, the Measure G Citizens’ Oversight Committee meeting was adjourned at 6:32 p.m.
COLTON JOINT UNIFIED SCHOOL DISTRICTExhibit A
MEASURE G MEASURE G MEASURE G MEASURE G CITIZENS’ BOND OVERSIGHT COMMITTEECITIZENS’ BOND OVERSIGHT COMMITTEE
NEW MEMBER ORIENTATIONNEW MEMBER ORIENTATIONNEW MEMBER ORIENTATIONNEW MEMBER ORIENTATION
CAPITAL IMPROVEMENT PROGRAMMarch 3, 2014
AGENDA
District Mission and Measure G
CJUSD Capital Improvement Program (CIP)
Program Review and UpdatesProgram Review and Updates
Program Outlook
CAPITAL IMPROVEMENT PROGRAM
District Mission
The Mission of the Colton Joint Unified School District, a team of caring employees dedicated to the education for children, is to ensure each student learns the academic knowledge and skills necessary to thrive in college or in the workforce and be responsible, productive citizens by providing engaging, p , p y p g g g g,challenging, and enriching opportunities and specialized programs in a safe environment in partnership with students, families and our diverse communitiesfamilies and our diverse communities.
CAPITAL IMPROVEMENT PROGRAM
Measure G
Measure “G” repairs, improves, and builds more schools to reduce overcrowding and attract quality teachers in every community and every school in the Colton Joint Unified School District. EVERY school benefits!Unified School District. EVERY school benefits!
CAPITAL IMPROVEMENT PROGRAM
PROGRAM TEAMPROGRAM TEAM
Board of Education
INITIATION / DIRECTIONINITIATION / DIRECTION
CAPITAL CAPITAL IMPROVEMENT
PROGRAM
District Facilities
Citizens’ Bond
Oversight Committee
RECOMMENDATION/RECOMMENDATION/EXECUTIONEXECUTION
VERIFICATIONVERIFICATION
Team Committee
CAPITAL IMPROVEMENT PROGRAMCJUSD FACILITIES TEAMCJUSD FACILITIES TEAM
Board of Education
Mr. Frank Ibarra – PresidentMr. Pilar Tabera – Vice President
Mrs. Patt Haro – ClerkMr. Randall Ceniceros
Mr. Dan FloresMr. Roger Kowalski
Mrs. Joanne E. Thoring-Ojeda
Superintendent
Jerry AlmendarezSuperintendent
Bond Oversight Committee
Ms. Elsa Aguilar – ChairMr. Forrest M John III
Jaime AyalaAssistant Superintendent
Business Services DivisionMrs. Laura Morales
Mrs. Amanda SalazarMr. Jorge Valdez
Mrs. Pamela ValdezMrs. Summer Zamora Jorrin
Facilities, Planning & Construction
Owen ChangDirector
Kasey KubotaAdmin Asst. 1
Craig SandiferFacilities Project Manager
Becky JoinerFiscal Analyst
CAPITAL IMPROVEMENT PROGRAM
Previous Board Direction
PROJECT IDENTIFICATION/ PRIORITIZATIONPROJECT IDENTIFICATION/ PRIORITIZATION
Previous Board Direction
Site Administration Request
Sig ifi t D f d M i t & R iSignificant Deferred Maintenance & Repairs
Division of State Architect Approval
F ili i M Pl N d AFacilities Master Plan Needs Assessment
o Key Planning Issues: Fire Life and Safety, Access, Structural
Equity among siteso Equity among sites
Funding Availability /Eligibility of Matching State Funds
Demographics/Enrollment AnalysisDemographics/Enrollment Analysis
State Agency Mandates
CAPITAL IMPROVEMENT PROGRAM
Develop Educational SpecificationsFACILITIES MASTER PLANFACILITIES MASTER PLAN
p pBased on meeting with staff and community.
Assessment of District FacilitiesR i diti f i ti f ilit d b ildi tReview condition of existing facility and building systems.
Input from District Maintenance & Operations, IT and other departments.Identifies Facilities needsDemographic AnalysisIdentifies possible solutions (Transformations)Identifies possible fundingIt does not specify a particular project
‐‐‐‐ ThereThere isis alwaysalways moremore needneed thanthan fundingfunding ‐‐‐‐
PROGRAM REVIEW/ UPDATE
FUNDINGFUNDING
FUNDING SOURCE ANTICIPATED RECEIVED
M B (2001) $113000000 $113000000*Measure B (2001) $113,000,000 $113,000,000*
Measure G (2008) $225,000,000 $102,837,000
STATE MATCH (B and G) $133000000 $125217253STATE MATCH (B and G) $133,000,000 $125,217,253
Fund 25 (Redevlop/Developer Fees)
$ 14,487,315 $14,487,315
TOTAL $485487315 $355541568TOTAL $485,487,315 $355,541,568
*Includes approximately $11 million in interest earnedIncludes approximately $11 million in interest earned
PROGRAM REVIEW/UPDATE
Measure Measure G G -- $225 Million$225 Million
40%(A&B)55%
Series A & B ($91M)
S i C ($11 9 M)(A&B)55%(REMAINING)
Series C ($11.9 M)
REMAINING BOND CAPACITY ($122 1 M)
5%(C)
CAPACITY ($122.1 M)
Series A,B,C = $102.9 Million
PROGRAM REVIEW/UPDATEMajor Completed ProjectsMajor Completed Projects
NEW CONSTRUCTION PROJECT PROJ. EXPENDITURE MEASURE G
GRAND TERRACE HIGH SCHOOL – INCREMENT 1 &2 $143,547,321 $17,596,475
JOE BACA MIDDLE SCHOOL $43,756,527 $24,768,026
Colton High School Math & Science Building $16 942 186 $4 038 824Colton High School Math & Science Building $16,942,186 $4,038,824
Bloomington High School Math & Science Building $14,529,757 $7,570,099
SUBTOTAL $218,775,791 $53,973,424
LARGE MODERNIZATIONLARGE MODERNIZATIONPROJECT PROJ. EXPENDITURE Measure G* 1
Crestmore Elementary $8,005,025$7,594,982
Grant Elementary $6,312,696 $6,151,152
Lewis Elementary $4,447,212 $4,284,890
Lincoln Elementary $5,537,367 $5,335,789
SUBTOTAL $24 302 300 $23 366 813SUBTOTAL $24,302,300 $23,366,813
*AMOUNT SHOW IS CURRENT EXPENDITURE AS OF 3/3/2014 AND DOES NOT REFLECT COMPLETE PROJECT COST.1 APPLICATIONS SUBMITTED TO STATE FOR FUTURE STATE SCHOOL FACILITIES PROGRAM. ANY FUTURE STATE BOND
MATCH RECEIVED WILL REPLENISH MEASURE G FUND.
PROGRAM REVIEW/UPDATE
UNDER CONSTRUCTIONUNDER CONSTRUCTIONSMALL MODERNIZATIONPROJECT Measure B/Fund 25
BUDGETMEASURE G
(Budget)
Reche Canyon Elementary $1,218,525 $27,400
San Salvador Preschool $4 204 687 $1 875 000San Salvador Preschool $4,204,687 $1,875,000
SUBTOTAL $5,423,212 $1,902,400
SCOPE OF WORK
San Salvador ElementaryModernization of 4 classrooms, replace 7 portables, MPR upgrades, lunch , p p , pg ,shelter, new site power upgrade, fire alarm upgrade, New PA, parking lot improvements addition, and ADA upgrades
Reche Canyon ElementaryE d ki l t ki l t h d t t d it d i fiExpand parking lot, new parking lot shade structure, upgrade site drainage, fire alarm upgrade, ADA upgrades,
PROGRAM REVIEW/UPDATE
Planning / DesignPlanning / DesignPLANNING
O C G COPROJECT BUDGET COMMENT
Zimmerman HVAC/Fire Alarm Upgrade $5,000,000 Construction 2014
Terrace View HVAC/Fire Alarm Upgrade $2,000,000 Construction 2014
Crestmore, Lewis, Lincoln, Grant ADA Upgrade $800,000 Construction 2014-2015
Bloomington High School Multi-Purpose Building $692,418 Approved For Design Only
Colton High School Multi-Purpose Building $773,956 Approved For Design Only
SUBTOTAL $9,266,374
PROGRAM OUTLOOK
FundingFunding SourceSource BalanceBalanceFund 21 (Measure A & B) $8,421,125
Fund 35 $2,632,978
Estimated Fund Balance in Q4 of 2015* $11,054,103$ , ,
* Projected fund balance in Q4 - 2015 after completion of Group 2/3 small modernization projects Zimmerman Elementary HVAC and Fire Alarm Upgrade Terrace View Elementaryprojects, Zimmerman Elementary HVAC and Fire Alarm Upgrade, Terrace View Elementary HVAC/Fire Alarm Upgrades, and Crestmore, Lewis, Lincoln, and Grant ADA upgrade.
PROGRAM OUTLOOK
Utilizes existing funds – No new funds anticipated*
State Bond is depleted. OPSC is accepting fundingapplications for future School Facilities Programapplications for future School Facilities Program.
Additional State school construction bond is needed.Additional State school construction bond is needed.
Need increase in assessed valuation prior to anotherlocal bond issuance.
* Matching Funds are being pursued for some modernization projects and may g g p p j ybe available for some future projects. Additional funding opportunities are always being explored.
PROGRAM OUTLOOK
BoardBoard Priority List (Previously Approved in 2012)Priority List (Previously Approved in 2012)
ProjectsProjects Estimated Estimated BudgetBudget
DurationDuration NotesNotes
•CMS athletic fields (RDA funds)
$840,000 1 year +/- RFQ Developed. Conceptual Rendering Provided
•CHS athletic fields $1,050,000 1 year +/- RFQ Developed(RDA funds)
, , y
•BHS baseball fields $490,000 1 year +/- RFQ Developed
•Athletic fields in Grand Terrace (RDA funds)
$840,000 1 year +/- RFQ Developed
•CHS locker room restroom weight $6 160 000* 2 years +/ RFQ Developed•CHS locker room, restroom, weight room
$6,160,000 2 years +/- RFQ Developed
•BHS Stadium $7,840,000* 2 years +/- RFQ Developed
•CMS Multi-Purpose Building $840,000 2 years +/- RFQ for Architectural Services – Further scoping needed
•CHS Multi-Purpose Building $9,400,000* 1.5 years +/- In DSA for review
•BHS Multi-Purpose Building $7,400,000* 12-16 months DSA Approved
Estimated Total Budget Pending Projects
$34,860,000Projects
* Rough Estimate of Total Project Cost – Board Priority Approval for Design Only
PROGRAM OUTLOOK
Facilities workshop scheduled with Board of Education on April 8, 2 014
RECOMENDATIONRECOMENDATIONProject Estimated Cost NotesBHS Stadium (Design Only) $500,000 Estimated Cost for Design Only
CHS Stadium/Locker Room/Wt. Room/Toilet (Design Only)
$450,000 Estimated Cost for Design Only
BHS Baseball Field $490,000 Estimated Budget
CHS Athletic Fields (RDA Funds) $1,050,000 Estimated Budget
Fire Alarm/Intercom Upgrade at Ruth Grimes, McKinley, Birney, Terrace Hill Middle School, Grand Terrace Elementary
$2,750,000 Estimated Budget
y
Washington Alt HS Modernization (or alternative campus not yet modernized)
$350,000 Planning and Design Only
Program Contingency $5,464,103 Shade Shelter, Marquee Signs, Curb A l Fi Al I t S itAppeal, Fire Alarm, Intercom, Security Improvements, Unforeseen Conditions.
Total Estimated Cost $11,054,103
Colton Joint Unified School District Printed 3/3/2014
Consolidated Budget Status ReportBudget versus Commitments and Expenditures for Multiple Projects (created 3/3/2014 12:40 pm)
Budget vs. Commitments and Expenditures
Project No. Project Name Total Budget Total Commitments % Budget
Committed Total Expenditures
% Budget
Spent
Remaining Against
Budget
Admin G Administrative Control - Program Costs for Measure G** 12,878,934 5,147,820 40.0% 5,053,158 39.2% 7,825,776
ACTIVE PROJECTS1F Colton High School - CHS New Math & Science Bldg. 17,871,431 16,406,233 91.8% 16,356,393 91.5% 1,515,039
2A Crestmore Elementary - Crestmore Modernization 8,606,980 8,362,008 97.2% 8,183,356 95.1% 423,624
2B D'Arcy Elementary - D'Arcy Modernization 2,120,711 1,416,285 66.8% 362,501 17.1% 1,758,210
2C Jurupa Vista Elementary - JV Modernization 2,033,599 1,567,136 77.1% 557,052 27.4% 1,476,546
2D Lewis Elementary - Lewis Modernization 5,017,223 4,499,390 89.7% 4,387,700 87.5% 629,523
2E Cooley Ranch Elementary - Cooley Ranch Modernization 3,308,182 2,352,097 71.1% 499,579 15.1% 2,808,603
2F Grant Elementary - Grant Modernization 6,596,044 6,312,696 95.7% 6,213,328 94.2% 382,716
2G Lincoln Elementary - Lincoln Modernization 5,788,679 5,797,756 100.2% 5,586,261 96.5% 202,418
2H Reche Canyon Elementary - Reche Canyon Modenziation 1,245,925 900,026 72.2% 234,858 18.9% 1,011,066
2I San Salvador - San Salvador Modernization 6,079,687 4,229,073 69.6% 690,187 11.4% 5,389,500
2J Ruth Harris Middle School - RHMS Modernization 3,058,826 2,280,124 74.5% 404,792 13.2% 2,654,034
27 Joe Baca Middle School - New Middle School #5 49,162,432 44,250,694 90.0% 42,923,437 87.3% 6,238,995
PENDING PROJECTS1M Colton High School - CHS Stadium Renovation & Expansion 4,325,000 251,838 5.8% 251,838 5.8% 4,073,162
1N Bloomington High School - BHS Stadium Renovation & Expansion 5,600,000 321,718 5.7% 321,718 5.7% 5,278,283
1Q Bloomington High School - BHS Kitchen & Multipurpose Renovation 7,652,418 637,237 8.3% 519,577 6.8% 7,132,841
1R Colton High School - CHS Kitchen & Multipurpose Renvoation 8,308,956 885,558 10.7% 728,268 8.8% 7,580,688
42 Terrace View Elementary - Terrace View Fire Alarm & Intercom 549,930 188,825 34.3% 76,662 13.9% 473,268
44 Zimmerman Elementary - Zimmerman Fire Alarm & Intercom 1,700,000 602,213 35.4% 443,382 26.1% 1,256,618
COMPLETED PROJECTS1E Bloomington High School - BHS New Construction Interim Housing 1,569,837 1,472,859 93.8% 1,472,859 93.8% 96,978
1E Bloomington High School - BHS New Math & Science Bldg. 13,451,813 13,086,289 97.3% 13,056,898 97.1% 394,915
1F Colton High School - CHS New Const. Interim Housing 767,228 585,793 76.4% 585,793 76.4% 181,435
11 Grand Terrace High School - GTHS - New High School # 3 151,373,055 144,186,923 95.3% 143,707,763 94.9% 7,665,292
35 Jurupa Vista, Reche Canyon, Wilson, BMS - Fire Alarm & Low Voltage Upgrades 2,167,851 1,914,072 88.3% 1,914,072 88.3% 253,778
47 Birney Elementary - Birney Bus Drop/Parking 337,365 312,285 92.6% 305,572 90.6% 31,793
50 Terrace View Elementary - Terrace View Parking/Shade Shelter 1,311,696 844,731 64.4% 844,731 64.4% 466,965
1J Terrace View Elementary - Terrace View Modernization 337,528 337,528
1K Washington High School - Washington Modernziation 251,090 251,090
1L Zimmerman Elementary - Zimmerman Modernization 313,556 313,556
3A Birney Elementary - Birney Modernization 28,600 28,600
3B Grand Terrace Elementary - Grand Terrace Modernizaiton 27,064 27,064
3C McKinley Elementary - McKinley Modernization 24,812 24,812
3D Wilson Elementary - Wilson Modernization 29,403 29,403
3E Grimes Elementary - Grimes Modernization 27,747 27,747
Expenditures Budget Commitments
Colbi Technologies Inc. (c) Page 1 of 2 Consolidated Budget Status Report
Colton Joint Unified School District Printed 3/3/2014
Consolidated Budget Status ReportBudget versus Commitments and Expenditures for Multiple Projects (created 3/3/2014 12:40 pm)
Budget vs. Commitments and Expenditures
Project No. Project Name Total Budget Total Commitments % Budget
Committed Total Expenditures
% Budget
Spent
Remaining Against
Budget
Expenditures Budget Commitments
3F Terrace Hills Middle School - THMS Modernization 191,615 191,615
3G Bloomington Middle School - BMS Modernization 277,880 277,880
3I Colton Middle School - CMS Modernization 664,754 664,754
3K Colton Middle School - CMS New Construction 277,063 277,063
3L Terrace Hills Middle School - THMS New Construction 194,232 194,232
3N Slover Mt. High School - Slover Mtn. Modernization 31,347 31,347
34 School # 30 - Cedar/Santa Ana Ave. - School # 30 - Cedar/Santa Ana Ave. 6,782 6,782
Totals 322,883,800 271,495,151 84.0% 258,365,206 80.0% 67,202,067
AP-Mt. Vernon LLC (rent for Suite 7A) - $122,220 (thru Sept. 2013)
Colbi Technologies - $165,625 (1 time capacity increase)
CJUSD Bond Admin Salaries - $275,000 (average Annual salaries @ 50%, since 10/11)
Davis Demograohics - $44,052 (2 yr contract)
Nigro & Nigro - $24,000 ($8,000 per yr @ 3 yrs)
NTD Architects (District wide master plan) - $312,200 (Lump Sum Fee)
School Facility Consultants - $156,080 ($240,000 total contract, balance divided with project costs above)
Spectrum Communication (data cables/phones @ Ste 7A) - $14,902 (one time fee)
Seville Construction Services (program management) - $3,206,766.96 Expended Fees (does not include $2,194,803.55 project
management cost, which is included in above budgets)
>>Seville Construction: re-negotiated contract as of 09/2011 not to exceed $3,557,342
Bond Cash Balance as of 03/03/2014
Measure B 969,243$
Measure G
Series A 16,106,070$
Series B 3,871,061$
Series C 1,110$
TOTAL 20,947,484$
**Program Costs for Measure G Includes the following items:
Colbi Technologies Inc. (c) Page 2 of 2 Consolidated Budget Status Report